Presentation Goals & Outline
• Power Density – Where we have
been- where we are now - where
we are going
• Limitations of Air Cooling – Air
Distribution, Effectiveness and
Heat Removal
Common Data Center Scene
IT Equipment Trends
*from The Uptime Institute (http://207.201.136.39/TUIpages/whitepapers/tuiheat1.0.html)
*from The Uptime Institute (http://207.201.136.39/TUIpages/whitepapers/tuiheat1.0.html)
Issues in the Data Center
Are We Hitting the Wall?
• “The failure rate at the top third of the rack is three
times greater than at the bottom.”
–Mr. Kenneth Brill, Executive Director: The Uptime
Institute, March 2003 DataCenter Dynamics
Conference
)
• The wall is at 3.5 KW/Cabinet (with raised floor)
• Without raised floor, 2.5 KW/Cabinet max.
How Do We Remove the Heat?
Water
• Water has 3500 times more heat
capacity than air by volume
Air
Overhead Air Distribution
• Limitations to capacity due to duct size /
space constraints
Underfloor Air Distribution
• Increased floor depth for higher flows
• Limitation of perforated tiles (400 cfm =
+- 4 kW/rack)
• UF obstructions
• Air Misdistribution – underfloor
velocity/static pressure
Above floor Plumes
Rack total airflow: 350cfm
Max inlet temp: 16
C/61
F
Rack total airflow: 700cfm
Max inlet temp:
18
C/64
F
Underfloor Plumes
1 kW / Cabinet – 24” Raised Floor
Column
HVAC Effectiveness
• Bypass Airflow
• Air Distribution Efficiency
ASHRAE Standards
Key Points of ASHRAE TC9.9
– Equipment Environmental Specifications
– Equipment Room Airflow
– Standardize Measuring / Monitoring Points
– Equipment Airflow Protocol Syntax
ASHRAE
Standards
The New Paradigm
Extraction
Versus
POINTS TO CONSIDER
• Effective for standard racks up to 6 KW only
• No cabinet doors.
• Cable management behind servers in “hot”
aisle.
• Limit air bypass – use rack blanking panels and
seal all floor cutouts.
• Limit mixing between hot and cold aisles.
– Partition panels above racks and doors at aisle
ends.
Rack Cooling–
Unit Options
•
Down flow Units
•
Centrifugal fan drive
•
EC fan drive
•
With DX system
Heat Density
0
5
10
15
20
25
Cabinet
Pre P3 Processor P3 Mobile Blade P4
Single Processor
1U
P4 Blades/P4
Multi-Processor 1U & 2U
Server
NextGen Ultra
Dense Blade &
Background to the Need for
Background to the Need for
Water Cooling
Water Cooling
•
Rising heat densities
• Limitations of air cooling
COOLING SYSTEMS CLOSER TO THE LOAD
.
Mounting the cooling modules as close as possible to
the source of heat—such as placing them directly
OPEN COOLING ARCHITECTURE
Closed cooling architecture
Closed architecture systems involve
extraction of room air in server rack
cabinets that are completely sealed from
room air and environmental conditions. In a
closed design, air is circulated through the
electronics and passes through a
Rack Cooling– Unit
Options
• CDU Cooling Distribution Unit
CDU with Rear Door Heat
exchanger
• Heat removal at source, rejected to water not room
•
Rear door heat exchangers on back of high heat load cabinets
without taking up any floor space
• High density racks can be added without need to upgrade CRAC
units
• Easily retrofitted as high density racks added
• Eliminates low air temp setpoints to compensate for high density
racks
• Only relatively small chilled water plant required
Data Racks & Rear Door Heat
Data Racks & Rear Door Heat
Exchangers
Exchangers
•
Industry Standard Data
Racks
• 600 wide 20kW Cooling
• 800 wide 30kW Cooling
• 6 Hot Swap Fans
• Retro-fittable to other
Racks
•Without swap fans for
“
Typical Installations
“
System Concept
System Concept
External chiller
Rear Door Heat Exchangers
Up to 6 racks
(or 12 racks at lower loads)
Minimal Thermal Impact Server Implementation using
Minimal Thermal Impact Server Implementation using
CDU & Rear Door Heat Exchangers
CDU & Rear Door Heat Exchangers
CDU
CDU
–
–
Cooling Distribution Unit
Cooling Distribution Unit
CDU120/150 Main Components
•120 to 150kW (409,450 –
511,815 BTU/Hr) capacity.
•Serves 1 to 6 rear door
heat exchangers (RDHx).
•380-480v 50/60Hz global
operation (+220v option).
•Run/Standby pumps.
•Run/Standby control
valves.
•Energy saving pump
speed control.
•240L/M (63.4 GPM) flow
capacity (40L/M per
RDHx).
•Dew point control.
•Inbuilt manifold system
with flow balancing.
•Quick release, self
sealing connections for
data rack hoses.
“
Hose Connections
Hose Connections
–
–
Process (to RDHx)
Process (to RDHx)
Primary Chilled Water Connections (1.1/2” Hose tails)
Secondary Circuit Rack Return Connections (3/4” Hose tails)
Secondary Circuit Rack Flow Connections (3/4” Hose tails)
Secondary Circuit
Connection:
• Quick release
couplings
for clean efficient
installation
• Fool-proof input and
output connections
• Tidy hose arrangement
C h ill ed W a ter Flo w / Retur n Heat Exchanger Rack 3 Rack 2 Flow Control Filter Control Valves Rack 4 Rack 5 Rack 6 Rack 3 Rack 4 Rack 5 Rack 6 40L/M 40L/M 40L/M 40L/M 40L/M T1
#
#
Redundant 2-way valve# # Redundant pump
Priming Pump P3 Filter Fill point Temp (T3) & Hum Sensor Air Eliminator Flowmeter Controller & Display D istr ibu tion manif o lds Q u ick R e le a s e C ouplings Level Sensor.
Rack 1 40L/M Bypass Valve Air Eliminator Pump P1 Pump P2 # # PS1 PS2 Speed Control PS3 PS4 T2b T2a TITLECDU PIPE SCHEMATIC
DRG. No.
A3NAD371
Iss.A
DATE 18/05/07 DR’N DSM C h ill ed W a ter Flo w / Retur n Heat Exchanger Rack 3 Rack 2 Flow Control Filter Control Valves Rack 4 Rack 5 Rack 6 Rack 3 Rack 4 Rack 5 Rack 6 40L/M 40L/M 40L/M 40L/M 40L/M T1 T1
#
#
Redundant 2-way valve# # Redundant pump
Priming Pump P3 Filter Fill point Temp (T3) & Hum Sensor Temp (T3) & Hum Sensor Air Eliminator Flowmeter Controller & Display D istr ibu tion manif o lds Q u ick R e le a s e C ouplings Level Sensor..
Rack 1 40L/M Bypass Valve Air Eliminator Pump P1 Pump P2 # # PS1 PS1 PS2PS2 Speed Control Speed Control PS3 PS3 PS4PS4 T2b T2a T2a TITLECDU PIPE SCHEMATIC
DRG. No.
A3NAD371
Iss.A
DATE 18/05/07