TECHNICAL SPECIFICATIONS
CM Engineering is providing professional engineering design services for this project, and has specified the following generator:
Generac QuietSource Series™ 22 kW Standby Power Generator (120/208V) (Premium-Grade) three phase model
GENERAL MECHANICAL AND ELECTRICAL REQUIREMENTS (following is a copy of requirements listed on architectural drawings from CM Engineering for ease in reading.) CM Engineering plan drawings follow on separate pages.
GENERAL MECHANICAL AND ELECTRICAL REQUIREMENTS
PART I - GENERAL:
3. PROVIDE ALL WORK AND MATERIALS AS REQUIRED HEREIN AND ON THE DRAWINGS IN FULL ACCORDANCE WITH NATIONAL, STATE, AND LOCAL CODES, ORDINANCES AND/OR REGULATIONS HAVING JURISDICTION OVER THIS WORK.
6. DRAWINGS ARE DIAGRAMMATIC AND INTENDED TO SHOW APPROXIMATE LOCATIONS UNLESS SPECIFICALLY DIMENSIONED. COORDINATE ALL PIPING RUNS WITH THE WORK OF OTHER CONTRACTORS.
7. ALL WORK SHALL BE COORDINATED WITH WORK OF OTHER TRADES PRIOR TO
INSTALLATION TO AVOID INTERFERENCES. SUBMISSION OF SHOP DRAWINGS WITH THE COMMENCEMENT OF THE INSTALLATION WORK IMPLIES THAT THIS SATISFACTORY COORDINATION HAS TAKEN PLACE. THEREAFTER, ANY COSTS FOR MODIFICATION DUE TO INTERFERENCES SHALL BE BORNE BY THE CONTRACTOR.
8. SUBMIT SHOP DRAWINGS FOR SUCH EQUIPMENT AND MATERIAL AS THE ENGINEER MAY REQUIRE FOR HIS REVIEW. ENGINEER'S REVIEW MUST TAKE PLACE BEFORE CONSTRUCTION BEGINS.
9. CONTRACTOR SHALL SUBMIT REQUESTS FOR SUBSTITUTIONS IN WRITING TO THE ENGINEER.
10.RECORD DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR IF INSTALLATION DEVIATES FROM THE ORIGINAL LAYOUT.
11. THE CONTRACTOR SHALL GUARANTEE ALL MATERIALS, EQUIPMENT, AND WORKMANSHIP FOR A PERIOD OF (1) YEAR AFTER THE FINAL ACCEPTANCE BY THE ARCHITECT, AND HE SHALL REPLACE AT HIS OWN COST ANY DEFECTIVE MATERIALS, EQUIPMENT OR
WORKMANSHIP WHICH SHALL PROVE TO BE DEFECTIVE WITHIN THE GUARANTEED PERIOD.
12. THE CONTRACTOR SHALL MAINTAIN A CAREFUL AND COMPLETE RECORD OF ALL ITEMS INSTALLED INCLUDING EXACT SIZES AND LOCATIONS AND UPON COMPLETION OF HIS WORK TURN OVER TO THE OWNER, A COMPLETE SET OF AS-BUILT REPRODUCIBLE DRAWINGS ON MYLAR OF HIS WORK.
13. THIS CONTRACTOR SHALL DO ALL CUTTING AND PATCHING REQUIRED TO INSTALL ANY PORTION OF THIS WORK. PATCH WITH NEW MATERIALS OF THE SAME TYPE THAT WAS REMOVED. REFINISH PATCHED SURFACE TO MATCH EXISTING ADJACENT SURFACES.
14. THE ENTIRE INSTALLATION SHALL BE PERFORMED BY LICENSED CONTRACTORS.
PART II - MATERIALS: NOT APPLICABLE
PART III - EXECUTION:
1. AT THE COMPLETION OF THE WORK, THIS CONTRACTOR SHALL REMOVE ALL RUBBISH, DIRT AND STAINS CAUSED BY HIS WORK AND SHALL THOROUGHLY CLEAN ALL EQUIPMENT, FIXTURES, PIPING, ETC.
2. TOUCH UP OR REFINISH THE FACTORY FINISH OR EQUIPMENT MARRED DURING SHIPMENT OR INSTALLATION.
DIVISION 15
SECTION 15000: GENERAL MECHANICAL REQUIREMENTS
PART I - GENERAL:
1. VERIFY FINAL LOCATIONS FOR ROUGH-INS WITH FIELD MEASUREMENTS AND WITH THE REQUIREMENTS OF THE ACTUAL EQUIPMENT TO BE CONNECTED.
2. REFER TO EQUIPMENT SPECIFICATIONS FOR ROUGH-IN REQUIREMENTS.
3. COORDINATE MECHANICAL SYSTEMS, EQUIPMENT, AND MATERIALS INSTALLATION WITH OTHER BUILDING COMPONENTS.
4. VERIFY ALL DIMENSIONS BY FIELD MEASUREMENTS.
5. ARRANGE FOR CHASES, SLOTS, AND OPENINGS IN OTHER BUILDING COMPONENTS DURING PROGRESS OF CONSTRUCTION, TO ALLOW FOR MECHANICAL INSTALLATIONS.
6. COORDINATE THE INSTALLATION OF REQUIRED SUPPORTING DEVICES AND SLEEVES TO BE SET IN POURED-IN-PLACE CONCRETE.
7. SEQUENCE, COORDINATE, AND INTEGRATE INSTALLATIONS OF MECHANICAL MATERIALS AND EQUIPMENT FOR EFFICIENT FLOW OF THE WORK.
PART II - MATERIALS: NOT APPLICABLE.
PART III - EXECUTION: NOT APPLICABLE.
SECTION 15400: PLUMBING
PART I - GENERAL:
1. UNLESS NOTED OTHERWISE, THIS CONTRACTOR SHALL FURNISH ALL LABOR, MATERIALS AND EQUIPMENT FOR THE INSTALLATION OF A COMPLETE OPERATING PLUMBING SYSTEM INCLUDING: GAS PIPING.
2. THIS CONTRACTOR SHALL DO ALL CUTTING AND PATCHING REQUIRED TO INSTALL ANY PORTION OF THIS WORK. PATCH NEW MATERIALS OF THE SAME TYPE THAT WAS REMOVED. REFINISH PATCHED SURFACE TO MATCH EXISTING ADJACENT SURFACES.
PART II - MATERIALS:
1. GAS PIPING: ASTM A53, TYPE E, ELECTRIC-RESISTANCE WELDED OR TYPE S, SEAMLESS, GRADE B, SCHEDULE 40 BLACK STEEL. ASME B16.3 CLASS 150 MALLEABLE IRON FITTINGS, STANDARD PATTERN WITH THREADS CONFORMING TO ASME B1.20.1 2. UNDERGROUND GAS PIPING: ASTM D 2683 POLYETHYLENE SOCKET-FUSION TYPE.
