• No results found

UAE Nuclear Power Programme : Status and Update

N/A
N/A
Protected

Academic year: 2021

Share "UAE Nuclear Power Programme : Status and Update"

Copied!
20
0
0

Loading.... (view fulltext now)

Full text

(1)

Hamad Alkaabi

Permanent Representative of the UAE to the IAEA

UAE Nuclear Power Programme :

Status and Update

Technical Meeting on Topical Issues in the Development of Nuclear Power Infrastructure

(2)

Background on Developing National Position:

UAE Electricity Demand

18593 21548 24126 27323 29444 3121 1 32814 34238 35881 37394 39104 40858 15546 13224 11742 0 5000 10000 15000 20000 25000 30000 35000 40000 45000 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 MW

Total UAE Committed Capacity Total UAE Projected Demand

Evaluation of future energy sources options :

After energy studies were conducted, nuclear power emerged as a proven, environmentally attractive and cost-competitive electricity-generation option.

(3)

UAE Programme Development

Nuclear Policy 2008 Creation of Nuclear Regulator, Nuclear Operator, adoption of

Federal Nuclear Law, Prime Contractor Selected 2009 Construction of Unit 1 begins 2012 Construction of Unit 2 begins 2013 Construction of Unit 3 begins 2014 Commissioning of Unit 1, followed by other Units 2017

(4)

FANR Achievements

The Federal Authority for Nuclear Regulation (FANR) monitors the UAE nuclear sector in the areas of safety, security, radiation protection and

safeguards, taking into account IAEA standards.

Achievements:

•Received, Assessed and Approved Construction License for Barakah

Units 1 and 2 in July 2012

•Received, Assessed and Approved Construction License for Barakah

Units 3 and 4 in September 2014

•Issued 14 regulations and ten regulatory guides to date

•Up to 2013, FANR has issued 2,889 permits for the import or export of regulated material

•In 2013, FANR issued 130 new licences and made 140 amendments to

existing licences to conduct regulated activities using regulated material

in different fields.

• Established the country’s State System of Accounting for and Control

(5)

Implementing International Instruments

The UAE has concluded all relevant international agreements and

conventions.

In 2014, the UAE joined the Convention on Supplementary Compensation for

Nuclear Damage,

 nuclear liability conventions

 Nuclear safety convention

 Safeguards and non-proliferation including the additional protocol ,  Physical protection

 UAE Government submitted its 2nd

National Report to the 6th Review

Meeting of the Convention on

Nuclear Safety (CNS) in March

2014, highlighting its implementation of obligations under the CNS to

strengthen national nuclear safety measures.

(6)

Cooperation with the IAEA

 Through the Technical Cooperation projects delivered by the IAEA, the UAE has been

receiving useful training and technologies to establish robust national capabilities

• A significant increase in number of UAE participants in IAEA activities up to 2014  The Integrated Work Plan for the UAE, enables all IAEA departments to address the

schedule and needs for implementation of the UAE nuclear power programme.

 UAE also participates

• in IAEA-hosted meetings to strengthen its national infrastructure (eg. Senior Regulator’s Meeting, Commission on Safety Standards, among others) • In hosting IAEA activities

(7)

IAEA Peer Review Services

UAE experts support IAEA International Peer Review Services, both through sending local experts to review missions in other countries and receiving missions to assess UAE programme.

To date, the UAE has received

IAEA Integrated Nuclear Infrastructure Review (INIR) mission in January 2011

IAEA Integrated Regulatory Review Service (IRRS) mission in December 2011

IAEA Safeguards Advisory Service (ISSAS) mission in May 2014 Three preparatory missions hosted in 2014 (pre-IRRS follow-up, pre-EPREV and pre-OSART)

(8)

Overall Peer Review Mission schedule

Acronym Full name UAE status

INIR Integrated Nuclear Infrastructure Review Mission Hosted in January 2011

INIR Phase 3 INIR during phase 3 of the ‘milestone approach’ To be hosted in 2015

IRRS Integrated Regulatory Review Service Hosted in December 2011

Pre-IRRS follow-up

Preparatory mission for the follow-up IRRS Hosted in September 2014

IRRS follow-up Follow-up mission to the IRRS To be held in February 2015

Pre-ISSAS Preparatory mission to the ISSAS Hosted in December 2013

ISSAS International SSAC Advisory Service Hosted in May 2014

Pre-EPREV Emergency Preparedness Review preparatory mission Hosted in October 2014

EPREV Emergency Preparedness Review Mission To be held in March 2015

Pre-ORPAS Preparatory mission to the Occupational Radiation Protection Appraisal Service

Hosted in September 2014

ORPAS Occupational Radiation Protection Appraisal Service To be held in October 2015

