• No results found

Site Inspection Check List2

N/A
N/A
Protected

Academic year: 2021

Share "Site Inspection Check List2"

Copied!
38
0
0

Loading.... (view fulltext now)

Full text

(1)

AGIP Oil Co. Ltd.

Libyan Branch

El Sharara-Mellitah 30” Pipeline

P

ETRO

J

ET

Libya

DOC. No. : 0222-160-P-PT-PTJ-0027

REV. No. : A2

Page 36 of 36

EL SHARARA-MELLITAH 30

EL SHARARA-MELLITAH 30

” PIPELINES

PIPELINES

CONTRACT NO. 222

SITE INSPECTION CHECK LIST

Document No.

0222-160-P-PT-PTJ-0027

A2

02/01/05

Issued for final approval

A1

23/12/04

Issued for approval

M. Elamir

A. Khater

Samir Helmi

E. Trovato

(2)

Inspection Check List Register

No

.

Control

Doc.

No.

Description

Rev.

Remarks

1

FQ-001

PRE-CONSTRUCTION SURVEY

A2

2

FQ-002

PIPE HANDLING AND TRANSPORTATION

A2

3

FQ-003

ROW CONSTRUCTION

A2

4

FQ-004

STRINGING

A2

5

FQ-005

LINING-UP, CLAMPING & WELDING

A2

6

FQ-006

WELDING /Pipe Lines- WELDING /Tie –ins

A2

7

FQ-007

NON-DESTRUCTIVE TESTING-RT

A2

8

FQ-008

NON-DESTRUCTIVE TESTING-UT

A2

9

FQ-009

NON-DESTRUCTIVE TESTING-PT & MT

A2

10

FQ-010

NON-DESTRUCTIVE TESTING-VT

A2

11

FQ-011

TRENCHING

A2

12

FQ-012

COATING PART1–FIELD JOINT COATING HSS &

REPAIRING OF PIPE COATING

A2

13

FQ-013

BEDDING & PADDING

A2

14

FQ-014

LOWERING-IN

A2

15

FQ-015

FOC LAYING

A2

16

FQ-016

HYDROSTATIC TESTING

A2

17

FQ-017

DRYING & NITROGEN FILLING (HOLD)

-18

FQ-018

COLD BENDING

A2

19

FQ-019

CROSSING

A2

20

FQ-020

CIVIL WORK

A2

21

FQ-021

CATHODIC PROTECTION

A2

22

FQ-022

ELECTRICAL INSTALLATION

A2

23

FQ-023

INSTRUMENT INSTALLATION

A2

24

FQ-024

COATING PART II-COATING FOR GROUND &

UNDERGROUND FACILITIES

A2

25

FQ-025

PIGGING & CLEANING

A2

26

FQ-026

REINSTATEMENT OF ROW AND RESTORATION WORK

A2

27

FQ-027

MECHANICAL INSTALLATION

A2

AGIP Oil Co. Ltd.

Libyan Branch

El Sharara-Mellitah 30” Pipeline

P

Libya

ETRO

J

ET

DOC. No. : 0222-160-P-PT-PTJ-0027

REV. No. : A2

Page 36 of 36

(3)

28

FQ-028

BACKFILLING

A2

29

FQ-029

PAINTING ABOVE GROUND

A2

30

FQ-030

PRE-COMMISSIONING (FOR INSTRUMENT SYSTEM)

A2

31

FQ-031

PRE-COMMISSIONING (FOR ELECTRIC SYSTEM)

A2

32

FQ-032

PRE-COMMISSIONING (FOR CATHODIC PROTECTION SYSTEM)

A2

33

FQ-033

HYDROTEST LVS and PTS (HOLD)

-34

FQ-034

MATERIAL/EQUIPMENT INSPECTION, RECEIVING AND

STORAGE

A2

PRE-CONSTRUCTION SURVEY

Location/Area

Pipe Size

Report No.

Alignment Sheet No. :

From : To :

Morphology Situation :

Plain □ Hill □ Desert Land □ Sand Dunes □ Rocky Area □ Wadi □

Type of Vegetation : Open View □ Cultivated □ Desert □

Control Doc. No. : FQ-001

Control Doc.

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1. Instruments & tools Performance of measuring instrument and tools meet technical specification. 2. Centerline location Check-up the information of centerline location and measurement. 3. Stakes

Each stake is clear, in right location and in right color (type): 1) Centerline Stake - steel bar (black)

2) Edge Stake - red flag 4.Underground

obstacle

Site mark of underground obstacle is clear. 5. Interval of each

stake

1) Centerline Stake - steel bar (black) 2) Edge Stake - red flag

(4)

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(5)

PIPE HANDLING AND TRANSPORTATION

Location/Area

Pipe Size

Report No.

