PMC to Implement
Area Based Development
Monthly
Progress
Report
November 2019
Monthly Progress Report
1565/MPR- 21(21/30)/November 2019/R0
Project Management Consultant (PMC)
to implement Area Based Development
Smart City Kochi
Cochin Smart Mission Limited, CSML
Cochin Smart Mission Limited, 9th Floor, Revenue Tower, KSHB, Opposite Ernakulam Boat Jetty, Ernakulam
DISCLAIMER
This report (including any enclosures and attachments) has been prepared by IPE Global Limited (IPE Global) in JV with Haskoning DHV Consulting Private Limited (HDC) for the exclusive use by Cochin Smart Mission Limited (CSML) and solely for the purpose for which it is provided. IPE Global in JV with HDC does not accept any liability if this report is used for an alternative purpose from which it is intended, nor to any third party in respect of this report. IPE Global in JV with HDC has used reasonable skill and care in checking the authenticity, accuracy and completeness of information obtained from the public domain or from external sources in the report. IPE Global in JV with HDC assumes no responsibility for such information. IPE Global in JV with HDC does not accept responsibility for any legal, commercial or other consequences that may arise directly or indirectly as a result of the use of third party information or information sourced from public domain in this report or used for an alternative purpose from which it is provided.
Revision Date Prepared by Checked By Approved by
EXECUTIVE SUMMARY ... 6
1
STATUS AS ON 30TH NOVEMBER ... 9
1.1
STAKEHOLDER MEETINGS CONDUCTED ... 9
1.2
SITE VISITS ... 10
1.3
BRIEF SUMMARY OF KEY MEETINGS ... 15
2
STATUS OF PROJECTS ... 17
2.1
PAN CITY... 17
2.2
STATUS OF ABD PROJECTS ... 17
2.2.1
Vacuum Sewer Network with House Connections and Sewage Treatment Plant under Cochin
Smart City Mission ... 21
2.2.2
DEVELOPMENT OF OTHER ROADS IN ERNAKULAM ... 23
2.2.3
DEVELOPMENT OF OTHER ROADS IN WEST KOCHI WARD 1 & 2 ... 25
2.2.4
DEVELOPMENT OF SMART ROADS IN ERNAKULAM ... 26
2.2.5
DEVELOPMENT OF SMART ROADS IN WEST KOCHI ... 32
2.2.5
INTELLIGENT TRAFFIC MANAGEMENT SYSTEM (ITMS) ... 33
2.2.6
DEVELOPMENT OF ELECTRICAL INFRASTRUCTURE AT ABD ... 36
2.2.7
SOLAR ROOFTOP PROJECT IMPLEMENTATION PROGRESS ... 37
2.2.8
Implementation of Smart LED Lights in ABD ... 39
2.2.9
HOUSEHOLD BINS AND BINS IN PUBLIC PLACES ... 41
2.1.7
PUBLIC BIKE SHARING IMPLEMENTATION PROGRESS ... 45
2.2.13
CANCER BLOCK- GENERAL HOSPITAL... 52
2.2.14
E-HEALTH SOLUTION FOR GENERAL HOSPITAL ... 53
2.2.15
CONSTRUCTION OF NEW BLOCK AT FORT KOCHI HOSPITAL ... 54
2.2.16
CONSTRUCTION OF NEW BLOCK AT MATTANCHERRY HOSPITAL ... 56
2.2.17
UPGRADATION OF DUTCH PALACE ENTRY AREA ... 61
2.2.18
INTEGRATED COMMAND CONTROL & COMMUNICATION CENTER (IC4) ... 63
2.3
UPDATED INTEGRATED PROJECTIVISATION ... 65
2.4
OVERALL PROGRESS ... 79
2.5
SECTOR PROGRESS ... 79
3
WAY FORWARD ... 82
3.1
IMMEDIATE AISSSITANCE REQUIRED ... 82
3.2
OVERALL ISSUES AND CONCERNS ... 82
3.3
NEXT STEPS ... 84
3.4
WAY FORWARD FOR FEW PROJECTS ... 84
3.5
OVERALL STAKEHOLDER ROLES & RESPONSIBILITIES ... 85
4
PMC TEAM MOBILISED ... 87
4.1
STAFF DEPLOYMENT ... 87
TABLE OF CONTENTS
5
SMART CITY PROJECTS IN MEDIA COVERAGE ... 88
ANNEXURES ... 92
ANNEXURE 1: LIST OF PROJECTS UNDER IMPLEMENTATION BY SPV... 92
ANNEXURE 3: TENDER DETAIL ... 96
ANNEXURE 5: PROJECT PROGRESS – INSTALLATION OF SOLAR PANELS IN GOVT. BUILDINGS ... 101
List of Tables
TABLE 1-1:SUMMARY ON STAKEHOLDER CONSULTATIONS BY PMC TEAM DURING THE MONTH OF NOVEMBER 2019... 9TABLE 1-2SUMMARY OF SITE VISITS CONDUCTED DURING THE MONTH OF NOVEMBER 2019 ... 10
TABLE 1-3 SUMMARY OF SITES SUPERVISION DURING THE MONTH OF NOVEMBER ... 13
TABLE 2-1:ACTION FOR KMC TO ENABLE TENDERING BY END OF DECEMBER 2019 ... 50
TABLE 3-1:PROJECTS REQUIRING STAKEHOLDER ASSISTANCE ... 83
TABLE 3-2:PROJECTS PROPOSED TO BE DROPPED FROM CENTRALMIS ... 84
LIST OF PHOTOGRAPHS FIGURE 1-1EARTH EXCAVATION AND DRAIN PLACING WORK AT AM ROAD ... 13
FIGURE 1-2DRAIN PLACING WORK AT AMROAD ... 13
FIGURE 1-3NORMAL AND MOUNTABLE KERB LAYING AT JOS JN. ... 14
FIGURE 1-4EXISTING PARKING FACILITY AROUND KACHERIPADY JN ... 14
FIGURE 1-5 PROPOSED PBS LOCATIONS ... 14
FIGURE 1-6PROPOSED PBS LOCATIONS ... 15
FIGURE 1-7LOCATIONS FOR PLACING FOR TRAFFIC SIGNALS IN ITMSPROJECT ... 15
FIGURE 1-8AWARENESS PROGRAMME ON SEWERAGE PROJECT AT WEST KOCHI ... 15
FIGURE 1-9POC-IC4APPLICATION... 16
FIGURE 2-3REVISEDSCHEDULE ... 22
FIGURE 2-4IMPLEMENTATION SCHEDULE ... 24
FIGURE 2-5TILE LAYING AT KUTTAPAYI ROAD ... 24
FIGURE 2-6DRAIN CLEANING WORK UNDER PROGRESS AT NARAKHATRA ROAD ... 24
FIGURE 2-7IMPLEMENTATION SCHEDULE ... 25
FIGURE 2-8LOCATION MAP-SMART ROAD ERNAKULAM ... 28
FIGURE 2-9IMPLEMENTATION SCHEDULE ... 28
FIGURE 2-10DRAIN PLACING WORK AT AMROAD ... 32
FIGURE 2-11FOOTPATH WORK UNDER PROGRESS AT JOS JN ... 32
FIGURE 2-12SMART ROAD -WEST KOCHI ... 33
FIGURE 2-13IMPLEMENTATION SCHEDULE ... 33
FIGURE 2-14ONGOING WORK OF SIGNAL PLACING AND CCR ... 35
FIGURE 2-15IMPLEMENTATION SCHEDULE ... 35
FIGURE 2-16IMPLEMENTATION SCHEDULE ... 37
FIGURE 2-17 GOVT SCHOOL EDAPALLY ... 38
FIGURE 2-18INSTALLATION AT KUNNUMPURAM HIGH SCHOOL(20KW) ... 38
FIGURE 2-19KUNNUMPURAM HIGHER SECONDARY SCHOOL(20KW) ... 39
FIGURE 2-20KUNNUMPURAM HIGHER SECONDARY SCHOOL(20KW) ... 39
FIGURE 2-21IMPLEMENTATION SCHEDULE ... 39
FIGURE 2-22LED LIGHTS AT JOS JN. ... 40
FIGURE 2-26SMART WASTE MANAGEMENT AWARENESS SESSION FOR KUDUMBASREE VOLUNTEERS OF WARD 1,2 AND 3
... 42
FIGURE 2-27IMPLEMENTATION SCHEDULE ... 42
FIGURE 2-28PBS LOCATIONS (BASE MAP BY PMC AND LOCATIONS PLOTTED BY SMART-SUT) ... 46
