BAAQMD Proposed NSR Changes:
Case Study for PSD Applicability
Oakland, CA ♦ April 5, 2012
Objectives
˃ Highlight key PSD Applicability Principles ˃ Calculation Basis
˃ Review Case Study Based on Proposed BAAQMD
Regulations
Proposed PSD Project Definition
˃ A new source or a modified source, or a combination of such new or
modified sources that are part of a single common project that falls into one of the following groups:
New Sources: Plant will be a major source
(>major source threshold of 100 or 250 tons/year or 100,000 tons/year of GHG (CO2e))
Existing Minor Sources: Make a modification that in itself is “major”
(>major source threshold of 100 or 250 tons/year or 100,000 tons/year of GHG (CO2e))
Existing Major Sources: Make a modification that exceeds PSD
Significant Emission Rates (SER)
Proposed Modified Source Definition
˃ Any physical change, change in method of operation, change in throughput or production, or other similar change at an existing source, that results in an increase in daily or annual emissions in any of the following amounts:
If the source’s daily and/or annual emissions are subject to an
enforceable permit limit established by NSR requirements (BAAQMD Reg.2, Rule 2, 40 CFR 52.21, or NSR avoidance), an increase in the source’s PTE above such permitted limit.
If the source’s daily and/or annual emissions are not subject to
any enforceable limit as described above, an increase in the source’s actual physical capacity to emit air pollutants as
installed and operated at the facility, above the lowest of the following:
♦ The maximum operational capacity of the source; ♦ The effective capacity of the source; or
Project Emission Increase (PEI)
Calculation Basis
˃
New Source EI = PTE
˃
Existing Source EI = Post Project PTE – BE
Baseline Emissions (BE) = average emissions from
a 3 year period prior to complete application
BE adjusted downward to reflect current
permitted limits
˃
PEI =
Σ
New Source EI +
Σ
Existing Source EI
˃
If PEI > SER, evaluate Net Emission Increase
Net Emission Increase (NEI)
Calculation Basis
˃ If PEI is greater than SER, can attempt to “net-out” of PSD review ˃ Net Emission Increase equals:
Project Emissions Increase minus
source-wide creditable contemporaneous decreases plus
source-wide creditable contemporaneous increases
˃ The contemporaneous period is the period ranging from 5 years
prior to the complete application date to the time normal operation commences for that change
˃ Contemporaneous Increases and Decreases are calculated as Post
Project PTE minus BE
Proposed BAAQMD Rules
Baseline Emissions = 20 tpy PTE = 50 tpy
Project Emission Increase = 30 tpy PM10 SER = 15 tpy
PSD is triggered (unless you can “net-out”)
Comparison of
Federal vs BAAQMD Proposed Rules
Year* PM10Actual Emissions 2009 15 tpy 2010 20 tpy 2011 25 tpy PTE 50 tpy 2015 35 tpy (projected) Year* PM10Actual Emissions 2010 20 tpy 2011 25 tpy 2012 30 tpy (projected) 2013 30 tpy (projected) 2014 32 tpy (projected) 2015/16 33 tpy (projected) Federal Rules
Baseline Actual Emissions = 22.5 tpy Projected Actual Emissions = 33 tpy Project Emission Increase = 10.5 tpy PM10 SER = 15 tpy
Case Study: Facility Expansion
˃ Facility pre-project PTE: 300 tpy NOx (major PSD source)
˃ Facility proposes the following:
Physically modify Emission Unit #1 to increase capacity
Install a new 100 MMBtu/hr natural gas boiler
Shut-down Emission Unit #2
˃ Historical Permitting:
2009: Installed Emission Unit #1
˃ Timing:
Emission Unit #2 will permanently shut-down prior to
modified Emission Unit #1 beginning normal operation.
The new boiler will begin normal operation concurrent with
Case Study: Significant Increase
˃ Only include project increases
˃ Assume the following:
Complete application: 01/2013
No new permit limits or permit exceedances during baseline period Example only evaluates NOx emissions
EU#1 currently has an annual PTE of 10 tpy NOxand post project PTE will be 15 tpy
NOx(therefore, EU#1 is a modified unit)
Emission Unit 2010 2011 2012 BE (tpy) PTE (tpy) Emission Increase (tpy) Emission Unit #1 3 5 7 5 15 10 New Boiler - - - 0 43 43 Totals: 5 58 53 NOx SER: 40 tpy
Case Study: Significant Net Increase
˃ Add in all contemporaneous increases and decreases between 01/2008 and 01/2015
˃ Assume the following:
Complete application: 01/2013 Emission Unit #1 installed: 2009
Emission Unit #2 shut-down: 12/2014
Project is complete and operational by 01/2015
No new permit limits or permit exceedances during baseline period.
How do you treat separate projects that occur in the contemp. period on the same emission
unit? Separately, as in the example below?
Emission Unit 2012 2013 2014 BE (tpy) PTE (tpy) Emission Increase (tpy)
Significant Increase, Project 5 58 53 EU #1, Initial Installation 0 10 10 EU #2, Shut down 15 17 16 16 0 -16
Total: 14 78 47
Conclusions/Comments
˃ Pay very close attention to the definition of modified
unit prior to conducting a PSD applicability assessment
˃ The proposed rules are less favorable for determining
baseline emissions for PSD (calculation methodology and adjustment)
˃ It is unclear how to treat multiple contemporaneous
projects that revolve around the same emission unit
˃ Currently, the proposed rules do NOT include a PM SER ˃ PSD Applicability can get very Complicated. Make sure