From :

To :

Control Doc. No. : FQ-002

Activities

Control Requirements or Accept Criteria

Inspection

Record

Remind

1.Pipe acceptance The pipe length and the trim size are complied with the Contract. (Spot Check). 2.Inspection

1) Coating of the pipes 2) Bevel

3) Pipe identification mark 4) Coating Visual Inspection 3.Storage and

preservation

The lifting tools are covered with soft material to prevent damage of the coating and bevel.

4.Bevel Protection

The bevel ends of the pipe are protected with bevel protector during handling and stocking.

5.Supports The supports on the truck shall meet the requirement and shared the weight equally. The supports are covered with soft material. 6.Security The secure belts or other facilities are sufficient to fasten pipes during transportation. 7.On trail

On each trail:

1) 30″pipes are no more than 3 tires.

8.Pipe stockpiling area in

marshalling

1) Be level off, tamped and cleaned.

2) The drainage and anti-rolling measures are ready prior pipes are stocked. 3) The height of the sand ridge is no less than 200mm.

4) Pipes are piled in types.

5) 30″pipes are no more than 4 tires. 6) The damaged pipes are separated.

9.Pipe stockpiling area on site

1) Be clear from vegetation, stubble, stones and flattened.

2) The location is kept at least 50m from vertical projection on the ground of overhead power line conductors.

3)The minimum distance from the ground to the bottoms of pipes is 200mm. 4) The pipes are piled on sand bags or sand ridge with sand bags.

5) Anti-rolling measures are taken.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor Company

Name

Signature

Date

(6)

ROW CONSTRUCTION

Location/Area

Pipe Size

Report No.

Alignment Sheet No.:

From : To :

Morphology Situation:

Plain □ Hill □ Desert Land □ Sand Dunes □ Rocky Area □ Wadi □

Excavated Material: To Dump Area □ Piled Up □ Screen Plant □

Control Doc. No. : FQ-003

Activities

Control Requirements or Accept Criteria Inspection Record

Remind

1.ROW width The width of the ROW is 30m when pipelines are installed separate trenches, 25m when pipelines are installed the same trench.

2.Underground obstacle

The warning signs for the underground obstacle are in the right location and clear.

3.Cleaning The ditches, dikes and steep slopes are cleared up to comply with the requirements of construction.

4.High/low points removal

The sharp high points and low points are removed to allow bending and laying of pipelines in accordance with the approved drawing.

5.Water Crossing The water crossing prevention measures for the ditches are checked.

6.Vehicle access Graded vehicle access strip is acceptable.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

Note: Activities record format is duly filled and signed.

(7)

Location/Area

From :

Pipe Size

To :

Report No.

Morphology Situation:

Plain □ Hill □ Desert Land □ Sand Dunes □ Rocky Area □ Wadi □

Work Area Characteristic: Sandy Area □ Sandy/Rocky Area □

Control Doc. No. : FQ-011

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1.Centerline The ditching is excavated follow the right centerline stakes. 2.Warning sign The warning signs for the underground /ground facilities are

obvious. 3.Minimum cover

1) Loose soil areas 1.000 m.

2) Rocky areas as per AGIP specs no. 3435-160-C-SP-TEK-00003, item 6.3

3) Cultivated areas 1.500 m.

4.Dimensions The dimensions (depth, width and slope ratio) of the ditch are complied with the procedure.

5.Cleaning The ditch is cleaned to prevent pipe coating damage. 6.Soil piling The excavated soil is piled 1m away from the edge of ditch. 7.Protective measures

When the route is close to/on the underground facilities, Company properties, private properties and Government properties, approved protective measures are taken. 8.High water table In the area with high water table, water in ditch is drained in

time.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

Note: Activities record format is duly filled and signed.

(8)

Location/Area

Pipe Size

Report No.

Alignment Sheet No.:

From : To :

Control Doc. No. : FQ-004

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1. Pipe size The pipe size is complied with the specifications of drawings before stringing.

2. Off loading When off loading pipes, there are protection measures for the pipe ends.

3. Gap There is a gap every 500 m.

4. Safe distance Pipes are stringed over 1.0 m away from edge of the trench bank.

5. Slope area

In the case of stringing in slope area:

1) If the slope is greater than 15°: the stringing is done accordance with the progress of welding.

2) If the slope is greater than 30°: pipes are strung in trench.

6. Longitudinal weld The longitudinal weld of the pipe is positioned within ±30°from the 0’clock position.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(9)

LINING-UP AND CLAMPING & WELDING

Location/Area

Pipe Size

Report No.

From : To :

Control Doc. No. : FQ-005

Activities

Control Requirements or Accept Criteria

Inspection

Record

Remind

1. Pipe size The pipe size is correct. 2. Pipe cleaning

Before lining-up, the pipe ends are clean no less than 30mm from the end surface. The cleaning Crew is no more than 5 welds ahead of welding Crew. The pipes are cleaned from inside too.