FIGURE 2-29BIKES AT LISSIE METRO STATION ... 46
FIGURE 2-30BIKES AT ERNAKULAM BOAT JETTY ... 46
FIGURE 2-31ERNAKULUM MARKET REDEVELOPMENT –PROJECT PLANNING ... 49
FIGURE 2-32ACTION TO BE TAKEN PRIOR TO TENDERING OF THE PROJECT ... 50
FIGURE 2-33LOCATION OF PROPOSED CANCER BLOCK ... 53
FIGURE 2-34IMPLEMENTATION SCHEDULE ... 53
FIGURE 2-35STRUCTURAL OUTLINE OF E-HEALTH SOLUTION ... 54
FIGURE 2-36IMPLEMENTATION SCHEDULE ... 54
FIGURE 2-37LOCATION OF PROPOSED BLOCK-FORT KOCHI HOSPITAL ... 55
FIGURE 2-38TEST PILE FORT KOCHI HOSPITAL ... 56
FIGURE 2-39IMPLEMENTATION SCHEDULE ... 56
FIGURE 2-40 LOCATION OF PROPOSED BLOCK-MATTANCHERRY HOSPITAL ... 57
FIGURE 2-41DESIGN MATTANCHERRY HOSPITAL ... 57
FIGURE 2-42IMPLEMENTATION SCHEDULE ... 57
FIGURE 2-43IDENTIFICATION OF TOURISM PROJECTS ... 60
FIGURE 2-44UPGRADATION OF DUTCH PLACE ENTRY AREA ... 61
FIGURE 2-45IMPLEMENTATION SCHEDULE ... 62
FIGURE 2-44INTEGRATION OF SMART SOLUTIONS WITH IC4 ... 64
EXECUTIVE SUMMARY
The smart city proposal of Kochi submitted for Smart Cities Challenges aims at integrating the
Fort Kochi & Mattancherry area with Central City Area through Water Metro. Thematic areas
for interventions under smart cities mission in Kochi are
Seamless Mobility
Reconstitution of Urban Form
World Class Urban Services & Inclusive Development
Revival of Identity and Culture
The Smart City proposal of Kochi has adopted retrofitting as the strategy for development
under the Mission. The vision for Kochi is to transform Kochi ABD, into a sustainable, inclusive
and economically vibrant city of opportunities with efficient urban services, traditional
hospitality and smart governance.
a) Area Based Development (ABD) projects
Area Based Development (ABD) as part of Smart City development consists of parts of five
wards west Kochi (1,2,3,4 and 5) and parts of three wards of mainland of KMC (62,66 & 67),
with a total area of 1024.16 acres. There are currently are 40 ABD projects under 18 modules
worth a total cost of Rs. 951 Crores.
The overall status of ABD projects is as follows:
(Amount in INR Crore)
S. No.
ITEMS
No of projects
TOTAL COST
INR Cr.
%
1
Projects Awarded
17
582
61%
2
Funding support to KMC for housing project 2
34 (13+21) 4%
3
Projects in tender stage
9
71
7%
4
DPR Prepared
4
148
16%
5
To be awarded nomination
3
9.7
1%
6
Housing/Canals/other projects
5
107
11%
Total Smart Cities Fund
40
951*
100%
Pan City projects
Pan city projects are convergence projects and being implemented by stakeholders. As part of SCP two projects were proposed as Pan City projects. Smart Card - Kochi 1 is a PPP project and implemented by KMRL. 24 X 7 WATER SUPPLY is being taken up by KWA for implementation.
Source of Fund No of Projects Project Estimated Cost (If any) or SCP cost
PPP
Project Completed 1 25
Other Sources
Status of Smart City Mission Kochi as on 30th November 2019
Total Project Cost-including convergence Rs 2194.43 cr
Central Assistance Released Rs. 196 cr
State Grant Released Rs 200 cr Central Assistance
Approved Rs. 500 cr
Tender Issued
(Ongoing)-SPV
Projects 9
Cost Rs. 71.05 cr
Work Order issued/under implementation - SPV Projects 17
SUMMARY OF PROGRESS BY PMC IN THE MONTH OF NOVEMBER 2019
CUMMULATIVE DELIVERABLES SUBMITTED BY PMC AS ON 30th NOVEMBER
Monthly Progress Report(1 Report, Oct. 2019) Tender /Re-Tendered (4 Projs.) BOQ/Revised (4 Projs.) Site Visits
(26 Nos )
Situation Analysis Report (1 Report)
Feasibility Reports (39 Projects) Monthly Progress Reports
(24 Reports)
Detailed Project Reports (38 Projects)
RFP/Tender Submitted (31 Projects) EoI & related Reports
(2 Projects)
Tender Issued (29 Projects)
Draft BERs prepared (26 Projects)
Draft CERs prepared (17 Projects) Project (Stakeholder) meetings (8 Nos.) Concept Note (2 Projects) EIA/EMP (15 Projects) SHE Training (1 no) Supervision - Site Visits
1
STATUS AS ON 30TH NOVEMBER
In the month of November, the Smart City team worked on Technical Bid evaluation of the
West Kochi Other Road projects, Public Toilets, Marine Drive walkway, Beach Front
Upgradation at Vasco Square in Fort Kochi - Part A, Revised BoQ/estimates of minor
bridges at Fort Kochi, Calvathy School and cost estimation of rehabilitation of Ernakulam
Market. DPR of Ernakulam Market, Broadway and concept note on Cultural Street- PT
Usha Road has been submitted. Revised DPR of Calvathy School and Intelligent Crime
Surveillance system has been submitted. DPR for upgradation of Anganwadi project is
being revised.
Status of the project given below:
1.1
STAKEHOLDER MEETINGS CONDUCTED
Stakeholder meetings conducted in the month of November are as follows:
Table 1-1: Summary on Stakeholder Consultations by PMC team during the month of November 2019 S. No Date of Consultati on Module Content Stakeholder Consultation Concerned Person in the Department Agenda Discussion by PMC Team Remarks 1. 02-11-2019
Sewerage Supreme pipe Co
KMRL Knowledge
centre visit
Inspected Supreme pipe company's knowledge centre and seen the different pipes & specials used for sewerage project 2.
05-11-2019
General GIZ GIZ
Representatives
Presentation of the GIZ projects in Ernakulam and West Kochi
The presentation of the projects undertaken by GIZ was explained in the meeting 43.37 128.07 128.07160.17 512.8 512.8 578.04 594.11 5.77 5.77 5.77 125.83 293.97 582.13 582.13 1.9 1.9 3.47 5.6 7.04 25.96 0 200 400 600 800 1000 Sept-Dec 17 Jan- Mar 18 Apr-June 18 Jul- Sept 18 Oct-Dec 18 Jan- Mar 19 Apri-June 19 Jul- Sept 19 Oct-Dec 19 Jan- Mar 20 April -Jun 20 Jul-Sept 20
PROJECTS - TENDERED , AWARDED & EXPENDITURE
Tendered- Cumulative Cumulative Awarded Proj - Amt Cumulative Exp.
