(S_schedule)
Require maintenance of TBM driving parameters (spoil
removal rate records) against theoretical earth volume to be removed, and tail grout quantity placed per
Mues, Bob 7/12/2011 9/12/2013 Proposed
tail grout quantity placed per ring of TBM advance, to
verify possible "over excavation"). Verify that Contractor's
remedial plan for this condition is in place with initial tunnel submittals, and that the equipment/materials noted are available and
functional throughout tunneling. Require additional
remedial grouting or refill where necessary.
Mues, Bob 8/1/2010 9/12/2013 Proposed
Verify the requirements of Specification 02311 for inspections and interventions into the pressure chamber of
the EPB TBM are met (Pressurized Face Tunneling
Plans, Method Statements, Procedures, Tunnel Safety
Plans).
Mues, Bob 8/1/2010 9/12/2013 Active
520 520 520
15
7/12/2011 9/12/2013 1 - Rare 5 - Catastrophic 5 - Catastrophic Mitigate
Maintain full-time CM QA inspection on the TBM when tunneling (per Spec 02311 requirements). Assure Contractor maintains adequate off-shift monitoring of pressure chamber and heading, esp at high risk areas. 75,000,000 112,500,000 150,000,000
Catastrophic event - loss of completed work
and extensive delay in starting over. Unrecoverable loss of tunnel and shaft. Wong, Johanna Open Technical Differing soil condition results in chimney to bottom of the Bay, blow-in to TBM, lose tunnel, submerge shaft and
start over. Tunnel Unplanned hyperbaric intervention, and results in loss of pressure to face of EPB TBM, which cannot be recovered due to nature of the material. 001
On-going check of thrust and lubrication data from TBM as
progressing.
Mues, Bob 7/12/2011 9/12/2013 Proposed
Assure TBM maintenance is performed as specified or more (if needed), particularly
prior to entering squeezing ground regions.
Hogan, Tom 7/12/2011 9/12/2013 Proposed
14 19.5 58.5 97.5
2 - Unlikely 3 - Moderate 4 - Major Technical Encounter reaches of squeezing ground causing TBM to get stuck. Tunnel Differing site conditions (highly plastic clay) of the San
Antonio formation in excess to those or at other locations than those expected from GBR. 9/12/2013 TBM gets stuck in these reaches, and impacts Contractor production rate. Wong,
Johanna Open 7/12/2011 Mitigate
Verify that the TBM thrust is at least as specified and that the
shield lubrication (bentonite injection port/injection system)
are functioning, lubrication material mixing and supply system are functioning
and ready, and that TBM maintenance is current. 1,312,350 3,937,050 6,561,750 CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day
. Total Daily Rate = $17,300. Add for loss of productivity for half of 75% of the tunnel = 9,750' - 10%, 20% & 50% reduction in progress at average of $1,000 per LF. 002
(S_schedule)
Assure Contractor submittals are in on schedule and properly reviewed and
approved.
Mues, Bob 1/1/2013 7/5/2013 Proposed
Assist Contractor with any other special measures
needed.
Mues, Bob 1/1/2013 7/5/2013 Proposed
0 0 0 0 - Contractor Risk 3 - Moderate 4 - Likely Open 3/1/2013 7/5/2013 0 Technical Unforeseen ground conditions between the Franciscan Formation and San Antonio Formation interface. Tunnel Interface between San Antonio Formation (softer ground) and Franciscan Formation Control of the tunnel (vertical/ horizontal) alignment between the San
Antonio Formation and Wong, Johanna Mitigate Although this subsurface discontinuity
is well defined in the GBR, assure that Contractor's EPB TBM design includes a suitable guidance 0 0 0 003 004 Technical Hitting unforseen Franciscan Formation in reaches not surveyed in the GBR
Tunnel Differing site conditions. Additional hyperbaric interventions needed to change cutterhead; productivity loss; TBM not designed for great lengths of hard ground. Wong,
Johanna Open 7/12/2011 3/12/2013 2 - Unlikely 3 - Moderate 3 - Moderate 10 15 20 673,000 1,009,500 1,346,000
CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day . Total daily cost = $17,300. Add for loss of productivity using $50,000 per day X the additional days to accomplish the work.
