Page 0 of 31          ROYAL MONETARY AUTHORITY OF BHUTAN                                                            Request for Proposal  RFP     For    CONSTRUCTION OF INTEGRATED DATA CENTER      Date 18th Sept. 2012          RMA: Thimphu  Post Box: 154  Tel   975‐2‐323111 Ext. 126  Fax: 02‐322847  Email: [email protected]  ;  Website: www.rma.org.bt         

(2)

Page 1 of 31 Table of Contents  List of Abbreviations ... 5  1.  Introduction ... 4  1.1.  Overview ... 4  1.2.  Intent and Purpose of RFP ... 4  1.3.  Organization of this RFP Document ... 4  2.  Background ... 6  2.1.  The Client ... 6  2.2.  Scope of Work ... 7  2.1.3  Architectural & Interior Work ... 8  3  Terms and Condition ... 9  3.1  Award ... 9  3.2  Contacts and Clarifications ... 9  3.3  Cost of Bidding ... 9  3.4  Reservation of Rights ... 9  3.5  Period of Validity of Proposal ... 10  3.6  Addenda to RFP ... 10  3.7  Price Quotations and Currency Instructions ... 10  3.8  Use and Disclosure of Information ... 10  3.9  Contractual Requirement ... 10  3.10  Hand Holding Period ... 11  3.11  Contract Negotiations ... 11  3.12  Quotation Form/Financial Proposal ... 11  3.13  Proposal Evaluation ... 11  3.14  Scoring procedure ... 12  3.15  Patent Rights ... 13  3.16  Standards ... 13  3.17  Liquidated Damages ... 13  3.18  Delays in the Vendor’s Performance ... 14  3.19  Inspection, Tests and Installation ... 14  3.20  Warranty ... 14  3.21  Third Parties ... 15  3.22  Vendor Designated Contact ... 15  3.23  Submission of Responses to the RFP ... 15 

(3)

Page 2 of 31 3.24  Timeline/ Schedule of Events ... 16  3.25  Bid Security ... 16  3.26  Performance Security ... 17  3.27  Tax Deducted at Source  TDS ... 17  3.28  Eligible Bidders ... 17  3.29  Client’s Right to Vary Quantities at Time of Award ... 18  4  Technical Specification ... 19  4.1  Electrical with panel, earthing & light Fittings ... 19  4.2  High Availability of Cooling Solution with PAC & AC ... 20  4.3  Raised Flooring, False ceiling and Partitioning ... 21  4.4  Access Control Systems ... 22  4.5  Fire Alarm Systems ... 23  4.6  Monitoring System ... 23  4.7  Rodent Repellent ... 24  4.8  Bill of Materials ... 24  5  Vendor Profile ... 26  5.1  Company Size, Organization and Location ... 26  5.2  Number of Customers/Related Sites ... 26  5.3  Client References ... 26  5.4  Implementation Timeline ... 26  5.5  Support Information ... 27  5.6  Strategic Alliances and Partnerships ... 27  5.7  Industry Awards and Certifications ... 27  5.8  Training and documentation ... 28  5.9  Project Team ... 28  5.10  Procurement Tracking Process ... 28  5.11  Financial Statement ... 28  6  Response Format ... 29  7  Appendix ... 30                 

(4)

Page 3 of 31 List of Abbreviations                                    AMC  Annual Maintenance Contract BICMA  Bhutan Infocomm and Media Authority BST  Bhutan Standard Time CCTV  Closed Circuit Television DB  Distribution Box  EIA  Electronics Industry Agency EMD  Earnest Money Deposit ICT  Information and Communications ISO  International  Organization for Standardization LAN  Local Area Network  LT  Lighting  MCB  Miniature Circuit Breaker MOU  Memorandum of Understanding NOC  Network Operations Center OEM  Original Equipment Manufacturer PVC  Polyvinyl chloride  RFP  Request for Proposal  RMA  Royal Insurance Corporation of Bhutan Limited RRCO  Regional Revenue and Customs Office SLA  Service Level Agreement TIA  Telecommunications Industry Association TPN  Triple Pole   Neutral  UAT  User Acceptance Test  UPS  Uninterrupted Power Supply VoIP  Voice Over Internet Protocol WAN  Wide Area Network  NEC  National Electrical Code PAC  Precision Air Condition NSP  Network Service Provider CFM  Cubic Feet per Minute

(5)

Page 4 of 31 1. Introduction 

1.1. Overview 

The  Royal  Monetary  Authority  RMA   of  Bhutan  purposes  to  build  and  construct  an  integrated  data  center  to  harmonize  and  house  in  various  heterogeneous  ICT  applications  which are currently residing across different physical locations. 