S. No Date of Consultati on Module Content Stakeholder Consultation Concerned Person in the Department Agenda Discussion by PMC Team Remarks 3. 13-11-2019
Sewerage Hon’ble MP Hon’ble MP Issue related to West Kochi STP area
Met the MP and appraised him on the present stage of STP problem and requested for his intervention for resolving the issue 4.
16-11-2019
IC4 Fire Department Dist. Fire Officer Integration with IC4
Discussion were held regarding the integration of fire services and sos with IC4 platform 5.
19-11-2019
IC4 Fire Department Dist. Fire Officer Integration with IC4
Discussion were held regarding the integration of fire services and sos with IC4 platform.
Requested fire
department to submit the SOPs of Fire department 6. 22-11-2019 Energy supply KSEB Superintending Engineer For planning Schematic diagram for Park Avenue Road.
KSEB detailed about Feeders not shown in schematic diagram and variations in transformers rating 7. 22-11-2019 Smart Road- ITMS
DMRC Chief- Engineer Open Trenching at Manorama Junction and Kadavanthara Junction in S A Road for laying of G. I . pipes for cable laying
DMRC pointed out that the SA road is being restored by DMRC and profile correction works are underway, so the open trenching work across the roads, if any should be completed at the earliest in these locations, in coordination with DMRC contract staff on ground. 8. 29-11-2019 Smart Road- ITMS GCDA Superintending Engineer GCDA - Kaloor Kadavanthara road - Work on hold opening trenching ITMS
GCDA pointed out that only after the signing of Agreement document between CSML and GCDA, and deposit of assurance amount of Rs. 2 lakhs as security, ITMS work shall be allowed to proceed in Kaloor-Kadavanthara road.
1.2
SITE VISITS
In the month of November following site visits and supervision visits have been taken up by
PMC:
Table 1-2 Summary of site visits conducted during the month of November 2019 S
No
Date Site Visited Agenda for Site visit
Location Notes from site visit
1. 04-11-2019 AGIS Excise Building Office, Plant and Testing and Inspection Ernakulam Installation completed in the mentioned sites, Punch lists are prepared for complying requirements as per RFP
S No
Date Site Visited Agenda for Site visit
Location Notes from site visit
2. 05-11-2019 Jayalakshmi Parking, KMRL Parking at Seematti, M. G. Road, Kacheripady - MLCP Sit Re-evaluation of existing parking in and around Kacheripad
Ernakulam Re-evaluation of existing parking in and around Kacheripady
3. 06-11-2019 PBS locations Approval of proposed PBS locations
Ernakulam The locations on AM road can be used for PBS after completion of the construction works.
Kadavanthara Bus Stop - PBS location to be shifted to more visible location (near metro station) 4. 06-11-2019 KSEB Central Section Office, Panampully nagar School, Plant Inspection and Testing and
Ernakulam Installation completed in the mentioned sites, Punch lists are prepared for complying requirements as per RFP documents
5. 07-11-2019 PBS locations Approval of proposed PBS locations
Ernakulam Locations were approved. PBS Hexi Point near KMRL Parking recommended to be shifted to the beginning of Streetscape after consultation with KMRL. 6. 07-11-2019 Jos Junction Site Inspection Ernakulam Erection of 5 m pole
7. 07-11-2019 Jos Junction Verification of pole location
Ernakulam Pole positions were checked with Keltron site engineers.
8. 08-11-2019 STP site STP site
inspection
West Kochi Attended the CEO's site inspection and appraised him the progress of sewerage project in West Kochi and the present STP site issue and received instructions.
9. 08-11-2019 Jos Junction ITMS pole erected - Cantilever Poles
Ernakulam The locations were checked, attended CEO’s inspection at Jos Junction
10. 08-11-2019 Old Age Home Thevara,
Palluruthy School,
Plant Inspection and Testing and
Ernakulam, West Kochi
Installation completed in the mentioned sites, Punch lists are prepared for complying requirements as per RFP documents 11. 08-11-2019 MLCP Kacheripady, Lisie Hospital Automated Parking Proposed MLCP site inspection
Ernakulam To show the Proposed MLCP site to NHIDCL site and the existing automated car parking facility in the city
12. 12-11-2019 Jos Junction, pallimuku Junction
Verification of pole location
Ernakulam Proposed pole positions were checked with Keltron site engineers.
13. 15-11-2019 AM Road Site inspection Ernakulam Site inspection for cable joint of 11 KV HT Cable
14. 18-11-2019 North Police Station
ITMS Control Room
Ernakulam Control Room site visit - assess the site conditions w.r.t proposed plan 15. 20-11-2019 General Hospital, Edakochi School, GGHSS Chittoor road, PWD Rest house Plant Inspection and Testing and
Ernakulam, West Kochi
Installation completed in the mentioned sites, Punch lists are prepared for complying requirements as per RFP documents
S No
Date Site Visited Agenda for Site visit
Location Notes from site visit
16. 21-11-2019 ITMS Sites ITMS Inspection Site Ernakulam Site trenching status, pole erection inspection - open status
17. 22-11-2019 PBS Locations Inspection/ Approval of proposed PBS locations
Ernakulam Cusat - Administrative Office Road (Loc 1), Administrative Office Road (Loc 2), Students Amenities Centre CUSAT, St. Joseph's E.M.H. Secondary School, School of Engineering CUSAT,
St. Paul’s College, HMT Junction JLN Stadium Road 18. 22-11-2019 Manorama Jn. Pole fixing location
issue
Ernakulam Location visited with Keltron and instructions were given to Keltron to remove the pole. Pole was removed the same night.
19. 22-11-2019 STP site STP inspection site West Kochi Inspected the network survey works and made arrangement for scrutiny of the level with the PMC Surveyor and Ultility Engineer
20. 25.11.2019 General Hospital Installation of GPON Network
Review of Work
progress.
Installation of Network Cable completed. Splicing of Network Cable ongoing
21. 26-11-2019 Karuvelipadi Hospital Fort Kochi Hospital
Plant Inspection and Testing and
Ernakulam, West Kochi
Installation completed in the mentioned sites, Punch lists are prepared for complying requirements as per RFP documents 22. 27-11-2019 Manorama Junction, Kadavanthara Junction, Shenoys -Padma jn, North RoB - opposite Town Hall, Kaloor Jn, Changampuzha Park, Edapally Approval and Concurrence from KMRL for metro median locations
Ernakulam Location visited with KRML and Keltron. Instructions were given to Keltron to be cautious of the electric cables and the advertisement board connection cables laid across the median.
23. 27-11-2019 JLN Metro Station IC4 Command and Control room
Ernakulam The site was handed over to MSI on 18th October for construction of CCR. Till date there is no work progress recorded. CEO instructed to start the Work at the earliest. 24. 28-11-2019 North Police Station ITMS Room Control Ernakulam Control finalization- visit with Keltron Room layout
Team 25. 29-11-2019 Judged Avenue Junction, Madhava Pharmecy Jn. Verification of pole location
Ernakulam Proposed pole positions were checked with Keltron site engineers.
26. 30-11-2019 STP site STP site
inspection
West Kochi STP site inspection made with LQEC team and assessed the environmental condition viz., smell, odour around the STP site. No smell - good response.
Table 1-3 Summary of sites supervision during the month of November S
No
Date Site Visited Agenda for Site visit Location Notes from site visit
1. 1/11/2019- 2/11/2019
AM Road Site Supervision Ernakulam Smart Road
Earth work excavation and Drain laying in progress. Discussion regarding the height of drain at Bus bay near ABAD.
