• No results found

Power Systems Laboratory 1

N/A
N/A
Protected

Academic year: 2021

Share "Power Systems Laboratory 1"

Copied!
10
0
0

Loading.... (view fulltext now)

Full text

(1)

Power Systems Laboratory

Experiment – 1

Aim:-To observe the power flow and different modes on the network with different Load Variation Curves (LVC) Power System Diagrams:

Important Points:

1. There are 4 modes to operation of the transmission line sensors, based on the MVA power limit of the line: a. Normal Mode: up to 80%

b. Alert Mode: 80%-100%

c. Emergency Mode :100%-150% (The Transmission line will function only for a few hours,

d. Contingency Mode: 150% (Circuit breakers will break the circuit at this point to save transmission line damages)

2. The Software has several errors in garbage collection mechanism. There is need of resetting the values to zero , otherwise we get erroneous results such as 375% power flow through the lines without circuit breaker action.

3. Care has to be taken to maintain the proper circuit and area number in all the components of the po wer system. Otherwise, it leads to miscalculations and illogical results. The SAVE button has to be clicked on changing attributes of any component for proper effect.

4. Proper limits have to set on the generators and transmission lines, for realistic modeling of the given power system. For this experiment we have maintain the generator to have a capability limit of 600MW , the Slack bus Generator to have capability of 1000MW and the transmission lines capacity is 100MVA. All other values are default from the experimental setup

Load Variation Curves

(2)

Observations

Load variation : 1.5 Both lines closed

Bus 1 to 2

Bus 2 to 1

Time

MW

MVA

MW

MVA

00

0.26

0.3

-0.26

0.3

30

0.18

0.2

-0.18

0.2

60

0.33

0.3

-0.33

0.3

90

0.48

0.5

-0.48

0.5

120

0.26

0.3

-0.26

0.3

150

0.41

0.4

-0.41

0.4

180

0.48

0.5

-0.48

0.5

210

0.27

0.3

-0.27

0.3

240

0.20

0.2

-0.20

0.2

270

0.20

0.2

-0.20

0.2

300

0.20

0.2

-0.20

0.2

330

0.20

0.2

-0.20

0.2

360

0.20

0.2

-0.20

0.2

Load variation : 2.5 Both lines closed

Bus 1 to 2

Bus 2 to 1

Time

MW

MVA

MW

MVA

00

0.35

0.4

-0.35

0.4

30

0.22

0.2

-0.22

0.2

60

0.32

0.3

-0.32

0.3

90

0.31

0.3

-0.31

0.3

120

0.17

0.2

-0.17

0.2

150

0.29

0.3

-0.29

0.3

180

20.20

20.4

-20.07

20.4

210

45.85

46.1

-45.22

46.1

240

75.27

75.5

-73.57

75.5

255

55.39

56.6

-55.42

56.6

270

40.32

40.6

-39.83

40.6

285

14.84

15.0

-14.77

15.0

300

0.19

0.2

-0.19

0.2

305

-0.31

0.3

0.31

0.3

315

-0.5

0.5

0.5

0.5

330

-0.18

0.2

0.18

0.2

360

-0.38

0.4

0.38

0.4

Load variation : 3 Both lines closed

Bus 1 to 2

Bus 2 to 1

Time

MW

MVA

MW

MVA

00

0.34

0.3

-0.34

0.3

30

0.33

0.3

-0.33

0.3

60

0.28

0.3

-0.28

0.3

90

0.47

0.5

-0.47

0.5

120

0.45

0.5

-0.45

0.5

150

36.90

37.1

-36.49

37.1

180

74.38

74.6

-72.71

74.6

210

94.84

95.0

-92.14

95.0

240

115.69

115.8

-111.67

115.8

255

136.18

136.2

-130.61

136.2

270

149.44

149.4

-142.74

149.4

(3)