Mitigate
Assure that the Contractor has planned to perform maintenance interventions prior to
each reach with geotechnical data "gaps"; assure that back-up equipment and
supplies are available.
Assure Contractor submittals are in on schedule and properly reviewed and
approved.
Mues, Bob 1/1/2013 7/5/2013 Proposed
On-going check of perimeter fencing integrity and site sign
visibility.
Hogan, Tom 6/1/2010 3/2/2015 Active
On-going check of security guard's presence on site
24/7.
Wakefield,
Rick 8/1/2010 5/15/2015 Active
Replacement or 24/7.
Work area lighting functional
(include winter evenings). Contractor 11/15/2010 12/31/2014 Proposed Maintain and repair (if
needed) fencing. Contractor 8/1/2010 5/15/2015 Active
Lock-ups inside site and provide safety covers over
potential hazards such as pipe trench at night.
Contractor 12/1/2010 5/15/2015 Proposed
Coordinate with SFPUC BEM to ensure they obtain a
Section 2081 Take Authorization from CDFG prior to working at Newark.
Peterson,
Megan 1/1/2011 4/1/2011 Proposed
Conduct preconstruction surveys prior to working at Newark and relocate CTS individuals, if found. Hand excavate burrows during the
dry season if work begins after May 1. Wilkerson, Cullen and/or Craighead, Kim 2/1/2011 3/1/2011 Proposed Wilkerson, Cullen; 60 0 0 0 Open 6/1/2010 Security Vandalism to site or construction property, damage Ravenswoo d/ Newark Shafts Breach in perimeter fence or bypass of guard station. repair to finished permanent works, safety hazard to "intruders" or perpetrators.
Contractor 2 - Minor 0 0 0 0 Contractor Risk Mitigate safety and security plan.Monitor and implement
5/15/2015
5 - Frequent 0 - Contractor Risk
2 - Unlikely 2 - Minor 2 - Minor 5 5/15/2015
Mitigate
Work in a proactive manner to anticipate issues before they become delays or cost
changes. Open 3/1/2011 766,000 1,532,000 2,298,000 CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day + Standby Costs @ $21,000/day = $32,500. Total daily rate = $38,300/day. Standby costs include
equipment, security, core crew costs, tunnel
lighting & ventilation,
20 40 Contractor delayed from starting work at Newark and/or additional restrictions to site implemented during site activities. Wong, Johanna Regulatory Unanticipated presence of endangered species. NewarkShaf t Protected species encountered during surveys or construction. 005 006 Monitor installation of exclusion fencing and initial ground-disturbing activities. Cullen; Craighead, Kim; Peterson, Eric 2/1/2011 5/1/2011 Proposed
lighting & ventilation, equipment maintenance, etc. activities.
(S_schedule)
Look into the feasibility of alternative mitigation measures as opposed to implementing a buffer zone
(e.g., barriers, etc.)
Peterson, Megan 1/1/2011 4/1/2011 Proposed Conduct preconstruction Restrictions due to Protected birds CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = Conduct preconstruction surveys according to the MMRP during the early portion of the 2011, 2012, 2013, 2014 and 2015 nesting seasons. Wilkerson, Cullen and/or Craighead, Kim 2/1/2011 3/1/2015 Proposed
Maintain an open dialog with regulatory agencies and take proactive steps to minimize
delays.
Peterson,
Megan 2/1/2011 5/1/2015 Proposed
Initiate discussions with USD early, and prior to moving into NVL to understand the requirements/restrictions
Contractor 2/1/2011 6/1/2011 Proposed
Obtain a NPDES VOC permit as a backup in the event
USD discharge is not allowed.
