Project plan and time frame: Revised 6 June 2014
▪ Project manager BNG: Julie Nyland
▪ Project manager VA SA NT: Olympia Vozvotecas
▪ Project Management Group: members of the National Standards Working Group (NSWG – CEOs from VSA&NT, VT & VWA) ▪ Project Reference Group (PRG): 2 representatives from each jurisdiction.
TASK RESPONSIBILITY DATE: Week
Beginning
STATUS
Stage 1: Review and development of materials and accreditation system options 1 - 23
Consultants meet with National Standards Working Group (NSWG): Finalise project plan
Identify Project Reference Group (PRG) members
BNG/ NSWG 26 May Complete
Project Reference Group members selected and invited to participate - Contact list to BNG NSWG 2 June
Initial review of current standards BNG 9 – 23 June
Project Reference Group convened for teleconference to identify issues for content review NSWG with BNG 23 June Date to be set Draft review papers and accreditation system options addressing:
Content review questions for consultation Suggested broad content changes in standards Models and costing for accreditation system options
BNG 30 June – 14
July
Draft consultation questions for online survey BNG 7 July
National Standards Working Group meet to review survey content NSWG with BNG 14 July Date to be set
Consultation on draft review papers and accreditation system options via circulation of review papers to all stakeholders with invitation to respond online
NSWG/BNG 14 July – 8 Aug
Working session with Project Reference Group on draft review papers and accreditation system options BNG 4 Aug Date to be set
Report on review findings BNG 11 – 18 Aug
Project Reference Group meeting to discuss findings and recommendations BNG 25 Aug Date to be set
Draft revised standards and recommendations for accreditation system and submit to National Standards Working Group
BNG 25 Aug – 5 Sep
2 BREAKING NEW GROUND | ABN 41 948 817 923
BRADFIELD NYLAND GROUP & BNG NGO SERVICES ONLINE| June, 2014
TASK RESPONSIBILITY DATE: Week
Beginning
STATUS National Standards Working Group meet to discuss:
▪ Draft revised standards and recommendations for accreditation system ▪ User test group participants
BNG & NSWG 22 Sep Date to be set (poss with PRG
w/b 29 Sep) Project Reference Group teleconference to provide feedback on draft evidence guides and
self-assessment tools
BNG 29 Sep Date to be set
VA sign off on revised standards NSWG 6 Oct
Finalise draft evidence guides and self-assessment tools incorporating Project Reference Group feedback
Submit final evidence guide and self-assessment materials to National Standards Working Group Finalise revised standards following VA sign off
BNG 29 Sep – 13 Oct
National Standards Working Group meet BNG & NSWG 20 Oct Date to be set
VA sign off on draft evidence guides and self-assessment tools NSWG 27 Oct
Finalise materials for user testing BNG 27 Oct – 7 Nov
Finalise materials related to accreditation system BNG 27 Oct – 7 Nov
Stage 2: User testing and finalisation of materials 23 – 36
Invite individuals to user test NSWG or BNG? 6 Oct
User testing BNG 10 -28 Nov
Review feedback and finalise materials BNG 1 – 12 Dec
National Standards Working Group (and Reference Group ?) meet BNG/ NSWG 15 Dec Date to be set
Layout of materials NSWG Mid – late Jan
2015
Stage 3: Launch of standards and accreditation program 37 - 38
Information/training session for State/Territory CEOs and VA representatives BNG Feb 2015
Webinar program for general volunteer organisations BNG Feb 2015
Roll out of accreditation program - Details and timing will depend on model adopted NSWG
3 BREAKING NEW GROUND | ABN 41 948 817 923
BRADFIELD NYLAND GROUP & BNG NGO SERVICES ONLINE| June, 2014
Project Reference Group: Meeting dates and commitments
The role of the Project Reference Group will be to review and provide comment and advice on: ▪ the issues to be considered in the review of the Standards
▪ the content of a draft set of revised Standards ▪ the options for an accreditation system
▪ support materials for organisations using the standards (evidence guides and self-assessment tools)
Activity Date Approximate time
commitment
Teleconference to identify issues for content review W/b 23 June 1.5 hrs
Review draft review papers and accreditation system options 21 July – 1 August 3 hrs Working session with Project Reference Group on draft consultation review papers and
accreditation system options
W/b 4 August 2.5 hrs if teleconference 1 day if face to face Teleconference to discuss findings of consultation and BNG recommendations on
revised Standards and the accreditation system
W/b 25 August 2 hrs Review draft evidence guides and self-assessment tools 16 – 26 September 4 hrs Teleconference to provide feedback on draft evidence guides and self-assessment tools W/b 29 September 2 hrs Possible teleconference to review results of user testing W/b 15 December 1.5 hrs
4 BREAKING NEW GROUND | ABN 41 948 817 923
BRADFIELD NYLAND GROUP & BNG NGO SERVICES ONLINE| June, 2014
5 BREAKING NEW GROUND | ABN 41 948 817 923
BRADFIELD NYLAND GROUP & BNG NGO SERVICES ONLINE| June, 2014