BUILDING & STRUCTURAL
SURVEYING
N5
CONTENTS
1. BASIC PRINCIPLE………..3
2. LINEAR MEASUREMENT………...6
3. LEVELLING………....18
3.1 RISE AND FALL METHOD………..19
3.2 COLLIMATION HEIGHT METHOD………....25
3.3 RECIPROCAL LEVELLING………..28
4 TACHEOMETRY………...30
5. TRAVERSING………....36
5.1 MEAN OBSERVATION ANGLE……….37
5.2 CO-ORDINATES (JOINING)………...42
6. SETTING OUT………..46
6.5 CUT AND FILL……….48
6.6 LENGTH AND SLOPE OF DRAINAGE PIPES………..52
6.7 ESTABLISHING HEIGHTS OF SIGHT RAILS………..59
7 AREAS AND VOLUMES……….63
CHAPTER 1
1. BASIC PRINCILPES
1.1 Terminology
1.1.1 Surveying
Surveying is the art of taking measurements upon the surface of the earth either
in the horizontal or vertical plane, the results are shown in the formof a map or plan or as calculated figure. The plan is later set out on the ground
1.1.2 Plane surveying
Plane surveying is the surveying whereby the are to be surveyed is small that
the curvature (shape) of the earth is not taken into account 1.1.3 Gravity
Gravity is the force the keeps the earth in equilibrium, keep us on earth and
gives us the sense of balance. It acts towards the centre of the earth
1.1.4 Topography
Topography is a survey done to locate the main natural and artificial features
earth surface, e.g hills, rivers, roads, buildings etc
1.1.4.1 Planimetry
It is the representation, in plan, of the natural and man made features
1.1.4.2 Relief
It is the indication, in plan, of variations in elevation of the
surface of the land. Relief maybe shown in the following methods a) Colour layering b) Shading c) Contours d) Form lines 1.1.5 Contour line
It is an imaginary line which links up a series of points of the same level on the
1.1.6 Reduced level
It is the calculated height of a point above or below a datum as deduced from
survey observation 1.1.7 Change point
Change point is the staff position at which a foresight reading was taken and
later a backsight was taken 1.1.8 Invert level
It is the level of the inside bottom surface of the pipe
1.1.9 Field book
It is the book in which all the details of the survey are recorded by the surveyor
1.1.10 Chainage
It is the distance to a point along a survey line, even though one talk of taping a
line than say chaining a line
1.1.11 Booking
It is the entering of all survey information and measurements in the field book
1.1.12 Setting out
Is the transfer of details from a drawing to a piece of ground 1.1.13 Zenith angle (Zenith distance)
It is the vertical angle measured from the vertical line (zenith line) downward
1.1.14 Offset
It is a distance measured at right angle to a chain line to some feature of the site
such as a tree, building etc 1.1.15 Height
It is the vertical distance of a feature above or below the datum or reference
surface
1.1.16 Optical square
Is a hand held instrument used to set out right angles in a building site
1.1.17 Dumpy
1.1.18 Instrument
It is a common site name given to a surveying instrument on a tripot
1.1.19 Distometer
It is an used together with a theodolite, it measures distance 1.1.20 Tri-beacon
It is the highest point of known height above sea level and of known co-ordinates
1.1.21 Grid
It is the representation on a map, of a system of equally spaced straight parallel lines
to Y and X of the co-ordinate system
CHAPTER 2
CHAIN SURVEYING
2.
CHAIN SURVEYING
2.1 METHODS OF FIXING A POINT
2.1.1 Offset method (rectangular)
Measure the perpendicular distance DC and the length of AD and BD
C
A B
D
Measure angle A and the length of AC
C
A B
2.1.3 Intersecting arcs
Measure the length of AC and BC C
A B
2.1.4 Triangulation (forward Intersection)
Measure angle A and angle B
C
A B
2.1.5 Trilateration (Resection)
Measure the angles formed at P by the rays to three known points A , B and C
a
P b B c
C
2.2 Field problems
2.2.1 Ranging and measuring over a hill
(obstacle to line of sight but not to measurement)
C D
A B
Step 1 Rod holders C and D position themselves so that D can see A, and C can see B
Step 2 C directs the rod holder of D into line between C and B
Step 3 D then directs the rod holder of C into line between A and D
Step 4 This will continue until no further movement is possible and they all are in line
2.2.2 Measuring around a pond / Building
(obstacles to measurement but not to sight) C D
A B E F a) Bring the survey line to from A to B
b) Set off line BC at right angle to AB c) Set off line CD at right angle to BC d) Set off line DE at right angle to CD e) At E set off line EF at right angle to DE
2.2.3 Measuring distance across a river
(obstacles to measurement but not to sight) B
A D C
F E To find distance AB
a) Set off line AC at right angle to AB b) Find D midpoint of AC
c) Set off line CE at right angle to AC
d) Move along line CE until point B and D are in line e) This will be point F
Distance AB = CF
2.3 Methods of taping
2.3.1 Surface taping
Measuring with the tape laid on the ground and fully supported by the ground
2.3.2 Catenary taping
Measuring with the tape suspended clear off the ground
Used when surface is very bad and involves the removal of grass, shrubs etc along
The line of suvey
2.4 How step chaining is conducted on site
1. When step chaining is conducted the tape should be stretched out horizontally from point A
2. The distance is limited to the tape being held comfortably at waist height
3. To obtain a true horizontal a plumb bob is held on the tape reading and at the same point a
peg is put on the ground.
4. The zero point of the tape is place on the second peg and the horizontal distance measured
using the waist height as our level.
