Data Centre Reliability
and Redundancy
What do they mean and are you
are getting what you need?
What's the message?
• Why consider Reliability and Redundancy?
• How do you know what Reliability and/or
Redundancy is required for your Data Centre?
• How do you communicate to the design
engineer?
• How does the design engineer communicate to
you?
• What are the typical issues and what can
typically go wrong?
• How to consider Reliability and Redundancy?
• Summary.
Why?
•
Why do we need to consider Reliability
and Redundancy?
1. Equipment or system Reliability can not be
guaranteed.
2. All equipment and systems require some
form of maintenance, repair and/or
replacement at some time.
3. Data centre users require certainty of
operation.
Reliability vs Redundancy
Reliability
Redundancy
None
100%
None
How?
•
How do you know what Reliability and/or
Redundancy is required for your Data
Centre?
1. Understand the intended Data Centre use.
2. Understand stakeholder expectations.
3. Understand the reliability of the equipment
proposed.
4. Understand the Reliability of the available
energy and water supplies.
How?
•
How do you communicate to the design
engineer?
•
How does the design
engineer communicate
to you?
Agree on a common
language!
What are the typical issues?
• Very complicated operational and servicing
inter-relationships.
• Poor briefing / wrong language used.
• Inadequate budget to meet brief.
• Downtime for repairs or maintenance.
• Cheaper equipment may be less reliable and
therefore require greater redundancy.
• Key stakeholders on ‘different pages’.
• Testing and Commissioning.
• Who will operate and maintain the systems?
• Understanding the various classifications, 999,
What can typically go wrong?
• Design does not meet the project
requirements.
• Single Point of Failure not properly
analysed.
• Partial or Multiple equipment failures not
considered properly.
• Equipment is not tested or commissioned
properly.
What else can go wrong?
• Complex systems difficult for technicians
to understand and maintain.
• Routine and/or monitored equipment
• End user compromises design through
poor change management.
• End user doesn’t understand design
principles.
How to consider Reliability and
Redundancy?
• Mean Time To Repair (MTTR)
• Mean Time To Failure (MTTF)
• Mean Time Between Failure (MTBF)
• Availability (MTBF / MTBF + MTTR)
• MIL-STD-756B
• Single Point Of Failure (SPOF)
• Failure Mode Analysis (FMA)
• Steady State Operation (SSO)
• TIA 942 Tier system
What is the relationship between
MTBF and Reliability?
• Reliability theory is a statistical approach to predicting
equipment failures.
• It can become very difficult to interpret in relation to Data
Centre infrastructure.
• Basic Theory is;
• MTBF = Mean Time Between Failure
• This is actually defined as the inverse of the failure rate
over a given time period.
• That is…failure rate (say failures per hour)
λ = 1/MTBF
• This then allows Reliability over a particular time period
to be estimated using an exponential equation of
MTBF Misconceptions
• Often thought to mean a certain
guaranteed time between failures.
• THIS IS NOT CORRECT!
• It is a calculated statistical average
assuming a constant failure rate.
• MTBF does NOT account for Infant
Mortality (Burn in) that occurs during
factory batch testing and specific project
commissioning activities.
More MTBF Misconceptions
• MTBF is NOT service life.
• Service life is determined by specific component
usage requirements and is addressed by
monitored and/or routine maintenance or
replacement regimes.
• An example of this is UPS battery replacement
and generator bearing replacements.
• It is important to note that in some cases MTBF
can exceed the service life of a component.
LED light fitting example
• MTBF
= 200,000 hours
• Duration of service (t) = 8,760 hours (1yr)
• Number of units
= 1000
• Reliability
= 95.62%
• Failure rate
= 4.38%
UPS System example
• MTBF
= 100,000 hours
• Duration of service (t) = 43,800 hours
(5y)
• Number of units
= 2
• Reliability
= 65%
• Failure rate
= 35%
Result
• It is therefore important to understand that
it is almost certain that one UPS will fail
over a 5 year period.
• Based on this understanding there must
be an expectation that any particular item
of critical plant will fail unexpectedly at
What does Reliability mean?
• Different things to different people!
• ICT vs Power vs Cooling.
• Short term power failure can result in long
term ICT failure.
• Short term cooling failure may not be critical.
• Can be defined as determining the risk of
Redundancy requirements
• Need to respond to equipment and / or
system failures.
• Depends on the specific Data Centre
requirements.
• Depends on the equipment installed.
• Depends on the tolerable ICT downtime
permissible.
• Depends on the specific system design
characteristics.
Communicating Redundancy
• We need a common language that
communicates redundancy
• There are very few recognized standards
that can be used
• One that has been useful is ANCI/TIA/942
• This is an American Standard and
therefore needs to be used carefully in
Australia.
Overview of Data Centre Critical
Systems
• ANSI/TIA 942 has an appendix that
addresses various aspects of redundancy
• It expands on the Uptime Institute Tier
System.
• The appendices cover components of a
Data Centre that affect reliability and
redundancy including Architectural,
Structural and fire systems in addition to
Mechanical and Electrical.