Contractor 12/1/2010 6/1/2011 Proposed
Evaluate additional design techniques to limit the influx of groundwater into shaft and
trench for tie-ins (e.g., Contractor 12/1/2010 6/1/2010 Proposed Develop a water
discharge contingency plan
0 0 0 Contractor Risk Mitigate
3/1/2011 8/1/2011 3 - Possible 0 - Contractor Risk 3 - Moderate 0 0 0 Regulatory
Union Sanitary District prohibits discharge of construction water
into their system
Newark Shaft
Contamination is too high and does not comply with USD requirements Additional permits, water treatment, or off-hauling of water. Contractor Open 0 Regulatory Restrictions due to nesting special-status shorebirds
(CA clapper rail, black rail, least tern, etc.) moving into an active construction area. Ravenswoo d/ Newark Shafts Protected birds nesting in adjacent marshlands during future nesting seasons.
5/15/2015 3 - Possible 2 - Minor 2 - Minor Contractor
delayed due implementation of buffer zones.
Wong,
Johanna Open 2/11/2011 9 Mitigate
Continually monitor status of birds in the area and develop an initial strategy for managing this risk. 1,532,000 3,064,000 6,128,000 $6,400 + office @ $100/day = $6,500/day + Standby Costs @ $21,000/day = $32,500. Total daily rate = $38,300/day. Standby costs include
equipment, security, core crew costs, tunnel
lighting & ventilation, equipment maintenance, etc.
40 80 160
007
008
trench for tie-ins (e.g., extending Ranger's cut-off
wall). CM QA Inspectors to verify
that Contractor has tested the water, and has a test plan in place to continually test and manage the water throughout the Newark shaft
installation work.
Hogan, Tom 3/1/2013 12/31/2013 Proposed
QA Inspectors assure that the shaft is sealed to avoid contaminated water from interfering with the tunnel completion and installation of
the final lining pipe into the tunnel and shaft, and the
surface pipe installation/connection to the
existing BDPL1.
Hogan, Tom 3/1/2013 12/31/2013 Proposed
On-going verification that Contractor meets requirements of their Union
Sanitary District discharge
Peterson,
Megan 3/1/2013 12/31/2013 Proposed
0
0 0
0
3 - Moderate Contractor Risk Mitigate
Contractor Open 3/1/2013 Safety
Handling of contaminated groundwater/soil at
Newarks shaft site in excess of amount specified. Newark Gravel lenses across site causing greater infiltration or existing contaminant plume has different constituents or higher concentrations.
Worker health & safety concerns if contaminated groundwater not handled appropriately. Contractor may be required to shut-down dewatering operation (and not be allowed to discharge by USD) if contaminants not properly treated prior to disposal. 0 0 0 12/31/2013 5 - Frequent 0 - Contractor Risk
Verification by ECM, EIs, and QA Inspectors
that Contractor has its plan, permits, disposal site, and resources for this contaminated water
in place prior to commencement of the
Newark Shaft installation. 009
Sanitary District discharge permit with dewatering
operation.
Megan 3/1/2013 12/31/2013 Proposed
On-going verification that Contractor's hyperbaric work
facilities are operational.
Mues, Bob 7/12/2011 9/12/2013 Proposed
Assure Contractor's contingency planning is in
place prior to the interventions.
Mues, Bob 5/1/2011 9/12/2013 Proposed
0 0 0
Contractor Open 7/12/2011 9/12/2013 3 - Possible 0 - Contractor Risk 3 - Moderate 0 Safety Injuries resulting from, or while working in, compressed air environment. Ravenswoo d Shaft Exposure to compressed air at face of TBM during inspections and maintenance.
Work will stop, worker must be transported to surface and quickly treated in decompression chamber or at Mitigate Ensure contractor provides the tools, equipment, and hyperbaric work facilities, and follows required contingency planning for carrying out
0 0 0 Contractor Risk
(S_schedule)
Require all equipment and systems for work under pressure be in place and
tested prior to commencement of work
Mues, Bob 4/12/2011 9/12/2013 Proposed
Require Contractor to adhere to decompression Exposure to
compressed air
Work will stop, worker must be transported to
Compressed air "hyperbaric" work cannot commence before all plans and
procedures are to decompression procedures and hyperbaric
work plans.
Mues, Bob 4/12/2011 9/12/2013 Proposed
Require Contractor to have medical resources in place for response, transport, and care of decompression sickness, either on site of at
nearby hospital or other qualified facilities.