PART III - EXECUTION:
1. TEST ALL PLUMBING PIPES AS REQUIRED BY STATE, CITY OF LOCAL CODES AND ORDINANCES.
DIVISION 16
SECTION 16000: GENERAL ELECTRICAL REQUIREMENTS
PART I - GENERAL:
1. THE GENERAL CONDITIONS OF THE CONTRACTS, CURRENT EDITION PUBLISHED IN STANDARD FORM BY AMERICAN INSTITUTE OF ARCHITECTS, SHALL BE PART OF THIS CONTRACT.
2. THE ARTICLES CONTAINED IN THIS DIVISION AND THE ARCHITECTURAL SPECIFICATIONS MAY AMEND, MODIFY, SUPERSEDE, VOID OR SUPPLEMENT THE ARTICLES OF THE
GENERAL CONDITIONS NOTED IN PARAGRAPH (1) ABOVE, AND SHALL TAKE PRECEDENCE OVER THE PROVISIONS OF THE GENERAL CONDITIONS IN (1).
3. REFER TO THE ARCHITECTURAL, STRUCTURAL, MECHANICAL AND ELECTRICAL PLANS AND SPECIFICATIONS WHICH ARE HEREBY MADE PART OF THE CONTRACT.
4. PROVIDE ALL WORK AND MATERIALS AS REQUIRED HEREIN AND ON THE DRAWINGS IN FULL ACCORDANCE WITH NATIONAL, STATE, AND LOCAL CODES, ORDINANCES AND/OR REGULATIONS HAVING JURISDICTION OVER THIS WORK.
5. THE CONTRACTOR SHALL TAKE OUT ALL NECESSARY PERMITS, LICENSES AND CERTIFICATES AND PAY ALL FEES CONNECTED THEREWITH.
6. CONTRACTOR SHALL INCLUDE ALL TAP FEES AND OTHER UTILITY INSTALLATION COSTS REQUIRED TO BRING UTILITIES TO THE BUILDING
7. BIDDERS SHALL VISIT THE SITE AND FAMILIARIZE THEMSELVES WITH ALL CONDITIONS SURROUNDING THE WORK SO THAT ANY DISCREPANCIES BETWEEN THE PLANS AND THE SITE ARE INCLUDED IN THE BID.
8. DRAWINGS ARE DIAGRAMMATIC AND INTENDED TO SHOW APPROXIMATE LOCATIONS UNLESS SPECIFICALLY DIMENSIONED. COORDINATE ALL PIPING RUNS WITH THE WORK OF OTHER CONTRACTORS.
9. ALL WORK SHALL BE COORDINATED WITH WORK OF OTHER TRADES PRIOR TO
INSTALLATION TO AVOID INTERFERENCES. SUBMISSION OF SHOP DRAWINGS WITH THE COMMENCEMENT OF THE INSTALLATION WORK IMPLIES THAT THIS SATISFACTORY COORDINATION HAS TAKEN PLACE. THEREAFTER, ANY COSTS FOR MODIFICATION DUE TO INTERFERENCES SHALL BE BORNE BY THE CONTRACTOR.
10.SUBMIT SHOP DRAWINGS FOR SUCH EQUIPMENT AND MATERIAL AS THE ENGINEER MAY REQUIRE FOR HIS REVIEW. ENGINEER'S REVIEW MUST TAKE PLACE BEFORE
CONSTRUCTION BEGINS.
11. CONTRACTOR SHALL SUBMIT REQUESTS FOR SUBSTITUTIONS IN WRITING TO THE ENGINEER.
12. "RECORD" DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR IF INSTALLATION DEVIATES FROM THE ORIGINAL LAYOUT.
13. THE CONTRACTOR SHALL GUARANTEE ALL MATERIALS, EQUIPMENT, AND WORKMANSHIP FOR A PERIOD OF (1) YEAR AFTER THE FINAL ACCEPTANCE BY THE ARCHITECT, AND HE SHALL REPLACE AT HIS OWN COST ANY DEFECTIVE MATERIALS, EQUIPMENT OR WORKMANSHIP WHICH SHALL PROVE TO BE DEFECTIVE WITHIN THE GUARANTEED PERIOD.
14. THE CONTRACTOR SHALL MAINTAIN A CAREFUL AND COMPLETE RECORD OF ALL ITEMS INSTALLED INCLUDING EXACT SIZES AND LOCATIONS AND UPON COMPLETION OF HIS WORK TURN OVER TO THE OWNER, A COMPLETE SET OF "AS-BUILT" REPRODUCIBLE DRAWINGS ON MYLAR OF HIS WORK.
15. THIS CONTRACTOR SHALL DO ALL CUTTING AND PATCHING REQUIRED TO INSTALL ANY PORTION OF THIS WORK. PATCH WITH NEW MATERIALS OF THE SAME TYPE THAT WAS
REMOVED. REFINISH PATCHED SURFACE TO MATCH EXISTING ADJACENT SURFACES.
16. THE ENTIRE INSTALLATION SHALL BE PERFORMED BY LICENSED CONTRACTORS.
17. NO INTERRUPTION OF BUILDING FUNCTIONS OR ELECTRIC SERVICE SHALL BE PERMITTED WITHOUT APPROVAL OF THE OWNER.
18. ELECTRICAL WORK SHALL NOT INTERFERE WITH CLEARANCES REQUIRED FOR GENERAL AND MECHANICAL CONSTRUCTION. SHOULD ELECTRICAL WORK BE INSTALLED AND THAT WORK INTERFERES WITH THE WORK OF THE OTHER CONTRACTORS, SUCH WORK SHALL BE CHANGED AT NO ADDITIONAL COST TO THE OWNER.
19. VERIFY FINAL LOCATIONS FOR ROUGH-INS WITH FIELD MEASUREMENTS AND WITH THE REQUIREMENTS OF THE ACTUAL EQUIPMENT TO BE CONNECTED.
20. REFER TO EQUIPMENT SPECIFICATIONS FOR ROUGH-IN REQUIREMENTS.
21. COORDINATE ELECTRICAL SYSTEMS, EQUIPMENT, AND MATERIALS INSTALLATION WITH OTHER BUILDING COMPONENTS.
22.VERIFY ALL DIMENSIONS BY FIELD MEASUREMENTS.
23.ARRANGE FOR CHASES, SLOTS, AND OPENINGS IN OTHER BUILDING COMPONENTS DURING PROGRESS OF CONSTRUCTION, TO ALLOW FOR ELECTRICAL INSTALLATIONS.