5. This is repeated up until point B is reached
2.5 How the 3 – 4 – 5 method of setting out a right angle is
applied
1. Three people are needed
2. from the point at which the perpendicular line is required the tape is held at zero and stretch
along the existing straight line for 4m and held by the second assistant at that point
3. The third assistant pulls the tape at an acute angle towards the first assistant holding the tape
at 7m
4. The remainder of the tape is held by the first assistant at 12m and the whole system is
Stretched to form a right angle triangle
2.6 Five requirements to obtain sufficient accuracy when
taping
1. Tape must be held horizontal
2. Tape must be held on its correct zero mark 3. The correct tension must be applied to the tape 4. Remove all kinks
5. Tape must be held on correct pegs 6. View tape vertically over the peg 7. Measure the centre of ranging rod
2.7 Care of steel tape
1. Pull tape straight in the direction in which it is curled 2. Ensure that no kinks are present
4. Wipe tape with oily cloth after use to prevent rust 5. Do not allow vehicle to run over the tape
2.8 CHAINAGE CORRECTIONS
2.8.1 Constants ( length of tape too short or too long) GTL ATL MD CD = × CD = correct distance
MD = measured distance (length) ATL = Actual tape length
GTL = Graduated tape length
2.8.2 Temperature C=L×e(Tm −Ts)
C = Temperature Correction L = Measured distance (length) e = Coefficient of linear expansion Tm = Measured temperature Ts = Standard temperature 2.8.3 Sag 2 23 24T L w C = for bay 3 24 3 2 3 2 × × = T L w C
For Three bays C = Sag correction
w
= Mass of the tape in kg/m L = Measured length (distance) in m T = Measured tension in kgF2.8.4 Slope
To calculate the horizontal distance To calculate the slope distance
C=L(1−cosθ) ) 1 (sec − =H A C
Sc = Slope correction SC = Correction
L = Measured length of the slope H = Measured horizontal distance
θ = Slope angle θ = Slope angle
2.8.5 Height at sea level R H L C = × CH = Correction
L = Measured length (distance) H = Height above or below sea level
OBSERVATION ANGLE
Z = Zenith distance
θ
= Angle of elevationVertical Zenith line of sight Zenith distance Z Angle of elevation θ Horizontal
Z = 90º – θ
θ = 90º – Z
Zenith distance Z θ Angle of depression line of sightZ = 90º + θ
θ = Z – 90º
NB: ALWAYS use angle θ which represents the angle of
Elevation or Depression
EXAMPLE 1
QUESTION
Calculate the reduced horizontal distance, if the measured distance is 87,281 m at a slope if 86º 22’ 44”
the distance is measured is three bays at a temperature of 16 ºC Standard temperature is 20ºC
Co-efficient of expansion is 1,13 x 10−5/ºC
Tension 65N
Mass of the tape is 0,015 kg/m Earth radius is 6373 km
Height above sea level 2 280,544 m
SOLUTION
Given : ts = 20ºC e = 1,13 x 10−5/ºC T = 65N w = 0,015 kg/m R = 6373 km H = 2280,544 m L = 87,281 m θ = 90 – 86º 22’ 44”= 3º 37’ 16” tm = 16ºC ) (Tm Ts e L C = × − ) 20 16 ( 10 13 , 1 281 , 87 × × 5 − = − C 0039 , 0 − = C 3 24 3 2 3 2 × × = T L w C 3 ) 5 , 6 ( 24 3 281 , 87 015 , 0 2 3 2 × × = C ( 65 N = 10 65 = 6,5 kgF ) 0164 , 0 = C ) cos 1 ( − θ =L C)
"
1 6
'
3 7
3
c o s
1
(
2 8 1
,
8 7
−
°
=
C
1743 , 0 = C mR H L C = × 6373000 544 , 2280 281 , 87 × = C 0312 , 0 = C m CD = 87,281 – 0,0039 – 0,0164 – 0,1743 – 0,0312 = 87,055 m
NB: CD = reduced distance or correct horizontal distance
EXAMPLE 2
QUESTION
Calculate the slope distance if the measured correct horizontal distance to be measured is 98,285 and the slope is 2º 22’ 15”
SOLUTION
) 1 (sec − =H A C)
1
"
1 5
'
22
2
(sec
2 85
,
9 8
°
−
=
C
AA
c o s1s e c
=
0842 , 0 = C m Slope distance = 98,285 + 0,0842 = 98,369 m OR Slope ="
1 5
'
2 2
2
co s
2 8 5
,
9 8
°
= 98,369 m
EXERCISE 1
Question 1.1
The standard temperature of a tape is 14ºC and the coefficient of expansion is 0,000012/ºC
What is the reduced horizontal distance, if the measured distance is 32,40 m on a slope of
5º 40’ and a temperature of 30ºC
Answer 32,248 m
Question 1.2
Given: Length of tape = 100m Standard temperature = 20ºC
Coefficient of expansion = 1,13
×
10–5/ºCTension = 7 kg.f
Mass of tape = 0,015 kg/m Radius of the earth = 6,373 km
1.2.1 Calculate the reduced horizontal distance, if the measured distance is 94,151 m
at a slope of 95º 15’. The distance is measured in three bays at a temperature of
14ºC Answer: 93,732 m
1.2.2 Calculate distance at sea level if the height was 2 017,443 above sea level,
use the distance in Question 2.1. Answer: 93,702 m
Question 1.3
A line A-D was measured in three sections A-B 90,288 @ slope 3º 44’ 20”
B-C 72,408 @ slope 4º 32’ 59” C-D 47,652 @ Slope 2º 09’ 07”
Calculate the horizontal distanceA-D Answer: 209,459 m
1.4.1 M to R is a distance to be pegged (as viewed on plan)
M to R lies on a slope of 0º 34’ 23” Calculate the distance on the slope M to R to be measured to obtain the correct horizontal distance of 1000 m
Answer: 1000,050 m
1.4.2 Determine the horizontal distance of a measurement of 136,57 m that was done on a
Slope of 3,64%
Answer: 136,479 m
Question 1.5
A measured distance of 164,81m was measured from T1 to T2 the reduced distance is 160,49 m
Calculate the angle of the slope and the zenith distance
Answer: 13º 8′ 50,8″ ; 76º 51′ 7,24″
Question 1.6
A steel tape is used to measure a baseline A-B. Each measurement is done in THREE bays
Calculate the correct baseline distance. Give the formula for each of your calculations A-B 94,01 m /96º 10’ @ 35ºC 83,14 m / 87º 30’ @ 11ºC Length of tape = 100m Standard temperature = 20ºC Coefficient of expansion = 0,0000112/ºC Tension = 70 N Mass of tape = 0,015 kg/m Answer: 176,504 m Question 1.7
A 100 m steel tape was compared with a 100 m standard base. The length of the base as
read on the tape was 99,997 m at a temperature of 22,4ºC. The coefficient of linear
expansion is 0,000014/ºC. Calculate the standard temperature of the tape.
CHAPTER 3
LEVELLING
3. HEIGHT MEASUREMENT ( REDUCED LEVEL)
3.1 RISE AND FALL METHOD
Poin
t BS IS FS Rise Fall Reduced level
A 2,50 50,00 B 2,00 0,50 50,50 C 2,25 0,25 50,25 D 1,75 1,80 0,45 50,70 E 1,60 0,15 50,85 4,25 –3,40 0,85 3,40 1,10 –0,25 0,85 0,25 50,85 –50,00 0,85 Steps to follow:
a) Enter the backsight, intermediate sight and the foresight in the appropriate column
in different rows. Except that at change point the FS and the BS are entered in the
same row ( as in row D)
b) The first reduced level is the height of the O.B.M or other datum which has been
c) If the IS or FS in smaller than the immediately preceding staff reading,
The difference between the two readings is placed in the rise column
Example: immediately preceding reading of 2,00 in row B is 2,50 in row A
Therefore 2,50 – 2,00 = 0,50
d) If the IS or FS in larger than the immediately preceding staff reading,
The difference between the two readings is placed in the fall column
Example: immediately preceding reading of 2,25 in row C is 2,00 in row B
Therefore 2,00 – 2,25 = – 0,25
e) A rise is added to the immediately preceding reduced level entry to obtain the
reduced level of a station.