3. Bevel face The bevel is cleaned and the dimensions are correct.

4. Bevel repairing Damaged pipe ends and bevels are repaired as per the procedure. 5. Clamp removing

The clamp is removed after.:

1) Full root bead is completed when internal clamp is used. 2) More than 60% of the total length of the root bead when external clamp is used.

6. High-low The high-low of the pipe with same wall thickness is no more than 2mm (in small section, at maximum 3mm is allowed).

7. Pipe piece The pipe piece is longer than twice of the pipe diameter or 1m. 8.Longitudinal weld . The longitudinal welds of the 30” pipes are positioned within

±30°from 0 o’clock and offset more than 200mm. 9.Support

The aligning pipes are supported and fixed on the load-bearing structural wood skids with sand bags. (Remove the skids after the welding).

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor Company

Name

Signature

Date

(10)

WELDING

P/L

Location/Area

Pipe Size

Report No.

Alignment Sheet No.:

From : To :

Control Doc. No. : FQ-006

Activities

Control Requirements or Accept Criteria

Inspection

Record

Remind

1.Welder qualification The re-welding is performed as per the specifications. The welder is qualified.

2. Welding material

1) Electrodes, wire used in the pipeline welding are maintained and used in accordance with the manufacturer instructions.

2) Low hydrogen type electrode is baked out before welding, the baking temperature and duration as specified by the manufacturer. Backed electrodes are stored in the insulation tank on site. 3) Electrodes baked for two times shall not be used in the site welding.

3.Welding equipment All the welding equipments are used under good and safe conditions. 4.Welding environment

The welding will stop in the:

-Very strong wind (As per welding inspector company) -Raining or relative humidity > 90%

5. Pipe preparation 1) The pipe is cleaned inside.

2) The damaged bevel and pipe ends are identified and repaired. 6.Pre-heating

Pre-heating temperature is at 100±20℃ for ND30” pipeline WT more than 12,7mm, or the ambient temperature is below 0℃. Except above, it is Pre-heated at 40—50℃ when the pipe ends are wet, raining or high humidity. The pre-heating range is at least 100mm from pipe ends.

7.Welding

1) Remove internal line up clamp after the first root pass finished; remove external line up clamp after 60% of root pass completed.

2) The cleaning among runs is completed properly. 3) Preheat 100℃.

8.Welds inspection

1) The surface of weld is free of defect such as scatter, welding slag, surface air bubble, non-fusion and undercut, etc. It shall be cleaned if any.

2) High-low: the pipe with same wall thickness is no more than 1.6mm (in small section, at maximum 3mm is allowed).

3) The longitudinal welds of the 30” pipes are positioned within ±30°from 0 o’clock and offset more than 200mm.

9.Parent material repair

The small defects or damaged areas on the base metal tested by NDT is repaired and eliminated by grinding. The allowed wall thickness decrease and welds repairing is in accordance with the applicable specifications and standards.

10.NDT Welds are inspected with specified NDT method and accepted in accordance with the specified criteria.

11.Repair & re-inspection All the rejected welds are repaired and re-inspected according to WPS. 12.Weld mark Welds are marked in accordance with the procedure.

13.Seal The welded pipeline is sealed with proper cover to prevent foreign mater entering.

Inspection Conclusion Proceeding work: YES

□ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company Welding Inspector

Name

Signature

Date

(11)

Location/Area

Pipe Size

Report No.

From : To :

Control Doc. No. : FQ-007

Activities

Control Requirements or Accept Criteria

Inspection Record Remind

1.Operator qualification Verify the Certificates of the RT operators. 2.RT equipments Verify the Certificates of the RT equipments.

3.RT operation Operation is carried out in accordance with the approved RT procedure.

4.Darkroom treatment The films are developed and fixed in accordance with the procedure.

5.Film quality

1) The sensitivity is proper 2) The density range is 2.0-3.5

3) Free of mechanical and chemical damage.

6.Films interpretation Films are interpreted in accordance the specified acceptance criteria.

7.Report All records and testing results shall be documented. 8.Film storage All films shall be kept properly till hand-over to Company.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company Welding Inspector

Name

Signature

Date

(12)

NON-DESTRUCTIVE TESTING-UT

Location/Area

Pipe Size

Report No.

From : To :

Control Doc. No. : FQ-008

Activities

Control Requirements or Accept Criteria Inspection Record

Remind

1.Operator qualification Verify the Certificates of the UT operators. 2.UT equipments Verify the Certificates of the UT equipments.

3.UT operation Operation is carried out in accordance with the approved UT procedure. 4.Indication interpretation Indication is interpreted in accordance the specified acceptance criteria. 5.Report All records and testing results shall be documented.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company Welding Inspector

Name

Signature

Date

(13)

NON-DESTRUCTIVE TESTING-PT/MT

Location/Area

Pipe Size

Report No.

From : To :

PT

□ MT □

Control Doc. No.: FQ-009

Activities

Control Requirements or Accept Criteria Inspection Record

Remind

1.Operator qualification Verify the Certificates of the operators.

