• No results found

Using Computational Fluid Dynamics (CFD) for improving cooling system efficiency for Data centers

N/A
N/A
Protected

Academic year: 2021

Share "Using Computational Fluid Dynamics (CFD) for improving cooling system efficiency for Data centers"

Copied!
45
0
0

Loading.... (view fulltext now)

Full text

(1)

Using Computational Fluid Dynamics

(CFD) for improving cooling system

efficiency for Data centers

Data Centre Best Practises Workshop

17th March 2009

(2)

You are Here

Data Centre Case Study – Geometrical Details

Introduction to CFD

CFD while designing of HVAC system CFD during installation of Data Centre

(3)

Computational (having to do with mathematics & computation) Fluid Dynamics (the dynamics of things that flow)

CFD is built upon fundamental physics equations: equations of motion and conservation. CFD applications range from numerical weather

prediction to vehicular aerodynamics design.

CFD applications are linked with advances in computing software and hardware. CFD software is characterized by the physical models in the software.

Fine-scale CFD applications closely match the true geometry of the physical objects and processes being modeled.

(4)
(5)
(6)

reactor vessel - prediction of flow separation and residence time effects.

(7)

ƒ Chemical Processing ƒ HVAC ƒ Hydraulics

ƒ

Aerospace

ƒ

Automotive

ƒ

Biomedical ƒ Power Generation ƒ Sports ƒ Marine

Temperature and natural convection currents in the eye following laser heating.

Aerospace

Automotive

Biomedicine

(8)

Flow around cooling towers

Marine

Sports Power Generation

(9)

You are Here

Data Centre Case Study – Geometrical Details

Introduction to CFD

CFD while designing of HVAC system CFD while installation of Data Centre

(10)
(11)

Introduction to the Case Study

• Case Study is taken from one of the project that we did for a Data Centre in India

• The case study includes what we did for the client also extends it for what could have been done for the same project using CFD

• There were two software applications used for the project : OpenSource CFD platform of OpenFoam and commercial CFD package of Fluent • Both packages produced about the same results, in this presentation the

(12)

Case Description

• The analyzed Data Centre is rectangular with of area 516m2 and height 3.35mt

• Cooling is to be provided using raised flooring layout and demarcation is done for Cold Aisle and Hot Aisle

• The sources of heat gain inside the data centre are listed below:

– Heat gain through exterior walls accounting for thermal resistance of the wall

– Heat gain from Server Racks, 154 Server racks each providing about 8 KW combine to about 1.26 MW

(13)

HVAC System Specification

10 CRAC units, 1 Standby Specification: – Each CRAC unit of 30,585 CMH

– Cooling capacity of Each Rack is 150 KW – Temperature of supply air is 9.4 o

C

– Return Air opening area (On top surface): 2.23 m2 •Supply Air Diffuser (Cold Aisle) Specifications:

–Dimension of 600mm X 600mm –70% open area

–1 supply diffuser per rack (Total 154)

–Supply air velocity can be controlled using under floor fan

Return Air Diffuser (Hot Aisle) Specification: –Dimension of 600mm X 600mm

–50% open area

(14)

Objective of the Study

To maintain recommended temperature by ASHRAE for

Class 1data centre

The recommended atmosphere is defined as:

– Temperature of 20oC - 25oC

– Relative humidity of 40% - 55 %

(15)
(16)

Design Parameters

(17)

You are Here

Data Centre Case Study – Geometrical Details Introduction to CFD

CFD while designing of HVAC system

CFD while installation of Data Centre

(18)

Base Case Design

Isometric View of the Designed Data Centre

(19)

Case Study Cont…

COLD AISLE Diffusers HOT AISLE Diffusers

Server Racks CRAC Units

(11 Nos.)

(20)

CFD Simulation of Base Case

(21)

Temperature Contour

(22)

CFD Simulation of Base Case

(23)

Temperature Contour

(24)

Temperature Contour in Middle Plane

(25)

CFD Simulation of Base Case

(26)

Temperature Contour

(27)

Temperature Contour in Middle Plane

(28)

Velocity Vectors in Middle Plane

(29)

Conclusion from the base case CFD

1.

The Average temperature on the rack surface at the cold

Aisle side is 15

2.

The temperature at Cold Aisle is varying from 12 to 17

3.

The Average temperature on the rack surface at the Hot

Aisle side is 27

4.

The temperature at Hot Aisle is varying from 18 to 32

5.