TIA 942 – Architectural (1)
Uptime Tiering
Reference
Site Selection
Proximity to flood hazard as
mapped on the federal flood
hazard boundry or flood
insurance map
No Requirement
Not in 50 year Flood
hazard area
Not within 100 year flood hazard
area and greaterthan 91m (300ft)
from 50 year flood hazard area
Greater than 91m (300ft) from
100 year flood hazard
Proximity to costal or inland
waterways
No Requirement
No Requirement
greater than 91m (300ft)
Greater than 0.8km (1/2 mile)
Proximity to major highway
trafic arteries
No Requirement
No Requirement
greater than 91m (300ft)
Greater than 0.8km (1/2 mile)
Proximity to major airports
No Requirement
No Requirement
Greater than 1.6km (1 mile) and
less than 48km (30 miles)
Greater than 8km/5 miles and
less than 48km/30 miles
Proximity to major
metropolitan area
No Requirement
No Requirement
less than 48km (30 miles)
less than 16km (10 miles)
Separate visitor and
employee parking areas
No Requirement
No Requirement
yes (physically separated with
separate enteries)
yes (physically separated by
fence or wall with separate
enteries)
Separate from loading docks
No Requirement
No Requirement
yes (physically separated with
separate enteries)
yes (physically separated by
fence or wall with separate
enteries)
Proximity of visitor parking to
data centre perimiter building
walls
No Requirement
No Requirement
9.1m (30 ft) minimum separation
with physical barrier to prevent
vehicle from driving closer
18.3m (60 ft) minimum
separation with physical
barrier to prevent vehicle
from driving closer
Multi-tenant occupancy
No Restriction
Allowed if occupancies
non- hazardous
Allowed if tenants are Data
Cenntres or Telecommunications
companies
Allowed if tenants are Data
Cenntres or
Telecommunications
Parking
Tier 4
Architectural
TIA 942 – Architectural (2)
Building Construction
Type of construction
No Restriction
No Restriction
Type IIA,IIIA or VA
Type 1A or 1B
Exterior bearing walls
Code requirement
Code requirement
1 Hour Minimum
4 Hours Miinimum
Interior bearing walls
Code requirement
Code requirement
1 Hour Minimum
2 Hours Minimum
Exterior nonbearing walls
Code requirement
Code requirement
1 Hour Minimum
4 Hours Miinimum
Structural frame
Code requirement
Code requirement
1 Hour Minimum
2 Hours Minimum
Interior non-computer room
walls
Code requirement
Code requirement
1 Hour Minimum
1 Hour Minimum
Interior computer room walls Code requirement
Code requirement
1 Hour Minimum
2 Hours Minimum
Shaft enclosures
Code requirement
Code requirement
1 Hour Minimum
2 Hours Minimum
Floors and Floor-ceilings
Code requirement
Code requirement
1 Hour Minimum
2 Hours Minimum
Roofs and roof-ceilings
Code requirement
Code requirement
1 Hour Minimum
2 Hours Minimum
Compliance with NFPA 75
No Requirement
Yes
Yes
Yes
Vapour barriers for computer
room
No Requirement
Yes for walls no
requirements for ceilings
Yes
Yes
building entrances with
security checkpoints
No Requirement
No Requirement
Yes (primary building entrance
manned)
Yes (primary building
entrance manned)
Access Floor Panel
construction (when provided)
No Requirement
No Requirement
Computer grade all steel
Computer grade all steel or or
computer grade steel with
concrete filled
Understructure (when access
floor is provided)
No Requirement
No Requirement
Bolted stringer
Bolted stringer with 1.2m x
1.2m (4 ft x 4 ft) basket weave
patten
Fire Resistive Requirements
TIA 942 – Architectural (3)
Ceiling construction
No Requirement
No Requirement
If provided - suspended with
clean room class 10M-100M
perforated tiles
Suspended with clean room
class 100 non perforated vinyl
coated gypsum board tiles
Ceiling Height (above raised
access floor if provided)
2.6m (8.5 ft) minimum
2.7m (9.0 ft) minimum
3.0m (10 ft) minimum (not less
than 460mm (18 in) above tallest
piece of equipment)
3.0m (10 ft) minimum (not less
than 600mm (24 in) above
tallest piece of equipment)
Class
No Restrictions
Class A
Class A
Class A
Type
No Restrictions
No Restrictions
redundant with
Non-combustible deck (no
mechanically attached systems)
Double redundant with
concrete deck (no
mechanically attached
systems)
Wind Uplift resistance
Minimum code
requirements
FM I-90
FM I-90 minimum
FM I-120 minimum
Roof slope
Minimum code
requirements
Minimum code
requirements
1:48 (1/4 in per foot) minimum
1:24 (1/2 in per foot) minimum
Fire Rating
Minimum code
requirements
Minimum code
requirements
Min Code Req, not less than 0.75
hour at Computer room
Min Code req, not less than
1.5 hours at Computer Room
Door Size
Minimum code
requirements
Minimum code
requirements
Min Code Req, not less than 1m
wide and 2.13m High
Min Code Req, not less than
1.2m wide and 2.13m High
Windows on perimiter of
computer room
Allowed with minimum
Code required fire
rating
Allowed with minimum
Code required fire rating
interior windows allowed with
minimum 1 hour fire rating no
exterior windows allowed
interior windows allowed
with minimum 1 hour fire
rating no exterior windows
allowed
Ceilings with in Computer areas (when provided)
Roofing
TIA 942 - Architectural (4)
Physically Separate from
other areas of Data Centre