24. COORDINATE THE INSTALLATION OF REQUIRED SUPPORTING DEVICES AND SLEEVES TO BE SET IN POURED-IN-PLACE CONCRETE AND OTHER STRUCTURAL COMPONENTS, AS THEY ARE CONSTRUCTED.
25.SEQUENCE, COORDINATE, AND INTEGRATE INSTALLATIONS OF ELECTRICAL MATERIALS AND EQUIPMENT FOR EFFICIENT FLOW OF THE WORK. GIVE PARTICULAR ATTENTION TO LARGE EQUIPMENT REQUIRING POSITIONING PRIOR TO CLOSING IN THE BUILDING.
26. WHERE MOUNTING HEIGHTS ARE NOT DETAILED OR DIMENSIONED, INSTALL SYSTEMS, MATERIALS, AND EQUIPMENT TO PROVIDE THE MAXIMUM HEADROOM POSSIBLE.
27.COORDINATE CONNECTION OF ELECTRICAL SYSTEMS WITH EXTERIOR UNDERGROUND AND OVERHEAD UTILITIES AND SERVICES. COMPLY WITH REQUIREMENTS OF GOVERNING REGULATIONS, FRANCHISED SERVICE COMPANIES, AND CONTROLLING AGENCIES.
PROVIDE REQUIRED CONNECTION FOR EACH SERVICE.
28. ALL EXISTING ELECTRICAL EQUIPMENT, DEVICES, WIRE AND/OR CONDUIT IN WALLS TO BE DEMOLISHED, AS SHOWN ON ARCHITECTURAL PLANS, SHALL BE REMOVED WHETHER OR NOT SPECIFICALLY SHOWN. CONDUIT AND WIRING SHALL BE REMOVED BACK TO THE NEAREST REMAINING JUNCTION BOX OR PANEL. KEEP EXISTING CIRCUITS IN OPERATION WHERE POSSIBLE.
PART II - MATERIALS - NOT APPLICABLE:
PART III - EXECUTION:
1. INSTALL SYSTEMS, MATERIALS, AND EQUIPMENT TO CONFORM WITH APPROVED SUBMITTAL DATA, INCLUDING COORDINATION DRAWINGS, TO GREATEST EXTENT POSSIBLE. CONFORM TO ARRANGEMENTS INDICATED BY THE CONTRACT DOCUMENTS, RECOGNIZING THAT PORTIONS OF THE WORK ARE SHOWN ONLY IN DIAGRAMMATIC FORM. WHERE COORDINATION REQUIREMENTS CONFLICT WITH INDIVIDUAL SYSTEM REQUIREMENTS, REFER CONFLICT TO THE ARCHITECT.
2. INSTALL SYSTEMS, MATERIALS AND EQUIPMENT LEVEL AND PLUMB, PARALLEL AND PERPENDICULAR TO OTHER BUILDING SYSTEMS AND COMPONENTS, WHERE INSTALLED EXPOSED IN FINISHED SPACES.
3. INSTALL ELECTRICAL EQUIPMENT TO FACILITATE SERVICING, MAINTENANCE, AND REPAIR OR REPLACEMENT OF EQUIPMENT COMPONENTS. AS MUCH AS PRACTICAL, CONNECT EQUIPMENT FOR EASE OF DISCONNECTING AND MINIMUM INTERFERENCE WITH OTHER INSTALLATIONS.
4. INSTALL ACCESS PANEL OR DOORS WHERE UNITS ARE CONCEALED BEHIND FINISHED SURFACES.
5. INSTALL SYSTEMS, MATERIALS, AND EQUIPMENT GIVING RIGHT-OF-WAY PRIORITY TO SYSTEMS REQUIRED TO BE INSTALLED AT A SPECIFIED SLOPE.
6. AT THE COMPLETION OF THE WORK, THIS CONTRACTOR SHALL REMOVE ALL RUBBISH, DIRT AND STAINS CAUSED BY HIS WORK AND SHALL THOROUGHLY CLEAN ALL EQUIPMENT, FIXTURES, PIPING, ETC.
7. TOUCH UP OR REFINISH THE FACTORY FINISH OR EQUIPMENT MARRED DURING SHIPMENT OR INSTALLATION.
SECTION 16100: ELECTRICAL EQUIPMENT AND MATERIALS PART I - GENERAL - NOT APPLICABLE:
PART II - MATERIALS:
1. ALL ELECTRICAL EQUIPMENT SHALL BE SPECIFICATION GRADE AND UL APPROVED UNLESS SPECIFIED OTHERWISE.
2. WIRING DEVICES SHALL MEET NEMA PERFORMANCE STANDARDS WD-2 AND WD-6, ANSI AND UL 498 AND COMPLY WITH FEDERAL SPECIFICATION WC-596. MINIMUM SIZE OF OUTLET BOXES SHALL BE 4" TRADE.
3. ALL CONDUCTORS SHALL BE COPPER, 600-VOLT, THHN; #12 MINIMUM SIZE. ALUMINUM WIRE SHALL NOT BE PERMITTED.
4. PANELBOARDS SHALL HAVE BUS RATING AND A.I.C. RATING GREATER THAN FAULT
CURRENT VALUE AT POINT OF APPLICATION.
5. CIRCUIT BREAKERS USED FOR LIGHT SWITCHING SHALL BE UL LISTED "SWITCHING DUTY BREAKERS".
PART III - EXECUTION:
1. GROUNDING SHALL COMPLY WITH THE CODE AND REQUIREMENTS OF THE POWER COMPANY SERVING.
2. ALL ITEMS OF ELECTRICAL EQUIPMENT ASSOCIATED WITH THE CONTROL OF ELECTRICAL APPARATUS SHALL BE IDENTIFIED WITH ENGRAVED PHENOLIC NAMEPLATES.
3. AT THE COMPLETION OF THE WORK, THIS CONTRACTOR SHALL REMOVE ALL RUBBISH, DIRT AND STAINS CAUSED BY HIS WORK AND SHALL THOROUGHLY CLEAN ALL EQUIPMENT, FIXTURES, PIPING, ETC.
4. ALL 120V 20A LIGHTING AND RECEPTACLE CIRCUITS REQUIRING MORE THAN 100' OF CONDUCTORS (ONE-WAY) SHALL BE #10 CONDUCTORS.