2. 1/11/2019-8/11/2019
Jos Junction Site Supervision Ernakulam Smart Road
Normal and mountable kerb laying at the RHS & LHS 3. 4/11/2019-
09-112019
AM Road Site Supervision Ernakulam Smart Road
Drain laying in progress between chainage 720-740(LHS) &1000-1050(RHS).CEO CSML visited the site on 08/11/19.
4. 9/11/2019-16/11/2019 Jos Junction Site Supervision Ernakulam Smart Road Normal and mountable kerb laying at the RHS & LHS and lamp post concreting (2 No’s),paver and hydraulic tile laying (RHS and LHS)
5. 11/11/2019- 16/11/2019
AM Road Site Supervision Ernakulam Smart Road
Drain laying in progress between
chainage
1050-1090(RHS).Trench laying started from chainage 1000 to 1020. KSEB Cable shifting completed at Pile location. 6. 18/11/2019-
22/11/2019
AM Road Site Supervision Ernakulam Smart Road
Drain laying in progress between chainage 940-920(RHS).Trench laying in progress b/w chainage 1000 to 1020.
7. 25/11/2019- 30/11/2019
AM Road Site Supervision Ernakulam Smart Road
Taluk Surveyor Marked the boundary of road near Lulu and Shobha Developers. Liner fixing started at Piling site. Drain laying in progress between chainage 900-870(RHS) & 710-760(LHS). 8.
18/11/2019-30/11/2019
Jos Junction Site Supervision Ernakulam Smart Road
Normal and mountable kerb laying at the LHS and lamp post concreting (4 No’s), levelling and setting out at the LHS
Photographs for existing conditions of the sites visited.
Figure 1-1 Earth excavation and Drain placing work
Figure 1-3 Normal and mountable kerb laying at Jos Jn.
Figure 1-4 Existing Parking Facility around Kacheripady Jn
Figure 1-6 Proposed PBS locations Figure 1-7 Locations for placing for Traffic signals in ITMS Project
1.3
BRIEF SUMMARY OF KEY MEETINGS
1. Awareness Programme
– Construction of Vacuum Sewer Network with House
Connection and sewage Treatment Plant in West Kochi on 2nd November 2019
CSML and Kochi Municipal Corporation had conducted an awareness programme in west
Kochi on Sewerage project. The proposed sewage collection system would cover 10,000
households along with commercial establishment. The sewerage scheme is proposed to
be implemented in two phases. Phase I would cover divisions one and two. A sewage
treatment plant with a capacity to treat 2.6 mld per day, will be constructed in first phase. In
the second phase, the project will cover division 3 to 5.
Figure 1-8 Awareness Programme on Sewerage project at West Kochi
2. Proof of Concept (POC)- Integrated Command and Control Center o 21st
November 2019.
A PoC for IC4 application had been presented by MSI Fluentgrid on 21st November, 2019.
MSI has explained the application and services which is being integrated with IC4
application. MSI has informed that till date 4 services has already been integrated and
integration process for other services is ongoing. MSI has also explained the GIS
application which has been developed for Kochi. CEO, CSML has instructed to expedite
the work and complete the work by at the end on December, 2019.
2
STATUS OF PROJECTS
2.1
PAN CITY
PAN City Project - 24x7 Water Supply
S. No Proposed interventions SCP Cost Clubbed / Segregated/ Estimated Cost Remarks 24 X 7 WATER SUPPLY 62100Being taken up by KWA. Has been included in 24 X 7 water supply proposal for which KWA has submitted a concept paper. The funding is yet to be decided (ADB / KIIFB)
Detailed Project Report under progress.
This project has been classified as
convergence project
as the project is being
implemented by KWA. CSML/PMC will continue taking status from KWA regarding the
progress made for the project as project is part of overall projects identified under SCP
project list. However, it is being proposed by MoHUA that as 24x7 is a huge project and its
implementation timelines will not run in parallel with Smart City timelines hence same may
be removed from central MIS.
2.2
STATUS OF ABD PROJECTS
This chapter provides an overview of all 80 projects listed in SCP for ABD. As envisioned
in SCP only part funding is met from Smart cities mission fund. Remaining projects to be
funded from various sources such as convergence, PPP, CSR, loans etc. The status of
projects under convergence and under SPV are provided below. All costs provided are in
INR lakhs in this section.
Module 1
Water supply
There were total of 14 projects identified under this module with serial number 1.1 to 1.14.
Based on the meetings conducted with Kerala Water Authority in initial phase of the project
it was suggested by the authority that KWA will implement all projects. Therefore, these
projects are categorized as convergence projects. In the Stakeholder’s meeting, KWA has
requested to take up Smart Meter project for selected area as pilot basis. Hence only one
project Smart Water Meter project is under scope of SPV implementation. KWA is to submit
to CSML final scope for smart meter project to be taken up by CSML. Under AMRUT
Rainwater Harvesting project has been taken up.
1.1 Karuvelipady Pump house – Pumping augmentation
S. No Proposed interventions SCP Cost Clubbed / Segregated/ Estimated Cost Remarks 1.1 Karuvelipady Pump house – Pumping augmentation 100To be taken up by KWA only after the sump and pump house/pumping mains in Karuvelipady is completed under AMRUT scheme and TS committee constituted. The AMRUT work will be completed within 15 months
This project has been classified as
convergence project
as the project is being
implemented by KWA. KWA as per meeting held in July 2019 to share status every month
with CSML. If the work is not tendered and awarded by March 2020 then CSML may request
MoHUA/ board to remove the project from MIS.
1.2 West Kochi - Extension of pipelines from Maradu to Island to be extended to
West Kochi to supply 12 MLD
S. No Proposed interventions SCP Cost Clubbed / Segregated/ Estimated Cost Remarks
1.2
West Kochi - Extension of pipelines from Maradu to Island to be extended to West Kochi to supply 12 MLD
55
85
Taken up under state plan and the works are completed. Work Completed.
Work completed (State plan)
This project has been classified as
convergence project
as the project is being
implemented by KWA. The KWA has reported that the project has been completed.
1.3 West Kochi - Replacement of pipelines from Perumanoor to Thevara and
Thoppumpady bridge to Karuvelipady
S. No Proposed interventions SCP Cost Clubbed / Segregated/ Estimated Cost Remarks1.3
West Kochi - Replacement of pipe lines from Perumanoor to Thevara and Thoppumpady bridge to Karuvelipady
1100 725
Replacement of Pipelines from perumanoor pump house to Karuvelippady has been taken up under State plan.
This project is
convergence project
as the project is being implemented by KWA. KWA as
per meeting held in July 2019 to share status every month with CSML.
1.4 West Kochi - Dedicated pumping main
S. No Proposed interventions SCP Cost Clubbed / Segregated/ Estimated Cost Remarks1.4
West Dedicated Kochi - pumping main350 350
Pumping main from Karuvelipadi pump house to Kovampadam OHT will be taken up under AMRUT and the works have been awarded during Feb 2018. The work will be completed within 15 months.
Work under implementation.
This project is convergence project as the project is being implemented by KWA. KWA as per meeting held in July 2019 to share status every month with CSML.
1.5 West Kochi - Storage capacity augmentation in Karuvelipady sump by 1.5
million litres
S. No Proposed interventions SCP Cost Clubbed / Segregated/ Estimated Cost Remarks1.5
West Kochi - Storage capacity augmentationin Karuvelipady sump by 1.5 million litres 800 1121
Taken up under AMRUT.
This project is convergence project as the project is being implemented by KWA. KWA as
per meeting held in July 2019 to share status every month with CSML.
S. No Proposed interventions SCP Cost Clubbed / Segregated/ Estimated Cost Remarks
1.6
West Kochi - Rejuvenation of the Three OH Tanks in the region (Modibath, Fort Kochi and Koovapadam)
75
Work is to be taken up as part of augmentation of WSS (24 X 7 water supply) to Kochi
This project is convergence project as the project is being implemented by KWA. KWA as
per meeting held in July 2019 to share status every month with CSML. .