   

Interested  Vendors,  therefore,  are  required  to  develop  a  proposal  for  the  service s   to  be  deployed  covering  all  bid  areas  and  the  implementation  plan  for  meeting  the  specified  requirements. The proposal must be submitted by 3:00 PM on October 19, 2012. 

1.2. Intent and Purpose of RFP 

This  specification  is  primarily  intended  to  develop  the  ICT  infrastructure  required  for  converting existing Clearing Hall residing in the RMA building into an integrated Data Center  for  the  purpose  of  running  various  applications  for  streamlining  the  access  to  and  automating  internal  processes,  and  monitoring  system  on  24  x  7  basis.  The  activities  will  essentially consist of various civil, electrical, mechanical and all other related works required  for building state of the art Data Center.  

 

This specification also means supply, installation, testing & commissioning of the necessary  physical  infrastructure  like  air  conditioning  system  comfort  &  precision ,  fire  detection,  electrical  system  including  lighting  system,  power  &  network  cabling,  multilayer  physical  security  infrastructure  like  proximity/smart  card  based  on  access  control  system,  CCTV  /surveillance  systems,  earthling  and  other  incidental  and  necessary  items  as  required  to  complete the job in question in all respect.    This specification further intends to establish effective & efficient infrastructure monitoring  and management practices to ensure reliability, availability, quality of services and security  of the information system.  1.3. Organization of this RFP Document  This RFP is structured as follows:  Section 1 ‐ Introduction  This section introduces the RFP, and explains its structure. It provides the background of the  project  Section 2 – Section 2 – Background   Section 3 ‐ Terms and Conditions  This section sets out the:    Conditions under which proposals would be accepted    Required validity of information    Required format of proposals    Contact policy during the evaluation period    Submission deadline 

(6)

Page 5 of 31 Sections 4 & 5 highlight enquiries that should be responded to, in the format described in Section 6.  The list of the sections is as follows:  Section 4 ‐ Technical Specification  Section 5 ‐ Vendor Profile   Section 6 – Response Format and Content Outline 

This  section  introduces  an  outline  for  the  structure  of  each  vendor’s  response  to  ensure  consistency, and thus an easy evaluation of each of the responses. It also highlights the required  structure/outline of vendor’s proposal 

 

Section 7 – Appendix   

(7)

Page 6 of 31 2. Background  2.1. The Client  The Client is the Royal Monetary Authority of Bhutan, RMA, based in Thimphu.     The Data Center is located in the RMA Building, Thimphu. The total area is specified as per  below  drawing.  The  data  center  should  house  all  servers,  communication  equipment,  and  other  enterprise  infrastructure  deployed  for  the  Client’s  business  operations.  It  has  an  approximate area of 22 X 20 sq feet and is located in the ground floor of the RMA building.  The total area should be divided into two areas viz. server room & NOC room.               

(8)

Page 7 of 31 2.2. Scope of Work  This infrastructure shall be able to host all the required hardware to run the application and  also to provide a fault proof environment to run the same.    The Data Center should be capable to provide an up time of 99%. It should be designed in a  way that it offers scalability over a period of minimum five years. The design should be done  with the key consideration for redundancy, scalability and maintainability.    Necessary measure should be taken for making the critical server room air tight, fire proof  and free from condensation  thermal insulation .     The structured cabling requirement for the server frame area and facilities area should meet  with Cat 6 based design system with flexible deployment option in the form of enclosures.   