5. NO CONDUITS ARE TO BE RUN IN OR SUPPORTED BY DUCTWORK. A PULL WIRE SHALL BE INSTALLED IN ALL EMPTY CONDUITS.
6. ALL CONDUITS THROUGH ROOF SHALL PENETRATE ROOF USING PROPER APPROVED ROOF FLASHING.
7. FLEXIBLE CONDUIT CAN ONLY BE USED FOR SHORT FINAL CONNECTIONS TO INTERIOR LIGHTING FIXTURES AND EQUIPMENT.
8. ALL ELECTRICAL EQUIPMENT AND CONDUIT EXPOSED TO WEATHER SHALL BE WEATHERPROOF.
9. PROVIDE TYPEWRITTEN INDEX CARDS FOR ALL PANELS.
10.PROVIDE ALL ELECTRICAL PANELS, DISCONNECT SWITCHES AND TIME CLOCKS WITH 1/2" LAMINATED PLASTIC NAMEPLATE.
11. THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROPERLY BALANCING ALL BRANCH CIRCUITS AMONG THE PHASES OF THE SYSTEM.
12. BEFORE COVERING OR CONCEALMENT, THE CONTRACTOR SHALL TEST HIS WIRING SYSTEMS AS REQUIRED BY APPLICABLE CODES OR REGULATIONS OR WHERE NONE SUCH EXIST, AS REQUIRED BY THE ARCHITECT.
General safeguards during construction:
*Construction equipment and materials shall be stored and placed so as not to endanger the public, the workers or adjoining property for the duration of the construction project.
*Required exits, existing structural elements, fire protection devices, and sanitary safeguards shall be maintained at all ti mes during remodeling, alterations, repairs or additions to any building or structure.
* Exception: When such required elements or devices are being remodeled, altered or repaired, adequate substitute provisions shall be made.
* Waste materials shall be removed in a manner which prevents injury or damage to persons, adjoining properties and public right-of-way.
*Pedestrians and occupants shall be protected during construction, remodeling and demolition activities. Alternate pedestrian routes will be displayed and maintained in accordance with city, county, state and federal regulations.
*Construction railings, if needed, shall be at least 42 inches in height and shall be sufficient to direct pedestrians around construction areas.
*Pedestrian protection required by this section shall be maintained in place and kept in good order for the entire length of time pedestrians may be endangered.
*Upon completion of the construction activity, shall immediately remove walkways, debris and other obstructions and leave property in as good a condition as it was before work began.
*Required means of egress shall be maintained at all times during construction, demolition, remodeling or alterations and additions to any building.
General Construction Notes:
1.The contractor is responsible for field verifying all site conditions, dimensions, quantities, etc. related to this work.
2. Contractor shall arrange for and include in bid pricing a dumpster adequate for removal and containment of all debris.
3. The contractor shall schedule the work to allow the continued occupancy of the building.
5. Contractor shall include in bid all work guarantees.
6. Contractor shall keep property clean daily throughout the duration of the project.
J
J
F
F
J TS P1
A E EXISTING
PANELS
B
EXISTING PANEL EXISTING FRONT DESK
RECEPTACLES FED BY CIRCUIT A-35 (VERIFY)
EXISTING FRONT DESK LIGHTING FED BY CIRCUIT A-12 (VERIFY)
EXISTING COUNTERTOP RECEPTACLES FED BY CIRCUIT B-9 (VERIFY) NEW EMERGENCY PANEL
FED BY TRANSFER SWITCH NEW AUTOMATIC TRANSFER SWITCH
REWIRE EXISTING CIRCUITS TO NEW EMERGENCY PANEL REWIRE EXISTING
CIRCUITS TO NEW EMERGENCY PANEL
EXISTING COUNTERTOP RECEPTACLES FED BY CIRCUIT B-8 (VERIFY)
EXISTING SERVER INDOOR AC UNIT FED BY CIRCUIT B-29,31 NEW GENERAC Q022 22KW 120/208V 3ø 4W GENERATOR 316 MBTU/H
P1-5
P1-1,3
P1-8
P1-12 EXISTING GAS METER
NEW 1-1/4" GAS PIPING ON ROOF
EXISTING 30A SERVER RECEPTACLES FED BY CIRCUITS B-30, B-32 EXISTING SERVER OUTDOOR AC UNIT FED BY CIRCUIT B-34,36 UNDERGROUND GAS PIPING
UNDERGROUND ELECTRICAL CONDUIT
5' - 0"
MAINTAIN 5' CLEARANCE TO COMBUSTIBLE STRUCTURES PER NFPA 37
006 BOILER ROOM
018 SERVER ROOM
007 CONFERENCE
048 FILES FACP
P1-13
EXISTING FACP FED BY CIRCUIT E-11 (VERIFY)
P1-9 EXISTING CONFERENCE
RECEPTACLES FED BY CIRCUIT A-24 (VERIFY)
P1-14
P1-15
EXISTING CONFERENCE LIGHTING FED BY CIRCUIT A-19 (VERIFY)
P1-16
DISCONNECT EXISTING LIGHT FIXTURES FROM CIRCUIT B-5 AND CONNECT TO NEW EMERGENCY PANEL
P1-10
NEW JUNCTION BOX FOR EXISTING CONDENSATE PUMP ABOVE CEILING.
REMOVE EXISTING CORD &
PLUG WIRING.
P1-2,4 P1-7 P1-11 EXISTING SECURITY SYSTEM RECEPTACLE. CONNECT TO NEW EMERGENCY PANEL.
P1-6
P1
GENERAC RTS100 120/208V 3ø 3-POLE
TRANSFER SWITCH NEW 120/208V 3ø
4W 24 CKT 100A MB PANEL
EXISTING PANELS
NEW GENERAC QT022 120/208V 3ø 22KW GENERATOR
TS B
MDP A
80
200
200
EXISTING SERVICE SWITCHBOARD
4 #4, 1 #8, 1-1/2" C.
41"X74.5" CONCRETE PAD PER MANUFACTURER'S INSTRUCTIONS NOTE: TRANSFER SWITCH SHALL BE 3 POLE WITH UNBROKEN LUGS FOR NEUTRAL CONNECTION. A VARIANCE TO THE BOONE COUNTY ORDINANCE
REQUIRING DISCONNECTION OF NEUTRAL IS REQUESTED.
80
INTEGRAL BREAKER
M
NEW 1-1/4" GAS PIPE ON ROOF
4 #4, 1 #8, 1-1/2" C.
4 #4, 1 #8, 1-1/2" C.
EXISTING GAS METER
PROPOSED GENERATOR
EXISTING OFFICEBUILDING
EXISTING OFFICEBUILDING
REV DATE NO.
d e s ig n e d b y:
d r a w n b y: c h e c k e d b y:
DATE ISSUED:
PROJECT NO.
65 20 1- 48 22
Su ite C
JOB # 00078 PLTD 00/00/00
C ol um bi a, M is so ur i
70 0 C he rry S tre et Fa x - 5 73 /8 74 -9 47 4 Ph . - 5 73 /8 74 -9 45 5
60'40'20'0 1:2030'20'10'00 1:103'2'1' 1/2"06'4'5'2'3'1'12'8'10'4'6'2'0 1/4"0 1/8"24'16'20'8'12'4' 1`"R
EE IN I OUR ST
AT
ST
RUSSELL A.