Example: immediately preceding reduced level of row B is row A = 50,00
Reduced level of B= 50,00 + 50 = 50,50
f) A fall is subtracted from the immediately preceding reduced level entry
Example: immediately preceding reduced level of row C is row B = 50,50
Reduced level of C = 50,50 – 0,25 = 50,25
Checking on booking
1) Sum up the BS readings and the FS readings Subtract FS from the BS
Total BS = 2,50 + 1,75 = 4,25 Total FS = 1,80 + 1,60 = 3,40 Difference = 0,85
2) Sum up Rise and Fall Subtract Fall from the Rise
Total Rise = 0,50 + 0,45 + 0,15 = 1,10 Total Fall = 0,25 Difference = 0,85
3) Subtract the first reduced level from the last reduced level
Last reduced level = 50,85 First reduced level = 50,00
0,85
NOTE:
If all their differences are the same then the
calculation are correct
NOTE:
Any entry that is underlined 3,456 or has a line
ontop 3,456
means the entry is negative
Example :
Rise and Fall method
NOTE: The numbers in brackets indicate the steps from the calculations below
Poin
t BS IS FS Rise Fall Reduced level
A 2,10
9 (A1) 130,50
B 3,20
4 (B1) 1,095 129,405(B2)
9 131,235 D 1,28 1 (D1) 4,400 135,635(D2) E 2,05 4 0,773(E1) 136,408(E2) F 1,90 6 2,200 (F1) 4,254 132,154(F2) G 1,65 4 1,812 (G1) 3,718 135,872(G2) H 2,850 (H1) 4,504 (H2) 131,368 5,48 0 – 4,61 2 0,86 8 4,612 10,721 –9,853 0,868 9,853 131,368 –130,50 0,868
Use the table above with the steps below to understand
A1. The BM is the reduced level in A which is 130,50
B1. To find the Rise or Fall in row B
BS in row A – IS in row B = Rise/Fall
2,109 – 3,204 = – 1,095 ( since its negative it is a Fall)
B2. To find the reduced level at B
Reduced level at A – Fall in B = Reduced level at B
2,109 – 3,204 = 129,405
C1. To find the Rise or Fall in row C
IS in row B – FS in row C = Rise/Fall
3,204 – 1,374 = 1,830 ( since its positive it is a Rise)
C2. To find the reduced level at C
Reduced level at B + Rise in C = Reduced level at C 129,405 + 1,830 = 131,235
D1. To find the Rise or Fall in row D
BS in row C – IS in row D = Rise/Fall
3,119 – ( –1,281) = 4,400 ( since its positive it is a Rise)
D2. To find the reduced level at D
Reduced level at C + Rise in D = Reduced level at D 131,235 + 4,400 = 135,635
E1. To find the Rise or Fall in row E
IS in row D – IS in row E = Rise/Fall
(–1,281) – (–2,054) = 0,773 ( since its positive it is a Rise)
E2. To find the reduced level at E
Reduced level at D + Rise in E = Reduced level at E 135,635 + 0,773 = 136,408
F1. To find the Rise or Fall in row F
IS in row E – FS in row F = Rise/Fall
–2,054 – 2,200 = – 4,254 ( since its negative it is a Fall)
F2. To find the reduced level at F
Reduced level at E – Fall in F = Reduced level at F 136,408 – 4,4254 = 132,154
G1. To find the Rise or Fall in row G
BS in row F – FS in row G = Rise/Fall
1,906 – (–1,812) = 3,718 ( since its positive it is a Rise)
G2. To find the reduced level at G
Reduced level at F + Rise in G = Reduced level at C 132,154 + 3,718 = 135,872
H1. To find the Rise or Fall in row H
BS in row G – FS in row H = Rise/Fall
–1,654 – 2,850 = –4,504 ( since its negative it is a Fall)
H2. To find the reduced level at H
Reduced level at G – Fall in H = Reduced level at H
135,872 – 4,504 = 131,368
CHECK ON BOOKING
Total BS – Total FS = 5,480 – 4,612 = 0,868 Total Rise – Total Fall = 10,721 – 9,853 = 0,868
Last R/level – First R/Level = 131,368 – 130,50 = 0,868
EXERCISE 2
Question 2.1
Reduce the field notes using the rise and fall method. Do the necessary checks
(If your calculation are correct then the check must give an answer of –1,6)
Poi
nt BS IS FS Rise Fall Reduced level Remarks
A
2,40
TBM 150,00B
2,00
C
1,90
D
2,80
1,40
E
2,00
F
1,30
2,60
G
0,60
3,00
H
1,70
7,10
–
8,70
–1,6
8,70
Question 2.2Reduce the field notes using the rise and fall method. Do the necessary checks
(If your calculation are correct then the check must give an answer of 4,64)
Poi
nt BS IS FS Rise Fall Reduced level Remarks
A
0,49
0,27
3,29
0,39
3,77
3,72
3,59
1,1
1
3,56
0,82
BM
3,89
1,36
BM 1
025,00
3,72
0,99
3,69
1,02
3,86
1,31
3,90
1,56
B
2,40
23,93
–
19,29
4,64
19,2
9
Question 2.3Reduce the field notes using the rise and fall method. Do the necessary checks
(If your calculation are correct then the check must give an answer of 4,09)
Poin
t BS IS FS Rise Fall Reduced level
BM
1
3,14
1
401,261
A
0,08
6
B
2,11
1
4,28
3
C
1,40
6
D
2,03
2
E
3,10
8
3,63
8
F
1,82
3
2,11
0
G
3,11
1
H
4,12
3
2,10
9
I
3,28
1
BM
2
3,08
3
3.2 COLLIMATION HEIGHT METHOD
NOTE:
1. BS, IS and FS reading are entered as in the rise and fall method 2. The first reduced level entry is the height of the OBM
3. The first BS reading which is taken with the staff held on the OBM is added to
the first reduced level to give the height of collimation and the entries are place
in the same row
4. The height of collimation is change only when the levelling instrument is moved
to a new position. The new height of collimation is obtained by adding the new BS to the reduced level at the change point
EXAMPLE
Point BS IS FS Collimation height Reduced level
A 3,16 (A2) 141,66 (A1) 138,50
B 1,95 141,66 (B1) 139,71
C 4,16 3,97 (C2) 141,85 (C1) 137,69
NOTE: Collimation height at A is used to find all the reduced level of B and C
But since C is a change point, the collimation height change
Step to follow
A1. The reduced level entered is the OBM or TBM etc given A2 How find the collimation height at A
Reduced level at A + Backsight at A = Collimation height at A 138,50 + 3,16 = 141,66
B1. How to find reduced level at B
Collimation height at A – Inter-sight at B = Reduced level at B 141,66 – 1,95 = 139,71
C1 How to find the reduced level at C