No Requirement
Yes
Yes
Yes
Fire separation from other
areas of Data Centre
Minimum code
requirements
Minimum code
requirements
Minimum code requirements (not
less than 1 Hour)
Minimum code requirements
(not less than 2 Hour)
Security Counter
No Requirement
No Requirement
Yes
Yes (physically separated)
Single person interlock to
prevent pass back
No Requirement
No Requirement
Yes
Yes
Physically Separate from
other areas of Data Centre
No Requirement
Yes
Yes
Yes
Fire separation from other
areas of Data Centre
Minimum code
requirements
Minimum code
requirements
Minimum code requirements (not
less than 1 Hour)
Minimum code requirements
(not less than 2 Hour)
Security Office
No Requirement
No Requirement
Yes
Yes
Physically Separate from
other areas of Data Centre
No Requirement
No Requirement
Yes
Yes
Fire separation from other
areas of Data Centre
Min Code Req
Min Code Req
Not less than 1 Hour
Not Less than 2 Hours
180 deg peepholes on
Security equipment and
rooms
No Requirement
Yes
Yes
Yes
Dedicated and hardened
security equipment and
monitoring rooms
No Requirement
Yes
Yes, with 16mm (5/8) plywood
walls and solid core door
Yes, with 16mm (5/8) plywood
walls and solid core door
Operations Centre physically
Separate from other areas of
Data Centre
No Requirement
No Requirement
Yes
Yes
Fire separation from other
areas of Data Centre
No Requirement
No Requirement
1 Hour
2 Hours
Proximity to computer room
No Requirement
No Requirement
Indirectly accessable (maximum
of 1 adjoining room)
Directly accessable
Adminstrative Offices
Operations Centre
Entry Lobby
TIA 942 - Architectural (5)
Proximity to computer roomand support areas
No Requirement No Requirement If immediately adjacent, provided with leak prevention barrier
Not immediately adjacent and provided with leak prevention barrier
Fire separation from computer room and support areas
Minimum code requirements
Minimum code requirements
Minimum code requirements (not less than 1 Hour)
Minimum code requirements (not less than 2 Hour)
Aisle widths for maintenance, repair, or equipment removal
No Requirement No Requirement Minimum code requirements (not less than 1m (3 ft) clear)
Minimum code requirements (not less than 1.2m (4 ft) clear) Proximity to computer room No Requirement No Requirement Immediately adjacent Immediately adjacent
Fire separation from other areas of Data Centre
Minimum code requirements
Minimum code requirements
Minimum code requirements (not less than 1 Hour)
Minimum code requirements (not less than 2 Hour)
Required Exit Corridors Fire separation from computer room and support areas
Minimum code requirements
Minimum code requirements
Minimum code requirements (not less than 1 Hour)
Minimum code requirements (not less than 2 Hour)
Width Min Code Req Min Code Req Minimum code requirements and
not less than 1.2m (4 ft) clear
Minimum code requirements and not less than 1.5m (5 ft) clear
Shipping and receiving area physically Separate from
No shipping and receiving area provided
no Yes Yes
Fire separation from other areas of Data Centre
Min Code Requirement if shipping and
receiving area present
Minimum code requirements
Not less than 1 Hour Not Less than 2 Hours
Physical protection of walls exposed to lifting equipment traffic
No Requirement No Requirement Yes (minimum 19mm (3/4 in) plywood wainscot)
Yes (steel bollards or similar protection)
Number of Loading docks No Requirement 1 per 2500sqm of computer room
1 per 2500sqm of computer room (2 Minimum)
1 per 2500sqm of computer room (2 Minimum)
Proximity to computer room and support areas
No Requirement No Requirement If within Data Centre Building - min 2 Hour separation from all other areas
Separate building or exterior weatherproof enclosures with Code required building separation
Proximity to publicly accessable areas
No Requirement No Requirement 9m (30 ft) or greater separation 19m (60 ft) or greater separation
Generator and Fuel Storage areas Restrooms and Break room areas
UPS and Battery Rooms
TIA 942 – Security (1)
Uptime Tiering
Reference
Security
Tier 1
Tier 2
Tier 3
Tier 4
System CPU UPS capacity
No requirement
Building
Building
Building + 8 hour
Battery minimum
Field Panels UPS capacity
No requirement
Building + 4 hourr Battery
minimum
Building + 8 hour Battery
minimum
Building + 24 hour
Battery minimum
Field Device UPS capacity
No requirement
Building + 4 hourr Battery
minimum
Building + 8 hour Battery
minimum
Building + 24 hour
Battery minimum
Dedicated Security staff per
shift
No security staffing provided
1 per 3000 sqm (1 Minimum)
1 per 2000 sqm (2 Minimum)
1 per 2000 sqm (3
Minimum)
No of 8 hour security shifts
No requirement
1 (minimum 5 days per week)
2 (7 days per week)
3 (7 days per week)
Generators
Industrial grade lock
Intrusion Detection
Card Access
Card Access
UPS, Telephone & MEP
Rooms
Industrial grade lock
Intrusion Detection
Card Access
Card Access
Fiber Vaults
Industrial grade lock
Intrusion Detection
Intrusion Detection
Card Access
Emergency Exit Doors
Industrial grade lock
Monitor
Delay egress per code
Delay egress per code
Accessible exterior
windows/openings
No Monitoring