VINSON NUMBER E OF MI SS
E
I G
R
AL I N S E S O ROF
P ED
R E2011015810
E G
EN
B O O N E C O U N T Y F A M IL Y R E S O U R C E S 12 09 E . W A LN U T S T. C O LU M B IA , M O 6 52 01
ME1
10-21-14
14008 14008 14008 14008
R A V R A V R A V R A V R A V R A V R A V R A V RRRR AAAA VVVV
N
SCALE: 1/8" = 1'-0"
SCALE: 1/8" = 1'-0"SCALE: 1/8" = 1'-0"
SCALE: 1/8" = 1'-0"
POWER PLAN POWER PLAN POWER PLAN POWER PLAN 01 01
01 01
Total Est. Demand:
Total Est. Demand:
Total Est. Demand:
Total Est. Demand: 44 A Total Conn.:
Total Conn.:
Total Conn.:
Total Conn.: 42 A Receptacle 10620 VA 97.08% 10310 VA Total Est. Demand:Total Est. Demand:Total Est. Demand:Total Est. Demand: 15804 VA Other 1444 VA 100.00% 1444 VA Total Conn. Load:Total Conn. Load: 15304 VATotal Conn. Load:Total Conn. Load:
Lighting 3240 VA 125.00% 4050 VA
Load Classification Load Classification Load Classification
Load Classification Connected LoadConnected LoadConnected LoadConnected Load Demand FactorDemand FactorDemand FactorDemand Factor Demand LoadDemand LoadDemand LoadDemand Load Panel TotalsPanel TotalsPanel TotalsPanel Totals Amps:
Amps:Amps:
Amps: 57 A 27 A 52 A
Total Load:
Total Load:Total Load:
Total Load: 6392 VA 3212 VA 5880 VA
23 SPARE 20 1 0 0 1 20 SPARE 24
21 SPARE 20 1 0 0 1 20 SPARE 22
19 SPARE 20 1 0 0 1 20 SPARE 20
17 SPARE 20 1 0 0 1 20 SPARE 18
15 CONFERENCE LIGHTS 20 1 1080 240 1 20 LIGHTS - SERVER ROOM 16
13 FIRE ALARM CONTROL PANEL 20 1 180 1620 1 20 CONFERENCE RECEPTACLES 14
11 SECURITY SYSTEM 20 1 180 2880 1 30 SERVER UPS 12
9 SERVER RM. RECEPTACLES 20 1 1080 180 1 20 CONDENSATE PUMP 10
7 SERVER RM. RECEPTACLES 20 1 1080 2880 1 30 SERVER UPS 8
5 LOBBY LIGHTS 20 1 1920 900 1 20 FRONT DESK RECEPTACLES 6
3 612 20 4
1 SERVER AC OUTDOOR UNIT 20 2 612 20
2 20 SERVER AC INDOOR UNIT 2 CKTCKT
CKTCKT Circuit DescriptionCircuit DescriptionCircuit DescriptionCircuit Description TripTripTripTrip PolesPolesPolesPoles AAAA BBBB CCCC PolesPolesPolesPoles TripTripTripTrip Circuit DescriptionCircuit DescriptionCircuit DescriptionCircuit Description CKTCKTCKTCKT Enclosure:
Enclosure:
Enclosure:
Enclosure: Type 1 MCB Rating:MCB Rating:MCB Rating:MCB Rating: 80 A Mounting:
Mounting:
Mounting:
Mounting: Surface Wires:Wires:Wires:Wires: 4 Mains Rating:Mains Rating:Mains Rating:Mains Rating: 100 A Supply From:
Supply From:
Supply From:
Supply From: Phases:Phases:Phases:Phases: 3 Mains Type:Mains Type: MBMains Type:Mains Type:
Location:
Location:
Location:
Location: SERVER ROOM 018 Volts:Volts:Volts:Volts: 120/208 Wye A.I.C. Rating:A.I.C. Rating: 10,000A.I.C. Rating:A.I.C. Rating:
PANEL:
PANEL:
PANEL:
PANEL: P1 P1 P1 P1
SCALE: NONE SCALE: NONESCALE: NONE SCALE: NONE
ELECTRIC RISER ELECTRIC RISER ELECTRIC RISER ELECTRIC RISER 02 02
02 02
N
SCALE: 1" = 100'-0"SCALE: 1" = 100'-0"SCALE: 1" = 100'-0"SCALE: 1" = 100'-0"SITE PLAN SITE PLAN SITE PLAN SITE PLAN 03
03 03 GENERAL NOTES 03
1. PRIMARY BID: FURNISH AND INSTALL GENERATOR AND TRANSFER SWITCH. COMPLETE ALL NECESSARY WORK PER DRAWINGS.
2. ALTERNATE #1: INSTALL OWNER PROVIDED GENERATOR AND TRANSFER SWITCH. COMPLETE ALL NECESSARY WORK PER DRAWINGS.
DIVISION 16
SECTION 16000: GENERAL ELECTRICAL REQUIREMENTS PART I - GENERAL:
1. THE GENERAL CONDITIONS OF THE CONTRACTS, CURRENT EDITION PUBLISHED IN STANDARD FORM BY AMERICAN INSTITUTE OF ARCHITECTS, SHALL BE PART OF THIS CONTRACT.
2. THE ARTICLES CONTAINED IN THIS DIVISION AND THE ARCHITECTURAL SPECIFICATIONS MAY AMEND, MODIFY, SUPERSEDE, VOID OR SUPPLEMENT THE ARTICLES OF THE
GENERAL CONDITIONS NOTED IN PARAGRAPH (1) ABOVE, AND SHALL TAKE PRECEDENCE OVER THE PROVISIONS OF THE GENERAL CONDITIONS IN (1).
3. REFER TO THE ARCHITECTURAL, STRUCTURAL, MECHANICAL AND ELECTRICAL PLANS AND SPECIFICATIONS WHICH ARE HEREBY MADE PART OF THE CONTRACT.
4. PROVIDE ALL WORK AND MATERIALS AS REQUIRED HEREIN AND ON THE DRAWINGS IN FULL ACCORDANCE WITH NATIONAL, STATE, AND LOCAL CODES, ORDINANCES AND/OR REGULATIONS HAVING JURISDICTION OVER THIS WORK.