Mues, Bob 4/12/2011 9/12/2013 Proposed
Assure Contractor's plans and employee training specifically address high risk
nature of work around the pressure bulkhead.
Mues, Bob 5/1/2011 9/12/2013 Proposed
Assure Contractor provides training of high risk work to any new workers involved in
tunneling operation.
Mues, Bob 5/1/2011 9/12/2013 Proposed
Safety Decompression sickness Tunnel compressed air at face of TBM during inspections and maintenance.
9/12/2013 3 - Possible 0 - Contractor Risk 3 - Moderate transported to surface and quickly treated in decompression chamber or at hospital.
Contractor Open 7/12/2011 0 Mitigate
procedures are acceptable pursuant to
California labor safety codes and standards,
including decompression process, equipment, and tables. 0 0 0 Contractor Risk 0 0 0 5 - Catastrophic Potential loss of EPB TBM and tunnel. Contractor Open 7/12/2011 Technical
Blow-in through the forward pressure bulkhead of the EPB
TBM (the bulkhead containing the face pressure monitoring instruments beyond which is the earth
plug, water table pressure and the Bay trying to come
in). Ravenswoo d Shaft Unintended penetration of the EPBM pressure bulkhead.
Contractor's plans must address the high risk of any maintenance work around the pressure
bulkhead and the dangers of any penetration (separate
from the hyperbaric intervention plans).
0 0 0 Contractor Risk
0 0
0 0 Mitigate
9/12/2013 2 - Unlikely 0 - Contractor Risk 011
012
tunneling operation.
Require expanded engineering controls for
sound attenuation (mufflers/enclosures of loud
equipment).
Mues, Bob 7/1/2010 5/15/2015 Active
Require increased distance (if possible) from sound source or sound walls (if
required).
Mues, Bob 7/1/2010 5/15/2015 Active
Remove/change out the
source or noise emitter. Mues, Bob 7/1/2010 5/15/2015 Active
Provide on-going updates to community via mailers, door hangers, blog of activities.
Kerby,
Christina 7/1/2010 5/15/2015 Active
Hold monthly coordination meetings with PG&E and Contractor to mitigate issues.
Wong,
Johanna 4/1/2010 3/31/2011 Active
Take appropriate steps to avoid any SFPUC caused
delays.
Mues, Bob 4/1/2010 3/31/2011 Active
0 0 0 20 60 180 in). Community Resident complaints, and irritation, with construction noise, dust, lighting, vibration, etc. Ravenswoo d Contractor's failure to comply
with noise and vibration code requirements, or if compliant, public irritation. 0 9/12/2013 Mitigate
2 - Unlikely 3 - Moderate 3 - Moderate 11
0 0 Contractor Risk Open 2 - Minor 3/31/2011 Potential work stoppage until complaints are addressed and mitigated.
Contractor Open 7/1/2010 5/15/2015 3 - Possible 0 - Contractor Risk
Technical Lack of sufficient power supply. Ravenswood
PG&E fails to provide power service when required; PG&E power failure. Delay to start of tunneling with insufficient power supply for
TBM; loss of power during
Wong, Johanna
Monitor site work to identify problem before
recognized by the public; provide proactive outreach to community of upcoming activities. 766,000 2,298,000 6,894,000 CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day + Standby Costs @ $21,000/day = Mitigate Closely monitor progress of the temporary construction power installations by PG&E. 0 013 014 delays.
Verify Contractor follows submittals and method
statements.
Mues, Bob 9/15/2010 6/1/2011 Active
Carefully inspect slab for leakage (following unwatering and cleaning).
Hogan, Tom 2/1/2011 6/1/2011 Proposed
If required, verify submittal of Contractor's remedial plan to repair leaks and assure
materials/methods are viable.
Mues, Bob 2/1/2011 6/1/2011 Proposed
Check to increase spare part inventory once condition is
verified.
Mues, Bob 7/12/2011 9/12/2013 Proposed
power failure. power during
tunneling. $32,500. Total daily rate = $38,300/day.