The  security  of  the  critical  Data  Center  area  has  to  be  taken  care  in  multiple  levels.  The  physical  access  restrictions  have  to  be  taken  care  of  through  Access  Control  System.  The  critical  areas  have  to  be  monitored  through  a  CCTV  surveillance  system  with  the  records  available in a stipulated time frame. 

 

The  equipment  and  human  safety  from  the  incidents  should  meet  with  the  help  of  addressable  fire  alarm  system  complimented  by  addressable  smoke  detector.  The  rodent  repellant system should be provided in the server room. 

 

2.1.1 Shifting and Rearrangement of Servers, Racks and equipment to the Integrated Data Center   

Currently,  the  client  has  servers,  central  UPS  and  other  equipment  located  in  different  physical location of RMA building.  

 

Vendor is required to shift all these equipment into the integrated DC without impacting the  day to day operation of the client. Vendor should plan and ensure to shift the critical servers  and  equipment  on  weekends  or  public  holiday  so  that  there  is  very  minimal  downtime  to  avoid affecting the business operation of the client.    2.1.2 Integration of current Network System    With the shifting of this core switch into the Integrated DC, there is a need  for laying out a  backbone link to various Distribution Switch located in the different floors of RMA building.  Vendor  is  required  to  plan  and  layout  the  backbone  Cat  6/fiber  cabling  to  the  entire  Distribution switches from the Integrated DC. 

 

The Client has independent Network for different system  CTS, EFTCS, BFS, etc  leased from  different  service  providers.  The  client  has  the  internal  network  distributed  from  the  Core  Switch located in the Data Center I  First floor of RMA building .  

 

To  manage  these  network  efficiently,  the  vendor  is  required  to  integrate  these  network  without compromising the current setup  All IP addresses should be retained  and possibly  design a  redundancy  network  with these  existing  network  service obtained from  different  ISP.  

 

Refer Section 7 for the detail of Servers and equipment available at RMA.   

The scope of work also covers any item of works which may not have been mentioned here  but  is  usual  or  necessary  to  complete  the  work  shall  be  deemed  to  be  included  with  this  specification. 

(9)

Page 8 of 31   The major components within the scope of these specifications are:‐    • Civil Works  • Electro‐mechanical Works  • Precision AC  • Comfort AC  • Fire Alarm System  • Access Control  • Surveillance system  • Rodent Repellant system  2.1.3  Architectural & Interior Work  The work under this sub head shall cover design and implementation of architectural and  interior  work  for  the  proposed  Data  Center  as detailed  in  the  specification, complete  with  supply  of  all  accessories/tools  required  for  aesthetic,  lasting  and  technically  superior  solution for the following but not limited to the following.     • Cutting & Chipping of existing floors  • Covering existing windows  • Paint work  Fire rated   • False flooring  Fire rated   • False ceiling  Fire rated   • Partitioning with concrete   • Aluminum Doors  • Insulation  floor   • Other miscellaneous civil work as per site requirement   

(10)

Page 9 of 31 3 Terms and Condition 

3.1 Award 

The Client reserves the right to award the contract to the best vendor without necessarily  holding discussion with other vendors that submitted a response to the RFP. Therefore, your  proposal  must  be  submitted  initially  on  the  most  favorable  terms  possible  from  a  pricing,  solution coverage, delivery, support and technical standpoint. 

3.2 Contacts and Clarifications 

Should  there  be  any  clarifications  concerning  RFP,  the  prospective  bidder  shall  notify  the  same  to  RMA  in  writing.  The  time  for  clarifications  shall  be  extended  till  the  deadline  for  submission of bids.    In an effort to maintain consistency and uniformity in responding to questions concerning  the RFP, Bidders are encouraged to direct all the questions to:        Hem Lal Chhetri    IT Department,  Royal Monetary Authority   Chhophel Lam, Kawajangsa    Thimphu    Bhutan.    Phone: 321698 or 323111 ext 126   Email: [email protected]      Copies of the response, where appropriate, shall be forwarded to all the bidders. No other  source of information shall be considered an authorized expression of the Client.  3.3 Cost of Bidding  All costs incurred by the Bidder in responding to this Request for Proposal, including cost for  embarking on client reference will be entirely borne by the Bidder.  3.4 Reservation of Rights  The Client reserves the right to: 