2.Material & equipments Verify the Certificates of the material and equipments. 3.Operation Operation is carried out in accordance with the approved

procedure.

4.Indication interpretation Indication is interpreted in accordance the specified acceptance criteria.

5.Report All records and testing results shall be documented.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company Welding Inspector

Name

Signature

Date

Note: Activities record format is duly filled and signed.

(14)

Location/Area

Pipe Size

Report No.

From : To :

Control Doc. No.: FQ-010

Activities

Control Requirements or Accept Criteria

Inspection

Record

Remind

1.Welding inspection

1) The surface of weld is free of defect such as scatter, welding slag, surface air bubble, non-fusion and undercut, etc. It shall be cleaned if any.

2) High-low: the pipe with same wall thickness is no more than 1.6mm (in small section, at maximum 3mm is allowed). 3) The longitudinal welds of the 30” pipes are positioned within ±30°from 0 o’clock and offset more than 200mm. 2.Material & equipments Verify the Certificates of the material and equipments and technicians. 3.Operation Operation is carried out in accordance with the approved procedure. 4.Indication interpretation Indication is interpreted in accordance the specified acceptance criteria. 5.Pipe class From the different pipe wall thickness shall be grinded ¼ of

groove as per ANSI/ASME B31.4

6.Report All records and testing results shall be documented.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company Welding Inspector

Name

Signature

Date

Note: Activities record format is duly filled and signed.

(15)

Location/Area

Pipe Size

Report No.

From : To :

Control Doc. No. : FQ-012

Activities

Control Requirements or Accept Criteria

Inspection

Record

Remind

1.Operator

qualification Only qualified operators are employed to apply shrink sleeves on site. 2.Equipments and

tools

The liquefied gas heater is used for heating, flame spray burning blower is in normal condition.

3.Material

1) Supplied with qualified certificate of inspection and instruction manual. 2) Be stored in a dry ventilated area.

3) Keep products sealed in original packing and avoid exposure to direct sunlight, rain, dust or other adverse environmental elements.

4) The storage temperatures of coating materials as per vendor instructions. 4.Pipe ends

cleaning

Within the length of 50 mm on weld joint on both sides are free from oil dirt, soil scar, slag, spatters.

5.Surface treatment of pipe joint

1) The mainline coating edges are beveled to 30. 2) Warm the joint area to 40-50℃ before grit blasting.

3) The width of sand blasting to the coating is no less than 85mm: 6.Appliciation of

epoxy primer

Apply mixed epoxy to a minimum uniform thickness of 4 mils on all exposed bare metal and less than 10 mm onto the adjacent pipe coating in width.

7. Pre-heating Preheat the epoxy and the abraded coating to85℃—95℃ in the whole circumference.

8.Installation and

location of tape Install the tape in accordance with the procedure.

10.Checking and inspecting

1) No cracks or holes in sleeve backing.

2) The overlap of the tape on the existing coating shall be at least 50 mm in both sides.

3) Holiday detection with 20kv voltage of leakage detection. 4)U.T. for thickness painting / Surface profile comparator 5) Destructive testing (Peel Test) (Adhesion of top coated system)

12.Repairing of

pipe coating Repair the pipe coating in accordance with procedure.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(16)

BEDDING & PADDING

Location/Area

Pipe Size

Report No.

Alignment Sheet No. :

From : To :

Control Doc. No. : FQ-013

Activities

Control Requirements or Accept Criteria

Inspection

Record

Remind

1.Bottom situation of trench

1) The water has been drained completely.

2) In soft ground section, the soil at the bottom of trench meet the requirement of bedding and trench bottom level; or

3) Laying bed have finished and leveled up.

2.Material

1) The laying bed is consist of fine graded soil or sand with the maximum particle size of 0-5mm in 75% corresponding proportion, 5-15mm in 15% and 15-20mm in 10%.

2) The padding material is crushed and screened before used in rock area if the material is come from the excavated material, and it should meet the requirement of work procedure.

3.Thickness of bedding

The bedding thickness is at least 200mm along the ditch bottom.

4.Padding and FOC protection

1) As-built survey has been carried out and recorded and then 300mm more fine material is padded on the FOC, at least 300mm is padding on pipe.

300mm of fine material is padded on the top of the pipe before laying FOC and then 300mm more fine material is padded on the FOC and pipe.

5.Room left for tie-in

Pipe at each side of tie-in and FOC joints are left exposed a certain length for operation and padded later.

6.Pipeline anchor In high slope the pipeline is anchored with sand or soil bags and the upper and lower part of the block is compact solidly. 7.Open-cut crossing Bedding and padding is carried out in open-cut crossing area meets the drawings TPYE in the procedure.

** Item 4 and 5 : signature by FOC inspector

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(17)

LOWERING-IN

Location/Area

Pipe Size

Report No.