Collimation height at A – Foresight at C = Reduced level at C 141,66 – 3,97 = 137,69
C2 How find the collimation height at C (Change point has both BS and FS)
Reduced level at C + Backsight at C = Collimation height at C 137,69 + 4,16 = 141,85
D1 How to find the reduced level at D
Collimation height at C – Foresight at D = Reduced level at D 141,85 – 1,62 = 140,23
EXERCISE 3
Question 3.1
Reduce the following notes by using the collimation height method Do the necessary checks
Poin
t BS IS FS Collimation height Reduced level
BM
2,4
0
150,00
A
2,0
0
B
1,9
0
C
2,8
1,40
0
D
2,0
0
E
1,3
0
2,60
F
0,6
0
3,00
G
1,70
Question 3.2Reduce the following notes by using the collimation height method Do the necessary checks
Poin
t BS IS FS Collimation height Reduced level
BM
1
4,61
884,86
A
3,54
B
1,69
C
1,80
3,21
D
2,40
E
2,89
3,62
F
1,20
G
2,20
H
1,46
BM
2
1,20
5,70
–1,61
4,09
1,61
Question 3.3Reduce the following notes by using the collimation height method Do the necessary checks
Poin
t BS IS FS Collimation height Reduced level
A
4,42
0
B
5,50
0
C
3,88
0
D
3,16
0
1,47
0
E
1,95
0
F
4,55
0
G
4,65
0
3,97
0
145,990
H
3,90
0
I
6,32
0
J
2,34
0
K
4,16
0
1,62
0
L
1,62
0
M
5,20
0
3.3 RECIPROCAL LEVELLING
y1 y x x1 station 1 C station 2 3m D 3mLet us assume the following staff reading
Reading taken 3m from C Reading taken 3m from D
C (y = 1,480m) D (x =
1,738m)
D (y1 = 1,852m ) C (x1 = 1,380)
One can see that all reading taken when staff was at C are larger than that of staff at D
We can therefore say a point with larger reading is lower and the one with smaller
readings is high. In this case we can say point D is lower and C is higher Therefore to find the reduced level of point use the following
1. Calculate the difference from readings taken at station C (e.g between
x
and x1)2 Calculate the difference from readings taken at station D (e.g between y and y2
3 Calculate the mean difference between the stations 4 Calculate the Reduced level required
4.1 R/L of a lower point = R/L of a higher point – mean difference
4.1 R/L of a higher point = R/L of a lower point + mean difference
EXAMPLE
Using the data given let, let us say that the reduced level of D is 352,710m
And we need to calculate the reduced level of C Solution
Difference between readings taken 3m from C = 1,852 – 1,480 = 0,372 m
Difference between readings taken 3m from D = 1,738 – 1,380 = 0,358 m Mean difference = 2 358 , 0 372 , 0 + = 0,365 m Reduced level of C = 352,710 – 0,365 = 352,345
EXERCISE 4
Question 4.14.1.1 The following readings were taken by ‘reciprocal’ levelling across a
swamp.
What is the correct elevation of point B if the elevation of A is 100,00 m Reading taken 3m from A Reading taken 3m from D
A 2,91 B 1,71
B 2,49 A 1,39
4.1.2 Make a neat sketch showing the above mentioned set ups and readings
Question 4.2 3,35 1,95 2,85 1,55 B 3m A 3m
The above sketch shows the reading taken by reciprocal levelling across a river. If the elevation
Of B is 139,50 Calculate the Reduced level of A
Question 4.3
4.3.1 The following readings were taken by ‘reciprocal’ levelling across a
swamp.
What is the correct elevation of point B if the elevation of A is 123,50 m Reading taken 3m from A Reading taken 3m from D
A 1,50 B 3,30
B 1,00 A 3,00
4.3.2 Make a neat sketch showing the above mentioned set ups and readings
CHAPTER 4
LEVELLING
4.
TACHEOMETRY
Use of Vertical angles
MH VD B θ Δh Height of B IH Height of A Datum line
When the instrument is at a lower point
Higher point = Lower point + IH + VD – MH
This means :
Reduced level B = height of A + Instrument height + vertical distance
– mean height θ IH VD A Δh Height of A MH B Height of B Datum line
When the instrument is at a higher point
( that means the angle given is more than 90º measured from the vertical line)
Lower point = Higher point + IH – VD – MH
This means :
Reduced level B = height of A
+
Instrument height–
vertical distance–
mean heightFORMULAE
1. I = TH – BH TH =Top hair BH = Bottom hair
2. VD = KI cosθ Sinθ or VD = 21 KI sin 2θ (cosθ Sinθ = 21 sin 2θ)
VD = Vertical distance
K = 100
θ = Slope angle 3. 2 BH TH MH = + MH = Mean height 4. HD = KI cos2 θ HD = Horizontal distance 5. HD VD m= or m=tan−1θ
m
= gradientExample
Given The height of point A is 24,135m, height of instrument at A is 1,60m
TH = 3,01 BH = 2,41
vertical angle is 86º 30’
Required to calculate 1.1 The reduced level of B 1.2 The horizontal distance A-B
SOLUTION 1.1 θ = 90 – 86º 30’ ( A is lower than B) = 3º 30’ 2 BH TH MH = + 2 41 , 2 01 , 3 + = MH MH =2,71 VD = KI cosθ Sinθ VD = 100(3,01 – 2,41) cos3º 30’ Sin 3º 30’ = 3,656m Reduced level at B = 24,135 + 1,60 + 3,656 – 2,71 = 26,681m 1.2 HD = KI cos2 θ HD = 100(3,01 – 2,41) (cos 3º 30’)2 = 59,776m
EXERCISE 5
Question 5.1If the height of point A is 900,00m and the height of the instrument at A is 1,162m
Observation to point B TH = 3,492
BH =1,250
Vertical angle = 97º 24’ 00”
5.1.1 Calculate the Reduced level of point B 5.1.2 Calculate the horizontal distance A-B
Answers 870,156m 220,480m
Question 5.2
A surveyor obtained the following information between two points, A and B: Height of A = 430,17m
Instrument height at A = 1,56m Stadia reading 0,97 1,43 1,89 Vertical angle = 82º 10’ 40”
5.2.1 Calculate the horizontal distance A-B 5.2.2 Calculate the Reduced level of B
Answer : 90,296m 442,705m
Question 5.3
A theodolite is set up at point P and the height of the instrument is 1,61m. The elevation of
Point Q is 1 718,440m TH = 2,14
BH = 0,93
Vertical angle = 96º 10’
Calculate the height of point P
Answer : 1 731,288m
Question 5.4