• Accept  or  reject  any  Bid,  in  part  or  in  full,  and  to  annul  the  bidding  process  and  reject all Bids at any time prior to Contract award.   • Accept the bid s  that is/are in the best interest of the Client  • Accept other than the lowest quoted price  • Cancel the project at any time prior to the signing of the contract without assigning  any reasons thereof. The Client has no obligation to explain to unsuccessful Bidders  the reasons for not proceeding with the contract. 

(11)

Page 10 of 31 The Client bears no responsibilities to issue a contract. All responses remain the property of  the Client. In the event a contract is agreed upon, responses to RFP may be referenced, in  whole  or  in  part,  and  considered  binding.    Proposals,  which,  in  the  sole  judgment  of  the  Client, are incomplete or considered non‐responsive may be rejected.   3.5 Period of Validity of Proposal   Proposals are valid for one  1  year from the closing date of submission of proposals and the  Client reserves the right to extend for an additional period of thirty  30  days with the same  terms and conditions. A proposal valid for a shorter period shall be rejected by the Client as  non‐responsive.  3.6 Addenda to RFP  • The client may amend or modify the RFP Documents by issuing addenda, for any reason,  and  at  any  time  prior  to  the  deadline  for  submission  of  proposal.  Any  addenda  to  the  RFP Documents shall be part of the RFP Document.  • All Bidders will be notified of the addenda to the RFP through e‐mail and in writing and  it shall be binding on the prospective Bidders.  • To allow Bidders reasonable time to take any addenda into account in preparing their  proposal, the client will extend, if necessary, the deadline for the submission of proposal.  3.7 Price Quotations and Currency Instructions  Price quotations will include but not limited to the following  items; details of all proposed  products  hardware,  software,  network,  etc ,  training,  documentation  and  services  necessary  for  the  successful  implementation  of  the  contract  except  as  may  be  otherwise  expressly provided herein and awarded.  

 

The  Bidder  should  quote  the  rates,  inclusive  of  all  taxes,  in  Ngultrum  CIF  RMA  Office,  Thimphu.   All quotations should be final, not estimates. Bidders should state clearly that the quotations  include all costs.  Bidders may be invited for further negotiations on their quoted bids. However, invitation for  further negotiations does not in any way imply a successful bid or intention by the Client to  award the bid to the Vendor.  3.8 Use and Disclosure of Information 

The  Bidder  shall  not  disclose  information  within  this  RFP  to  any  third  party  without  a  written approval from Client.  Likewise, information within this RFP shall not be used for any  other purpose not directly related to the response to this RFP or to the job in the case of an  award. 

3.9 Contractual Requirement 

Vendors  are  requested  to  indicate  their  acceptance  of  each  of  the  following  terms  and  conditions and provide the additional information requested below: 

This  RFP,  Bidders’  proposals,  any  associated  documentation,  and  any  interchange  of  correspondence or information by way of elucidation or amplification, will form the basis of  the  Bidder’s  contractual  obligations.  However,  such  contractual  obligation  will  be  solely  under the discretion of the Client. 

(12)

Page 11 of 31 Vendors should note that final contracts will be based on provided Terms and Conditions,  and would be expected to include the following provisions:  • Confidentiality of details of the proposed services/products  • Suitability for the stated technical specifications requirements  • Timeliness, covered by, for example, liquidated damages  • Guaranteed availability of key vendor staff 

• Overall  component  guarantees,  including  compensation  for  missing  agreed  reliability levels 

• Service  level  agreements  for  maintenance  and  support  including  compensation  if  not met 

• Fixed  prices  on  initial  supply  with  limitations  on  price  increases  for  subsequent  products and support charges   • Control of publicity  • Successful completion of implementation  3.10 Hand Holding Period  The vendor shall be part of the Infrastructure Stabilization Period for any reconfiguration or  optimization of the infrastructure components. The Client expects a minimum of 5 months  for  handholding/stabilization  of  the  deployed  solution s .  The  vendor  should  specify  the  duration  of  infrastructure  stabilization  period,  with  the  minimum  of  5  months  for  handling/stabilization of the deployed solution s , they are willing to support with details of  support engagement during this period. The infrastructure stabilization period commences  from the day the proposed solution s  are accepted by the Client. 