Intrusion Detection (with offsite
monitoring during shifts when no
security staff is present)
Intrusion Detection (with offsite
monitoring during shifts when
no security staff is present)
Intrusion Detection
Security Operations Centre
No requirement
No requirement
Card Access
Card Access
Network Operations Centre
No requirement
No requirement
Card Access
Card Access
Security Equipment Rooms
No requirement
Intrusion Detection
Card Access
Card Access
TIA 942 – Security (2)
Doors into computer rooms
Industrial grade lock
Intrusion Detection
Card or biometric access for
ingress
Card or biometric
access for ingress and
egress
Perimiter Building doors
No requirement
Intrusion Detection
Card access if main entrance;
intrusion detection all others
Card access if all
entrance
Main door onto computer
room floor
Industrial grade lock
Card Access
Single person Interlock to
prevent passback
Single person interlock
to prevent passback,
with biometric
Security counter in lobby
No requirement
No requirement
Level 3 minimum
Level 3 minimum
Security counter in shipping
and receiving
No requirement
No requirement
No requirement
Level 3 minimum
CCTV Monitoring
Building Perimiter and
parking
No requirement
No requirement
Yes
Yes
Generators
No requirement
No requirement
Yes
Yes
Access Controlled doors
No requirement
Yes
Yes
Yes
Computer room floors
No requirement
No requirement
Yes
Yes
UPS, Telephone & MEP
Rooms
No requirement
No requirement
Yes
Yes
CCTV
CCTV recording of all
activity on all cameras
No requirement
No requirement
Yes - Digital
Yes - Digital
Recording rate (Frames/sec)
No requirement
No requirement
20 frames/sec min
20 frames/sec min
TIA 942 - Structural
Uptime Tiering Reference
Structural Tier 1 Tier 2 Tier 3 Tier 4
Any seismic zone acceptable, but may require special support mechanisms
No Restriction No Restriction No Restriction No restriction
Facility designed to seismic zone requirements No Restriction No Restriction No Restriction In seismic zone 0, 1, 2 to Zone 3 requirements, in siesmic zone 3 & 4 to
Zone 4 requirements Site specific response spectra - degree of local
seismic accelerators
No No With operation status after 10% in
50 year event
With operation status after 5% in 100 year event
Importance factor I=1 I=1.5 I=1.5 I=1.5
Telcommunications equipment racks/cabinets anchored at base or supported top and bottom
No Base only Fully braced Fully braced
Deflection limitations on telcommunications equipment within acceptable limits
No No Yes Yes
Bracing of electrical conduits and cable trays Per code Per code with importance factor Per code with importance factor Per code with importance factor Bracing of mechanical system major duct runs Per code Per code with importance factor Per code with importance factor Per code with importance factor Floor loading capacity superimposed live load 7.2kPa (150lbf/sqsf) 8.4kPa (175lbf/sqft) 12kPa (250lbf/sqsf) 12kPa (250lbf/sqsf)
Floor hanging capacity for ancillary loads suspended from below
1.2kPa (25lbf/sqsf) 1.2kPa (25lbf/sqsf) 2.4kPa (50lbf/sqsf) 2.4kPa (50lbf/sqsf)
Concrete slab thickness at ground 127mm 127mm 127mm 127mm
Concrete topping over flutes for elevated floors affects size of anchor which can be installed
102mm 102mm 102mm 102
Building LFRS (Shearwall/braced
frame/moment frame) indicates displacement of structure
Steel/Conc MF Conc.Shearwall/Steel BF Conc.Shearwall/Steel BF Conc.Shearwall/Steel BF
Building Energy Dissipation - Passive Dampers/base isolation (energy absorption)
None None Passive dampers Passive dampers/Base isolation
Battery/UPS floor vs building composition. Concrete floors more difficult to upgrade for intense loads. Steel framing with metal deck and fill much more easily upgraded
PT Concrete CIP Mild Concrete Steel Deck & Fill Steel Deck & fill
Steel deck and Fill/ Pre tension concrete/ CIP Mild - PT slabs much moore difficult to install anchors
TIA 942 – Electrical systems (1)
Uptime Tiering
Reference
Electrical Tier 1 Tier 2 Tier 3 Tier 4
Ststem allowance concurrent maintenance
No Down to but not including UPS Output Panelboards
Down to but not including Power Distribution Units
Throughout Distribution Systems
Single points of failure One or more single points of failure fo rthe distribution systems
serving electrical equipment or mechanical
systems
One or more single points of failure fo rthe distribution systems serving electrical equipment or mechanical
systems
No more than single points of failure for the distribution systems serving electrical equipment or mechanical
systems
No single points of failure fo rthe distribution systems serving electrical equipment
or mechanical systems
Power Syatem Analysis Short Circuit Study Coordination Study Arc
Falsh Analysis
Short Circuit Study Coordination Study Arc Falsh
Analysis
Short Circuit Study Coordination Study Arc Falsh Analysis Load Flow
Study
Short Circuit Study Coordination Study Arc Falsh Analysis Load Flow
Study Computer and
Telecommunications Equipment Power Cords
Single cord feed with 100% capacity
Single cord feed with 100% capacity
Redundant cord feed with 100% capacity on remaining