Alignment Sheet No. :

From : To :

Morphology Situation:

Plain □ Hill □ Desert Land □ Sand Dunes □ Rocky Area □ Wadi □

Type of Vegetation: Open View □ Cultivated □ Desert □

Control Doc. No. : FQ-014

Activities

Control Requirements or Accept Criteria

Inspection

Record

Remind

1.Ditch dimensions The dimensions (depth, width and slope ratio) of the ditch are complied with the procedure. 2.Dithc cleaning The ditch is cleaned to prevent pipe coating damage.

3.Holiday detection There is no holiday under

4.Pre-check There are no person, equipment and tools in the ditch. There are no one standing, no construction material or tools placed between the pipeline and ditch. 5.Pipe ends

protection The pipe ends are sealed with cups to prevent ingress of foreign objectives. 6.Lifting

equipments & tools

The lifting equipments and tools are under good conditions as per HSE specs.

7.Lower-in

4 sidebooms , space 20m, are used to lower-in the 30″pipe, the maximum height for the pipeline lift above the ground and above the bottom of the ditch is less than 1m.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(18)

FOC LAYING

Location/Area

Report No.

From : To :

Morphology Situation:

Plain □ Hill □ Desert Land □ Sand Dunes □ Rocky Area □ Wadi □

Type of Vegetation: Open View □ Cultivated □ Desert □

Control Doc. No. : FQ-015

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1.Visual check 1) Type of the FOC is complied with the drawing. 2) No damage and distortion of the reel and cable

2.Depth & location The depth & location of the FOC is complied with the procedure.

3.Caution tape Caution tape is buried above the FOC. 4.Tie-in of FOC Tie-in of FOC is complied with the procedure. 5.Spare cable Enough spare cable is left.

** Signature by Company FOC inspector

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(19)

HYDROSTATIC TESTING

Location/Area

From :

Control Doc. No. : FQ-016

Pipe Size:

To :

Report No.

DRYING & NITROGEN FILLING (OPTION)

Location/Area

Pipe Size:

Report No.

From : To :

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1.Water treatment Testing water should answer for the requirement of the criterion/specification after test and approved by Company. 2.Testing system The testing system should be installed and inspected according to relative procedure. 3.Work permit Inform Company and get the Work permit after Testing system qualified. 4.Testing Testing should follow the procedure, and record the changes of all of the relative parameters. 5.Drainage Draining should answer for the Testing procedure and HSE

procedure.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(20)

Control Doc. No. : FQ-017

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1.Equipment & ganges

1) The instruments and equipments used in the process of vacuum drying and nitrogen filling are answer for the requirement of work procedure.

2) Pressure gauge and sensor and other instruments indispensable shall be examined and acceptable.

2.Vacuum drying

1) The installation of vacuum drying system is acceptable 2) Leak check is acceptable.

3) Final pressure is acceptable. 3.Records and

reports for drying All records and reports are accomplished according to the requirements of work procedure. 4.Preparation for

nitrogen filling The equipments for nitrogen filling having been installed properly and vacuum drying accomplished acceptable. 5. Nitrogen inspect Purity and dew point of nitrogen are acceptable and be record. 6.Pressure inspection There is no less than 95% of nitrogen inside of pipeline trunk

with a pressure of 0.5 bar as minimum.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(21)

COLD BENDING

Location/Area

From :

Pipe Size:

To :

Report No.

Control Doc. No. : FQ-018

Activities

Control Requirements or Accept Criteria

Inspection

Record

Remind

1.Pipe size The pipe type and size is complied with the drawing.

2.Pipe coating The coating shall be free from bubbles, pits, wrinkles and with uniform color. 3.Mandrel position The accuracy of the mandrel position is kept with pre-set rods (the rod at the center point of bending machine and the rod close to the lift tongue). 4.Wall thickness

reduction

Use a pachometer to test the Wall thickness reduction at trial-produce phrase of cold bending:

1) 5 points on the outer arc of the bending section.

2) The wall thickness reduction is no less than 95% of the originate wall thickness.

5.Straight section length

The length of the straight section is not less than 1.5m from the open end of the bended pipe.

6.Out of roundness The Out-of-roundness is not more than 2% of the outside diameter of the pipe at any point. 7.Bend coating Visual and holiday detection of the bend coating.

8.Identification Check the identification of the bend.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(22)

CROSSING

Location/Area

From :

Pipe Size:

To :

Report No.

Control Doc. No. : FQ-019

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1.Preparation

1) All of the underground facilities are located in and/or near crossing location.

2) All necessary information (drawing, distance, depth, structure and geological condition etc.) are provided to the working spread.

3) Proper warning signs and temporary road are ready in the crossing area.

4) Ditching depth meets the design requirement.

2.Equipments All of the equipments used for crossing are in good condition. 3.Casing installation The casing pipes for mainline and FOC are installed according to the construction procedure.

4.Inspection *

1) Offset of crossing centerline is acceptable. 2) The benchmark of crossing is correct.