3.11 Contract Negotiations 

After selection of the highest ranking bidder, the Client may enter into negotiations with the  bidder  for  purpose  of  signing  a  contract  with  respect  to  the  proposed  solution s .  If  the  highest  ranking  bidder  fails  to  negotiate,  the  Client  shall  enter  into  negotiation  with  the  second most bidder and so on. 

3.12 Quotation Form/Financial Proposal 

Quotes  should  include  the  cost  of  purchase,  installation  and  configuration  of  all  Infrastructure  components  and  support/maintenance  over  one  1   year  period.  Indicate  your best unit price for each of the configurations listed in this RFP. Please note:        Each Bid Price should be for one  1  unit of the item indicated    Base Price should only include specified equipment and the subcomponents such as Cables,  pluggable components which are part of standard configuration and warranty  3.13 Proposal Evaluation 

The  Client’s  evaluation  of  your  response  to  this  Request  for  Proposal  will  be  based  on  its  subjective assessment of each element of your response, including intangible factors, such as  the Client’s perception of your ability to meet your commitments.  

(13)

Page 12 of 31 The Client reserves the right to accept or reject any or all responses at its sole discretion and  to  negotiate  the  terms  of  any  subsequent  agreements.  The  Client  is  looking  for  reliable,  competent Solution Providers who have the ability to meet or exceed the stringent selection  criteria.  These selection criteria include, but are not limited to the following:    Company Evaluation See section 5 for details     Solution Capabilities    Service Coverage    Cost Competitiveness    Project Experience    Project Delivery Timeline  Accordingly, each is discussed below:    Company Evaluation – Detailed assessment of the history of the Solution Providers  in terms  of  financial  stability,  profile  of  the  key  technical  staff  proposed  for  the  solution,  project  management standards and procedure, training etc  

  Solution  Capabilities  –  Assessment  of  the  functional  fit  of  the  proposed  solution s   to  the  business requirements of the Client  

  Solution  Coverage  –  Vendors  should  bid  on  all  requirements  covered  by  this  Request  for  Proposal.  In this context, solution provider who are able to reliably provide a broader range  and depth of solution s  to the Client will receive preference in the selection process    Cost Competitiveness – Vendors must provide highly competitive pricing – pricing reserved  for their largest and most important accounts – both at the outset of the relationship and on  an ongoing basis.  The Client expects its providers to assist in identifying opportunities to  reduce the total cost of ownership of the proposed solution    Project Experience – The Client wishes to work closely with proven and tested end‐to‐end  solution providers.  This will be judged, in part, through similar project implementation and  customer references.  It is also expected that vendors live up to the commitments they make  with the Client    Project Delivery Timeline – Vendors with strong capacity to deliver the required solution s   in good time, based on past experience will receive higher consideration  3.14  Scoring procedure  The scoring parameter for the evaluation of vendor response is segregated into different bid  areas, which will include every bid areas defined in the RFP. The evaluation will be carried  out in discreet manner covering two major attribute, the Technical and Financial.    Technical Bid‐ the evaluation criteria set for construction of Data Center is subjected to with  wide  range  of  scoring  parameters  such  as  company  expertise,  company  profile,  human  resource, financial capability, maintenance, warranty, etc.    The following are the major components for the overall technical evaluation procedure:  • Meeting the specified technical specifications of the products proposed by the Client  – compliance statement.  • Company profile of the bidding firm. 