Standby costs include
PG&E. Potentially have to replace shaft floor slab. Contractor Open 11/15/2010 Technical Water leakage around the perimeter seal or through the shaft floor slab (tremie
concrete). Ravenswoo d Shaft Contractor does not follow specifications/ Contractor means & methods faulty.
Verify that Contractor follows specifications, places shaft floor slabs accordingly, inspect for
conformance. 0 0 0 Contractor Risk 0 0 0 More abrasive Different subsurface 0 Mitigate 6/1/2011 2 - Unlikely 0 - Contractor Risk 2 - Minor Excessive TBM head, face chamber, cutter, and screw conveyor wear Wong,
Assure that there are adequate spare parts CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day 015
(S_schedule)
Issue field order for immediate spare parts procurement, if schedule (long lead item) becomes an
issue.
Mues, Bob 7/12/2011 9/12/2013 Proposed
Technical ground conditions than anticipated.
Tunnel materials than those presented
in the GBR.
9/12/2013 3 - Possible 3 - Moderate 2 - Minor and hyperbaric
maintenance of those parts that are exposed to
ground pressure.
Wong,
Johanna Open 7/12/2011 12 Mitigate
adequate spare parts available at start and throughout tunneling. 1,346,000 2,019,000 2,692,000 $100/day = $6,500/day
. Total daily cost = $17,300. Add $1M, $1.5M & $2M for replacement parts, lost
time for replacement and lost productivity.
20 30 40
016
Check that Contractor has provided an adequate base
for crane support.
Hogan, Tom 8/1/2010 12/1/2010 Active
Check that Contractor is following load limits and protocol as perscribed in the
JHAs.
Hogan, Tom 8/1/2010 12/1/2010 Active
Hire specialty archaeological and paleontological monitors in the event of discoveries.
Peterson,
Megan 12/1/2010 2/1/2010 Completed
Ensure that worker training is conducted according to the
MMRP and specifications.
Peterson,
Eric 4/1/2010 12/31/2014 Active
Coordinate with the Contractor in the event of a
find to quickly assess the significance and possible need for work stoppage.
Peterson,
Megan 4/1/2010 12/31/2014 Active
Inspect the work area daily for any cover or other
potential habitat. Peterson, Eric 4/1/2010 12/31/2014 Active 0 0 0 Safety Damage to BDPLs 1& 2 or PG&E transmission lines
due to crane tip over. Shafts Unbalanced/ excessive load or unstable crane platform base during installation of diaphragm slurry wall rebar
Electrocution, if PG&E transmission lines hit; power outage. Service outage, if BDPLs hit; damage
requiring
Contractor Open 8/1/2010 Mitigate
Assure Contractor is well prepared with acceptable JHAs for each portion of slurry wall construction. 0 0 0 Contractor Risk Regulatory Unanticipated cultural or paleontological discoveries during shaft excavation, tunneling, or tie-ins Ravenswoo d/ Newark Bay Margin is known to contain prehistoric and paleontological resources, but construction methods prevent surveys and monitoring 3 - Moderate 0 0 - Contractor Risk 8/1/2010 5/15/2015 2 - Unlikely 2 - Minor 3 - Possible 11/15/2010 Mitigate 766,000 1,532,000 CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day + Standby Costs @ $21,000/day = $32,500. Total Daily Rate = $38,300/day. Standby costs include equipment, security, core crew costs, tunnel
lighting & ventilation, equipment Work stoppage until the resource can be properly evaluated/ recovered. Wong, Johanna Open 5 2,298,000
Carelessness Work stoppage
2 - Minor
Implement existing procedures for
unanticipated discoveries and work
quickly to mobilize specialists to the field. 017
018 20 40 60
Train individuals on significance of "take" of the
species.Conduct tailgate trainings prior to working in
sensitive areas.
Peterson,
Eric 4/1/2010 12/31/2014 Active
Coordinate with SFPUC BEM to ensure the 2081for CTS is
in hand prior to work beginning Newark
Peterson,
Megan 12/1/2010 3/1/2011 Active
Host SWPPP workshop for Bay Division Region to faciliate understanding of requirements. Peterson, Megan 4/1/2010 5/31/2010 Completed Develop expandable modular WTP for Ravenswood. Contractor 4/1/2011 10/30/2010 Active
CM team provides daily environmental inspection to
help identify issues.