cord or cords
Redundant cord feed with 100% capacity on remaining
cord or cords
Utility entrance Single feed Single feed N+1 Redundant Feed 2N Redundant Feed from
different utility substations Main Utility Switchboard
Service Shared Dedicated Dedicated Dedicated
Construction Panel Board with bolt on circuit breakers
Switchboard with stationary circuit breakers
Switchboard with drawout circuit breakers
Switchboard with drawout circuit breakers
Surge Suppression Optional Optional Yes Yes
Generators correctly sized for UPS
Yes Yes Yes Yes
Utility
Uninterruptible Power Supply System General
TIA 942 – Electrical systems (2)
Redundancy N N N+1 2N
Topology Single or Parallel
Modules
Single or Parallel Modules with Static Bypass
Parallel Redundant modules, Distributed Redundant Modules or Block Redundant
Systems
Parallel Redundant modules, Distributed Redundant Modules or Block
Redundant Systems
Automatic Bypass None Non dedicated maintenance
bypass feeder to UPS output switchboard
Dedicated maintenance bypass feeder to UPS output
switchboard
Dedicated maintenance bypass feeder to UPS output
switchboard Maintenance Bypass
arrangement
Bypass from same source Bypass from same source Bypass from same source Bypass from reserve UPS system
Output Power Distribution Panelboard incorporating standard thermal magnetic trip breakers
Panelboard incorporating standard thermal magnetic trip
breakers
Panelboard incorporating circuit breakers that are coordinated under overload
and ground fault current condition
Panelboard incorporating circuit breakers that are
coordinated under all overcurrent conditions Battery String Common string for
multiple modules
Dedicated string for each module
Dedicated string for each module
Dedicated string for each module
Battery Type 5 year valve regulated lead acid
10 year valve regulated lead acid or flood type
15 year valve regulated lead acid or flood type
20 year lead acid flood type Battery Minimum Backup
Time
5 minutes 7 minutes 10 minutes 15 minutes
Battery Monitoring System Optional Optional String level by UPS system Centralised automated system to check each cell for, voltage and impedance
or resistance
Flywheel Allowed Allowed Allowed Allowed
Power Distribution Unit
Transformer Optional K-rated or harmonic
cancelling
K-rated or harmonic cancelling, Front accessable
for maintenance
K-rated or harmonic cancelling low inrush, Front accessable for maintenance
Overcurrent Device NA Fuse Circuit breaker Circuit breaker
Maintenance Bypass NA Manual non Guided Manual Guided Manual Guided
Output NA Single circuit breaker Dual circuit breaker Dual circuit breaker
TIA 942 – Electrical systems (3)
Grounding
Lighting Protection System
Based on Risk analysis
Based on Risk analysis
Yes
Yes
Service entrance grounds
and generator grounds fully
comply to NEC or local
codes
Yes
Yes
Yes
Yes
Data Centre grounding
infrastructure in Computer
room
Optional
Optional
Yes
Yes
Installation
Do not install if not
required by Authorities
having juristriction
Do not install if not required by
Authorities having juristriction
Do not install if not required
by Authorities having
juristriction
Do not install if not required
by Authorities having
juristriction
Test Mode
Optional
Optional
Yes
Yes
Alarm
Optional
Optional
Yes
Yes
Abort Switch
Optional
Optional
Yes
Yes
Monitored Points
None
Utility, UPS, Generator
Utility, Main Transformer,
UPS, Generator, Automatic
Static Switch, PDU,
Automatic Transfer Switches
Utility, Main Transformer,
UPS, Generator, Automatic
Static Switch, PDU,
Automatic Transfer
Switch,es, Surge Protection
Devce, Critical Load Branch
Circuits
Notification Method
NA
Control Room console
Control Room console,
Pager, email, Text message
Control Room console,
Pager, email, Text message
Computer Room Emergency Power Off (EPO) System
TIA 942 – Electrical systems (4)
Separate room
No
Yes
Yes
Yes
Individual battery banks
isolated from each other
No
Yes
Yes
Yes
Shatterproof viewing glass
in Battery room door
No
No
No
Yes
Generator Sizing
Sized for UPS System
only
Sized for UPS & mechanical
System
Sized for total building load
with N+1 redundancy
Sized for total building load
with 2N redundancy
Generators on single bus
Yes
Yes
Yes
No
Installation
None
Provision for portable
Provision for portable
Permenant
Equipment Tested
NA
Generator
Generator, UPS
Generator, UPS
Auto Shutdown
NA
None
Automatic upon failure of
utility
Automatic upon failure of
utility
Factory Acceptance Testing
Optional
Optional
Yes
Yes
Site Circuit Breaker Testing
Optional
Optional
Contact resistance test for all
critical circuit breakers in
critical and essential paths,
225 Amps and higher
Primary injection and
Contact resistance test for
all critical circuit breakers in
critical and essential paths,
225 Amps and higher
Commissioning
Optional
Component level, system level
Component level, system
level, Integrated system
Component level, system
level, Integrated system
Testing
Battery Room
Standby Generating Systems
TIA 942 - Maintenance
Uptime Tiering Reference
Maintenance Staff
On site day shift Only.
On call at other times
On site day shift Only.