1.7 West Kochi - Replacement of 20 kms of Distribution line with D.I. pipes
including Road cutting charges
S. No Proposed interventions SCP Cost Clubbed / Segregated/ Estimated Cost Remarks 1.7
West Kochi - Replacement of 20 kms of Distribution line with D.I. pipes including Road cutting charges
3500
Work is to be taken up as part of augmentation of WSS (24 X 7 water supply) to Kochi
This project is convergence project as the project is being implemented by KWA. KWA as
per meeting held in July 2019 to share status every month with CSML.
1.8 West Kochi - Replacement of Household connections (last mile) for across
10,000 HSCs with Smart Metering and isolation valves
S. No Proposed interventions SCP Cost Clubbed / Segregated/ Estimated Cost Remarks 1.8
West Kochi - Replacement of Household connections (last mile) for across 10,000 HSCs with Smart Metering and isolation valves
2500
Work is to be taken up as part of augmentation of WSS (24 X 7 water supply) to Kochi
This project is convergence project as the project is being implemented by KWA. KWA as
per meeting held in July 2019 to share status every month with CSML.
1.9 West Kochi - Bulk Meters and Isolation valves with remote meter reading
S. No Proposed interventions SCP Cost Clubbed / Segregated/ Estimated Cost Remarks 1.9West Kochi - Bulk Meters and Isolation valves with remote meter reading
100
Work is to be taken up as part of augmentation of WSS (24 X 7 water supply) to Kochi
This project is convergence project as the project is being implemented by KWA. KWA as
per meeting held in July 2019 to share status every month with CSML
1.10
Mainland - Rider line for increased water supply
S. No Proposed interventions SCP Cost Clubbed / Segregated/ Estimated Cost Remarks 1.10Mainland - Rider line for increased water supply 1000
Work is to be taken up as part of augmentation of WSS (24 X 7 water supply) to Kochi
This project is convergence project as the project is being implemented by KWA. KWA as
per meeting held in July 2019 to share status every month with CSML
1.11 Mainland - Overhead Storage Reservoir + 1 Million Litre Sump + pump near
Ernakulam Ground
S. No Proposed interventions SCP Cost Clubbed / Segregated/ Estimated Cost Remarks 1.11Mainland - Overhead Storage Reservoir + 1 Million Litre Sump + pump near Ernakulam Ground
300
Work is to be taken up as part of augmentation of WSS (24 X 7 water supply) to Kochi
This project is convergence project as the project is being implemented by KWA. KWA as
per meeting held in July 2019 to share status every month with CSML .
1.12 Replacement of connections (last mile) for across 10,000 HSCs (Commercial
and Domestic) with Smart Metering and isolation valves- Mainland
S. No REVISED Name of Project SCP Cost Clubbed / Segregated/ Estimated Cost Remarks 1.12 Mainland - Replacement of connections (last mile) for across 10,000 HSCs (Commercial and Domestic) with Smart Metering and isolation valves
Replacement of connections (last mile) for across HSCs (Commercial and Domestic) with Smart Metering and isolation valves for selected Area 2000 100 KWA during meeting held on 29 July 19 had confirmed to share scope for implementing smart meter project on pilot basis. KWA confirmation awaited
This project is convergence project as the project is being implemented by KWA. KWA as
per meeting held in July 2019 to share status every month with CSML
1.13
Mainland - Bulk Meters and Isolation valves with remote meter reading
S. No Proposed interventions SCP Cost Clubbed / Segregated/ Estimated Cost Remarks 1.13Mainland - Bulk Meters and Isolation valves with remote meter reading
150
Smart metering by CMSL on pilot basis. KWA to confirm feasible locations to be taken up
KWA to provide confirmation on scope of smart meter project on pilot basis for integration
with IC4.
1.14
General - Rainwater structures in ~5000 households
S. No Proposed interventions REVISED Name of Project SCP Cost Clubbed / Segregated/ Estimated Cost Remarks 1.14 General - Rainwater structures in ~5000 households Rainwater harvesting structures in 13 Govt. buildings 1125 75Initially KMC and other stakeholders suggested that the project may be done for Govt buildings instead of households
Later it was informed CSML that RWH project is under implementation under
Module 2
UGSS
There were total of 3 projects identified under this module with serial number 2.1 to 2.3.
Based on the meetings conducted with Kerala Water Authority and Kochi Municipal
Corporation 2 projects are under scope of SPV implementation. Further the project
“Improvements to Elamkulam STP and collection system Mainland (JNNURM scheme)”
has been segregated in two projects. The project “Improvement to Elamkulam STP” has
been taken up by KWA.
S. No Proposed interventions REVISED Name of Project SCP Cost Clubbed / Segregated/ Estimated Cost Remarks 2.1 Decentralized Treatment and collection system for West Kochi under ADB (Mundamveli) Sewerage System for West Kochi 2200 16600
The Sub Module 2.1 and 2.2 will be planned together as the small-bore sewer for on-site sanitation is part of sewer collection system. These two components will not be separated as two different works for design as well as execution. The project under the module would focus on ward nos. from 1 to 5 of Kochi Corporation
The LoA has been issued to M/s LC Infra QUAVAC and ENVIRO Consortium 2.2 Small bore sewer/ Vacuum system for onsite sanitation - Includes storage facility for treated water
use for landscaping 11000 2.3 Improvements to Elamkulam STP and collection system Mainland (JNNURM scheme) Improvements to sewer collection system for Mainland 7000 2230
Elamkulam STP INR 13.70 tendered by Kerala Water Authority (KWA). Remaining INR 22.30 Cr (from the module) yet to be initiated by KWA Sewerage in mainland approx. INR 22.30 Cr balance amount from the SCP estimate project not yet taken up by KWA.Based on the meeting held with MD, KWA project scope confirmation awaited from KWA if KWA proposes CSML to take up the project
Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM duration confirmation on scope to be shared by KMA at the earliest. With limited SCM duration. Confirmation on scope needs to be expedited.
Improvement to Elamkulam STP
1370
2.2.1
Vacuum Sewer Network with House Connections and Sewage
Treatment Plant under Cochin Smart City Mission
Project cost:
INR 166.00 Crores
Duration: 18 Months
Project Start date:
12 Sept 2019
End date (expected): 12 March 2021
Contractor:
M/s LC Infra QUAVAC and ENVIRO CONSORTIUM
Current status:
Household survey- Started on 23 Sept 2019 and 8816 numbers surveyed out of
9280 (95%)
Submitted the baseline schedule
Key staff Mobilisation under progress
Any Challenges to be discussed:
Councillors to assist CSML in sanitation and awareness regarding project.
Residents need to be made aware regarding the project and some disruption that
it may cause during construction.
Soil test stalled due to public protest. KMC & DC to take action.
Figure 2-1 REVISED SCHEDULE
Module 3
NMT Roads and Pedestrianized areas
There were total of 4 projects identified under this module with serial number 3.1 to 3.4
Three projects Relaying of roads, Standard Footpaths including signages and Restoration/
Rehabilitation of Storm water drains in the proposed area have been combined as these
components are part of right of way of the road itself and for coordinated implementation
need to be done together.