• Technical  manpower  of  the  firm  trained  experienced  and  qualified  personnel  for  the  performance  and  completion  of  all  the  Contractual  Obligations,  arising  out  of  this document  

(14)

Page 13 of 31       

 

Financial  bid‐ The  financial  bid  score  will  consist  40%  of  the  total  evaluation  score.  The  lowest bidder will be awarded 40% directly.    Overall score‐ The consolidation will be based on the following formula:    E    Fl / F  * 40     T / Th  * 60     Where   

E   total score for the vendor response  combining technical and financial bids   F   financial bid quoted by a particular vendor  Fl   lowest of all evaluated bid prices among the responsive bidders  T   technical score awarded to a particular vendor  Th   technical score of a vendor who scored highest among the responsive bidders     The Client retains the right to alter the evaluation criteria at any point in the process     The highest scoring firm shall be invited for negotiation. Should the negotiation fail, the next  highest scoring firm shall be invited for negotiation.   

The  representative,  other  than  the  proprietors  themselves,  conducting  negotiations  on  behalf  of  the  selected  bidder  must  have  written  authority  to  negotiate  and  to  conclude  a  binding agreement.     The successful Bidder will be required to sign an agreement incorporating entire terms and  conditions covered in this RFP and any additional terms and conditions agreed during the  negotiation.  3.15 Patent Rights 

The  Vendor  shall  indemnify  the  Client  against  all  third  party  claims  of  infringement  of  patent,  trademark  or  industrial  design  rights  arising  from  use  of  the  provided  services/solutions or any part thereof in Bhutan 

3.16 Standards 

These  General  conditions  shall  apply  to  the  extent  that  they  are  not  superseded  by  provisions  in  other  parts  of  the  contract.    The  components  hardware,  software,  network  etc     of  the  solution  provided  by  the  vendor  under  this  Contract  shall  conform  to  the  standards  mentioned  in  the  Technical  Specifications  /  Requirement  List  and,  when  no  applicable standard is mentioned, to the authoritative standard appropriate to the solution  required, and such standards shall be the latest issued by the concerned institution. 

  

3.17 Liquidated Damages 

The Vendor shall be liable  to pay liquidated damages at the rate of zero point one  0.1%   percent  of  the  Contract  Price  for  every  day  of  delay.  The  aggregate  liquidated  damages,  payable by the Vendor shall not exceed 10% of the Contract Price.   

(15)

Page 14 of 31 3.18 Delays in the Vendor’s Performance 

Delivery  of  the  solution s   and  performance  of  Services  shall  be  made  by  the  Vendor  as  specified in the Implementation Timeline and/or the Contract.    An unexcused delay by the Vendor in the performance of its delivery obligations shall render  the Vendor liable to any or all of the following sanctions: imposition of liquidated damages,  and or termination of the Contract for default.    If at any time during performance of the contract, the Vendor or its subcontractor s  should  encounter conditions impeding timely delivery of the agreed solution s  and performance of  services, the Vendor shall promptly notify the Client in writing of the fact of the delay, it’s  likely duration and its causes s . As soon as practicable after receipt of the Vendor's notice,  the Client shall evaluate the situation and may at its discretion extend the Vendor's time for  performance, in which case the extension shall be ratified by the parties by amendment of  the contract.  3.19 Inspection, Tests and Installation  The Client or its representative shall have the right to inspect and/or to test the deployed  solution s ,  to  verify  conformity  to  the  specifications  stated  in  the  design/Contract.  The  inspection  procedures  and  tests  to  be  conducted  by  the  Client  in  respect  of  the  service s /solution s   being  provided  will  be  agreed  with  the  Vendor  during  execution  of  the  Project,  and  the  relevant  details  will  be  specified  in  the  Contract.  This  test  must  be  carried  out  before  the  Job  Completion  Form/  Delivery  sign‐off  can  be  obtained  on  any  provided solution. 

 

Installation will be treated as incomplete in one/all of the following situations:    

• Non‐delivery  of  any  hardware  or  software  modules  mentioned  in  this  RFP  document.   • Non‐delivery of the supporting documents.   • Delivery, but no installation of the components and/or software.   • System operational, but unsatisfactory to RMA  3.20 Warranty  • The Supplier must provide a warranty for at least 1 year from date of project completion  • The Supplier must provide a warranty that the solution  software, hardware, etc  provided 

under  the  Contract  will  comply  strictly  with  the  Contract,  shall  be  top  rated  in  every  particular case and shall be free from defects.  