On call at other times
On site 24 hrs M-F, on-call
weekends
Onsite 24 x 7
Preventative Maintenance
None
None
Limited preventative
maintenance program
Comprehensive preventative
maintenance program
Facility Training Programs
None
None
Comprehensive training
program
Comprehensive program including
manual operation procedures if it is
necessary to bypass control system
Tier 4
TIA 942 – Mechanical systems (1)
Uptime Tiering Reference
General
Routing of water or drain
piping not associated with the
Data Centre Equipment in data
centre spaces
Permitted but not
recommended
Permitted but not
recommended
Not Permitted
Not permitted
Positive pressure in comuter
room and associated spaces
relative to outdoors and non
data centre spaces
No requirement
Yes
Yes
Yes
Floor drains in computer room
for condensate drain water,
humidifers flush water and
sprinkler discharge water
Yes
Yes
Yes
Yes
Mechanical systems on
Standby generator
No requirement
Yes
Yes
Yes
Water Cooled Systems
Indoor terminal Air
Conditioning units
No Redundant units
One redundant AC unit per
critical area
Qty of A/C units sufficent to
mainain critical area during loss
of one source of electrical power
Qty of A/C units sufficent to
mainain critical area during loss
of one source of electrical power
Humidity control for Computer
rooms
No requirement
Humidification provided
Humidification provided
Humidification provided
Electrical Service to
Mechanical Equipment
Single path of Electrical
power to A/C equipment
Single path of Electrical
power to A/C equipment
Multiple paths of electrical power
to AC equipment. Connected in
checkerboard fashion for cooling
redundancy
Multiple pathsof electrical power
to AC equipment. Connected in
checkerboard fashion for cooling
redundancy
Mechanical
TIA 942 – Mechanical systems (2)
Heat Rejection Dry Coolers (w here applicable)
No redundant dry coolers One redundant unit per system
Qty of units sufficent to provide minimal temporary capacity to critical area during loss of one
source of electrical pow er
Qty of units sufficent to mainain critical area during loss of one
source of electrical pow er Closed- circuit fluid coolers
(w here applicable)
No redundant fluid coolers One redundant unit per system
Qty of units sufficent to provide minimal temporary capacity to critical area during loss of one
source of electrical pow er
Qty of units sufficent to mainain critical area during loss of one
source of electrical pow er Circulating pumps No redundant condenser
w ater pumps
One redundant unit per system
Qty of units sufficent to provide minimal temporary capacity to critical area during loss of one
source of electrical pow er
Qty of units sufficent to mainain critical area during loss of one
source of electrical pow er Piping system Single path condenser
w ater system
Single path condenser w ater system
Headed parallel piped condenser w ater system
Dual path condenser w ater system
Chilled Water System Indoor Terminal Air Conditioning units
No Redundant AC units One redundant AC unit per critical area
Qty of units sufficent to provide minimal temporary capacity to critical area during loss of one
source of electrical pow er
Qty of A/C units sufficent to mainain critical area during loss of one source of electrical pow er Humidity Control for Computer
rooms
No requirement Humidification provided Humidification provided Humidification provided Electrical Service to
Mechanical Equipment
Single path of Electrical pow er to A/C equipment
Single path of Electrical pow er to A/C equipment
Multiple paths of electrical pow er to AC equipment
Multiple paths of electrical pow er to AC equipment
Heat Rejection
Chilled Water Piping System Single path chilled w ater piping system
Single path chilled w ater piping system
Dual path ladder drop chilled w ater system w ith isolation valves
Dual path chilled w ater system
Chilled Water Pumps No Redundant units One redundant unit per system
Qty of units sufficent to mainain critical area during loss of one
source of electrical pow er
Qty of units sufficent to mainain critical area during loss of one
source of electrical pow er Air-cooled Chillers No Redundant units One redundant unit per
system
Qty of units sufficent to provide minimal temporary capacity to critical area during loss of one
source of electrical pow er
Qty of units sufficent to maintain critical area during loss of one
source of electrical pow er Water Cooled Chillers No Redundant units One redundant unit per
system
Qty of units sufficent to provide minimal temporary capacity to critical area during loss of one
source of electrical pow er
Qty of units sufficent to maintain critical area during loss of one
source of electrical pow er Cooling Tow ers No Redundant units One redundant unit per
system
Qty of units sufficent to provide minimal temporary capacity to critical area during loss of one
source of electrical pow er
Qty of units sufficent to maintain critical area during loss of one
source of electrical pow er Condenser Water Pumps No Redundant units One redundant unit per
system
Qty of units sufficent to provide minimal temporary capacity to critical area during loss of one
source of electrical pow er
Qty of units sufficent to maintain critical area during loss of one
source of electrical pow er Condenser Water Piping
System
Single path condenser w ater system
Single path condenser w ater system
Headed parallel piped condenser w ater system
Dual path condenser w ater system
TIA 942 – Mechanical systems (3)
Air-Cooled Systems
Indoor Terminal Air
Conditioning units/Outdoor
Condensors