S. No Proposed interventions REVISED Name of Project SCP Cost Clubbed / Segregated/ Estimated Cost Remarks 3.1 Relaying of roads Development of
Other Roads in Ernakulam under Smart City Mission
4200 4360
LoA issued on 9th April, 2019 to M/s Deens Group
Work under progress 3.2 Standard Footpaths
including signages
Development of Other roads in West Kochi 1 & 2
2853 3473
LoA has been issued to M/s. K V Jacob & Sons on 06th Septembre 2019. 3.3 Restoration/ Rehabilitation of Stormwater drains in the proposed area Development of Other roads in West Kochi 3,4 & 5
2360 3249
RFP for ward 3,4 & 5 in Technical Bid evaluation process
S. No Proposed interventions REVISED Name of Project SCP Cost Clubbed / Segregated/ Estimated Cost Remarks complex at Kacheripady MLCP at GCDA land at Marine Drive 10.0
Project scope to be confirmed by stakeholder. Post that DPR preparation to be taken up MLCP at KTDC
complex at
Maneka
7.0
Project scope to be confirmed by stakeholder. Post that DPR preparation to be taken up. Project essential to support
Broadway street pedestrianisation Smart Parking solutions at various location in ABD
1.90 To be taken up based on fund availability
Progress of the Project:
2.2.2
DEVELOPMENT OF OTHER ROADS IN ERNAKULAM
Project cost:
INR 43.60
Crores
Duration: 15 Months
Project Start date:
20 June
2019
End date (expected): 19 September 2020 July 2019
Contractor:
M/s Deens Group
Current status:
Kuttappayi road 100 mm interlock tile laying completed.
Saucer drain placing and mountable kerb laying completed at Ranimatha Road.
Drain and trench placing completed at St. Alphonsa Road. Kerb laying work started
Drain cleaning at Narakathara Road completed
Joint inspection with KMRL, CSML, and contractor for Gopalaprabhu road,
Kovilvattom road, Basin Road, and market road are completed.
Survey for 10 other road has been completed
Concerns:
Slow progress in mobilization and finalization of proposals by the contractor
Exact locations of underground utilities such as water supply line, electric cables,
data cables etc. are unknown.
Mobilization of Manpower, equipment, Laboratory, Batching Plant, Casting Yard etc.
took longer than expected.
Survey and Submission of Working drawings by the Contractor are lagging behind
the schedule.
Figure 2-2 Implementation schedule
Figure 2-3Tile laying at Kuttapayi Road Figure 2-4 Drain cleaning work under progress at Narakhatra Road
List of Drawings issued to the Contractor
Sl
No.
Drawing Reference No.
Description of Drawing
Revision
Date
1
CSML/M4/DRA/EKM/PL-011
Ernakulam Drainage Plan - 1
R0
13-Jul-18
2
CSML/M4/DRA/EKM/PL-012
Ernakulam Drainage Plan - 2
R0
13-Jul-18
3
CSML/M4/DRA/EKM/PL-013
Ernakulam Drainage Plan - 3
R0
13-Jul-18
4
CSML/M4/DRA/EKM/PL-014
Ernakulam Drainage Plan - 4
R0
13-Jul-18
5
CSML/M4/ORD/EKM/PL-015
Other Roads EKM Plan - 1
R0
13-Jul-18
6
CSML/M4/ORD/EKM/PL-016
Other Roads EKM Plan - 2
R0
13-Jul-18
7
CSML/M4/ORD/EKM/PL-017
Other Roads EKM Plan - 3
R0
13-Jul-18
Sl
No.
Drawing Reference No.
Description of Drawing
Revision
Date
10
CSML/M4/ORD/EKM/TCS/020 Other Roads EKM TCS - 2
R0
13-Jul-18
11
CSML/M4/ORD/EKM/TCS/021 Other Roads EKM TCS - 3
R0
13-Jul-18
12
CSML/M4/SMR/TAT-025
Typical Tabletop Crossing Details
R0
25-May-18
13
CSML/M4/SMR/CLV-026
Typical Culvert Drawings
R0
04-May-18
14
CSML/M4/SMR/DRA-027
Typical Drain Drawings
R0
04-Jul-18
2.2.3
DEVELOPMENT OF OTHER ROADS IN WEST KOCHI WARD 1 & 2
Project cost:
INR 34.73 Crores
Duration: 15 Months
Project Start date:
06 September
2019
End date (expected): December 2020
Contractor:
KV Jacob & Sons
Current status:
LoA issued on 6th September, 2019
Survey works under progress – 50% Completed
Any Challenges to be discussed:
Slow progress in mobilization
Module 4
Main roads
There were total of 5 projects identified under this module related to roads with serial
number 4.1 to 4.3. Projects 4.4 & 4.5 will be separate project.
S. No Proposed interventions REVISED Name of Project SCP Cost Clubbe d / Segreg ated/ Estimat ed Cost Remarks
4.1 World class Arterial roads -- KB Jacob & Amravati Road/ Bellar Road in West/ -- Avenue, MG Rd, DH Rd, Banerjee Rd, Abraham Madamakkal road in Central city Development of Smart Roads Ernakulam 5,287 6153
LoA issued on 9th April, 2019 to
M/s Deens Group in Consortium with Deens Constructions
Work under progress
4.2 Relaying of roads, Aesthetic and improved Urban design Pedestrian facilities with Street furniture, Boulevards and urban greenery
Development of Smart Roads in West Kochi
1650
3031
LoA issued on 9th April, 2019 to M/s ABC Builders
Work under progress 4.3 Utility ducting for SWD, Water
supply, Sewerage, OFC etc
3300 4.4 Signages, Junction
improvement with Intelligent Traffic management
Signages 97
240
Segregated as signages & ITMS have separate projects. Junction improvement taken up under Roads combined project.
DPR has been submitted for Approval.
Integrated Traffic Management System
2690
Contract Agreement signed on 16th May, 2019. Work commenced
4.5 Construction of 3 Minor Bridges and
2 Foot over Bridges in West Kochi
240
1312 DPR prepared for FOBs in Thuruthy. Project tendered
Progress of the projects:
2.2.4
DEVELOPMENT OF SMART ROADS IN ERNAKULAM
Project cost:
INR 61.53 Crores
Duration: 15 Months
Project Start date:
20 June 2019
End date (expected): 19 September 2020
Contractor:
M/s Deens Group in Consortium with Deens Constructions
Current status:
Kerb laying at Left hand side started from Ch. 60 to 150 mtr at Swami Chinmyanad
Road at Jos Jn. to east.
Right hand side at Chittoor Road junction bell mouth kerb laying completed
GSB levelling of RHS completed up to Chittoor Road.
GSB levelling at LHS from Ch. 60 to 150 mtr completed up to Chittoor Road.
Utility trench laying at RHS Ch. 950 to 1000 mtr completed at Jos Jn.
LHS footpath completed at Jos Jn.
LHS precast drain laying completed from Ch. 950 to 1050 mtr. completed at AM
Road.
Two No of working piles completed at AM road
RHS trench and drainage placing work ongoing
Challenges:
Delay in contractor's mobilization.
Delay in finalizing the proposals due to incomplete and improper submissions by the
contractor.
Delay in Utility shifting - from Contractor as well as from authorities such as KSEB,
KWA etc.
Interfacing between various contractors not in line yet.
Figure 2-6 Location Map- Smart Road Ernakulam
List of Drawings issued to the Contractor
Sl
No.
Drawing Reference No.