A theodolite is set up at point A and the height of the instrument is 1,20m. When sighted to a staff held at B, the upper and lower stadia lines read 2,00 and 0,80 respectively. The angle of elevation of the instrument is 6º 20’ Calculate the Reduced level of A if the reduced level of B is 104,68m
Answer : 917,23m
Question 5.5
A theodolite is set up at point C and the instrument height is 1,58m. The elevation of C is
2 015,67m. Sighting staff held at D, the following observation are recorded
STADIA CIRCLE READINGS
2,55 1,6 0,65 98º 16’ 00” 210º 50’ 40” Calculate: 5.5.1 Vertical angle 5.5.2 Vertical distance 5.5.3 Horizontal distance 5.5.4 Height of D
5.5.6 The slope distance
5.5.7 The gradient of the slope
Answer: ---- 27,034 186,072 1988,616 188,026 0,145
Question 5.6
6.1 If the angle of elevation is of the instrument 5º 22’ 30”. Calculate the zenith distance
6.2 If the angle of depression is of the instrument 6º 25’ 32”. Calculate the zenith distance
6.3 If the vertical circle reading 97º 30’ 35”. Calculate the vertical angle and state whether
it is an angle of elevation or depression
6.4 If the vertical circle reading 82º 18’ 45”. Calculate the vertical angle and state whether
it is an angle of elevation or depression
Answer not given Question 5.7
The following information was recorded during field survey The slope distance from point C to D is 500m
The reduced level at point C is 1,284m The reduced level at point D is 12,484m Calculate the following:
5.7.1 The horizontal distance A to B 5.7.2 The slope angle at A
CHAPTER 5
TRAVERSING
CIRCLE LEFT
NORTH
When this circle on the left of the telescope is turned to face left The readings will be between º and 180º
Usually in the vicinity of 90º Direction of sight 360º start position 0º B 25º 40’ 05” G 289º 34’ 00” C 80º 22’ 40” 270º A 90º F 229º 20’ 10” E 186º 31’ 50” D 135º 14’ 20” 180º
CIRCLE RIGHT
NORTH
With the circle on the right of the telescope The readings will be between 180º and 360º Usually in the vicinity of 270º
180º Direction of sight Start position B 205º 40’ 25” G 109º 34’ 14” C 260º 22’ 40” 90º 270º
F 49º 21’ 10”
E 06º 31’ 20” D 315º 14’ 30”
0º
360º
ENTRY OF THE READINGS
Poin
t Circle Left Circle Right Mean angle Correction Corrected Angle
B 25º 40’ 05” 205º 40’ 20” C 80º 22’ 40” 260º 22’ 40” D 135º 14’ 20” 315º 14’ 30” E 186º 31’ 50” 06º 31’ 20” F 229º 20’ 10” 49º 21’ 10” G 289º 34’ 00” 109º 34’ 14” B 25º 40’ 05” 205º 40’ 25”
5.1.1
How to calculate the mean observation
angle
5.1.1.1. Given the reading of
one point ONLY
When the Circle right is Smaller than Circle left add 180º to Circle right
When the Circle right is larger than Circle left subtract 180º from Circle right
Example
128º 45’ 12” 308º 45’ 20”
Solution (Circle right is larger 308º – 180º = 128º)
This is enter as in the following table
Point Circle Left Circle Right Mean angle
128º 45’ 12” 308º 45’ 20”
128º 45’ 12” 128º 45’
20” 128º 45’ 16”
NOTE: Mean angle =
2 " 20 ' 45 128 " 12 ' 45 128° + ° = 128º 45’ 16”
5.1.1.2
Given reading from
more than one point
Example Given : Circle left Circle right A 87º 40’ 20” 267º 40’ 35”
B 110º 32’ 30” 290º 32’ 45” C 184º 14’ 20” 04º 13’ 33” D 286º 25’ 30” 106º 25’ 50” A 87º 40’ 40” 267º 40’ 55” Solution: (Use the table with the calculations below)
Circle left Circle right Mean angle Correct
ion Corrected angle
A 87º 40’ 20” 267º 40’ 35” B 110º 32’ 30” 290º 32’ 45” (1) 22º 52’ 10” (2) 22º 52’ 10” (3) 22º 52’ 10”
5
"
22º 52’ 05” B 110º 32’ 30” 290º 32’ 45” C 184º 14’ 20” 04º 13’ 33” (4) 73º 41’ 50” (5) 73º 41’ 48” (6) 73º 41’ 49”5
"
73º 41’ 44” C 184º 14’ 20” 04º 13’ 33” D 286º 25’ 30” 106º 25’ 50”(7) 102º 11’ 10” (8) 102º 11’ 17” (9) 102º 11’ 13,5”
5
"
102º 11’ 8,5” D 286º 25’ 30” 106º 25’ 50” A 87º 40’ 40” 267º 40’ 55” (10) 161º 15’ 10” (11) 161º 15’ 05” (12) 161º 15’ 7,5”5
"
161º 15’ 2,5” Total 360º 00’ 20” 360º 00’ 00” Correction =4
"
2
0
=5
"
STEPS TO FOLLOWNOTE: When the number subtracting is smaller add 360º to the number B minus A 1. 110º 32’ 30” – 87º 40’ 20” = 22º 52’ 10” 2. 290º 32’ 45” – 267º 40’ 35” = 22º 52’ 10” (1) + (2) = 45º 44’ 20” 3. Mean angle =
2
"
20
'
44
44
°
= 22º 52’ 10” C minus B 4. 184º 14’ 20” – 110º 32’ 30” = 73º 41’ 50” 5. 364º 13’ 33” – 290º 32’ 45” = 73º 41’ 48” ( add 360º to the 4º) (4) + (5) = 147º 23’ 38” 6. Mean angle =2
"
48
'
41
147
°
= 73º 41’ 49” D minus C 7. 286º 25’ 30” – 184º 14’ 20” = 102º 11’ 10” 8. 106º 25’ 50” – 04º 13’ 33” = 102º 11’ 17” (7) + (8) = 204º 22’ 27”9. Mean angle =
2
"
27
'
22
204
°
= 102º 11’ 13,5” A minus D 10 447º 40’ 40” – 286º 25’ 30” = 161º 15’ 10” ( add 360º to the 87º) 11 267º 40’ 55” – 106º 25’ 50” = 161º 15’ 05” (10) + (11) = 322º 30’ 15” 12. Mean angle =2
"
15
'
30
322
°
= 161º 15’ 7,5”13. Add ALL the mean angles 14. If the answer is less than 360
Divide the difference by the number of mean angle Add the answer to each mean angle
15. If the answer is more than 360
Divide the difference by the number of mean angle Subtract the answer from each mean angle
From the example above :
In this case the total mean angles is 360º 00’ 20” which is 20” more Therefore divide 20” by 4 and the answer is 5”
We then subtract 5” from each mean angle
OTHER FORMULAE Collimation error (E)
E =
[
(
CR−180°)
−CL]
2 1 CL = Circle left CR = Circle right Index error E = ( CL + CR) – 360ºEXERCISE 6
QUESTION 6.1
The following reading were obtained from a survey station “P”. Calculate the mean observed angles QPR , RPS, SPT, TPQ Check the calculations
Target
station Circle left Circle right
Q 168 : 11 : 43 348 : 11 : 42 R 17 : 11 : 50 197 : 11 : 56 S 104 : 03 : 42 284 : 03 : 43 T 105 : 04 : 43 285 : 04 : 43 Q 168 : 11 : 45 348 : 11 : 42 QUESTION 6.2
The following reading were obtained from a survey station “A”.