285

122.98

123.0

-118.44

123.0

300

97.45

97.6

-94.59

97.6

305

66.95

67.2

-65.59

67.2

315

40.69

40.9

-40.19

40.9

330

21.82

22.0

-21.68

22.0

360

-0.91

0.9

0.91

0.9

Load variation : 1.5 One line open

Bus 1 to 2

Bus 2 to 1

Time

MW

MVA

MW

MVA

05

0.96

1

-0.96

1

50

0.78

0.8

-0.78

0.8

100

0.56

0.6

-0.56

0.6

160

0.73

0.8

-0.73

0.8

210

0.76

0.8

-0.76

0.8

240

0.79

0.8

-0.79

0.8

280

0.79

0.8

-0.79

0.8

320

0.79

0.8

-0.79

0.8

360

0.79

0.8

-0.79

0.8

Load variation : 2.5 One Line Open

Bus 1 to 2

Bus 2 to 1

Time

MW

MVA

MW

MVA

10

0.84

0.9

-0.84

0.9

30

0.52

0.5

-0.52

0.5

60

0.66

0.7

-0.66

0.7

90

0.86

0.9

-0.86

0.9

130

0.5

0.5

-0.5

0.5

170

15.13

15.3

-15.06

15.3

190

55.95

56.2

-55.00

56.2

240

147.9

147.9

-141.33

147.9

280

48.12

48.4

-47.42

48.4

300

-0.88

0.9

0.88

0.9

330

-0.67

0.7

0.67

0.7

360

-0.47

0.5

0.47

0.5

(4)

Both closed Initial ckt + Extra load ( load variation :1.5)

Bus 1 to 2

Bus 2 to 1

Bus 2 to 3

Bus 3-2

Time MW

MVA MW

MVA

MW

MVA MW

MVA

05

0.44

0.4

-0.44

0.4

104.5

107

-101.07

101.1

15

0.28

0.3

-0.28

0.3

106.7

109.3 -103.11

103.1

25

0.24

0.2

-0.24

0.2

108.93 111.8 -105.19

105.2

35

0.46

0.5

-0.46

0.5

111.26 114.3 -107.34

107.3

45

0.5

0.5

-0.5

0.5

113.7

116.9 -109.59

109.6

60

0.48

0.5

-0.48

0.5

116.8

120.3 -112.43

112.4

75*

Ckt breaker Action on Line between Bus 2 and 3

120

0.21

0.2

-0.21

0.2

0

0

0

0

150

0.16

0.2

-0.16

0.2

0

0

0

0

180

0.34

0.3

-0.34

0.3

0

0

0

0

210

0.49

0.5

-0.49

0.5

0

0

0

0

240

0.25

0.3

-.25

0.3

0

0

0

0

280

0.25

0.3

-.25

0.3

0

0

0

0

320

0.25

0.3

-.25

0.3

0

0

0

0

360

0.25

0.3

-.25

0.3

0

0

0

0

Load variation :3 Both lines closed

Bus 1 to 2

Bus 2 to 1

Time

MW

MVA

MW

MVA

05

0.77

0.8

-0.77

0.8

30

1.05

1.1

-1.05

1.1

45

0.95

1.0

-0.95

1.0

60

0.44

0.4

-0.44

0.4

90

0.46

0.5

-0.46

0.5

120

0.90

0.9

-0.90

0.9

135

36.66

36.9

-36.25

36.9

150

75.07

75.3

-73.38

75.3

160

99.21

99.3

-96.25

99.3

180

155.69

155.7

-148.49

155.7

210

241.9

243.1

-224.17

243.1

225

289.78

293.2

-264

293.2

235

322.7

328.6

-290.33

328.60

245

311.55

316.5

-281.5

316.5

270

191.17

191.4

-180.19

191.4

300

75.14

75.3

-73.44

75.3

320

-0.65

0.7

0.65

0.7

343

-0.19

0.2

0.19

0.2

360

-0.34

0.3

0.34

0.3

(5)

Both Closed Initial ckt + Extra load (Load Variation : 2.5)

Bus 1 to 2

Bus 2 to 1

Bus 2 to 3

Bus 3-2

Time MW

MVA MW

MVA MW

MVA MW

MVA

05

0.19

0.2

-0.19

0.2

107.11

109.8 -103.49 103.5

15

0.22

0.2

-0.22

0.2

114.09

117.4 -109.96 110

25

0.31

0.3

-0.31

0.3

120.61

124.5 -115.96 116

35

0.3

0.3

-0.3

0.3

129.13

134

-123.74 123.8

45

Circuit Breaker Action

70

0.21

0.2

-0.21

0.2

0

0

0

0

90

0.46

0.5

-0.46

0.5

0

0

0

0

120

0.21

0.2

-0.21

0.2

150

0.17

0.2

-0.17

0.2

170

7.56

7.6

-7.55

7.6

195

32.49 32.7

-32.19

32.7

240

72.35 72.6

-70.77

72.6

280

26.4

26.6

-26.23

26.6

300

0.83

0.8

-0.83

0.8

330

-0.4

0.4

0.4

0.4

360

-0.34 0.4

0.34

0.4

One open one closed Initial ckt + Extra load (Load Variation : 1.5)