• The  Supplier  further  warrants  to  the  Client  that  all  materials,  equipment  and  supplies  furnished  by  the  vendor  will  be  new,  merchantable  of  the  most  suitable  grade,  and  fit  for  their  intended  purposes.  The  warranty  period,  shall  be  as  given  by  the  OEMs  and/or  otherwise agreed in Conditions of Contract between the Client and the Supplier.  

• The  Client  shall  promptly  notify  the  Supplier  in  writing  of  any  claim  arising  under  this  Warranty.  Upon  receipt  of  such  notice,  the  Supplier  shall  promptly  repair  or  replace  the  defective  Goods  or  parts  thereof,  inclusive  of,  where  applicable,  the  cost  of  delivery  of  repaired or replaced Goods or parts from the port of entry to the final destination and their  installation. 

•  If the Supplier, having been notified, fails to remedy the defect  s  in accordance with the  Contract, the vendor may proceed to take such remedial action as may be necessary, at the  Supplier’s expense. 

(16)

Page 15 of 31 3.21 Third Parties  

The Client will have the right, at any time at its sole discretion, to contract with third parties  to perform all or any part of the services provided for in this RFP. In case the Vendor is not  directly  present  within  the  territories  of  Bhutan,  the  vendor  should  detail  out  the  engagement  model  for  the  delivery  of  Products  and  Services  to  the  Client  as  part  of  the  response. The Vendor will cooperate with such third parties and the Client. Additionally, the  Vendor will adhere to the following requirements: 

  Delegation  –  The  Vendor  will  neither  delegate  nor  subcontract  any  of  its  responsibilities,  without prior written approval of the Client 

  Sub‐contractors – If the Vendor intends to use subcontractors, the Vendor’s proposal must  include a list of proposed material subcontractors containing the firm name, a description of  the work to be subcontracted, an explanation of why that work is to be subcontracted, and  descriptive information about each subcontractor’s ability to perform the work 

  Standards  –  Sub‐contractors  will  adhere  to  the  standards,  policies,  and  procedures  of  the  Client and the primary Vendor’s which are in effect from time to time 

  Vendor  Capability  –  the  Vendor  must  confirm  that  it  will  remain  responsible  for  all  obligations  performed  by  subcontractors  to  the  same  extent  as  if  such  obligations  were  performed by the Vendor 

3.22 Vendor Designated Contact 

The respondent should identify the name, title, address, telephone, fax and e‐mail of a single  point of contact  and one alternate  for the duration of this RFP process.  The availability of  this person should be specified. 

3.23 Submission of Responses to the RFP 

Vendor  shall  give  the  postal  address,  telephone,  fax  numbers  and  email  addresses  of  the  contact person authorized to receive all communications on the  vendor’s behalf. The client  would only send communication to this address. Initials/seals of the bidders must be placed  on all the pages of the proposal 

 

These  copies  should  be  sealed  in  separate  envelopes,  subscripted  as  “Proposal  for  Construction of Integrated Data Center‐Technical” and “Proposal for Proposal for Construction  of Integrated Data Center‐Commercial” respectively. Thus, the vendor shall submit one sealed  envelope containing two separate sealed envelopes viz. Technical and Commercial. 

(17)

Page 16 of 31 The Technical and Commercial offers would need to be delivered in person, by the vendor’s  representative to:          The Director  Administration and Finance Department  Royal Monetary Authority of Bhutan  Thimphu: Bhutan    Tel:  975‐2‐323112/323111/ 975‐2‐323113  Fax:  975‐2‐322487  Post Box No. 154   

The  electronic  version  of  the  response  must  also  be  submitted  in  a  CD‐ROM  and  must  be  placed in the sealed cover only. This copy of the response must be in any of the Microsoft  Office Suite formats  Word, Excel, PowerPoint, and Visio .  

All packages must be delivered to RMA by 3:00 PM on Thursday October 19, 2012.   