5. THE CONTRACTOR SHALL TAKE OUT ALL NECESSARY PERMITS, LICENSES AND CERTIFICATES AND PAY ALL FEES CONNECTED THEREWITH.
6. CONTRACTOR SHALL INCLUDE ALL TAP FEES AND OTHER UTILITY INSTALLATION COSTS REQUIRED TO BRING UTILITIES TO THE BUILDING
7. BIDDERS SHALL VISIT THE SITE AND FAMILIARIZE THEMSELVES WITH ALL CONDITIONS SURROUNDING THE WORK SO THAT ANY DISCREPANCIES BETWEEN THE PLANS AND THE SITE ARE INCLUDED IN THE BID.
8. DRAWINGS ARE DIAGRAMMATIC AND INTENDED TO SHOW APPROXIMATE LOCATIONS UNLESS SPECIFICALLY DIMENSIONED. COORDINATE ALL PIPING RUNS WITH THE WORK OF OTHER CONTRACTORS.
9. ALL WORK SHALL BE COORDINATED WITH WORK OF OTHER TRADES PRIOR TO INSTALLATION TO AVOID INTERFERENCES. SUBMISSION OF SHOP DRAWINGS WITH THE COMMENCEMENT OF THE INSTALLATION WORK IMPLIES THAT THIS SATISFACTORY COORDINATION HAS TAKEN PLACE. THEREAFTER, ANY COSTS FOR MODIFICATION DUE TO INTERFERENCES SHALL BE BORNE BY THE CONTRACTOR.
10. SUBMIT SHOP DRAWINGS FOR SUCH EQUIPMENT AND MATERIAL AS THE ENGINEER MAY REQUIRE FOR HIS REVIEW. ENGINEER'S REVIEW MUST TAKE PLACE BEFORE
CONSTRUCTION BEGINS.
11. CONTRACTOR SHALL SUBMIT REQUESTS FOR SUBSTITUTIONS IN WRITING TO THE ENGINEER.
12. "RECORD" DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR IF INSTALLATION DEVIATES FROM THE ORIGINAL LAYOUT.
13. THE CONTRACTOR SHALL GUARANTEE ALL MATERIALS, EQUIPMENT, AND WORKMANSHIP FOR A PERIOD OF (1) YEAR AFTER THE FINAL ACCEPTANCE BY THE ARCHITECT, AND HE SHALL REPLACE AT HIS OWN COST ANY DEFECTIVE MATERIALS, EQUIPMENT OR
WORKMANSHIP WHICH SHALL PROVE TO BE DEFECTIVE WITHIN THE GUARANTEED PERIOD.
14. THE CONTRACTOR SHALL MAINTAIN A CAREFUL AND COMPLETE RECORD OF ALL ITEMS INSTALLED INCLUDING EXACT SIZES AND LOCATIONS AND UPON COMPLETION OF HIS WORK TURN OVER TO THE OWNER, A COMPLETE SET OF "AS-BUILT" REPRODUCIBLE DRAWINGS ON MYLAR OF HIS WORK.
15. THIS CONTRACTOR SHALL DO ALL CUTTING AND PATCHING REQUIRED TO INSTALL ANY PORTION OF THIS WORK. PATCH WITH NEW MATERIALS OF THE SAME TYPE THAT WAS REMOVED. REFINISH PATCHED SURFACE TO MATCH EXISTING ADJACENT SURFACES.
16. THE ENTIRE INSTALLATION SHALL BE PERFORMED BY LICENSED CONTRACTORS.
17. NO INTERRUPTION OF BUILDING FUNCTIONS OR ELECTRIC SERVICE SHALL BE PERMITTED WITHOUT APPROVAL OF THE OWNER.
18. ELECTRICAL WORK SHALL NOT INTERFERE WITH CLEARANCES REQUIRED FOR GENERAL AND MECHANICAL CONSTRUCTION. SHOULD ELECTRICAL WORK BE INSTALLED AND THAT WORK INTERFERES WITH THE WORK OF THE OTHER CONTRACTORS, SUCH WORK SHALL BE CHANGED AT NO ADDITIONAL COST TO THE OWNER.
19. VERIFY FINAL LOCATIONS FOR ROUGH-INS WITH FIELD MEASUREMENTS AND WITH THE REQUIREMENTS OF THE ACTUAL EQUIPMENT TO BE CONNECTED.
20. REFER TO EQUIPMENT SPECIFICATIONS FOR ROUGH-IN REQUIREMENTS.
21. COORDINATE ELECTRICAL SYSTEMS, EQUIPMENT, AND MATERIALS INSTALLATION WITH OTHER BUILDING COMPONENTS.
22.VERIFY ALL DIMENSIONS BY FIELD MEASUREMENTS.
23.ARRANGE FOR CHASES, SLOTS, AND OPENINGS IN OTHER BUILDING COMPONENTS DURING PROGRESS OF CONSTRUCTION, TO ALLOW FOR ELECTRICAL INSTALLATIONS.
24. COORDINATE THE INSTALLATION OF REQUIRED SUPPORTING DEVICES AND SLEEVES TO BE SET IN POURED-IN-PLACE CONCRETE AND OTHER STRUCTURAL COMPONENTS, AS THEY ARE CONSTRUCTED.
25.SEQUENCE, COORDINATE, AND INTEGRATE INSTALLATIONS OF ELECTRICAL MATERIALS AND EQUIPMENT FOR EFFICIENT FLOW OF THE WORK. GIVE PARTICULAR ATTENTION TO LARGE EQUIPMENT REQUIRING POSITIONING PRIOR TO CLOSING IN THE BUILDING.
26. WHERE MOUNTING HEIGHTS ARE NOT DETAILED OR DIMENSIONED, INSTALL SYSTEMS, MATERIALS, AND EQUIPMENT TO PROVIDE THE MAXIMUM HEADROOM POSSIBLE.
27. COORDINATE CONNECTION OF ELECTRICAL SYSTEMS WITH EXTERIOR UNDERGROUND AND OVERHEAD UTILITIES AND SERVICES. COMPLY WITH REQUIREMENTS OF GOVERNING REGULATIONS, FRANCHISED SERVICE COMPANIES, AND CONTROLLING AGENCIES.
PROVIDE REQUIRED CONNECTION FOR EACH SERVICE.
28. ALL EXISTING ELECTRICAL EQUIPMENT, DEVICES, WIRE AND/OR CONDUIT IN WALLS TO BE DEMOLISHED, AS SHOWN ON ARCHITECTURAL PLANS, SHALL BE REMOVED WHETHER OR NOT SPECIFICALLY SHOWN. CONDUIT AND WIRING SHALL BE REMOVED BACK TO THE NEAREST REMAINING JUNCTION BOX OR PANEL. KEEP EXISTING CIRCUITS IN OPERATION WHERE POSSIBLE.
