Semester 2 15/16
POWER SYSTEMS I EEPB353 POWER FLOW ASSIGNMENT
NAME: MUHD. SYAHMI AZRI BIN SANSUL BAHRI ID: EP092693
SECTION: 3
LECTURER: MR. JOHN STEVEN NAVAMANY
No .
Title Page
1 Introduction 1
2 Load flow application 1
3 Simulation results 4-16
4 Discussions 17
5 Conclusions 18
6 References 18
Power flow studies or also known as load flow is an important part of power system analysis[1]. Normally, numerical methods are used to solve the load flow. These are important for planning, economic scheduling, as well as control of an existing system and for future expansion. Load flow focusses on voltage and voltages angle at each bus, and real power and reactive power for lines and loads. Computer software such as PSS®E Xplore 34 and MATLAB are very essential to calculate the desired parameters. By running the simulation tools in the software, one can simulate and solve the power system in real life with real conditions. To solve complex and multiple circuits with many diagrams, it is convenient to solve using a computer software. One also can draw the diagram using the software mention above. For this assignment, PSS®E Xplore 34 will be used.
Load Flow Applications
Generally, load flow solutions are mostly used for the power system design, planning and its operations. These are some another essential applications for any electrical power engineers in power flow analysis [2]:
1. Operation planning for transmission division expansion. 2. Operation planning for distribution expansion planning.
3. Industrial/Commercial distribution system planning, operational planning 4. Network interconnection, Grid interconnection studies
5. Evaluation of energy used.
6. Sizing of transformers, cables, overhead lines, transformer tap ranges, shunt capacitors, shunt reactors, reactive power management, HVDC operation
Impedance Calculations Base values: SB = 100 MVA VB1 = 13.8 kV VB2 = 13.8 kV VB3 = 13.8 kV VB4 = 13.8 kV VB5 = 13.8(230/13.8) = 230 kV VB6 = 230 kV VB7 = 230 kV VB8 = 230 kV VB9 = 230 kV VB10 = 230 kV VB11 = 13.8 kV Generators Impedances: XG1 = 0.1 (100MVA/100MVA) = 0.1 pu XG2 = 0.1 (100MVA/200MVA) = 0.05 pu XG3 = 0.1 (100MVA/500MVA) = 0.02 pu XG4 = 0.1 (100MVA/300MVA) = 0.03333 pu XG5 = 0.1 (100MVA/100MVA) = 0.0125 pu
XT15 = 0.1 (100MVA/100MVA) S5 = (70MW+ j15MVAR)/100 MVA = 0.1 pu = 0.7 + j0.15 pu
XT26 = 0.1 (100MVA/100MVA) S6 = (50MW+ j10MVAR)/100 MVA = 0.1 pu = 0.5 + j0.1 pu
XT37 = 0.1 (100MVA/200MVA) S7 = (80MW+ j20MVAR)/100 MVA = 0.05 pu = 0.8 + j0.2 pu
XT48 = 0.1 (100MVA/200MVA) S8 = (60MW+ j10MVAR)/100 MVA = 0.05 pu = 0.6 + j0.1 pu XT11,10 = 0.1 (100MVA/200MVA) S9 = (250MW+j20MVAR)/100MVA = 0.05 pu = 2.5 + j0.4 pu Lines Impedances: ZBL = (230kV)2/100MVA Z79 = (0.07 + j0.9 Ω/km) x 30km/529 Ω = 529 Ω = 0.003970 + j0.05104 pu Z56 = (0.05 + j0.6 Ω/km) x 15km/529 Ω Z8,10 = (0.05 + j0.6 Ω/km) x 15km/529 Ω = 0.001418 + j0.017 pu = 0.004537 + j0.005671 pu Z57 = (0.05 + j0.7 Ω/km) x 60km/529 Ω = 0.005671 + j0.0794 pu Z59 = (0.05 + j0.9 Ω/km) x 30km/529 Ω = 0.002836 + j0.05103 pu Z68 = (0.06 + j0.8 Ω/km) x 60km/529 Ω = 0.006805 +j0.09074 pu Z6,10 = (0.06 + j0.1 Ω/km) x 30km/529 Ω = 0.003402 + j0.005671 pu Z78 = (0.07 + j0.8 Ω/km) x 15km/529 Ω = 0.001985 + j0.02268 pu Scenario 1
Bus: Bus Number Base (kV) Voltage (pu) Angle (deg) Normal Vmax (pu) Normal Vmin (pu) Emergency Vmax (pu) Emergency Vmin (pu) 1 13.8 1.0000 -2.62 1.1 0.9 1.1 0.9 2 13.8 1.0000 -2.53 1.1 0.9 1.1 0.9 3 (swing bus) 13.8 1.0000 0.00 1.1 0.9 1.1 0.9 4 13.8 0.9994 0.14 1.1 0.9 1.1 0.9 5 230 0.9872 -4.36 1.1 0.9 1.1 0.9 6 230 0.9877 -4.27 1.1 0.9 1.1 0.9 7 230 0.9897 -2.90 1.1 0.9 1.1 0.9 8 230 0.9907 -2.75 1.1 0.9 1.1 0.9 Machines: Bus number P gen (MW) P max (MW) P min (MW) Q gen (Mvar) Q max (Mvar) Q min (Mvar) M base (MVA) X source (pu) 1 30 50 0 13.2777 30 -30 100 0.1 2 30 50 0 12.7478 30 -30 100 0.05 3 100.177 7 150 0 23.2107 50 -50 100 0.02 4 100 200 0 20.0000 20 -20 100 0.03333 Loads:
