Page 1 of 5
Page 1 of 5
JOB SAFETY ANALYSIS WORK SHEET
JOB SAFETY ANALYSIS WORK SHEET
JS
JS
A
A
#
#
23
23
Dat
Dat
e
e
D
D
/
/ M
M
/
/
Y
Y
Contractor:
Contractor:
Contract No/ BI. No.:
Contract No/ BI. No.:
JJS
SA
A
F
Fu
un
nc
cttiio
on
n
N
Na
am
me
e
B
Ba
ad
dg
ge
e#
#
JJo
ob
b
T
Tiittlle
e
M
Mo
ob
biille
e
P
Ph
ho
on
ne
e
#
#
CONTRACTOR Site
CONTRACTOR Site
Supv./ Frmn.
Supv./ Frmn.
CONTRACTOR Engineer
CONTRACTOR Engineer
CONTRACTOR Site
CONTRACTOR Site
Safety Supervisor
Safety Supervisor
SAPMT Safety Advisor
SAPMT Safety Advisor
SAPMT Representative
SAPMT Representative
DESCRIPTION OF TASK:
DESCRIPTION OF TASK: Hydrostatic Pressure Testing of MGS Filter Station Various Pipe Auxiliaries
Hydrostatic Pressure Testing of MGS Filter Station Various Pipe Auxiliaries
Work Location/
Work Location/ (Area then station numbers):
(Area then station numbers):
Prepared by/ Signature:
Prepared by/ Signature:
(Contractor)
(Contractor)
________________
________________
Project
Project Engineer Engineer SignatureSignature
________________
________________
HSE
HSE Supervisor Supervisor SignatureSignature
Reviewed By/ Signature:
Reviewed By/ Signature:
(SAPMT)
(SAPMT)
_____________
_____________
Safety
Safety Advisor Advisor SignatureSignature
_____________
_____________
SAPMT
SAPMT Supt. Supt. SignatureSignature
Reviewed By/ Signature:
Reviewed By/ Signature:
(LPD)
(LPD)
___________
___________
Loss
Loss Prevention Prevention SignatureSignature Representative
Representative
Approved By/ Signature:
Approved By/ Signature:
(Client)
(Client)
______________
______________
Lead
Lead Proj. Proj. Engr. Engr. SignatureSignature
Operation
Operation Rep.
Rep. ___________
______________
___
Signature Signature Revised Revised New New
Page 2 of 5
Reference GIs & SAES:
Work Permit GI. 2.100, Gas Testing Procedure using 3 in 1 Gas Monitor G.I. 2.709, Traffic and Vehicle Safety G.I. 6.030, Mobile Heavy Equipment Operator Testing and Certification G.I. 7.025, Crane Lifts: Types and Procedures G.I. 7.028, Inspection and Testing of Requirements of Elevating/Lifting Equipment G.I. 7.030, Fire Fighting Training Company Personnel G.I. 1783.001, Safety Spectacles G.I. 8.002, Protective (Safety) Footwear G.I. 8.005, Environmental Conservation Policy Implementation G.I. 2.714, Isolation, Lock Out and Use of Hold Tags G.I. 6.012, Safety Requirements for Scaffolds G.I. 8.001, Pressure Testing Safely G.I. 0002.102, General Requirements for Pressure Testing 004, Pressure Testing of Plant Piping and Pipelines SAES-L-150, Safety Instruction Sheet SAES-A-005, Hydrostatic Testing Fluids and Lay-up Procedure SAES-A-007, Disposal of Waste Water from Cleaning, Flushing and Hydrostatic Test SAEP-327, Pressure Testing Saudi Aramco Construction Safety Manual Section III-V-3, Emergency Procedures Saudi Aramco Construction Safety Manual Section I-5
Ite
m
SEQUENCE/ BASIC STEPS
POTENTIAL
HAZARDS
HAZARD CONTROLS
ACTION BY
1 1. Preliminary site inspection • Injury/Incident due to
work not being carried out safely.
• Permit Issuer and Receiver to conduct joint site
inspection to discuss the hazards and precautions required for conducting the job safely.
• Ensure no work is conducted in this area until signed
permits to work are in place.(GI- 2-100, GI-2-709)
• Ensure tool box meeting is conducted prior to start of
work
1
CONTRACTOR/ Operation2
SAPMT(follow-up)2. Emergency evacuation • Panic
• Miscommunication
• Indentify the assembly area and put signboards • Provide full orientation on Emergency Procedure. • Post SA emergency NO.110 around work area. • Mobile phone with Supervisors & Safety personnel at
site.
CONTRACTOR/ Operation SAPMT(follow-up)
3. Movement of vehicle and construction equipment (pick up , water tanker, bus etc)
• Traffic/safety hazard to
other users in the area
• Vehicle/equipment
collision
• Contact with personnel.
• Sign boards to be posted. Site speed restrictions to be
observed (40kmph)
• Spotters to control equipment and traffic.