Description of Drawing
Revisio
n
Date
Revision
Date
Revision
Date
1
RD/SR/EKM/JOS/SC-001
Jos Junction- Streetscape Part plan- Part 1
R3
25-Jun-19
R5
08-Aug-19
2
RD/SR/EKM/JOS/SC-002
Jos Junction- Streetscape Part plan- Part 2 R3
25-Jun-19
R4
12-Jul-19
R5
08-Aug-19
3
RD/SR/EKM/JOS/SC-003
Jos Junction- Streetscape Part plan- Part 3 R3
25-Jun-19
R4
12-Jul-19
R5
08-Aug-19
4
RD/SR/EKM/JOS/SE-001
Jos Junction- Streetscape Section
R3
25-Jun-19
5
RD/DR/TYP-001
Typical RCC details of duct
R2
27-Jun-19
6
CSML/M4/SRD/RD/ST/TE
ST PILE-00
Dimesnsion and Reinforcement Detail of
pile for Abutment
R1
01-Jun-19
7
RD/SR/EKM/JOS/SWD-001
Jos Junction- Storm Water Drain
detail-001
R4
08-Jul-19
8
RD/SR/EKM/AM/SC-001-008
Abraham Madamakal - Road Layout Part
Plan-01
(chaingage
-
0+000
to
0+150meter
R0
02-Jul-19
9
RD/SR/EKM/AM/SC-002-008
Abraham Madamakal - Road Layout Part
Plan-02
(chaingage
-
0+150
to
0+250meter
R0
02-Jul-19
10
RD/SR/EKM/AM/SC-003-008
Abraham Madamakal - Road Layout Part
Plan-03
(chaingage
-
0+250
to
0+400meter
R0
02-Jul-19
11
RD/SR/EKM/AM/SC-004-008
Abraham Madamakal - Road Layout Part
Plan-04
(chaingage
-
0+400
to
0+550meter
R0
02-Jul-19
12
RD/SR/EKM/AM/SC-005-008
Abraham Madamakal - Road Layout Part
Plan-05
(chaingage
-
0+550
to
0+700meter
Sl
No.
Drawing Reference No.
Description of Drawing
Revisio
n
Date
Revision
Date
Revision
Date
13
RD/SR/EKM/AM/SC-006-008
Abraham Madamakal - Road Layout Part
Plan-06
(chaingage
-
0+700
to
0+850meter
R0
02-Jul-19
14
RD/SR/EKM/AM/SC-007-008
Abraham Madamakal - Road Layout Part
Plan-07
(chaingage
-
0+850
to
1+000meter
R0
02-Jul-19
15
RD/SR/EKM/AM/SC-008-008
Abraham Madamakal - Road Layout Part
Plan-08
(chaingage
-
1+112
to
1+000meter
R0
02-Jul-19
16
RD/SR/EKM/AM/SC-101
Abraham
Madamakal
-
Streetscape
Section -01 (chaingage - 0+00 to
1+112meter
R0
02-Jul-19
17
RD/SR/EKM/JOS/SC-004
Jos Junction - Junction Improvement Plan
- Part-1
R0
12-Jul-19
18
RD/SR/EKM/JOS/SC-005
Jos Junction - Junction Improvement Plan
- Part-2
R0
12-Jul-19
19
RD/SR/EKM/JOS/SE-002
Jos Junction -Streetscape -Prpoerty Entry
Section-001
R0
11-Jul-19
20
RD/SR/EKM/JOS/SE-003
Jos Junction -Streetscape -Bike Parking
Section-002
R0
11-Jul-19
21
CSML/M4/SRD/RD/ST-001
Dimesnsion and Reinforcement Detail of
Pile for Abutment
R0
06-Aug-19
22
RD/SR/EKM/AMR/SC-001
Abraham Madamakkal Road -Part Plan
01&02-CH. +0.00M+340.00M
R1
27-Aug-19
23
RD/SR/EKM/AMR/SC-002
Abraham Madamakkal Road -Part Plan 03
&04-CH.+340.00M to +650.00M
R1
27-Aug-19
24
RD/SR/EKM/AMR/SC-003
Abraham Madamakkal Road -Part Plan
05&06-CH.+650.00M to 970.00M
Sl
No.
Drawing Reference No.
Description of Drawing
Revisio
n
Date
Revision
Date
Revision
Date
25
RD/SR/EKM/AMR/SC-004
Abraham Madamakkal Road -Part Plan
07& Section-CH.+970.00M to 1112.00M
R1
27-Aug-19
Details of Changes in Drawings in Jos Junction to Railway Station Road
Sl
No
Drawing
Reference
No.
Description of
Drawing
Revisio
n/
Date of
Issue
Remarks
Revision/
Date of
Issue
Remarks
Revision/
Date of
Issue
Remarks
1
RD/SR/EKM
/JOS/SC-001
Jos Junction-
Streetscape Part
plan- Part 1 (Ch
+0.00 to +50.00)
R3/24-06-2019
Good for
Construction
Drawing of
RHS Side
Issued to
Contractor
No changes
R5/08-08-2019
In Part 1: Private entry width/Light
Pole position changed based on
property owner’s requirements and
Clients
Instruction.
Kerb
&
Boundary
setup
dimensions
incorporated. Tabletop
crossing
layout added.
In Part 2: Private entry width/Light
Pole Position changed based on
site conditions.
In part -3: Private entry width/ Light
Pole Position changed based on
site condition. Duct Bank detail
incorporated.
General
Comments
Things
Incorporated: - Kerb & Boundary
setup dimensions, Drain Inlet &
Revised Light pole position, RMU &
Feeder Pillar Locations/ Proposed
Tree Locations.
2
RD/SR/EKM
/JOS/SC-002
Jos Junction-
Streetscape Part
plan- Part 2 (Ch
+50.00 to +120.00)
R4/12-07-2019
Based on site
conditions
drop off bay
reduced
3
RD/SR/EKM
/JOS/SC-003
Jos Junction-
Streetscape Part
plan- Part 3 (Ch
+120.00 to +180.00)
R4/12-07-2019
Based on site
conditions
Property entry
incorporated
4
RD/SR/EKM
/JOS/SC-004
Jos Junction-
Figure 2-8 Drain placing work at AM Road Figure 2-9 Footpath work under progress at Jos Jn
2.2.5
DEVELOPMENT OF SMART ROADS IN WEST KOCHI
Project cost:
INR 30.31 Crores
Duration: 15 Months
Project Start date:
20 June 2019
End date (expected): 19 September 2020
Contractor:
M/s ABC Builders
Current status:
Topographical Survey completed for 3.71 KM.
Drainage desilting completed – 1 Km
Casting yard development works under progress
Batching plant erection under progress
KB Jacob Road - Utility Duct Casted – 20Nos
Challenges:
Slow progress in mobilization and finalization of proposals by the contractor
Underground and overhead utilities (KSEB, KWA & BSNL)
Handing over roads by the stakeholders to the Contractor.
Location map
Figure 2-10 Smart Road - West Kochi
Figure 2-11 Implementation schedule
List of Drawings issued to the Contractors
Sl
No.
Drawing Reference No.
Description of Drawing
Revision
Date
1 RD/SR/WK/GN-003
Layout of Bicycle Docking Station - Road 42
R0
01-Jul-19
2 RD/SR/WK/GN-002
Layout of Bicycle Docking Station - Santa
Cruze Road
R0
01-Jul-19
3
CSML/M08/POS/WTP/AR-001
Paving Pattern Detail - Bicycle docking area
R0
01-Jul-19
2.2.5
INTELLIGENT TRAFFIC MANAGEMENT SYSTEM (ITMS)
Project cost:
INR 26.90 Crores
Duration: 12 Months
Project Start date:
22 February
2019
End date (expected, excl. O&M):
21 February 2020
Contractor:
M/s KELTRON
Current status:
Agreement Signed, Bank Guarantee received, kick off meeting and Solution document
submitted on 18th May 2019
Road cutting locations, Signal pole locations, VMS locations, Control box locations and
Camera pole locations, Pelican Signal locations, have been identified.
Observation on Design Solution document submitted to KELTRON.
At
8 Junctions
work under progress for
Road Cutting, Cable Laying and Pole
Erection for installation of VA signals
Work under progress for erection of poles at 2 location for PTZ and RLVD cameras
Command and Control room - Work progressed in North Police Station and then as per
IG's instructions shifted to 12th Floor Revenue Tower.