3) 100% of NDT for the mainline joints are acceptable. 4) Hydrostatic testing is up to grade.

5) Electrical insulation test is carried out and acceptable according to the procedure.

6) Holiday inspection is acceptable

** Item 3 : Signature by FOC inspector

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(23)

CIVIL WORK

Location/Area

From :

Control Doc. No. : FQ-020

Report No.

To :

Note: Activities record format is duly filled and signed.

Activities

Control Requirements or Accept Criteria

Inspection Record Remind

1.Construction drawing Construction drawings be used in the work site are approved by Company and they are the latest version.

2.Mateirial inspection All of the materials be used in the construction are inspected and qualified.

3.Ground leveling and location measurement

1) Obstacles underground are all fixed and marked.

2) Obstacles aboveground are all removed, and ground level achieve to the requirement of drawings.

3) Survey and measurement of location are carried out as per the procedure, and such work be affirmed.

4.Equipment foundation construction

Equipment foundation construction be carried out as per the regulation of procedure.

5. Road construction Road construction be carried out as per the regulation of procedure.

6.Undergroun building

1) Underground building construction be carried out as per the regulation of procedure.

2) Floating floor installation meets the requirement of the design.

7.Aboveground building

1) Aboveground building construction be carried out as per the regulation of procedure.

2) Laying of external wall tiles meet the requirement of the design.

8.Fence construction Fence construction be carried out as per the regulation of procedure. 9.Tests and records

1) All of the inspections and tests are completed as per the procedure.

2) All of the relative records are made out and pass muster.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(24)

CATHODIC PROTECTION

Location/Area

Pipe Size:

Report No.

From : To :

Control Doc. No. : FQ-021

Note: Activities record format is duly filled and signed.

Activities

Control Requirements or Accept Criteria

Inspection Record Remind

1.Material and equipment

All of the material and equipment should be qualified according to the engineering documentation and/or other requirement and proved with relative certificates.

2.Seat testing pile position

The location of testing pile should meet the requirement of approved drawings.

3.Installation (testing pile/ equipment)

1) Treating of the cable ends answer for the requirement of procedure. 2) The location of welding point is at the correct place.

3) Steel pipe/casing surface treatment is qualified. 4) Tools and materials for welding are correct.

5) The connection of cable to pipe/casing/testing pile/anode is correct. 6) Sacrificial anodes are installed correct

7) The coating of all joints are qualified.

8) Installation and debugging of all equipments for cathodic protection should be up to mustard.

4.Testing

1) The resistance between welding point and steel pipe/casing shall not more than 0.1 Ohm.

2) All joints are acceptable through holiday inspection.

3) The potential testing that be carried out according to the procedure is up to the mustard.

4) The system debugging is completed and acceptable.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(25)

ELETRICAL INSTALLATION

Location/Area

From :

Report No.

To :

Installing facility:

No.:

Control Doc. No. : FQ-022

Activities

Control Requirements or Accept Criteria

Inspection Record Remind

1.Cable Laying

Cable laying order, route comply with construction

drawing, the insulation resistance between cable and

grounding is not less than 500MΩ

2.Grounding

System

Grounding trench depth more than 800MM, Tie-in with

grounding electrodes and grounding line fastness, the

grounding resistance is not more than 10Ω.

3.Power

Distribution

Panel

The position of PDP's construction is comply with

construction drawing required.

4.Lighting

The loops of lighting are right, haven't short circuit

between different loops and haven't grounding of the

loops. the lighting system work right.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(26)

INSTRUMENT INSTALLATION

Location/Area

From :

Report No.

To :

Installing facility:

No.:

Control Doc. No. : FQ-023

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1.Preparation for construction

1. Construction environment meets requirement. 2. Equipment and tools for installation are ready.

3. Check the type, certification and instruction of installed equipment material.

4. Pre-fabrication field is ready (if necessary)

2.Instrument installation

1. Local instrument, remote instrument, level instrument, electrical actuator, fire spy head, fuse cable, and other kind of instrument installation is according to corresponded installation flowchart and procedure.

2. Installation location is correction as per corresponded drawings.

3. Record. 3.The connection of

the instrument to process

Allocation an installation of connection of the instruments to process meet requirements.

4.Installation of support

Supports prefabricate and install as per corresponded drawings and procedure.

5.Cables and junction

1. Location of digging, laying of cables, installing of conduits and junction boxes are correct.

2. Record.

6.Earthing Every location needing earth is connected to the earthling network and connecting is good.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(27)

COATING PART II-COATING FOR GROUND & UNDERGROUND FACILITIES

Location/Area

: Pipe Size:

Report No.

From :

Control Doc. No. : FQ-024

To :

Note: Activities record format is duly filled and signed.

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1.Preparation of coating

1) Coating material is qualified.

2) The tool is suitable for coating operation.

3) Facility/parts of the system that will be coated has a qualified surface treatment.

