• No results found

Direction or angle

In document SURVEY NOTES N5 (Page 47-55)

Cirlce left Circle right

96º 43’ 20” 276º 43’ 00”

6.3.4 The following directions were observed from P toQ. Reduce the mean direction

Cirlce left Circle right 7º 01’ 00” 187º 00’ 40”

5.2 CO – ORDINATES (JOIN CALCULATIONS)

SA co-ordinate system –x (180º)

((θ + 90) (θ + 180)

+y (90º) – y (270º)

θ (θ + 270)

+x (0º and 360º) FORMULAE

yAB =yB yA

xAB =xB xA

Note: If given AB ( meaning from A to B) then its B minus A If given BA ( meaning from B to A) then its A minus B

Distance or length

AB = (y)2 +(x)2

Direction or angle

θ =

x

1 y tan NOTE:

2. To get the direction ( D) use the following

2.1 If is positive and is positive, we are in the 1 quadrant

The co-ordinates of point A and B are Y X

A – 248,17 – 58,47

B – 150,27 – 260,80

Calculate the orientated direction and distance between A and B (

Distance from A to B

2

Direction = 25º 49′ 14,24″ + 270 = 295º 49′ 14,24″

Question

The co-ordinates of point A and B are Y X

A – 248,17 – 58,47

B – 150,27 – 260,80

Calculate the orientated direction and distance between B and A (

Distance from A to B

2

= 115º 49′ 14,24″

EXERCISE 7

7.1 The co-ordinates of point A and B are Y X

A +310 248,17 – 1 058,47

B +309 295,17 – 1 688,04

Calculate the orientated direction and distance between A and B

7.2 The co-ordinates of point A and B are Y X

A –467,89 +120,45

B –120,45 +467,89

Calculate the orientated direction and distance between B and A

7.3 Study the information below showing point that formulate boundaries of a property. Calculate the lengths of all the side of the property

SIDES (Metres) ANGLES OF

DIRECTION

B

728

C Scale 1/1000

The figure A B C D E F represents 2100 square metres of land being

ERF PORTION OF ERF WALMER

Situated in the municipality and Administrative District of Port Elizabeth surveyed in June 1981

This diagram is annexed to No

Dated i.f.o

Registrar of Deeds

The original diagram is

No 7494/1981 annexed to Transfer/Grant

No

File No s/7902/94 S.R No

Comp. BO-8CC/x43

CHAPTER 6

SETTING OUT

6.1

How a traveller is used with profiles to control excavation and foundation levels

a) Two profiles ate place at each end of the excavation.

b) A small cross bar is fixed at each profile at a level equal to the invert level of the

excavation plus the traveller (follower)

c) The depth if the excavation is therefore controlled by dipping the traveller such

that the line of sight between the two bars of the profiles is in line with that of the

cross bar of the traveller

6.2

How to set up a rectangular site along a road and use the road as a reference on the site plan

a) Offsets must be taken from the road reserve to the boundary of the site that is required

b) A baseline parallel to the road drawn.

c) The corresponding chainage of the site boundary are then identified

d) the required site shape is then set out from the baseline

6.3

On site, how to set out two points A and B stationed on a third point known co-ordinates

a) Set up the instrument and calculate the direction between the point on which the instrument

is set up and point A and the distance between the two points b) Also calculate the direction between the point on which the instrument is set up and point B

and the distance between the two points

c) Orientate direction from instrument to point A and measure the distance and put a peg

d) Swing the instrument to point B using the calculated direction of point B and measure the

distance from the instrument to point B and put a peg

6.4

How to set out a rectangular proposed building using simple surveying instrument for

earthworks

Equipment: 100m tape, Four steel pegs or droppers ±2m long, Lime, Fish line,

Levelling instrument. Traveller ±2m high

Measure the distance of the proposed structure from all the four corners and make it ±1m less

From each side of the building.

Put the steel pegs or droppers on these new found points and mark them for a 2m traveller

taking the 150m depth of the top soil into consideration

The area to be removed top soil is the one that is indicated by ABCD

A B

C D

6.5 CUT AND FILL

Ground level

Depth of excavation at A A

Depth of excavation at B

Invert level at A Δh

B Invert level at B

Steps to follow:

1. Calculating the Fall ( difference in height)

Δh = gradient x distance from first to the last point

2. Calculating the invert level of the first point Invert level at A = ground level – excavation

3. Calculating the invert level of the last point

Invert level at B = invert level at A – Δh

4 Calculating invert level at other points e.g. chainage is 00 20 40 55 60

invert level at 00 is the invert level of the first point invert level at 60 is the invert level of the last point Invert level at 20 = invert level at A – gradient (20) Invert level at 40 = invert level at A – gradient (40) Invert level at 55 = invert level at 40 – gradient (55) 5. How to determine Cut or Fill

Ground level of a point – invert level of that point = Cut or Fill If the answer is positive then it is a Cut

If the answer is negative then it is a Fill

EXAMPLE

Given :

Chainage Ground level A 0 50,76

20 50,00

40 45,75

45 47,28

B 60 49 20

The information above refers to a drain between point A and B. The depth of excavation at A is 1,96m

and the fall from A to B is 1:40. Calculate the Cut and Fill in metres 1. Δh = gradient x distance

Δh = 0,025 ×60 NOTE:

Δh = 1,5m

2. Invert level at A = 50,76 – 1,96

= 48,8 m (write this figure in the invert level column as shown in table 1)

3. Invert level at B = 48,8 – 1,5

= 47,3 m (write this figure in the invert level column as shown in table 1)

4. Invert level at 20 = 48,8 – 0,025(20)

= 48,3 m (write this figure in the invert level column as shown in table 1)

5. Invert level at 40 = 48,8 – 0,025(40)

= 47,8 m (write this figure in the invert level column as shown in table 1)

6. Invert level at 45 = 48,8 – 0,025(45)

= 47,675 m (write this figure in the invert level column as shown in table 1)

In document SURVEY NOTES N5 (Page 47-55)

Related documents