Bus number P load (MW) Q load (Mvar)
5 70 15
6 50 10
7 80 20
8 60 10
From bus To bus Line R (pu) Line X (pu) 5 6 0.001418 0.017 5 7 0.005671 0.07940 6 8 0.006805 0.090740 7 8 0.001985 0.022680 2 winding transformers: From bus To bus Specified X (pu) Winding (MVA) base Winding 1 Nominal (kV) Winding 2 Nominal (kV) Rating (MVA) 1 5 0.1 100 13.8 230 100 2 6 0.1 100 13.8 230 100 3 7 0.05 100 13.8 230 200 4 8 0.05 100 13.8 230 200 Y-admittance matrix 4, 4, 0.00000000000000 , -20.0000000000000
4, 8, -0.00000000000000 , 20.0000000000000 2, 2, 0.00000000000000 , -10.0000000000000 2, 6, -0.00000000000000 , 10.0000000000000 1, 1, 0.00000000000000 , -10.0000000000000 1, 5, -0.00000000000000 , 10.0000000000000 5, 5, 5.76764273643494 , -80.9476242065430 5, 1, -0.00000000000000 , 10.0000000000000 5, 7,-0.894970655441284 , 12.5305366516113 5, 6, -4.87267208099365 , 58.4170875549316 8, 8, 4.65151566267014 , -74.7153940200806 8, 4, -0.00000000000000 , 20.0000000000000 8, 7, -3.82966136932373 , 43.7565307617188 8, 6,-0.821854293346405 , 10.9588632583618 7, 7, 4.72463202476501 , -76.2870674133301 7, 5,-0.894970655441284 , 12.5305366516113 7, 8, -3.82966136932373 , 43.7565307617188 7, 3, -0.00000000000000 , 20.0000000000000 6, 6, 5.69452637434006 , -79.3759508132935 6, 2, -0.00000000000000 , 10.0000000000000 6, 5, -4.87267208099365 , 58.4170875549316 6, 8,-0.821854293346405 , 10.9588632583618 Power Flow Diagram
Bus: Bus Number Base (kV) Voltage (pu) Angle (deg) Normal Vmax (pu) Normal Vmin (pu) Emergency Vmax (pu) Emergency Vmin (pu) 1 13.8 0.9793 -5.83 1.1 0.9 1.1 0.9 2 13.8 0.9823 -5.27 1.1 0.9 1.1 0.9 3 (swing bus) 13.8 1.0000 0.00 1.1 0.9 1.1 0.9 4 13.8 0.9596 1.11 1.1 0.9 1.1 0.9 5 230 0.9501 -8.91 1.1 0.9 1.1 0.9 6 230 0.9531 -8.33 1.1 0.9 1.1 0.9 7 230 0.9560 -6.37 1.1 0.9 1.1 0.9 8 230 0.9549 -5.15 1.1 0.9 1.1 0.9 9 230 0.9347 -11.70 1.1 0.9 1.1 0.9 Machines: Bus number P gen (MW) P max (MW) P min (MW) Q gen (Mvar) Q max (Mvar) Q min (Mvar) M base (MVA) X source (pu) 1 50 50 0 30.0 30 -30 100 0.1 2 50 50 0 30.0 30 -30 100 0.05 3 212.095 150 0 99.7437 50 -50 100 0.02 4 200 200 0 20.0 20 -20 100 0.03333 Loads:
Bus number P load (MW) Q load (Mvar)
5 70 15 6 50 10 7 80 20 8 60 10 9 250 20 Branch
From bus To bus Line R (pu) Line X (pu)
5 6 0.001418 0.017
6 8 0.006805 0.090740 7 8 0.001985 0.022680 5 9 0.002836 0.051040 7 9 0.003970 0.051040 2 winding transformers: From bus To bus Specified X (pu) Winding (MVA) base Winding 1 Nominal (kV) Winding 2 Nominal (kV) Rating (MVA) 1 5 0.1 100 13.8 230 100 2 6 0.1 100 13.8 230 100 3 7 0.05 100 13.8 230 200 4 8 0.05 100 13.8 230 200 Admittance Matrix 9, 9, 2.60007083415985 , -39.0068264007568 9, 5, -1.08529078960419 , 19.5321731567383 9, 7, -1.51478004455566 , 19.4746532440186 4, 4, 0.00000000000000 , -20.0000000000000 4, 8, -0.00000000000000 , 20.0000000000000
2, 2, 0.00000000000000 , -10.0000000000000 2, 6, -0.00000000000000 , 10.0000000000000 1, 1, 0.00000000000000 , -10.0000000000000 1, 5, -0.00000000000000 , 10.0000000000000 5, 5, 6.85293352603912 , -100.479797363281 5, 9, -1.08529078960419 , 19.5321731567383 5, 1, -0.00000000000000 , 10.0000000000000 5, 7,-0.894970655441284 , 12.5305366516113 5, 6, -4.87267208099365 , 58.4170875549316 8, 8, 4.65151566267014 , -74.7153940200806 8, 4, -0.00000000000000 , 20.0000000000000 8, 7, -3.82966136932373 , 43.7565307617188 8, 6,-0.821854293346405 , 10.9588632583618 7, 7, 6.23941206932068 , -95.7617206573486 7, 9, -1.51478004455566 , 19.4746532440186 7, 5,-0.894970655441284 , 12.5305366516113 7, 8, -3.82966136932373 , 43.7565307617188 7, 3, -0.00000000000000 , 20.0000000000000 6, 6, 5.69452637434006 , -79.3759508132935 6, 2, -0.00000000000000 , 10.0000000000000 6, 5, -4.87267208099365 , 58.4170875549316 6, 8,-0.821854293346405 , 10.9588632583618