Calculate the mean observed angles BAC , CAD, DAE, EAF, FAG, GAB Check the calculations
Target
station Circle left Circle right
B 07 : 00 : 40 187 : 01 : 00 C 96 : 43 : 20 276 : 43 : 00 D 187 : 22 : 10 07 : 21 : 50 E 204 : 15 : 15 24 : 15 : 40 F 276 : 35 : 10 96 : 35 : 50 G 342 : 20 : 05 162 : 20 : 00 B 07 : 01 : 00 187 : 00 : 40 Question 6.3
6.3.1 A direction on a circle left observation of a theodolite was 36º 10’ 21”. The same direction on a
circle right observation was 216º 11’ 08”. Calculate the collimation error of the theodolite
6.3.2 Vertical angle on the circle left and circle right to a distant point are CL 93º 56’ 10”
CR 266º 04’ 40”
6.3.3 The following directions were observed from A to R. Reduce the mean direction
Cirlce left Circle right
96º 43’ 20” 276º 43’ 00”
6.3.4 The following directions were observed from P toQ. Reduce the mean direction
Cirlce left Circle right 7º 01’ 00” 187º 00’ 40”
5.2 CO – ORDINATES (JOIN CALCULATIONS)
SA co-ordinate system –x (180º) ((θ + 90) (θ + 180) +y (90º) – y (270º) θ (θ + 270) +x (0º and 360º) FORMULAE ∆yAB =yB −yA ∆xAB =xB −xA
Note: If given AB ( meaning from A to B) then its B minus A If given BA ( meaning from B to A) then its A minus B
Distance or length
AB = (∆y)2 +(∆x)2Direction or angle
θ = ∆ ∆ − x y 1 tan NOTE:2.1 If is positive and ∆ is positive, we are in the 1 quadrant D = ∆ ∆ − x y 1 tan
2.2 If ∆yis positive and ∆xis negative, we are in the 2nd quadrant
D = ∆ ∆ − x y 1 tan + 90
2.3 If ∆yis negative and ∆xis negative, we are in the 3rd quadrant
D = ∆ ∆ − x y 1
tan + 180 2.4 If ∆yis negative and ∆xis positive, we are in the 4th quadrant D = ∆ ∆ − x y 1 tan + 270 EXAMPLE Question
The co-ordinates of point A and B are
Y X
A – 248,17 – 58,47
B – 150,27 – 260,80
Calculate the orientated direction and distance between A and B (
Answer ( remember it’s A to B )
A B AB y y y = − ∆ ) 17 , 248 ( 150 − − − = ∆yAB = 97,9 A B AB x x x = − ∆ ) 47 , 58 ( 80 , 260 − − − = ∆xAB = −202 ,33 Distance from A to B 2 2 ( ) ) ( y x AB = ∆ + ∆ 2 2 ( 202,33) ) 9 , 97 ( + − = AB 771 , 224 = AB m θ = ∆ ∆ − x y 1 tan θ = − 33 , 202 9 , 97 tan 1 θ = 25º 49′ 14,24″
Since ∆yis negative and ∆xis positive, we are in the 4th quadrant D =
∆ ∆ − x y 1 tan + 270
∴
Direction = 25º 49′ 14,24″ + 270 = 295º 49′ 14,24″Question
The co-ordinates of point A and B are
Y X
A – 248,17 – 58,47
B – 150,27 – 260,80
Calculate the orientated direction and distance between B and A (
Answer ( remember it’s B to A )
B A BA y y y = − ∆ ) 150 ( 17 , 248 − − − = ∆yBA = −97,9 B A BA x x x = − ∆ ) 80 , 260 ( 47 , 58 − − − = ∆xBA = 202 ,33 m Distance from A to B 2 2 ( ) ) ( y x AB = ∆ + ∆ 2 2 (202,33) ) 9 , 97 (− + = AB 771 , 224 = AB m θ = ∆ ∆ − x y 1 tan θ = − 33 , 202 9 , 97 tan 1 θ = 25º 49′ 14,24″
Since ∆yis positive and ∆xis negative, we are in the 2nd quadrant D =
∆ ∆ − x y 1 tan + 90
∴
Direction = 25º 49′ 14,24″ + 90= 115º 49′ 14,24″
EXERCISE 7
7.1 The co-ordinates of point A and B are
Y X
A +310 248,17 – 1 058,47
B +309 295,17 – 1 688,04
Calculate the orientated direction and distance between A and B
7.2 The co-ordinates of point A and B are
Y X
A –467,89 +120,45
B –120,45 +467,89
Calculate the orientated direction and distance between B and A
7.3 Study the information below showing point that formulate boundaries of a property. Calculate the lengths of all the side of the property
SIDES (Metres) ANGLES OF DIRECTION CO-ORDINATES Y AB BC CD DE EF FA 335 : 24 : 20 66 : 04 : 20 155 : 24 : 20 246 : 04 : 20 155 : 24 : 20 246 : 04 : 20 A B C D E F Constant: 0,00 – 53 937,40 – 53 963,29 – 53 930,38 – 53 918,31 – 53 921,96 – 53 908,23 +3 700 000,00 + 60 210,88 + 60 267,26 + 60 281,86 + 60 255,49 + 60 253,86 + 60 223,86 * 377 P5 – 54 006,63 + 60 267,44 * 378 P5 – 53 879,14 + 60 320,80
All beacons are 12 mm iron pegs
A
723 F 726 E
B 728
C Scale 1/1000
The figure A B C D E F represents 2100 square metres of land being
ERF PORTION OF ERF WALMER
Situated in the municipality and Administrative District of Port Elizabeth surveyed in June 1981
This diagram is annexed to
No Dated i.f.o
Registrar of Deeds
The original diagram is
No 7494/1981 annexed to Transfer/Grant No File No s/7902/94 S.R No Comp. BO-8CC/x43
CHAPTER 6
SETTING OUT
6.1
How a traveller is used with profiles to control excavation and foundation levelsa) Two profiles ate place at each end of the excavation.
b) A small cross bar is fixed at each profile at a level equal to the invert level of the
excavation plus the traveller (follower)
c) The depth if the excavation is therefore controlled by dipping the traveller such
that the line of sight between the two bars of the profiles is in line with that of the
cross bar of the traveller
6.2
How to set up a rectangular site along a road and use the road as a reference on the site plana) Offsets must be taken from the road reserve to the boundary of the site that is required
b) A baseline parallel to the road drawn.
c) The corresponding chainage of the site boundary are then identified
d) the required site shape is then set out from the baseline
6.3
On site, how to set out two points A and B stationed on a third point known co-ordinatesa) Set up the instrument and calculate the direction between the point on which the instrument
is set up and point A and the distance between the two points b) Also calculate the direction between the point on which the instrument is set up and point B
c) Orientate direction from instrument to point A and measure the distance and put a peg
d) Swing the instrument to point B using the calculated direction of point B and measure the
distance from the instrument to point B and put a peg
6.4
How to set out a rectangular proposed building using simple surveying instrument forearthworks
Equipment: 100m tape, Four steel pegs or droppers ±2m long, Lime, Fish line,
Levelling instrument. Traveller ±2m high
Measure the distance of the proposed structure from all the four corners and make it ±1m less
From each side of the building.
