• No results found

Turbine Controls Update

N/A
N/A
Protected

Academic year: 2021

Share "Turbine Controls Update"

Copied!
29
0
0

Loading.... (view fulltext now)

Full text

(1)

Turbine Controls Update

David Cicconi,

Business Development Manager Emerson Process Management Power & Water Solutions

(2)

Define Project Scope and Objectives

Define Project Scope and Objectives

Address obsolescence

Best solution for new operational environment (grid requirements)

Add enhanced control features

‒ Improve start-up and loading times

‒ Improve turn-down

‒ Remote operation and/or dispatch control (AGC)

Address specific field problems

Integrate PLC control into DCS

Reduce system maintenance costs

Simplify operator training needs

(3)

Changing Generation Profiles –

Abnormal is the New Normal

Changing Generation Profiles –

Abnormal is the New Normal

2012 2008

(4)

Customer Considerations For Vendor

Pre-selection

Customer Considerations For Vendor

Pre-selection

Typical Choices:

 PLC

– ControlLogix, GE Fanuc PAC, Siemens S7

– PLC providers do not control hardware

– Customized system with various control components  DCS

– ABB, Emerson, Honeywell, Foxboro, Siemens

 Proprietary system

– Woodward MicroNet Plus, GE MKVIe, Triconex

Considerations:

 Lifecycle costs

– Spare parts – availability, future costs, support

 Training

 Technology / platform basis – will

this platform be readily available for 10-15 years?

 Migration path for the future  Dependence on third parties  Turbine controls native to DCS

(5)

Application-Specific Solution

Application-Specific Solution

• Application-specific designs

• 100% compatibility with existing field devices

• Fully engineered solution (no field design)

• Drop-in panel replacement (ease of install)

• New cabinets in existing space

• Full factory testing minimizes problems during commissioning

• Maintain existing wire/cable numbers (ease of maintenance)

(6)

• Advanced control and turbine protection schemes for the CT and ST

• Local and remote operation capability

• Improved data acquisition for predictive maintenance and scheduling

• Integrated BOP control systems

• More precise and reliable fuel control

• Advanced graphical interface

• Historical logging and trending

• Diagnostics for preventative maintenance

Turbine Control Features Should Include:

Turbine Control Features Should Include:

(7)

Project Solution – Key Elements

Project Solution – Key Elements

Objective is to minimize risk, achieve high-quality and on-time performance

• Project planning

• Application-specific solution

• Complete engineering package

• Update other affected drawings

• Good software control

• Comprehensive testing system

• Installation design package

(8)

Security - NERC CIP

Security - NERC CIP

• Is the unit a “critical asset”?

• Does the new control system need to meet

customer’s security policies as well as NERC CIP?

• Cyber security is an ever-changing field — as new

threats emerge, new defenses must be developed and implemented

• Critical to keep all assets updated with the latest

defenses as legacy systems will be at greater risk

• Change management will be important to assure

new resources and patches are certified to not cause problems as they are applied

(9)

Cyber Security Latest Revisions

Cyber Security Latest Revisions

• NERC CIP Ver.5 Update

‒ Effective April 1, 2016

‒ Moving towards impact-based categorization ‒ More assets will fall under NERC CIP

(10)

Security Center / Vendor Support

Security Center / Vendor Support

• Vulnerability Assessment (VA)

• Patch Management (PM)

• Anti-Virus Defense (AV)

• Malware Prevention (MP)

• System Backup & Recovery (SBR)

• Security Incident & Event Management (SIEM)

• Network Intrusion Detection (NID)

• Network Attached Storage (NAS)

(11)

Catastrophic damage caused by overspeed...

Mechanical Overspeed to

Electrical Overspeed

Mechanical Overspeed to

Electrical Overspeed

RETAINER RING FAILED 

DUE TO OVERSPEED EVENT

DUVHA, SA USED THEIR TURBINE TO 

TEST THE OVERPSEED SYSTEM

DESTRUCTIVE OVERSPEED OF 

(12)

Overspeed Protection System

Overspeed Protection System

Test/Trip Contacts Controlled by TCS

(13)

6300 Overspeed Protection

2 Out Of 3 Voting “Internal” or “External”

6300 Overspeed Protection

2 Out Of 3 Voting “Internal” or “External”

PROBES MONITORS 1 2 3 CONVERTERS 1 2  3 SHUT DOWN VALVE TURBINE OR COMPRESSOR

1      2      3

VOTING ON 

BACKPLANE (A6371/00)

NON‐VOTING  

BACKPLANE (A6371/10)

INTERNAL

(14)

Scope Definition – Solve Problem Items Scope Definition – Solve Problem Items

• Electric actuators

• Trip system upgrades

• Igniter issues resolved

• Dual fuel conversions

• Emission reductions (SCR)

• Power augmentation (inlet fogging, steam injection)

• Improved turn-down

• Electronic overspeed protection upgrades

(15)