4) Work circumstance answer for the requirement. 2.Coating

operation

Coating operation accord with procedure or the regulation of manufactory.

3.Inspection in coating

1) Visual check is acceptable. (As per Surface profile comparator

2) Holiday inspection is acceptable. 3) Thickness inspection is acceptable 4) Peel test is acceptable (if need).

4.Repair All of the repair have finished and acceptable.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(28)

PIGGING & CLEANING

Location/Area

Pipe Size:

Report No.

From : To :

Control Doc. No. : FQ-025

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1.Pig and pig traps

1) Pigs for cleaning and gauging are answer for the requirement of work procedure.

2) Pig receiver and pig launcher are installed correctly. 2.Cleaning system

installation

Pig cleaning system and the relative equipments and instruments are installed properly in good state.

3.Inspection The gauging plate shall be examined and taken photos immediately after the pigs have get from pig receiver.

4.Record and report Records and reports for the process of pig cleaning and gauging have been accomplished according to the work procedure.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(29)

REINSTATEMENT OF ROW AND RESTORATION WORK

Location/Area

Pipe Size:

Report No.

From : To :

Morphology Situation: Plain □ Hill □ Desert Land □ Sand Dunes□ Rocky Area □ Wadi□

Type of Vegetation: Open View □ Cultivated □ Desert □

Control Doc. No. : FQ-026

Note: Activities record format is duly filled and signed.

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1.Reinstatement of ROW

1) Public\ private lawns or courtyards or entrances etc. in the ROW have the same or better condition than before.

2) The cropland and water supply and drainage system and walls/fences which be destroyed are all be reinstated and acceptable.

3) All the residual materials and waste materials are moved to the proper place.

4) The original physiognomy in other place are all be reinstated.

5) The bund on the trench is acceptable. 2.Reinstatement of

banks and embankments

The banks and embankments which be destroyed are all reinstated and acceptable.

3. Photograph The reinstatement of physiognomy be proved by essential photographs. 4.Pipeline marker posts

and warning signs

The marker posts (KP posts, CP posts etc.) and warning signs are all setup and installed according to the relative requirement and acceptable.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(30)

STATION MECHANICAL INSTALLATION

Location/Area

From :

Report No.

To :

Control Doc. No. : FQ-027

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1.Acceptance to Equipment, fitting & material

All equipments, fitting and material meet the requirements of engineering and the quality certificates and/or calibration certificates are the evidence.

2.Cleaning The piping system should be cleaned before the installation of equipments and fittings. 3.Inspection to the

base of the equipment

Inspect the center line of equipment base. 4.Installation to the

equipment, fitting and auxiliary

1) The installation to equipment and fitting accordant correspond with the related procedure.

2) Station weld meets the requirements of the related WPS for station

5. Inspection* 1) Visual check is acceptable 2) Dimension check is acceptable 3) NDT check is acceptable

6. Record and report Records and reports for the process of installation have been accomplished according to the work procedure.

** Item 5 : Signature by company welding inspector

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(31)

BACKFILLING

Location/Area

Pipe Size

Report No.

Alignment Sheet No. :

From : To :

Morphology Situation:

Plain□ Hill□ Desert Land□ Sand Dunes□ Rocky Area□ Wadi□

Control Doc. No. : FQ-028

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1.Backfilling material

1) There is no stones in which the diameter more than 150mm 2) The surface material answer for the requirement of original morphology situation.

2.Shape The shape of ground meets the requirements of work procedure after backfilling. 3.Residual material Residual material has been disposed in proper methods acceptable. 4.Backfilling high The crown high above trench cannot be more than 300mm

except in cultivated area. 5.Room left for tie-in

and FOC joints*

pipe at each side of tie-in and FOC joints are left exposed a certain length for operation and padded later.

6.Pipeline anchor In high slope the pipeline is anchored with sand or soil bags and the upper and lower part of the block is compact solidly. 7.Crossing area The backfilling soil in crossing area meets the requirement of design.

** Item 5 : Signature by FOC inspector

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(32)

PAINTING ABOVE GROUND

Location/Area

From :

Report No.

To :

Control Doc. No. : FQ-029

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1.Preparation of painting

1) The tool is suitable for painting operation

2) Facility/parts of the system that will be painted has a qualified surface treatment

3) Surface roughness test is acceptable

2.Painting operation Painting operation accord with procedure, specifications and regulation of manufactory. 3.Inspection in

painting

1) Visual check is acceptable 2) Thickness check is acceptable 3) Destructive tests is acceptable 4) Check of adhesion is acceptable 4.Repair All the repair have finished and acceptable

**Note : Signature by painting inspector contractor

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(33)

PRE-COMMISSIONING (FOR INSTRUMENT SYSTEM)

Location

From :

Report No.