Based on results above, the P gen obtained is 212.095 MW and Q gen obtained is 99.7437 Mvar. Both P gen and Q gen are more than the generator’s limit. This means, the generator 3 must produce more power to fulfill the demand of new load even though all other 3 plants are
operating at maximum capacity. Therefore, the power network is not capable of handling the new load. Scenario 3 Bus: Bus Number Base (kV) Voltage (pu) Angle (deg) Normal Vmax (pu) Normal Vmin (pu) Emergency Vmax (pu) Emergency Vmin (pu)
1 13.8 1.0000 -0.26 1.1 0.9 1.1 0.9 2 13.8 1.0000 1.11 1.1 0.9 1.1 0.9 3 (swing bus) 13.8 1.0000 0.00 1.1 0.9 1.1 0.9 4 13.8 0.9892 2.33 1.1 0.9 1.1 0.9 5 230 0.9740 -3.21 1.1 0.9 1.1 0.9 6 230 0.9791 -1.82 1.1 0.9 1.1 0.9 7 230 0.9765 -3.01 1.1 0.9 1.1 0.9 8 230 0.9813 -1.51 1.1 0.9 1.1 0.9 9 230 0.9579 -6.98 1.1 0.9 1.1 0.9 10 230 0.9842 -1.39 1.1 0.9 1.1 0.9 11 230 1.0000 3.86 1.1 0.9 1.1 0.9 Machines: Bus number P gen (MW) P max (MW) P min (MW) Q gen (Mvar) Q max (Mvar) Q min (Mvar) M base (MVA) X source (pu) 1 50 50 0 27.2927 30 -30 100 0.1 2 50 50 0 22.1775 30 -30 100 0.05 3 102.485 1 150 0 49.7330 50 -50 100 0.02 4 130 200 0 20.0000 20 -20 100 0.03333 11 180 400 0 39.8275 50 -50 100 0.0125 Loads:
Bus number P load (MW) Q load (Mvar)
5 70 15 6 50 10 7 80 20 8 60 10 9 250 20 Branch
From bus To bus Line R (pu) Line X (pu)
5 6 0.001418 0.017 5 7 0.005671 0.07940 6 8 0.006805 0.090740 7 8 0.001985 0.022680 5 9 0.002836 0.051040 7 9 0.003970 0.051040
6 10 0.003403 0.005671 8 10 0.004537 0.005671 2 winding transformers: From bus To bus Specified X (pu) Winding (MVA) base Winding 1 Nominal (kV) Winding 2 Nominal (kV) Rating (MVA) 1 5 0.1 100 13.8 230 100 2 6 0.1 100 13.8 230 100 3 7 0.05 100 13.8 230 200 4 8 0.05 100 13.8 230 200 11 10 0.05 100 13.8 230 200
Y admittance matrix 11, 11, 0.00000000000000 , -20.0000000000000 11, 10, -0.00000000000000 , 20.0000000000000 10, 10, 163.817749023438 , -257.168655395508 10, 11, -0.00000000000000 , 20.0000000000000 10, 8, -86.0182647705078 , 107.518096923828 10, 6, -77.7994842529297 , 129.650558471680 9, 9, 2.60007083415985 , -39.0068264007568 9, 5, -1.08529078960419 , 19.5321731567383 9, 7, -1.51478004455566 , 19.4746532440186 4, 4, 0.00000000000000 , -20.0000000000000 4, 8, -0.00000000000000 , 20.0000000000000 2, 2, 0.00000000000000 , -10.0000000000000 2, 6, -0.00000000000000 , 10.0000000000000 1, 1, 0.00000000000000 , -10.0000000000000 1, 5, -0.00000000000000 , 10.0000000000000 5, 5, 6.85293352603912 , -100.479797363281 5, 9, -1.08529078960419 , 19.5321731567383 5, 1, -0.00000000000000 , 10.0000000000000 5, 7,-0.894970655441284 , 12.5305366516113 5, 6, -4.87267208099365 , 58.4170875549316 8, 8, 90.6697804331779 , -182.233490943909 8, 10, -86.0182647705078 , 107.518096923828 8, 4, -0.00000000000000 , 20.0000000000000 8, 7, -3.82966136932373 , 43.7565307617188 8, 6,-0.821854293346405 , 10.9588632583618 7, 7, 6.23941206932068 , -95.7617206573486 7, 9, -1.51478004455566 , 19.4746532440186 7, 5,-0.894970655441284 , 12.5305366516113 7, 8, -3.82966136932373 , 43.7565307617188 7, 3, -0.00000000000000 , 20.0000000000000 6, 6, 83.4940106272697 , -209.026509284973