No Redundant AC units
One redundant AC unit per
critical area
Qty of AC units sufficent to
provide minimal temporary
capacity to critical area during
loss of one source of electrical
power
Qty of A/C units sufficent to
mainain critical area during loss
of one source of electrical power
Electrical Service to
Mechanical Equipment
Single path of Electrical
power to A/C equipment
Single path of Electrical
power to A/C equipment
Multiple paths of electrical power
to AC equipment
Multiple paths of electrical power
to AC equipment
Humidity control for Computer
rooms
No requirement
Humidification provided
Humidification provided
Humidification provided
HVAC Control System
HVAC Control System
Control system failure will
interrupt cooling to critical
area
Control system failure will
not interrupt cooling to
critical area
Control system failure will not
interrupt cooling to critical area
Control system failure will not
interrupt cooling to critical area
Power source to HVAC control
system
Single path of Electrical
power to HVAC control
system
Redundant, UPS electrical
power to BMS control
Redundant, UPS electrical power
to BMS control
Redundant, UPS electrical power
to BMS control
Plumbing (for Water-cooled
heat rejection)
Make-up Water
Single water supply with no
on-site storage
Dual sources or one source
+ on-site storage
Dual sources or one source +
on-site storage
Dual sources or one source +
on-site storage
Points of connection to
condenser water system
TIA 942 – Fuel Oil
Uptime Tiering Reference
Bulk Storage tanks
Single storage tank
Single storage tanks
Multiple storage tanks
Multiple storage tanks
Storage tanks, pumps and
piping
Single pump and/or
supply pipe
Multiple pumps and
multiple supply pipes
Multiple pumps and
multiple supply pipes
Multiple pumps and
multiple supply pipes
Generator fuel capacity at full
load
8 hrs
24 hrs
72 hrs
96 hrs
Tier 4
TIA 942 – Fire Suppression
Uptime Tiering Reference
Fire Detection System
No
Yes
Yes
Yes
Fire Suppression System
When required
Pre-action (when
required)
Pre-Action (when
required)
Pre-Action (when
required)
Gaseous suppression system
No
No
Clean agents listed in
NFPA
Clean agents listed in
NFPA
Early warning smoke detection
system
No
Yes
Yes
Yes
Water leak detection system
No
Yes
Yes
Yes
Tier 4
TIA 942 - Items beyond the designers
control
THIS IS A LIST OF ITEMS BEYOND THE CONTROL OF THE DESIGNER
ITEM
Tier 1
Tier 2
Tier 3
Tier 4
SECURITY
Dedicated Security staff
per shift
No security staffing
provided
1 per 3000 sqm (1
Minimum)
1 per 2000 sqm (2
Minimum)
1 per 2000 sqm (3 Minimum)
No of 8 hour security
shifts
No requirement
1 (minimum 5 days
per week)
2 (7 days per week)
3 (7 days per week)
MAINTENANCE
Maintenance Staff
On site day shift Only.
On call at other times
On site day shift Only.
On call at other times
On site 24 hrs M-F,
on-call weekends
Onsite 24 x 7
Preventative
Maintenance
None
None
Limited
preventative
maintenance
program
Comprehensive preventative
maintenance program
Facility Training
Programs
None
None
Comprehensive
training program
Comprehensive program
including manual operation
procedures if it is necessary
TIA 942 - Additional items beyond designers
control
These items are also beyond the control of the designer as they are determined by site selection rather than data centre design
ITEM Tier 1 Tier 2 Tier 3 Tier 4
Site Selection
Proximity to flood hazard as mapped on the federal flood hazard boundry or flood insurance map
No Requirement Not in 50 year Flood hazard area
Not w ithin 100 year flood hazard area and greaterthan 91m (300ft) from 50 year flood hazard area
Greater than 91m (300ft) from 100 year flood hazard
Proximity to costal or inland w aterw ays
No Requirement No
Requirement
greater than 91m (300ft) Greater than 0.8km (1/2 mile)
Proximity to major highw ay trafic arteries
No Requirement No
Requirement
greater than 91m (300ft) Greater than 0.8km (1/2 mile)
Proximity to major airports No Requirement No
Requirement
Greater than 1.6km (1 mile) and less than 48km (30 miles)
Greater than 8km/5 miles and less than 48km/30 miles Proximity to major metropolitan
area
No Requirement No
Requirement
less than 48km (30 miles) less than 16km (10 miles) STRUCTURAL
Telcommunications equipment racks/cabinets anchored at base
or supported top and bottom
No Base only Fully braced Fully braced
Floor loading capacity superimposed live load
7.2kPa (150lbf/sqsf)
8.4kPa (175lbf/sqft)
12kPa (250lbf/sqsf) 12kPa (250lbf/sqsf)
Concrete slab thickness at ground 127mm 127mm 127mm 127mm
Concrete topping over flutes for elevated floors affects size of anchor w hich can be installed
102mm 102mm 102mm 102
Building LFRS (Shearw all/braced frame/moment frame) indicates
displacement of structure
Steel/Conc MF Conc.Shearw all /Steel BF
Conc.Shearw all/Steel BF Conc.Shearw all/Steel BF Building Energy Dissipation -
Passive Dampers/base isolation (energy absorption)
None None Passive dampers Passive dampers/Base isolation
ELECTRICAL
Utility entrance Single feed Single feed N+1 Redundant Feed 2N Redundant Feed from different utility substations
Factory Acceptance Testing Optional Optional Yes Yes
Site Circuit Breaker Testing Optional Optional Contact resistance test for all critical circuit breakers in critical and essential paths, 225
Amps and higher
Primary injection and Contact resistance test for all critical circuit breakers in critical and essential paths, 225 Amps and higher
TIA 942 - Design parameters that are
affected by capital cost
ITEM
Tier 1
Tier 2
Tier 3
Tier 4
ELECTRICAL
Battery Type
5 year valve regulated
lead acid