• All drivers/operators shall have the necessary licenses
and certificates.
• All operators/drivers advised via TBT of driving safety. • Designated parking areas.
• (GI- 006- 030)
3
CONTRACTOR/ Operation SAPMT(follow-up)4. Check equipment • Personnel injury • Daily check of all tools & equipment prior to start of
job.
• Communicate defects found in equipments and
organise for replacements so that defective equipment is never used.
• Tag the defective tools as “Do not use”.
4
CONTRACTOR/ OperationPage 3 of 5
1. Hydro test preparation • Personal injury • Conduct tool box talk with the team. • Barricade the area and sign board. • Limit entry for authorized personnel.
• Ensure the tools and equipment is free from defects. • Ensure the measuring and monitoring devices are
having valid calibration.
• Ensure the pumps, hoses, spades and gasket are
suitable for the pressure rating(GI- 2-102)
• Pressure tests the equipment prior to putting in
service.
5
CONTRACTOR/ Operation6
SAPMT(follow-up)2. Hydro testing Failure of joints Failure of pipe Personal injury Damage to property
• (Refer toGI- 2-102, SAES-A-004, SAES-L-150)
• The test procedure to be reviewed and approved by
Inspection/SAPMT.
• During water filling vent the line from the highest
elevation point.
• Raise the pressure gradually. Pressurization shall not
exceed 2bar/min.
• Ensure the pressure relieving device is set at
maximum allowable pressure for weakest portion of the segment to be hydro-tested.
• Never increase the hydro-test pressure more than the
maximum allowable pressure for the weakest portion in the segment or pressure rating of the hose & coupling.
• Keep away from the pressurized segment of the
system being hydro-tested.
• Monitor the pressure gauge from a safe distance away
from the potential source of high pressure jetting (Such as Flange Joint, Spade, and Coupling etc.)
• Support the system adequately to withstand the
pressure and weight.
• Conduct a low pressure leak test before pressure test. • Do not work or strike on the line to stop leakage while
it is under pressure.
• Ensure the workers are wearing Appropriate
PPE.
• Do not leave the pressurized hose or pump unattended
when the hydro-test is going on.
• Isolate the equipment from all source of energy when
not in use.
• Do not change (exceed / decrease) the duration of
hydro-test without permission from I nspection
7
CONTRACTOR/ OperationPage 4 of 5
Engineer.
• Ensure that anEmergency Repair Kit is readily
available incase of any leaks. 3. Depressurizing and housekeeping Injury from high pressure
jets
Slips trips and falls Damage to environment
• Ensure the depressurization is done at a safe and slow
rate.
• Do not depressurize by loosening flanges; use the
depressurizing valves and piping.
• Dispose the test fluid as perSAEP 327
• All accessories and equipments to be disconnected
and stored.
• Hoses and cables to be kept away from walkway • Clean the spillage
• Barricades and warning signs for slippery areas
CONTRACTOR
#
Recommendations/Notes
Assigned
to
Mobile
Phone
#
1 All site personnel are required to wear PPE/ such as safety helmet, safety glasses, gloves, and safety shoes.
CONTRACTOR/ Operation & SAPMT
2 Conduct Tool Box Safety Meeting prior to every work activity. CONTRACTOR Safety Officer & Foremen
3 Explain to key personnel the purpose of the JSA and enforce the implementation of content. CONTRACTOR Project Engineer
4 Use the JSA to identify hazards and list the precautions on the work permit. CONTRACTOR / Operation 5 Garbage’s shall be disposed properly on a daily basis. CONTRACTOR Safety Officer
& Foremen 6 If an injury or near miss occurs, the JSA shall be reviewed immediately to determine
whether changes are needed in the job procedures.
CONTRACTOR Safety Supervisor 7.
Incase of any emergencies, the Project Emergency Response Plan / Procedure shall be followed by ALL affected personnel and a Certified First Aider and Ambulance shall be readily available.
CONTRACTOR Project Engineer EMERGENCY RESPONSE PROCEDURE
In an EMERGENCY, or on hearing the “Stop Work Alarm”, every supervisor shall ensure the following:
1. ALL work is stopped at once. 2. ALL Equipment is shut down.
3. ALL personnel are evacuated to the
pre-EMERGENCY CONTACT NUMBERS: Inside Saudi Aramco EMERGENCY Dial
1.
Saudi Aramco Landline -110When reporting an emergency give the clear information’s such as:
1. Your exact location. 2. Nature of emergency.
3. Service required and repeat the message. 4. Your name & badge number.
Page 5 of 5
determined assembly area.
4. A roll call is taken and every man is accounted for.
5. No one is permitted to return to work until notification has been received from operations or from the company representative that it is safe to do so.
2.
By Mobile Phone – (03) 8720650 (03) 8743000 (03) 8742006 (03) 6787836 (03) 6787116 (03) 6730110 0506837 304Stay on the telephone until you are told to hang-up. If possible, post a lookout to direct the ambulance, fire truck or helicopter to the right location.