To :

System :

Control Doc. No. : FQ-030

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1. Preparation prior to pre-commissioning

1) Mechanical completion is ready 2) Personnel for pre-commission are ready. 2. Pre-commissioning

All equipments are subjected to the following tests •The connections and continuity test

•Insulation test

•Verify every instrument in good condition and calibration. 3. Record Each record required is ready

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(34)

PRE-COMMISSIONING ( FOR ELECTRIC SYSTEM)

Location

From :

Report No.

To :

System:

Control Doc. No. : FQ-031

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1.Preparation prior to pre-commissioning

1) Mechanical completion is ready 2) Personnel for pre-commission are ready.

2.Pre-commissioning

Check and test following items: •Solar panels unit

•Control board

•Low voltages switchboard (D.C or A.C.) •Storage battery

•Trailer-movable diesel generator •Rectifier cabinet

3.Record Each record required is ready

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(35)

PRE-COMMISSIONING (FOR CATHODIC PROTECTION YSTEM)

Location

From :

Report No.

To :

System:

Control Doc. No. : FQ-032

Activities

Control Requirements or Accept Criteria

Inspection Record

Remind

1.Preparation prior to pre-commissioning

1) Mechanical completion is ready 2) Personnel for pre-commission are ready.

2.Pre-commissioning

Check and test following items:

•Insulating joints and casing protection pipes •Reference cells and test points

•Ground beds •DC feeders (TR/R) •Electrical cables •Pipeline natural potential 3.Record Each record required is ready

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(36)

HYDROTEST LVS and PTS

Number of LVS and PTS

From :

Report No.

To :

Control Doc. No. : FQ-033

Activities

Control Requirements or Accept

Criteria

Inspection

Record

Remind

1.Water for Pressure Test

The water for pressure test comply with the requirement of procedure.

2.Testing System

The pressure test system shall be installed and checked according to the related procedure and obtained Company’s approval.

3.Testing Pressure

During testing it shall be in accordance with the requirement of the procedure and the pressure comply with the procedure.

4. Dewatering Dewatering shall be in accordance with the Testing procedure and HSE procedure after testing.

5. Record Each record required is in accordance with the requirement.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(37)

Purchase Order No. :

Goods Name :

Packing List No. :

Report No. :

Control Doc. No. : FQ-034

Activities

Control Requirements or Accept Criteria

Inspection

Record

Remind

1.Acceptance of material and equipment

The material and/or equipment are inspected as per the Purchase Order and Packing List for acceptance with qualified certificates. Damaged or unqualified material is reported to Warehouse Supervisor and managed according to the procedure.

2.Piece count and visual check

The account is correct, the packing is not damaged and polluted, the goods is free from damp and corrosion.

3.Storage and preservation

Accepted material or equipment is stored in accordance with the relevant procedure; preservation measures are taken according to the storage requirements of the material recommended by material Vendors.

4.Control of Non-conformed Products

Unacceptable material or equipment is isolated and marked. No non-conformed material is issued for construction. Detail inspection record of damaged and unqualified material or equipment is provided.

5.Requirements for warehouse.

The warehousing is complied with the following items: 1) closed by fences.

2) At least 10cm support is padded and graded for drainage.

3) The elements are shielded with proper material (like polyethylene, tarps or temporary structures).

4) The boxes and package are not stacked unless allowed by Vendor’s instructions. 5) Visual check for the material is convenient.

6) Identification marks are clear and visible. 7) Materials on shelves are carefully classified. 8) Other specifications in the Vendor’s instruction. 6.Handling &

transporting equipments.

The handling and transporting equipments are operated under good condition.

Inspection Conclusion

Proceeding work: YES □ NO □ Date:

Approved by

Contractor Rep.

QA/QC Contractor

Company

Name

Signature

Date

(38)

AGIP Oil Co. Ltd.

Libyan Branch

El Sharara-Mellitah 30” Pipeline

P

ETRO

J

ET

Libya

References

Related documents

false pulse protection Circuitry designed to avoid false pulses during power on or power down action or to disable the output of a sensor or sensing system until the power

The application of ABA significantly (P < 0.05) increased grain filling rate, starch accumulation rate and content, remobilization of dry matters to kernels, and 1000-grain weight

Table 6 ⋅ Differential pressure tables ⋅ Balanced valve plugs with PTFE balancing seal with metal bellows seal. Values specified in the shadowed columns correspond to the

Renowned educational scholar Paulo Freire’s emancipatory theory of learning calls for people to develop an “ontological vocation,” in which individuals are viewed as

But, based on interviews with lower class Dalit women, this investigation has found that vulnerable women possess limited human and personal resources, family and social

The curve fits better if economic development is measured by alternative indicators instead of per-capita GDP, namely life expectancy and an Economic Development

In energy-related upgrades of buildings, Siemens Building Technologies promotes investments in energy efficiency that liter- ally finance themselves through guaran- teed

“In two years I received my associate degree from SCCC and then transferred to Ramapo College where I earned my bachelor’s degree in Communication. SCCC was a great place for