IPPAS International Physical Protection Advisory Service To be held in 2016

Pre-OSART Preparatory mission for the Operational Safety Review Team programme

To be held in 2016

OSART Operational Safety Review Team programme To be held after operation starts

Follow-up OSART

Follow-up mission to the OSART 12-18 months after regular

(9)

Construction work update

Unit 1 overall progress:

61.7%

(10)

Construction work update

Unit 1 & 2 overall progress:

55.7%

Unit 3 & 4 overall progress:

19.4%

Overall progress in all

units 1, 2, 3 & 4:

(11)

Additional on-site progress

In April 2014, ENEC inaugurated the Simulator Training Centre at Barakah

•The first of its kind in the Middle East

•The simulator replicates the actual conditions and environment that reactor operators would experience in a real time situation

•Each student requires more than 800 hours of advanced simulator training to receive the SRO certification, which FANR controls and issues

(12)

Construction work update

In May 2014, the Reactor Vessel for Unit 1 in place in line with the

project’s timeline.

(13)

Construction work update

In September 2014, ENEC celebrated the pouring of the first

safety concrete for Unit 3 at Barakah, following the receipt of the

(14)

Construction work update

In December 2014, the concrete dome for the Unit 1 Reactor

Containment Building was completed.

(15)

Milestones 2015

March

Submit Units 1 and 2 Operating License Application (OLA) to FANR

July

Start Reactor Vessel Installation for Unit 2

October

Energize Transmission Substation for Unit 1

November

Pour First Safety Concrete for Unit 4

(16)

Milestones 2016-2020

OCTOBER Fuel Loading MAY Complete Unit 2 MAY Complete Unit 1 MAY Complete Unit 3 MAY Complete Unit 4

(17)

Human Capacity Building

UAE is building its nuclear cadre through nuclear

education and training :

Scholarship programmes (ENEC and FANR)

Nuclear-related workshops, courses, programmes (eg. GNEII) Hosting IAEA Nuclear Energy Management School and training Cyber Learning Platform (CLP4NET) installed at Khalifa

University

• In May 2014, the first batch of 13 local operators returned from South Korea after completing specialized training programmes.

• In September 2014, ENEC celebrated the graduation of 46

students from ENEC’s scholarships programme, including

Bachelors, Masters and HDNT

Total number of scholars: 375 Higher Diploma in Nuclear Technology: 196 Master of Nuclear Engineering: 171 PhD in Nuclear Engineering: 1

(18)

Capacity building

ENEC Recruitment Statistics:

Total number of employees: 1400 from 25 different nationalities

Number of Emirati employees: 876 (Emiratis account for more than 60% of the total number of ENEC employees)

Percentage of female employees at ENEC is more than 21%.

By 2020, ENEC expects to require approximately 2,500 employees to operate the UAE’s four nuclear power plants

ENEC Workforce Statistics:

 Currently, the total number of workers at the Barakah site is

approximately 15,000

 Total Man-Hours since the beginning of the project is 87,865,137 Hours

FANR Staffing:

 As of December 2013, FANR had 151 staff members of which 49% were Emirati.

(19)

Outreach and Public acceptance

UAE communicates transparently on a constant basis with its

residents, employees, government agencies and the international community through:

ENEC and FANR Public Forums

Social Media: Twitter, YouTube, Instagram and Flickr Monthly electronic Newsletters

UAE Permanent Mission official website

UAE nuclear energy programme exhibitions worldwide

82% of UAE residents are positive and in favour of nuclear energy in their country

(20)

References

Related documents

While walking around vehicle in a counterclockwise direction, open left rear door (if applicable) and check operation of window regulator and door lock, set child safety door locks

The sensitivity of the data point for samples can be determined from the slope of the plotting, TL response as a function of dose the response dose of the sample irradiated

Ans) The description given above regarding the pressure belt and the prevailing planetary winds is mostly valid on March 21 and September 23 because the sun is directly overhead at

Personal credit Bank financing in the firm owner’s name Business credit Bank financing in the firm’s name Personal credit card balance Balance on personal credit cards

Contents at a Glance Getting Startedxi Exploring the Interface and Working with Real Instruments Lesson 1 Make Music with Logic Now Lesson 2 Recording Audio Lesson 3 Editing

Each fiscal year, FSA targets a portion of its direct and guaranteed farm ownership and operating loan funds to beginning farmers and ranchers.. FSA makes and guarantees loans

There is no significant difference in education lecturers’ assessment of quality of teaching practice in Nigerian universities based on job status (junior and senior).. There is

LO1: Use basic and advanced Excel functions. LO2: Use a modern software tool to perform statistical calculations. 23) The easiest way to locate a particular function is to select