Any Issues/ Challenges:
Timely permissions from relevant stakeholders for ITMS components installation which
will require tasks such as road cutting.
Delay in submission of control room layout.
Delay in response from KELTRON. Revision of solution document ongoing for more than
4 months.
Detailed drawings to be submitted for approval for road cutting (only line diagram
submitted)
KELTRON to chase all stakeholders for road cutting permissions
KELTRON to mobilise team
Road restoration
Project components
Figure 2-12 Ongoing work of Signal Placing and CCR
Figure 2-13 Implementation schedule
Module 5
Energy Supply
There were total of 16 projects identified under this module with serial number 5.1 to 5.16.
Based on the meetings conducted with KMC, KSEB and PWD these all projects have been
combined into one as it will be implemented along with Smart Roads.
S. No Proposed interventions REVISED Name of Project SCP Cost Clubbed / Segregated/ Estimated Cost Remarks 5.1 – 5.16 Compact Secondary Substation (990 KVA) Underground HT Line Underground LT Line LT UG for Streetlights AMR Metering - Single phase AMR Metering - Three phase AMR Metering - HT
RMU with Remote terminal units
Distribution panel board Installation of feeder pillars Underground Cabling - 11 KV LT UG Cabling
Installation of Transformers (Compact Sub-stations) Installation of Ring Main Units with Remote terminal units Smart Meters (AMR) Installation of feeder pillars
Development of Electrical
Infrastructure in ABD
12,253
7198
All projects have been clubbed LoA has been issued to M/s Polycab India Ltd.
The scope of projects is to implement System Improvement & Augmentation Scheme for
existing Electrical Network in various Smart Road area. The contractor’s scope of work
includes but not limited to: Survey, network design, manufacturing, Working testing,
inspection, packing, dispatching, loading, unloading and storage at site, transit/storage and
construction insurance, assembly, erection, civil structural work, complete
pre-commissioning checks, testing & pre-commissioning at site, obtaining statutory clearance &
certification from State Electrical Inspectorate, Kerala State Electricity Board, Kochi
Municipal Corporation etc. and handing over to the Owner after satisfactory commissioning
of complete augmentation of existing Electrical Network in Cochin Smart Mission Limited
Project ABD.
2.2.6
DEVELOPMENT OF ELECTRICAL INFRASTRUCTURE AT ABD
Project cost:
INR 71.97 Crores
Duration:
15 Months
Project Start date:
14th September
End date: 13th October, 2020
Contractor:
M/s Polycab India Pvt Ltd.
Current status:
LoA has been issued to M/s Polycab India Pvt Ltd on 17th August 2019.
Kick off Meeting held on 20th September 2019.
PBG has been submitted.
Joint Site visit with KSEB done for 5 Smart Roads
Schematic Diagram of Jos Junction and AM Road submitted to PMC/CSML &
KSEB for approval.
GTP of 11kV Cable, Polycab Make approved by PMC.
Concern:
Figure 2-14 Implementation schedule
Module 6
Energy efficiency
There were total of 2 projects identified under this module with serial number 6.1 to 6.2.
Based on the meetings conducted with Kerala State Electricity Board and Kochi Municipal
Corporation all projects are under scope of SPV implementation.
S. No
Proposed interventions REVISED Name of Project SCP Cost Clubbed / Segregated/ Estimated Cost Remarks
6.1 Solar based LED with Smart poles Smart LED Lights in ABD area 1,250 3209 LoA issued to M/s Schnell Energy Equipment Private Limited on 27th June 2019. Intelligent Street Poles in Kochi 30158 (PPP) DPR submitted Tender Cancelled.
6.2 Solar panels in Households and Institutions - Grid connected
Solar panels in Govt. buildings
1,758 570 Work awarded on
Nomination basis to BHEL. Work under implementation.
In module 6: Solar based LED with Smart poles has been mentioned as one single project.
Smart Pole & Solar LED are two different entities hence should be considered as two
different projects. Smart poles are proposed to be implemented as a PPP project.
Smart pole project now proposed by CSML board to be taken up on EPC. It combines 2
projects together Safety and Security and smart poles.
Progress of the Projects
2.2.7
SOLAR ROOFTOP PROJECT IMPLEMENTATION PROGRESS
The Contract agreement for the implementation of the project has signed on 24th
September 2018. The BHEL started site feasibility study and other paper works in the month
of December 2018. Clearance for installation of Solar panels has been given to BHEL for
26 buildings. The total capacity of solar panels in these buildings is 1000 KWp.
Project cost:
INR 5.70 Crores
Duration:
6 months + 2 months EOT
Project Start date:
24 September 2018
End
date
(expected,
excl.
O&M):30
September 2019
Contractor:
M/s BHEL
Current status:
Installation of Modules and inverter 100% completed.
Solar system has been commissioned in Gandhinagar Fires station.
Inspection of Court Complex and General Hospital by Electrical Inspectorate done.
Inspection completed by KSEB for General Hospital and court complex. (pre
commissioning check-up)
Final Clearance Energisation Certificate obtained = 4 District court, Old age home, General
Hospital
Liaising works with KSEBL and Electrical Inspectorate under progress for the
commissioning of the completed facilities.
Issues:
Approval for Dwg and site inspection from Electrical Inspectorate (EI).
Ladder with openable door installation for maintenance and EI inspection.
Additional DB shall be installed for conversion of single phase to three phase system for
Paramara and Perumbotta Ground Buildings as a variation item. Permanent electrical
connection to be obtained by Excise Department for completion of Solar System.
Inadequate site supervision/ frequent replacement of Site in charge by BHEL.
For 14 buildings, the connected load is less than installed solar capacity. Hence Service wire
need to be changed as extra item.
Way forward
BHEL to increase the staff strength of the implementation team.
BHEL to do rigorous follow-up with EI.
Presence of BHEL’s experienced Site in charge till the completion of the Project
Monthly project review Meeting between senior management team of BHEL with CSML and
PMC.
Project photographs
Figure 2-17 Kunnumpuram Higher Secondary School(20kW) Figure 2-18 Kunnumpuram Higher Secondary School(20kW)
Figure 2-19 Implementation schedule
2.2.8
Implementation of Smart LED Lights in ABD
Project cost:
Rs 32.06 crore
Duration:
15 Months
Project Start date:
01 August 2019
End date (expected): 01 February, 2021
Contractor:
M/s. Schnell Energy Equipment Private Limited
Current status:
Erection of 15 poles done at Jos Junction.
AB Cabling- Submitted drawing of 8 Access Roads to KSEB for approval.
Survey work of 32 Access roads completed.
Issues
HSE safety officer, electrical engineer, Civil engineer mobilized and Project manager to be
mobilized.
Figure 2-20 Led Lights at Jos Jn.
Figure 2-21 Implementation schedule
Module 7
Solid waste and Sanitation
There were total of 4 projects identified under this module with serial number 7.1 to 7.4.
Based on the meetings conducted with Kochi Municipal Corporation all projects are under
scope of CSML implementation. Only one project was proposed to be dropped by KMC as
it was not successful in earlier attempts made by Govt. Authorities.
S. No Proposed interventions REVISED Name of Project SCP Cost Clubbed / Segregated/ Estimated Cost Remarks 7.1 Equipment including Smart Street sweepers/ GPS 600 Segregated
S. No Proposed interventions REVISED Name of Project SCP Cost Clubbed / Segregated/ Estimated Cost Remarks
Supply, Operation and Maintenance of Portable
Compactor for
Secondary Storage & Transportation of Solid Waste
440 Tender Cancelled due to technical disqualification of bidder. Project to be retendered with new analysis.
Smart & Improved Battery-Operated Tricycles for Primary Waste Collection at West Kochi & Ernakulam in ABD Area
100 DPR submitted KMC
concurrence awaited to proceed with tendering