Put the steel pegs or droppers on these new found points and mark them for a 2m traveller
taking the 150m depth of the top soil into consideration
The area to be removed top soil is the one that is indicated by ABCD
A B
C D
6.5 CUT AND FILL
Ground level Depth of excavation at A A Depth of excavation at B Invert level at A Δh B Invert level at B Steps to follow:Δh = gradient x distance from first to the last point 2. Calculating the invert level of the first point
Invert level at A = ground level – excavation
3. Calculating the invert level of the last point
Invert level at B = invert level at A – Δh 4 Calculating invert level at other points
e.g. chainage is 00 20 40 55 60
invert level at 00 is the invert level of the first point invert level at 60 is the invert level of the last point Invert level at 20 = invert level at A – gradient (20) Invert level at 40 = invert level at A – gradient (40) Invert level at 55 = invert level at 40 – gradient (55) 5. How to determine Cut or Fill
Ground level of a point – invert level of that point = Cut or Fill If the answer is positive then it is a Cut
If the answer is negative then it is a Fill
EXAMPLE
Given : Chainage Ground level A 0 50,76 20 50,00 40 45,75 45 47,28 B 60 49 20The information above refers to a drain between point A and B. The depth of excavation at A is 1,96m
and the fall from A to B is 1:40. Calculate the Cut and Fill in metres 1. Δh = gradient x distance
Δh = 1,5m
2. Invert level at A = 50,76 – 1,96
= 48,8 m (write this figure in the invert level column as shown in table 1)
3. Invert level at B = 48,8 – 1,5
= 47,3 m (write this figure in the invert level column as shown in table 1)
4. Invert level at 20 = 48,8 – 0,025(20)
= 48,3 m (write this figure in the invert level column as shown in table 1)
5. Invert level at 40 = 48,8 – 0,025(40)
= 47,8 m (write this figure in the invert level column as shown in table 1)
6. Invert level at 45 = 48,8 – 0,025(45)
= 47,675 m (write this figure in the invert level column as shown in table 1)
calculating the cut and fill
At 00 chainage 50,76 – 48,8 = 1,96 Cut At 20 chainage 50,00 – 48,3 = 1,70 Cut At 40 chainage 45,75 – 47,8 = –2,05 Fill At 45 chainage 47,28 – 47,675 = –0,395 Fill At 60 chainage 50,76 – 48,8 = 1,96 Cut
Table 1
Chainage Groundlevel Invert levels Cut Fill
A 0 50,76 48,8 1,96 20 50,00 48,3 1,70 40 45,75 47,8 2,05 45 47,28 47,675 0,395 B 60 49,20 47,3 1,90
EXERCISE 8
Quesrtion 8.1A drain is laid between A and B. The excavation at A is 1,58m and the fall from A to B is 1:75
Calculate the cut and fill in metres. Use the data given below Chainage Ground
A 0 250,15 20 251,26 40 247,99 60 252,56 65 253,01 80 247,323 100 250,08 B 120 249,67 Question 8.2
A drain is laid between a House (H) and the manhole (M). the depth of the excavation at House
1,368m and the fall from the house to the manhole is 0,76%. Use the information given below to
calculate the cut and fill in metres
Chainange Ground level
House 0 322,80 25 326,42 40 327,42 60 320,42 75 319,46 80 324,22 100 325,44 105 326,47 Manhole 120 322,10 Question 8.3
The information below refers to the details of a drain which is to be laid between P and Q. the depth
of the excavation at Q is 2,4m the rise from Q to P is 0,82%. Calculate the invert level at the different
points and also the Cut and Fill
Chainange Ground level
P 0 420,90 15 424,40 25 425,43 40 420,42 60 419,46 75 424,22 80 425,44 100 426,47 Q 120 420,20 Question 8.4
A drain is laid between A and B. The Reduced level at B is 47,3m and the fall from A to B is 1:80
Calculate the cut and fill in metres. Use the data given below
6.6 LENGTH AND THE SLOPE OF DRAINAGE PIPE
]1. Slope = ∆chainage∆h Chainage Ground
level Invert level A 0 50,76 20 50,00 40 47,16 60 49,57 80 49,00 100 48,80 B 120 48,50 47,30
Δh = difference between invert levels
Δchainage (distance) = difference between chainage
2. Length of the pipe = (∆h)2 +(∆chainage )2
NOTE: Length of pipe is the same as the length of the slope
3. Slope as a percentage of the pipe = ×100% ∆ ∆ chainage h
EXAMPLE
QUESTION
A BC DATUM MSL 300 GROUND LEVEL INVERT LEVEL DISTANCE ( CHAINAGE) 4 6 0 0 ,0 0 3 0 9 ,2 7 8 3 1 0 ,8 0 4 6 6 0 ,0 0 3 1 1 ,1 0 0 3 1 2 ,4 0 4 7 3 6 ,6 0 3 0 7 ,9 0 0 3 0 9 ,2 2
The diagram below shows a longitudinal section of a pipeline 1. Calculate the total length of the piping required from A to C 2. Calculate the slope as a percentage of the pipeline
SOLUTION
1.1 AB = (∆h)2+(∆chainage )2 ( )2 ( )2 4600 4660 278 , 309 10 , 311 − + − = AB ( ) ( )2 2 60 822 , 1 + = AB 028 , 60 = AB m 2 2 ( ) ) ( h chainage BC = ∆ + ∆ ( )2 ( )2 4660 6 , 4736 9 , 307 10 , 311 − + − = BC ( ) (2 )2 6 , 76 2 , 3 + = BC 667 , 76 = BC m Total length AC = 60,028 + 76,667 = 136,695 m 2. slope A to B 100 4600 4660 278 , 309 10 , 311 × − − = = 3,037 % slope B to C 100 4660 6 , 4736 9 , 307 10 , 311 × − − = = 4,178 % 3 slope A to B 4600 4660 278 , 309 10 , 311 − − = = 60 822 , 1 =32,1931 Ratio = 1 : 32,931 slope B to C =3114736,10,6−−3074660,9 =763,2,6 =23,1938 Ratio = 1 : 23,938EXERCISE 9
Question 9.1
The diagram below is a longitudinal section of a pipeline Carefully study the drawing and calculate the following:
9.1.1 the length of the required piping between point A and B and B and C and C and D
9.1.2 The slope as a percentage of the pipeline between A and B and B and C and C and D
9.1.3 The slope as a ratio of the pipeline between A and B and B and C
B C A D E
200 DATUM MSL
GROUND LEVEL INVERT LEVEL DISTANCE 3 8 0 0 ,0 2 0 9 ,4 8 9 2 1 0 ,9 0 3 8 6 0 ,0 2 1 1 ,2 0 0 2 1 2 ,5 0 3 9 2 3 ,0 2 1 1 ,0 2 2 1 2 ,2 0 3 9 3 6 ,6 2 0 8 ,0 0 2 0 9 ,3 2 9 6 7 ,5 2 0 7 ,9 0 2 0 9 ,4 8 63
Question 9.2
A sewer internal reticulation longitudinal section MHO20 – MHO26 is shown below
9.2.1 Calculate the length on the pipeline between MHO23 and MHO25 9.2.2 Calculate the slope of the terrain between MHO24 and MHO25
PIPE NGL MHO20 MHO21 MHO22 MHO23 MHO24 MHO25 MHO26 Datum 55m