Peterson, Eric and Mirzad, Slay
5/20/2010 3/1/2015 Active
Provide QSP to oversee site compliance with NPDES
permit.
Contractor 5/20/2010 5/1/2015 Active
Various: BCDC CM/SFPUC 9 FTE @
$150.00/hr = 1 - Rare 0 - Contractor Risk 4 - Major 0 5/20/2010 5/15/2015 Implement requirements as specified in project documents and develop comprehensive training program Regulatory Inadvertantly injuring or killing an endangered, threatened, or fully protected species (SMHM, CTS, etc.) Ravenswoo d/ Newark Carelessness and/or not following project requirements; accidental collisions with equipment; work in wetlands, etc. Work stoppage by USFWS and/or CDFG until additional mitigation measures can be developed/ approved. Contractor Open Regulatory Additional RWQCB requirements as a result of risk assessment prior to Sept 2, 2011. Ravenswoo d/Newark Additional requirements imposed by higher risk level
under NPDES General Construction Stormwater Permit due to duration of project.
0 0 0 Contractor Risk Mitigate
0 0
5/15/2015 4 - Likely 1 - Insignificant 1 - Insignificant Mitigate
Design water treatment plant to accommodate
new permit requirements (e.g., modular system that can easily be expanded). Close coordination between CM team and Contractor to understand new requirements and prepare risk assessment/SWPPP 50,000 100,000 250,000 Additional SWPP requirements and monitoring. Estimated costs by PUC/CM Team. 7 Additional time and costs incurred by Contractor and CM team associated with sampling, monitoring and reporting; additional RWQCB coordination. Wong, Johanna Open 5/20/2010 019 020 0 0 0 0 021 Regulatory
BCDC will not issue permit for tunneling under the Bay.
Tunnel
want removal of BDPLs 1&2;
BCDC may claim jurisdiction
below the Bay; subsurface easements are Cannot start tunnel excavation. Wong,
Johanna Open 9/20/2010 6/30/2011 2 - Unlikely 5 - Catastrophic 5 - Catastrophic 21 60 120 240 1,488,000 2,976,000 5,952,000
$150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day + Standby Costs @ $7,500/day = $14,000/day. Total Daily Rate = Avoid
Work with BCDC and City Attorney to get agreements in place well before the start of
tunneling.
Work with BCDC. Enlist help from City Attorney to avoid BDCD claiming jurisdiction below the Bay.
Zhang, Yin Lan 9/20/2010 6/30/2011 Active 022 Management Subsurface Easement is not obtained from Cargill, SamTrans, and Mid Peninsula Open Space District.
Tunnel Terms of Agreement not acceptable to parties; Board of Supervisors reject purchase of subsurface easement. Cannot start tunnel excavation. Wong,
Johanna Open 9/20/2010 6/30/2011 2 - Unlikely 5 - Catastrophic 5 - Catastrophic 21 60 120 240 1,488,000 2,976,000 5,952,000
CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day + Standby Costs @ $7,500/day = $14,000/day. Total Daily Rate = $24,800/day. Standby costs include equipment, security, Avoid
Work with property owners and City
Attorney.
Finalize Agreement with Property Owners. Submit Agenda Item to
the Board of Supervisors
Morelli, Brian 9/20/2010 30-Jun-11 Active
Check on-going monitoring of BDPLs and check that data is consistent with no movement.
Hnat, Steve 8/1/2010 5/15/2015 Active
BDPLs will require owner repair, which
Assure Contractor installs and monitors survey monuments CM/SFPUC 9 FTE @
$150.00/hr = $10,800/day and CS 8
(S_schedule)
Assure Contractor's means and methods are consistent with specifications for protection of
existing improvements.
Mues, Bob 8/1/2010 5/15/2015 Active
Develop contingency plan in the event of BDPL 1 or 2 failure and need for Ops access and repair.