PART II - MATERIALS - NOT APPLICABLE:
PART III - EXECUTION:
1. INSTALL SYSTEMS, MATERIALS, AND EQUIPMENT TO CONFORM WITH APPROVED SUBMITTAL DATA, INCLUDING COORDINATION DRAWINGS, TO GREATEST EXTENT
POSSIBLE. CONFORM TO ARRANGEMENTS INDICATED BY THE CONTRACT DOCUMENTS, RECOGNIZING THAT PORTIONS OF THE WORK ARE SHOWN ONLY IN DIAGRAMMATIC FORM. WHERE COORDINATION REQUIREMENTS CONFLICT WITH INDIVIDUAL SYSTEM REQUIREMENTS, REFER CONFLICT TO THE ARCHITECT.
2. INSTALL SYSTEMS, MATERIALS AND EQUIPMENT LEVEL AND PLUMB, PARALLEL AND PERPENDICULAR TO OTHER BUILDING SYSTEMS AND COMPONENTS, WHERE INSTALLED EXPOSED IN FINISHED SPACES.
3. INSTALL ELECTRICAL EQUIPMENT TO FACILITATE SERVICING, MAINTENANCE, AND REPAIR OR REPLACEMENT OF EQUIPMENT COMPONENTS. AS MUCH AS PRACTICAL, CONNECT EQUIPMENT FOR EASE OF DISCONNECTING AND MINIMUM INTERFERENCE WITH OTHER INSTALLATIONS.
4. INSTALL ACCESS PANEL OR DOORS WHERE UNITS ARE CONCEALED BEHIND FINISHED SURFACES.
5. INSTALL SYSTEMS, MATERIALS, AND EQUIPMENT GIVING RIGHT-OF-WAY PRIORITY TO SYSTEMS REQUIRED TO BE INSTALLED AT A SPECIFIED SLOPE.
6. AT THE COMPLETION OF THE WORK, THIS CONTRACTOR SHALL REMOVE ALL RUBBISH, DIRT AND STAINS CAUSED BY HIS WORK AND SHALL THOROUGHLY CLEAN ALL
EQUIPMENT, FIXTURES, PIPING, ETC.
7. TOUCH UP OR REFINISH THE FACTORY FINISH OR EQUIPMENT MARRED DURING SHIPMENT OR INSTALLATION.
SECTION 16100: ELECTRICAL EQUIPMENT AND MATERIALS PART I - GENERAL - NOT APPLICABLE:
PART II - MATERIALS:
1. ALL ELECTRICAL EQUIPMENT SHALL BE SPECIFICATION GRADE AND UL APPROVED UNLESS SPECIFIED OTHERWISE.
2. WIRING DEVICES SHALL MEET NEMA PERFORMANCE STANDARDS WD-2 AND WD-6, ANSI AND UL 498 AND COMPLY WITH FEDERAL SPECIFICATION WC-596. MINIMUM SIZE OF OUTLET BOXES SHALL BE 4" TRADE.
3. ALL CONDUCTORS SHALL BE COPPER, 600-VOLT, THHN; #12 MINIMUM SIZE. ALUMINUM WIRE SHALL NOT BE PERMITTED.
4. PANELBOARDS SHALL HAVE BUS RATING AND A.I.C. RATING GREATER THAN FAULT CURRENT VALUE AT POINT OF APPLICATION.
5. CIRCUIT BREAKERS USED FOR LIGHT SWITCHING SHALL BE UL LISTED "SWITCHING DUTY BREAKERS".
PART III - EXECUTION:
1. GROUNDING SHALL COMPLY WITH THE CODE AND REQUIREMENTS OF THE POWER COMPANY SERVING.
2. ALL ITEMS OF ELECTRICAL EQUIPMENT ASSOCIATED WITH THE CONTROL OF ELECTRICAL APPARATUS SHALL BE IDENTIFIED WITH ENGRAVED PHENOLIC NAMEPLATES.
3. AT THE COMPLETION OF THE WORK, THIS CONTRACTOR SHALL REMOVE ALL RUBBISH, DIRT AND STAINS CAUSED BY HIS WORK AND SHALL THOROUGHLY CLEAN ALL
EQUIPMENT, FIXTURES, PIPING, ETC.
4. ALL 120V 20A LIGHTING AND RECEPTACLE CIRCUITS REQUIRING MORE THAN 100' OF CONDUCTORS (ONE-WAY) SHALL BE #10 CONDUCTORS.
5. NO CONDUITS ARE TO BE RUN IN OR SUPPORTED BY DUCTWORK. A PULL WIRE SHALL BE INSTALLED IN ALL EMPTY CONDUITS.
6. ALL CONDUITS THROUGH ROOF SHALL PENETRATE ROOF USING PROPER APPROVED ROOF FLASHING.
7. FLEXIBLE CONDUIT CAN ONLY BE USED FOR SHORT FINAL CONNECTIONS TO INTERIOR LIGHTING FIXTURES AND EQUIPMENT.
8. ALL ELECTRICAL EQUIPMENT AND CONDUIT EXPOSED TO WEATHER SHALL BE WEATHERPROOF.
9. PROVIDE TYPEWRITTEN INDEX CARDS FOR ALL PANELS.
10. PROVIDE ALL ELECTRICAL PANELS, DISCONNECT SWITCHES AND TIME CLOCKS WITH 1/2" LAMINATED PLASTIC NAMEPLATE.
11. THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROPERLY BALANCING ALL BRANCH CIRCUITS AMONG THE PHASES OF THE SYSTEM.
12. BEFORE COVERING OR CONCEALMENT, THE CONTRACTOR SHALL TEST HIS WIRING SYSTEMS AS REQUIRED BY APPLICABLE CODES OR REGULATIONS OR WHERE NONE SUCH EXIST, AS REQUIRED BY THE ARCHITECT.
GENERAL MECHANICAL AND ELECTRICAL REQUIREMENTS PART I - GENERAL:
1. THE GENERAL CONDITIONS OF THE CONTRACTS, CURRENT EDITION PUBLISHED IN STANDARD FORM BY AMERICAN INSTITUTE OF ARCHITECTS, SHALL BE PART OF THIS CONTRACT.
2. THE ARTICLES CONTAINED IN THIS DIVISION AND THE ARCHITECTURAL SPECIFICATIONS MAY AMEND, MODIFY, SUPERSEDE, VOID OR SUPPLEMENT THE ARTICLES OF THE GENERAL CONDITIONS NOTED IN PARAGRAPH (1) ABOVE, AND SHALL TAKE PRECEDENCE OVER THE PROVISIONS OF THE GENERAL CONDITIONS IN (1).
3. PROVIDE ALL WORK AND MATERIALS AS REQUIRED HEREIN AND ON THE DRAWINGS IN FULL ACCORDANCE WITH NATIONAL, STATE, AND LOCAL CODES, ORDINANCES AND/OR REGULATIONS HAVING JURISDICTION OVER THIS WORK.