6, 10, -77.7994842529297 , 129.650558471680 6, 2, -0.00000000000000 , 10.0000000000000 6, 5, -4.87267208099365 , 58.4170875549316 6, 8,-0.821854293346405 , 10.9588632583618 Power Flow Diagram
Discussions
For scenario 3, the problem of lack of power supply in scenario 2 can be solved by building a new power plant. All generators can operate under their maximum capacity with all loads operating. Generator 3 expected to generate 102.4851 MW of real power and 49.733 Mvar reactive power which are less than its limits. Therefore, the proposed new power plant can fulfill the needs of new power system.
For scenario 1, the generators can support all loads given without having to run at maximum capacity. If the generators are generating more power than needed, this means the excessive power will go to the swing bus and thus the power is wasted. One can check this result with the software by setting generators 1,2 and 4 at maximum capacity. As a result, a negative sign will be shown at bus 3. Meanwhile, power system at scenario 2 has a problem with overloading.
Line impedances is also important for a power system. The higher the impedance value, the more power losses in the line, thus reducing efficiency. The length of the transmission line affects the power losses. The longer the transmission length, the higher the power losses. Therefore, the utility company usually use the short route to transmit the electricity. Keeping them closer is a good idea to reduce power losses in the transmission line cables.
In real life, the generators are usually not run at maximum capacity. They usually run at lower rate than its limit. This is very crucial to ensure that the generators can operate for longer time. Besides that, the power plants are interconnected between each other with national grid network [3]. When a power plant is under maintenance, the particular area still can receive power supply as the other generators still producing and sending the power via the transmission lines. The power plants don’t operate independently as this will increase the operating costs.
There are some important factors for planning a power network. The most important is the reliability and the capacity of generators to supply enough power to the big loads. Usually the load demand in a particular area expands per year. So, a utility company must consider and do a forecast on the increasing number of electricity demands every year.
Conclusions
To plan, design, construct and operate a power system correctly, load flow study is necessary to ensure that power is supplied correctly to the load with good efficiency. It is more convenient to use a computer software for the calculations using Gauss Seidel method. The software also allows us to determine emergency parameters. By using this PSSE software, one or an engineer is able to save time and cost in order to perform accurate calculations. The
generators are not operated at their maximum capacity so that they can be used for a long period of time. A generator also is not isolated with other generators as they should be interconnected with national grid network. Last but not least, the reliability of generator to handle such huge number of loads is very crucial when designing a good power system network.
References
[1] Hadi Saadat, “Power flow solution” in Power System Analysis, 2th ed. New York: McGraw-Hill, 1999, ch. 6, pp. 208.
[2] “Load Flow or Power Flow or Contigency Ranking and Evaluation” [Online]. Retrieved from: http://www.powerapps.org/PAES_LoadFlow.aspx
[3] Abdullah M. Al-Shaalan, “Essential aspects of power system planning in
developing countries”, Journal of King Saud University – Engineering Sciences, vol. 23, pp.