Bus 1 to 2

Bus 2 to 1

Bus 2 to 3

Bus 3-2

(6)

Time MW

MVA MW

MVA MW

MVA MW

MVA

30

0.47

0.5

-0.47 0.5

109.86

112.9 -106.04

106.1

60

0.77

0.8

-0.77 0.8

116.84

120.4 -112.49

112.5

70

Ckt brk action Bet.n bus 2 n 3

85

0.64

0.6

-0.64 0.6

0

0

0

0

120

0.72

0.7

-0.72 0.7

160

0.52

0.5

-0.52 0.5

200

0.77

0.8

-0.77 0.8

240

0.74

0.8

-0.74 0.8

280

0.74

0.8

-0.74 0.8

320

0.74

0.8

-0.74 0.8

360

0.74

0.8

-0.74 0.8

Initial ckt + Extra load (LV : 2.5)

One open one closed

Bus 1 to

2

Bus 2 to

1

Bus 2 to

3

Bus 3-2

Time

MW

MVA

MW

MVA

MW

MVA

MW

MVA

15

0.91

0.9

-0.91

0.9

113.46

116.7

-109.38

109.4

45

0.11

0.1

-0.11

0.1

135.03

140.7

-129.09

129.1

75

0.81

0.8

-0.81

0.8

155.8

165.0

-147.63

147.6

90

32.66

32.9

-32.34

32.9

165.09

176.4

-155.75

155.8

120

116.69

116.7

-112.6

116.7

187.7

206

-174.97

175

150

212.67

213.2

-199.04

213.2

213.2

244.4

-195.28

195.3

160

Blackout…..

(7)

Initial ckt + Extra load (LV : 3)

One open one closed

Bus 1 to

2

Bus 2 to

1

Bus 2 to

3

Bus 3-2

Time

MW

MVA

MW

MVA

MW

MVA

MW

MVA

10

0.45

0.5

-0.45

0.5

113.91

117.2

-109.79

109.8

25

0.37

0.4

-0.37

0.4

125.54

130

-120.47

120.5

100

0.29

0.3

-0.29

0.3

0

0

0

0

125

9.57

9.7

-9.54

9.7

165

56.51

56.7

-55.54

56.7

205

112.31

112.4

-108.52

112.4

10

0

0

0

0

109.9

112.8

-106.1

106.1

25

0.95

1

-0.95

1

126.69

131.3

-121.51

121.5

50

1.06

1.1

-1.06

1.1

0

0

0

0

85

0.8

0.8

-0.8

0.8

0

0

0

0

125

19.95

20.1

-19.83

20.1

170

134.15

134.2

-128.75

134.2

Inferences

1. There are two types of buses in the first part of the experiment. Bus 1 is the Slack bus .Bus 2 is the PV bus. However, during analysis,

we treat the slack bus as PQ bus absorbing negative real power (as discussed in the power systems minor 2). The second part has three buses, Bus 2 is still the PV bus, although now Bus 1 is the slack bus, and Bus 3 is the load bus.

2. The Slack bused take are of any losses incurred on the transmission lines, apart from fulfilling the shortfall by the PV bus. The PV bus

(8)

compensate the increasing demand for power .Although the power from the Slack bus could be used, but has to be transmitted fr om another generator leading to more losses and increased economic costs.

3. In the first part, the given experimental setup is designed for the 1.5 load variation, in which the system runs under normal mode ,

for most of the time , drawing bare minimum power from the Slack bus. This is attributed to transients on the network and slo w operation of AGC. The network also adjusts for the load variation case 2.5. However, when there is a high power demand , as in the load variation 3 case, the sensor trigger an alert mode initially and then escalating to emergency, although no contingency mode is detected. (No circuit action is detected.)

4. When the third load is connected, the Transmission line between bus 2 and bus 3 is already overloaded triggering an emergency mode , and finally due to high power transfer on the line. However, the system blackout is not prevalent in the load variation 1.5 case. However, in case ,of load variation 2.5 and 3 , there is a system wide blackout to high power (150 MVA ) on both the li nes , causing circuit breaker action.