INVERT LEVEL GROUND LEVEL CHAINAGE (m) 0 0 ,0 0 0 6 7 ,3 0 9 6 5 ,9 0 0 1 8 ,1 9 4 6 5 ,5 9 7 4 5 ,9 5 6 6 6 ,5 8 1 6 5 ,1 3 4 6 3 ,9 1 4 5 4 ,8 9 0 9 1 ,9 1 2 6 5 ,8 9 4 6 4 ,5 1 0 1 5 0 ,9 1 2 6 3 5 9 2 6 2 ,3 3 7
Question 9.3
From ANNEXURE C on REESTON INTERNAL SERVICES AREA C’-SEWER LAYOUT details junction C1 – C7
(NB: There are five sections of the pipeline to be considered) Calculate the total length of pipework C1 to C7
ANNEXURE C
REESTON INTERNAL SERVICES AREA C – AS-BUILT SEWER LEVELS
Question 9.4
The information below is for a layout plan of a pipeline from MHO10 – MHO134 Calculate the pipe length required from
9.4.1 MHO10 to MHO16 9.4.2 MHO16 to MHO15 9.4.3 MHO15 to MHO14 9.4.4 MHO14 to MHO13
6.7 Calculating the staff reading and height of sight
rails (SR)
Collimation line
Staff staff reading at A
Staff reading at B datum A Traveller sight rail Invert level A B Δh Invert level B
NOTE: This is base on the assumption that we are given the Depth of excavation
Step 1 Calculate the collimation height
Collimation height = BS + BM
Step 2 Calculate the fall (difference in height)
Δh = gradient x distance
Step 3 Calculate the Invert level at A (if not given invert level
of A)
Invert level at A = Ground level – Excavation Step 4 Calculate the Invert level at B
Invert level at B = Invert level at A – Δh Step 5 Calculate the staff reading at A
Staff reading at A = Collimation height – (Invert level at A + height of the traveller)
Step 6 Calculate the staff reading at B
Staff reading at B = Collimation height – (Invert level at B + height of the traveller)
EXAMPLE
Question
A drain PQ is to be set out using a tilting level, given the following information Length of the drain 225m
Gradient PQ falling from P to Q at 0,80% Ground level at P is 229,38m
Depth of excavation at P 0,90m
Length of the traveller (Boning rod) is 1,90m
A backsight of 1,50m is taken on a benchmark with an elevation of 230,31m Calculate the staff reading necessary to locate sight rails over P and Q
SOLUTION
Collimation height = 1,5 + 230,31 = 231,81
Falling = 200 100 × = 1,6 Invert level at P = 229,38 – 0,9 = 228,48 Invert level at Q = 228,48 – 1,6 = 226, 88 Staff reading at P = 231,81−
(
228,48+1,9)
= 1,43 Staff reading at Q = 231,81−(
226,88 +1,9)
= 3,03EXERCISE 10
Question 10.1A drain AB is to be set out using a tilting level, given the following information Length of the drain 200m
Gradient AB falling from A to B at 1 : 125 Ground level at A is 207,49m
Depth of excavation at A 1,00m
Length of the traveller (Boning rod) is 2,00m
A backsight of 1,50m is taken on a benchmark with an elevation of 208,21m Calculate the staff reading necessary to locate sight rails over A and B
Question 10.2
Length of the drain 225m
Gradient PQ falling from P to Q at 0,80% Ground level at P is 229,38m
Depth of excavation at P 0,90m
Length of the traveller (Boning rod) is 1,90m
A backsight of 1,60m is taken on a benchmark with an elevation of 230,31m Calculate the staff reading necessary to locate sight rails over P and Q
Question 10.3
A drain AB is to be set out using an automatic levelling instrument from the following information
Length of the drain pipe 155m
Gradient AB falling from A to B at 1 : 180 Invert level of pipe at A 100,400m
Thickness of the pipe 30mm Bedding depth 50mm
Length of the traveller (Boning rod) is 1,800m
A backsight of 1,400m is taken on a benchmark with an elevation of 102,220m Calculate the staff reading necessary to locate sight rails over A and B
Question 10.4
Calculate the staff readings necessary to locate sight rails over N and M. Given the following information
Length of the drain pipe 165m
Gradient NM rising from N to M at 1 : 100 Invert level of pipe at N is 280,400m
Length of the traveller (Boning rod) is 2,00m
A backsight of 2,60m is taken on a benchmark with an elevation of 282,00m Calculate the staff reading necessary to locate sight rails over N and M
Calculate the staff readings necessary to locate sight rails over A and B Given the following information
Length of the drain pipe 180m
Gradient AB rising from A to B at 0,75% Ground level at P is 312,50m
Depth of excavation at P is 1,00m
Length of the traveller (Boning rod) is 2,00m
A backsight of 1,80m is taken on a benchmark with an elevation of 195,00m Calculate the staff reading necessary to locate sight rails over A and B
CHAPTER 7
AREAS AND VOLUMES
7.1 AREA
Difference between the ordinate and mid-ordinate Given the following Sketch
5m 6m 7m
3m 5m and 7m are ordinate
6 2
7 5
=
mid-ordinate = sum of two ordinate divide by two FORMULAE
7.1.1
Mid ordinate rule
a) If given mid-ordinates
Area = width x sum of the mid ordinates
Example
Given: mid-ordinate 6, 8, 7, 4 all in m and the width between the ordinate is 10m
Area = 10( 6 + 8 + 7 + 4) Area = 250 m2
b) If given ordinates
Area = width st last ord sum..of ..other ..ordinates
2 .. 1 + + Example
Given: ordinate 8, 7, 9, 6, 5, 3, 0 all in m and the width between the ordinate is 15m Area = 15 + +7+9+6+5+3 2 0 8 Area = 15 x 34 Area = 510 m2
7.1.2
Trapezoidal rule
(ONLY when given ordinates)Area =
[
1 2( .. .. .. )]
2 last sum of other ordinates
width st + +
Example
Given: ordinate 8, 7, 9, 6, 5, 3, 0 all in m and the width between the ordinate is 10m Area =
[
8 0 2(7 9 6 5 3)]
2 15 + + + + + + Area = 7,5 x 68 Area = 510 m27.1.3
Simpson’s rule
(ONLY when given ordinates)Area =
[
1 4( .. .. .. ) 2( .. .. .. )]
3 last sum of even ord sum of odd ord
width st + + +
Example
Given: ordinate 8, 7, 9, 6, 5, 3, 0 all in m and the width between the ordinate is 15m Area =
[
8 0 4(7 6 3) 2(9 5)]
3 15 + + + + + + Area = 5 x 100 Area = 500 m2Exercise 11
Question 11.1From a straight line AB Offsets to the bank of a river are
A B
Distance (m) 00 50 100 150 200
0ffsets (m) 21 26 22 23 21
Calculate the area between AB and the river using the following methods 11.1.1 Trapezoidal rule
11.1.2 Mid-ordinate rule 11.1.3 Simpson’s rule