The simulation shows that a good number of servers are

experiencing temperature well above and below the

ASHRAE recommended temperature levels

(30)

Optimizing number of CRAC units & Supply Air Velocity

1. Maximum heat load : 154 X 8 = 1264 KW (1.26 MW) 2. Heat capacity of each CRAC : 150 KW

3. Minimum number of CRAC required: [8.4] = 9

4. The system was designed with 9 CRAC units and velocity of supply air was adjusted to avoid short circuiting and temperature stratification 5. In this case the velocity of 2.2 m/s is coming out to be higher

6. The simulation was conducted with velocity of 1.6, 1.7, 1.8, 1.9, 2.0 & 2.1 m/s

(31)

Temperature Distribution with 9 CRACs & 1.8 m/s

(32)

Velocity Vectors with 9 CRACs & 1.8 m/s

(33)

Results of improved design CFD

1.

The Average temperature on the rack surface at the cold

Aisle side is 16

2.

The temperature at Cold Aisle is varying from 13 to 17

3.

The Average temperature on the rack surface at the Hot

Aisle side is 23

4.

The temperature at Hot Aisle is varying from 19 to 29

5.

Short circuiting of cold air is reduced to a substantial level,

however still prevalent

6.

The simulation shows that a most of the servers are

(34)

Conclusion

Using Computational Fluid Dynamics the system was

designed to reduce to 90% of original design, thus bringing

about first cost saving of 10% in the capital cost.

(35)

You are Here

Data Centre Case Study – Geometrical Details Introduction to CFD

CFD while designing of HVAC system

CFD during installation of Data Centre

(36)

Case Description

The capacity of this data centre of of 42 X 154 = 6,468

Server Blades

4,000 server blades are to be installed

1,000 servers are by Dell, 2,000 by IBM & 1000 by Sun

The design variables are:

– Number of CRAC units

– Which CRAC unit should be operational

(37)

CFD Simulation Setup

The power requirement of 3000 Server is minimum 713 KW

– 5 CRAC (750KW) are minimum number of units which

can provide the required tonnage

The CFD simulation were conducted with various locations

of Servers, CRAC’s and Supply air velocity

The best result was found with following parameters:

– Top Racks are empty

(38)

CFD Simulation Results

(39)

CFD Simulation Results

(40)

Temperature Distribution with 5 CRACs & 1.2 m/s

(41)

Velocity Vectors in Middle Plane

(42)

Calibration during Installation

Temperature Sensors

The Result from CFD shall be compared with average

reading shown by temperature and velocity sensors

(43)

You are Here

Data Centre Case Study – Geometrical Details Introduction to CFD

CFD while designing of HVAC system CFD during installation of Data Centre

(44)

Feedforward System

Whenever capacity of the data centre is to be increased, the

design parameters like number of CRACs and supply air

velocity should be determined using CFD

If the capacity ramp up is not that frequent than CFD

simulation can be conducted at that stage to arrive at design

parameters

If ramp-up/ramp-down is very frequent then a custom made

CFD code should be developed using OpenSource Libraries.

This would enable data centre administrator to conduct

(45)

Conclusion

9 CFD can help design and operate the data centre HVAC

system with optimum efficiency

References

Related documents

and Scherpen, J.M.A., “Power shaping: A new paradigm for stabilization of nonlinear RLC circuits”, IEEE Trans. and Jeltsema, D., “Power shaping control of nonlinear systems: a

There are different Session Key Exchange methods / algorithms Like Diffie-Hellman, Secure Hill Cipher Modifications and Key Exchange Protocol, Integration of

Paper on “Overview of the Legal and Regulatory Framework for Doing Business in Nigeria” at the South-Africa Nigeria Conference held in Johannesburg, South Africa

This is why we decided to restrict ourselves to the curation of the basic data (audio, video, written text files) with their transcriptions, and to include only test

Keberhasilan implementasi pengendalian hayati hama utama jambu mete di tingkat petani, secara umum harus didukung oleh beberapa faktor yaitu (a) keinginan kuat petani untuk

The 2002 Forest Grove Parks, Recreation and Open Space Master Plan (PROMP) identifies the trail system as being a major feature among city recreational opportunities.. This community

B—Patient placement engagement: we empowered the charge nurses to maintain regular communication regarding patient flow and to assert more control especially over the assigned

Special attention in teacher education programmes at South African Universities, should be given to the inclusion of knowledge on the importance of establishing a culture