Mues, Bob 12/1/2010 5/15/2015 Proposed
30 8/1/2010 5/15/2015 Operations Failure of BDPL1 or 2 in vicinity of Ravenswood or Newark shafts. Ravenswood/ Newark Possibly caused by non-construction means, such as age
related joint failure.
owner repair, which may be problematic regarding access and safety concerns
with construction operations on-going nearby. May cause
some delay.
Mazza, Paul Mitigate
monitors survey monuments on BDPLs throughout construction; consider contingency planning for Ops
access in the event that BDPLs fail and need to be
shut-down and repaired adjacent to construction. 483,000 866,000 1,249,000 $6,400 + office @ $100/day = $6,500/day + Standby Costs @ $21,000/day = $32,500. Total Daily Rate = $38,300/day. Standby costs include equipment, security, core crew costs, tunnel 2 - Unlikely 3 - Moderate 2 - Minor 11
Open
023 10 20
need for Ops access and repair.
Check functioning of submersible
pumps before planned shut-down. Contractor 9/1/2014 2/10/2015 Proposed
Check suppliers through Contractor to verify supply of available back-up
pumps.
Mues, Bob 9/1/2014 2/10/2015 Proposed
core crew costs, tunnel lighting & ventilation,
0
Open 9/1/2014 2 - Unlikely 0 - Contractor
Risk Operations Delay in shut-down
schedule. Ravenswood
Failure of the contractor supplied submersible pumps during disinfection of the pipe within
the tunnel.
3 - Moderate 0
Potentially weeks of delay while the pumps are either repaired or rental units are located; it might also result in re-disinfecting, etc.
Contractor Mitigate
Assure Contractor's submersible pumps are functioning well before the start of shut-down; check that
supplies of back-up pumps are readily available (if
needed).
0 0 0 Contractor Risk
0 2/10/2015
024 0
(S_schedule)
0 0 0
Safety Earthquake (Major) Bay Tunnel Act of God 1 - Rare 5 - Catastrophic 5 - Catastrophic
Temporary site facilities may be damaged. May have to re-excavate shaft and portions of Wong,
Johanna Open 8/5/2010 15 Accept
Implementation of Safety Plan.
0 0 0 Contractor Risk
3/2/2015 025
Ensure proper physical security elements (fencing,
barriers, gates, etc.) and ACAMS (access control and
monitoring system) are in place at all critical facilities. Communications (ensure safety plan, standard protcol)
Work with Ops on contingency schedule (either before or after) the
planned shut-down to see if alternate date can be found.
Wong, Johanna 9/1/2013 2/10/2015 Proposed
Assure Contractor has all
0 0 0
Safety Earthquake (Major) Bay Tunnel Act of God and portions of 1 - Rare 5 - Catastrophic 5 - Catastrophic
the tunnel to re-access. Integrity
of shaft and tunnel possisbly
compromised.
Johanna Open 8/5/2010 3/2/2015 15 0 0 0 Contractor Risk Accept Safety Plan.
025 Bomb, projectile of any kind, biological contamination etc. Physical damage or biological contamination to SFPUC Water System. Wong, Johanna Open
026 Security Terrorism - Direct Impact Bay Tunnel Mitigate
Mitigation and response through additional security and improved
emergency preparedness to avoid any damage that might result from a terrorism
event. 0 0 0 0 Contractor Risk 5 - Catastrophic 15 0 0 8/5/2010 3/2/2015 1 - Rare 5 - Catastrophic Bay Tunnel Operations or other projects don't allow shutdown to make tie in at Unable to complete tie in of Bay Tunnel (BDPL5) to Wong, Johanna 027 Operations Failure to meet contractual
shut-down schedule for Open 9/14/2014 2/10/2015 1 - Rare 2 - Minor 2 - Minor 4 30 300,000
Possible de-mob/re-mob of contractor or shift work to another contractor if the window is missed and
Mitigate
Keep current with WSIP program shut-down schedules, contingency
plans, and any
60 365 100,000 200,000
Assure Contractor has all required shut-down submittals in on schedule.
Mues, Bob 9/1/2014 2/10/2015 Proposed
make tie in at appropriate time. (BDPL5) to BDPLs 1 and 2. Johanna down schedule for