5. Contingency Mode was prevalent on the two wire, and the three wire case one of the lines between bus 1 and bus 2 was disconnected.

6. Losses on the power lines are proportional to amount of power flowing through it.

Remedies

 As stated formerly, the given circuit was designed for the 1.5 load variation cases , and barely withstands the 2.5 load variation Therefore proper surveying should be conducted for current and future trends in the network.

 The power transfer capability of the transmission systems is limited by current (thermal) related constraints, voltage related constraints and operating related constraints . The strategies employed in dealing with these are:

a. Voltage Uprating:Transmission systems are typically submitted to two voltage constraints: a maximum operating voltage equal to 105% of the nominal voltage and a minimum operating voltage equal to 95% of the nominal voltage. It is possible to increase the power transfer capability of a transmission system by increasing the operating voltage

within a voltage class, by controlling reactive power flows and consequently reducing voltage drops, and by increasing the operating voltage of its transmission lines and substation equipment. This is called Voltage Uprating.This kind of uprating can be a good option when: the line loading is limited by voltage drop or stability considerations; the line has margins in terms of electrical clearances; the uprating can be done with minimal line modifications or it will be applied to several circuits simultaneously or the line design criteria can be relaxed. Some of the techniques for voltage uprating are described below : 1. Adding insulator units to transmission line insulator strings

2. Keeping appropriate conductor to ground clearances while increasing transmission line voltage by re –tensioning the string, or by performing sag adjustments.

3. Bundling the original line conductor with another one. or replacing the line conductor by a bigger one, to assure a good corona performance

4. Converting HVAC lines to HVDC lines.

b. Thermal Uprating: It is possible to increase the power transfer capability of a transmission system by increasing the current carrying capacity of its transmission lines and substation equipment. This is called Thermal Uprating. This kind of uprating can be a good option when the line loading is limited by thermal constraints and the line has margin in terms of maximum

allowable conductor temperature. Some effective techniques are as follows: 1. Performing Dynamic Thermal Rating Monitoring.

2. Bundling the original line conductor with another one, or replacing the line conductor by a more conductive me, to increase the line current-carrying capacity.

(9)

 However , reliance only on circuit breakers isn’t enough to transmission line tripping of a single power line will eventually load the other ( maybe already overloaded ) power lines, into a cascading effect leading to a system wide collapse. In such a case, we need to increase the number of transmission lines , which probably is an expensive and not possible in case of underground power lines . One solution is to increase the capacity of generator near the loading areas, so that less power flows on the transmission lines as shown in the image. This also reduces the economic cost of

the system, since we use the cheaper locally generated power.

 Although Series capacitive compensators are used to increase the transmittable active power over a given line but they are unable to control the reactive power flowing, and thus the proper load balancing of the line. With a Inter Line Power Flow Controller (IPFC), it is possible to equalize both active and reactive power flow between the lines, reduce the burden of overloaded lines by active power transfer and increase the effectiveness of the overall compensating system for dynamic disturbances

A Basic IPFC can be modeled as shown above. Here SSSC are the Static Synchronous Series Compensator .

(10)

References

Related documents

Since Taiwan is the ¢fth largest export market for Australian beef ABARE 1998 and demand for beef in Taiwan is expected to continue to grow in the future, a declining market share in

Because of prostate tissue specificity, no release to the blood, and high expression in prostate cancer tissues, PSCA serves as an important target for prostate cancer

“Today’s parents didn’t grow up seeing their peers affected by these diseases, or living in fear of being diagnosed themselves,” says Amanda.. Dempsey, M.D., a pediatrician

Best Teacher Award: School of Politics, Philosophy, and Public Affairs Graduate Student Association, Washington State University, Pullman, WA, 2012-2013 Haridas

The assurance of manganese from phosphatic glass soluble in water determine the obtaining of superior bioproductive indices at broiler chickens comparative with

troops, certainly of the Athenian contingent. The exploits noted previously in the decree were those of the leader, Demetrius. It was in order for the soldiers to receive

In the study on needs for research and in the study on care needs, patients formulated challenges relating to receiving the correct diagnosis, finding the right treatment,

MEDC 8-bus system shown in Fig. 7 is used to illustrate proposed model and solution algorithm. Therefore, the impact of ramping-up and ramping-down limits on LMPs can be ignored and