Scope Definition – Solve Problem Items

Scope Definition – Solve Problem Items

• Flame detection

– New detectors

• Water cooling is no longer required • Electronics removed from high

temperature zone

• Detection by thermocouples • New fuel valve

‒ Replace pneumatic or hydraulic with an electric

• Generator metering

‒ Upgrade multiple individual

transducers for V, I, MW, Mvars ‒ Replace with modern digital power

(16)

Generator Metering & Protection

Generator Metering & Protection

• Upgrade multiple

individual transducers for V, I, MW, Mvars

• Replace with modern digital power meter

• Replace generator protection relays with a digital system

(17)

Scope Definition – Vibration Monitoring

& Protection

Scope Definition – Vibration Monitoring

& Protection

• Vibration monitoring & protection systems to monitor existing vibration sensors

• Integrated with turbine control system

• Time to add new/additional probes

• Diagnostic software to help pinpoint problems (existing and future)

(18)

Turbine Vibration Monitoring & Protection

Turbine Vibration Monitoring & Protection

• Vibration monitoring & protection systems to

monitor existing vibration sensors gas or steam

turbines:

‒ CSI 6500 Machinery Health™ Monitor

‒ Remote or integrated

(19)

Excitation Replacement Project Drivers

Excitation Replacement Project Drivers

• Does the OEM still support the equipment?

• Can you get spare parts?

• Is there training available on the equipment?

• Will the AVR communicate with new DCS?

• Does the existing equipment provide Power System Stabilizers (PSS)?

(20)

SFC / LCI Controls

SFC / LCI Controls

• Same obsolescence issues as the CT controls and exciter controls

• Integrated approach for new controls

(21)

Auxiliary Retrofit Advantages

Auxiliary Retrofit Advantages

• Seamless operator interface

• Enhanced alarms and diagnostics

• Historical trending of generator data to DCS

• Enhanced control options

• Eliminate third-party protocols

• DCS compatibility

• Minimize spare parts inventory

(22)

Software – HMI Graphics

Software – HMI Graphics

HMI graphics

‒ Standard graphics set ‒ Willing to customize

‒ Review done in advance of FAT

‒ Review should include Operations personnel

(23)

Testing – Functional Test

Testing – Functional Test

Comprehensive testing to ensure all bugs worked out prior to shipment

• 100% hardware testing using actual panel and application software through to HMI

• Software testing using closed-loop simulator

‒ Full dynamic simulation of all turbine main parameters (speed, fuel flow, Tx, MW, etc)

(24)

Testing – Simulator

Testing – Simulator

• Start-up and loading – almost identical to actual unit ‒ Trends represent realistic conditions

• Ability to freeze simulator data at various operating points – no need to “restart” unit

• Fault conditions are easily created

• Used for operator training

(25)

Start-up and Site Testing

Start-up and Site Testing

• Review commissioning procedure in advance

• System tuning

• Close coordination with dispatch required

• Possible tests for droop / isochronous response, AGC response, start-up time

• Operations personnel required for system commissioning

(26)

Typical Project Schedule

Typical Project Schedule

Milestones # of Weeks

Order 0

Design Submittal 12 weeks

FAT 16 weeks

Shipment 20 weeks

Start Site Activities 24 weeks ARO

(27)

On-Site Preparation

On-Site Preparation

• Complete installation design package

• Unit-specific startup procedures

‒ Demolition/installation engineering package

‒ Commissioning procedures ‒ Site planning

• Experienced on-site team for installation & commissioning

(28)

Summary – Keys to a Successful GT

Controls Retrofit

Summary – Keys to a Successful GT

Controls Retrofit

• Vendor pre-qualification – proven hardware & experienced supplier

• Define scope – include any system improvements

• Application-specific design

• Well-defined engineering deliverables

• Customer participation in design reviews

• 100% testing – dynamic simulation

• Detailed outage planning

(29)

Questions?

Contact Dave Ciccioni

412-963-3855

References

Related documents

In order to have a more comprehensive knowledge of the evolution of regional income distribution, section 4 presents the kernel density estimates to draw the shape

Further, comparative cointegrating evidences show that the positive economic growth promoting factors is tax revenue, trade openness and foreign direct investment,

In 2016, the University of Vermont’s Northwest Crops & Soils Program conducted a forage brassica variety trial to evaluate yield and quality of commercially

(The returns from portfolios based on the prediction of net income in year t+2—not reported—follow closely the pattern in Figure 3.) Surprisingly, Model 1 (second bar from left)

The concept of a partnership through profit and loss sharing could cause Islamic banks to be very cautious in providing financing through the musharakah and

The Latent Dirichlet Allocation topic model and the Dynamic Topic Model are applied in finding underlying topics from the Internet discussion forum data.. The discussion data

A rapid increase in true positive rate at high ( >0.9 ) false positive rates is a common trend for many factors, indicating that a portion of sequence motifs that are in