10 year valve regulated
lead acid or flood type
15 year valve regulated lead
acid or flood type
20 year lead acid flood type
Factory Acceptance
Testing
Optional
Optional
Yes
Yes
Site Circuit Breaker
Testing
Optional
Optional
Contact resistance test for all
critical circuit breakers in
critical and essential paths,
225 Amps and higher
Primary injection and Contact
resistance test for all critical
circuit breakers in critical and
essential paths, 225 Amps and
higher
FUEL SYSTEM
Bulk Storage tanks
Single storage tank
Single storage tanks
Multiple storage tanks
Multiple storage tanks
Storage tanks, pumps
and piping
Single pump and/or supply
pipe
Multiple pumps and
multiple supply pipes
Multiple pumps and multiple
supply pipes
Multiple pumps and multiple
supply pipes
Generator fuel capacity
at full load
8 hrs
24 hrs
72 hrs
96 hrs
FIRE
Fire Suppression
System
When required
Pre-action (when
required)
Pre-Action (when required)
Pre-Action (when required)
Gaseous suppression
system
No
No
Clean agents listed in NFPA
Clean agents listed in NFPA
TIA 942 - Non Australian references
ITEM Tier 1 Tier 2 Tier 3 Tier 4
Building Construction
Type of construction No Restriction No Restriction Type IIA,IIIA or VA Type 1A or 1B
roofing Class No Restrictions Class A Class A Class A
Fire Resistive Requirements
Exterior bearing w alls Code requirement Code requirement 1 Hour Minimum 4 Hours Miinimum Interior bearing w alls Code requirement Code requirement 1 Hour Minimum 2 Hours Minimum Exterior nonbearing w alls Code requirement Code requirement 1 Hour Minimum 4 Hours Miinimum Structural frame Code requirement Code requirement 1 Hour Minimum 2 Hours Minimum Interior non-computer room
w alls
Code requirement Code requirement 1 Hour Minimum 1 Hour Minimum Interior computer room w alls Code requirement Code requirement 1 Hour Minimum 2 Hours Minimum Shaft enclosures Code requirement Code requirement 1 Hour Minimum 2 Hours Minimum Floors and Floor-ceilings Code requirement Code requirement 1 Hour Minimum 2 Hours Minimum Roofs and roof-ceilings Code requirement Code requirement 1 Hour Minimum 2 Hours Minimum
Compliance w ith NFPA 75 No Requirement Yes Yes Yes
Roofing STRUCTURE Building LFRS (Shearw all/braced frame/moment frame) indicates displacement of structure Steel/Conc MF Conc.Shearw all/St eel BF Conc.Shearw all/Steel BF Conc.Shearw all/Steel BF
Building Energy Dissipation - Passive Dampers/base isolation (energy absorption)
None None Passive dampers Passive dampers/Base isolation
ELECTRICAL
Pow er Distribution Unit - Transformer Optional K-rated or harmonic cancelling K-rated or harmonic cancelling, Front accessable for maintenance K-rated or harmonic cancelling low inrush, Front accessable for maintenance
UPS Output Pow er Distribution
Panelboard incorporating standard thermal magnetic trip breakers Panelboard incorporating standard thermal magnetic trip breakers Panelboard incorporating circuit
breakers that are coordinated under overload and ground fault current condition
Panelboard
incorporating circuit breakers that are coordinated under all overcurrent conditions These are examples w here TIA942 calls up standards that are not familiar to Australian designers. In some cases it is not possible to easily interpret these requirements
TIA 942 - Common design deficiencies (1)
THE FOLLOWING LIST OF ITEMS FROM TIA REPRESENT AREAS WHERE DESIGNS ARE OFTEN DEFICIENT
ITEM Tier 1 Tier 2 Tier 3 Tier 4
Ststem allow ance concurrent maintenance
No Dow n to but not including UPS Output
Panelboards
Dow n to but not including Pow er Distribution Units
Throughout Distribution Systems
Single points of failure One or more single points of failure fo rthe distribution systems
serving electrical equipment or mechanical
One or more single points of failure fo rthe
distribution systems serving electrical
equipment or
No more than single points of failure for the
distribution systems serving electrical
equipment or
No single points of failure fo rthe distribution systems serving electrical
equipment or mechanical systems
Pow er Syatem Analysis Short Circuit Study Coordination Study Arc
Falsh Analysis
Short Circuit Study Coordination Study Arc
Falsh Analysis
Short Circuit Study Coordination Study
Arc Falsh Analysis Load Flow Study
Short Circuit Study Coordination Study Arc Falsh Analysis Load Flow Study
Construction Panel Board w ith bolt on circuit breakers
Sw itchboard w ith stationary circuit
breakers
Sw itchboard w ith draw out circuit
breakers
Sw itchboard w ith draw out circuit breakers
Grounding
Lighting Protection System Based on Risk analysis Based on Risk analysis Yes Yes Service entrance grounds
and generator grounds fully comply to NEC or local codes
Yes Yes Yes Yes
Data Centre grounding infrastructure in Computer room
Optional Optional Yes Yes
Computer Room Emergency Pow er Off (EPO) System
Installation
Do not install if not required by Authorities
having juristriction
Do not install if not required by Authorities
having juristriction
Do not install if not required by Authorities
having juristriction
Do not install if not required by Authorities
having juristriction
Test Mode Optional Optional Yes Yes
Alarm Optional Optional Yes Yes
Abort Sw itch Optional Optional Yes Yes
Electrical Service to Mechanical Equipment
Single path of Electrical pow er to A/C equipment
Single path of Electrical pow er to A/C equipment
Multiple paths of electrical pow er to AC equipment. Connected
in checkerboard fashion for cooling
redundancy
Multiple pathsof electrical pow er to AC equipment.
Connected in checkerboard fashion for