4. THE CONTRACTOR SHALL TAKE OUT ALL NECESSARY PERMITS, LICENSES AND CERTIFICATES AND PAY ALL FEES CONNECTED THEREWITH.
5. BIDDERS SHALL VISIT THE SITE AND FAMILIARIZE THEMSELVES WITH ALL CONDITIONS SURROUNDING THE WORK SO THAT ANY DISCREPANCIES BETWEEN THE PLANS AND THE SITE ARE INCLUDED IN THE BID.
6. DRAWINGS ARE DIAGRAMMATIC AND INTENDED TO SHOW APPROXIMATE LOCATIONS UNLESS SPECIFICALLY DIMENSIONED. COORDINATE ALL PIPING RUNS WITH THE WORK OF OTHER CONTRACTORS.
7. ALL WORK SHALL BE COORDINATED WITH WORK OF OTHER TRADES PRIOR TO INSTALLATION TO AVOID INTERFERENCES. SUBMISSION OF SHOP DRAWINGS WITH THE COMMENCEMENT OF THE INSTALLATION WORK IMPLIES THAT THIS SATISFACTORY
COORDINATION HAS TAKEN PLACE. THEREAFTER, ANY COSTS FOR MODIFICATION DUE TO INTERFERENCES SHALL BE BORNE BY THE CONTRACTOR.
8. SUBMIT SHOP DRAWINGS FOR SUCH EQUIPMENT AND MATERIAL AS THE ENGINEER MAY REQUIRE FOR HIS REVIEW. ENGINEER'S REVIEW MUST TAKE PLACE BEFORE CONSTRUCTION BEGINS.
9. CONTRACTOR SHALL SUBMIT REQUESTS FOR SUBSTITUTIONS IN WRITING TO THE ENGINEER.
10. RECORD DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR IF INSTALLATION DEVIATES FROM THE ORIGINAL LAYOUT.
11. THE CONTRACTOR SHALL GUARANTEE ALL MATERIALS, EQUIPMENT, AND WORKMANSHIP FOR A PERIOD OF (1) YEAR AFTER THE FINAL ACCEPTANCE BY THE ARCHITECT, AND HE SHALL REPLACE AT HIS OWN COST ANY DEFECTIVE MATERIALS, EQUIPMENT OR
WORKMANSHIP WHICH SHALL PROVE TO BE DEFECTIVE WITHIN THE GUARANTEED PERIOD.
12. THE CONTRACTOR SHALL MAINTAIN A CAREFUL AND COMPLETE RECORD OF ALL ITEMS INSTALLED INCLUDING EXACT SIZES AND LOCATIONS AND UPON COMPLETION OF HIS WORK TURN OVER TO THE OWNER, A COMPLETE SET OF AS-BUILT REPRODUCIBLE DRAWINGS ON MYLAR OF HIS WORK.
13. THIS CONTRACTOR SHALL DO ALL CUTTING AND PATCHING REQUIRED TO INSTALL ANY PORTION OF THIS WORK. PATCH WITH NEW MATERIALS OF THE SAME TYPE THAT WAS REMOVED. REFINISH PATCHED SURFACE TO MATCH EXISTING ADJACENT SURFACES.
14. THE ENTIRE INSTALLATION SHALL BE PERFORMED BY LICENSED CONTRACTORS.
PART II - MATERIALS: NOT APPLICABLE PART III - EXECUTION:
1. AT THE COMPLETION OF THE WORK, THIS CONTRACTOR SHALL REMOVE ALL RUBBISH, DIRT AND STAINS CAUSED BY HIS WORK AND SHALL THOROUGHLY CLEAN ALL
EQUIPMENT, FIXTURES, PIPING, ETC.
2. TOUCH UP OR REFINISH THE FACTORY FINISH OR EQUIPMENT MARRED DURING SHIPMENT OR INSTALLATION.
DIVISION 15
SECTION 15000: GENERAL MECHANICAL REQUIREMENTS PART I - GENERAL:
1. VERIFY FINAL LOCATIONS FOR ROUGH-INS WITH FIELD MEASUREMENTS AND WITH THE REQUIREMENTS OF THE ACTUAL EQUIPMENT TO BE CONNECTED.
2. REFER TO EQUIPMENT SPECIFICATIONS FOR ROUGH-IN REQUIREMENTS.
3. COORDINATE MECHANICAL SYSTEMS, EQUIPMENT, AND MATERIALS INSTALLATION WITH OTHER BUILDING COMPONENTS.
4. VERIFY ALL DIMENSIONS BY FIELD MEASUREMENTS.
5. ARRANGE FOR CHASES, SLOTS, AND OPENINGS IN OTHER BUILDING COMPONENTS DURING PROGRESS OF CONSTRUCTION, TO ALLOW FOR MECHANICAL INSTALLATIONS.
6. COORDINATE THE INSTALLATION OF REQUIRED SUPPORTING DEVICES AND SLEEVES TO BE SET IN POURED-IN-PLACE CONCRETE.
7. SEQUENCE, COORDINATE, AND INTEGRATE INSTALLATIONS OF MECHANICAL MATERIALS AND EQUIPMENT FOR EFFICIENT FLOW OF THE WORK.
PART II - MATERIALS: NOT APPLICABLE.
PART III - EXECUTION: NOT APPLICABLE.
SECTION 15400: PLUMBING PART I - GENERAL:
1. UNLESS NOTED OTHERWISE, THIS CONTRACTOR SHALL FURNISH ALL LABOR, MATERIALS AND EQUIPMENT FOR THE INSTALLATION OF A COMPLETE OPERATING PLUMBING SYSTEM INCLUDING: GAS PIPING.
2. THIS CONTRACTOR SHALL DO ALL CUTTING AND PATCHING REQUIRED TO INSTALL ANY PORTION OF THIS WORK. PATCH NEW MATERIALS OF THE SAME TYPE THAT WAS REMOVED. REFINISH PATCHED SURFACE TO MATCH EXISTING ADJACENT SURFACES.
PART II - MATERIALS:
1. GAS PIPING: ASTM A53, TYPE E, ELECTRIC-RESISTANCE WELDED OR TYPE S, SEAMLESS, GRADE B, SCHEDULE 40 BLACK STEEL. ASME B16.3 CLASS 150 MALLEABLE IRON FITTINGS, STANDARD PATTERN WITH THREADS CONFORMING TO ASME B1.20.1 2. UNDERGROUND GAS PIPING: ASTM D 2683 POLYETHYLENE SOCKET-FUSION TYPE.
PART III - EXECUTION:
1. TEST ALL PLUMBING PIPES AS REQUIRED BY STATE, CITY OF LOCAL CODES AND ORDINANCES.