RMA reserves the right to disqualify Bidders whose responses are not submitted by this date  and  time.  No  responses  will  be  accepted  after  the  deadline  for  submission  of  bids  unless  RMA determines in its sole judgment, to do so. The Client may, at its discretion, extend the  deadline for the submission of Bids by amending the Bidding Documents, in which case all  rights  and  obligations  of  the  Client  and  Bidders  previously  subject  to  the  deadline  shall  thereafter  be  subject  to  the  deadline  as  extended.  The  proposal,  along  with  all  supporting  documents shall become the property of the Client  

3.24 Timeline/ Schedule of Events  

This  Request  for  Proposal  RFP   represents  one  of  several  steps  taken  to  assist  the  Client  efficient  solution  that  will  meet  its  business  requirement.  The  Client  reserves  the  right  to  adjust the RFP schedule listed below: 

 

Activity Date / Timeline

RFP announcement in the media September 19, 2012 

Questions & clarifications  October 20, 2012 

Receive responses to RFP  deadline October 20, 2012 

Evaluate Technical Bids vendor response  October 20‐26, 2012  Cost negotiation, selection and award of contract October 30‐31, 2012    The Client will do all that is feasible within foreseeable limits to ensure strict adherence to  this timeline.    3.25 Bid Security   • The bidder shall furnish a fixed amount of Nu. 100,000/‐  Ngultrum One Hundred Thousand  only  as an earnest money  bid security , which is refundable. 

 

• The  earnest  money  deposit  should  be  enclosed  in  the  same  sealed  envelope  as  the  “commercial  Proposal”.  The  bid  not  accompanied  by  a  responsive  Bid  Security  shall  be  rejected by the Client as non‐responsive.   

(18)

Page 17 of 31 • The bid security shall be in the form of a demand draft drawn in favor of the Royal Monetary  Authority of Bhutan, Thimphu and payable at banks located in Thimphu.    • While the bid security of the unsuccessful Bidder shall be returned as promptly as possible  upon award of Contract, the bid security of the successful bidder shall be returned upon the  bidder’s executing the contract and furnishing the performance security.    

• The  bid  security  shall  be  forfeited  if  a  bidder  withdraws  its  bid  during  the  period  of  bid  validity; or if a bidder does not accept the arithmetical corrections of its bid price. In the case  of a successful bidder, the bid security may be forfeited, if the bidder fails to sign the contract  or to furnish the performance security within the given time.  

 

3.26 Performance Security 

• Prior  to  signing  of  the  Contract  the  successful  bidder  shall  be  required  to  furnish  Performance Security at the rate of ten percent  10%  of the contract value within fifteen  15  working days after the notice of the award.    •  The performance security shall be in the form of a demand draft/Bank Guarantee issued by  a reputed Financial Institution in favor of RMA and payable at banks located in Thimphu.     • The performance security shall be discharged and returned to the vendor upon expiration of  the warranty period.       3.27 Tax Deducted at Source  TDS   All payments are subject to deduction of Tax Deducted at Source  TDS  and other taxes and  duties  in  accordance  with  the  taxation  rules  and  regulations  of  the  Royal  Government  of  Bhutan at a rate prevailing during the time of payment. The client shall be responsible for  furnishing the TDS certificate within two weeks of payment.    3.28   Eligible Bidders  Invitation of bid is open to all registered IT firms in Bhutan who hold a valid license from the  Royal Government of Bhutan, with competency in Network and Data Center technology. Bids  unaccompanied by such license will be rejected. For availability of better & prompt services  & support the Bidder’s Head Office must be in Thimphu.    The bidder shall furnish the following documentary evidence:    I. Latest BICMA Certificate signed by authorized official.   

II. Valid  trade  License  or  other  documents  to  prove  the  legal  status  and  place  of  registration of the business.    III. The average annual turnover of the prime bidder for strictly IT Products and service  for last 5 years should be minimum 5 million Ngultrum  audited financial statement  should be submitted .   

IV. A  record  of  similar  assignments  carried  out  in  Bhutan  by  the  firm  or  strategic  partner in the last 3 years. 

(19)

Page 18 of 31  

V. Manufacture's authorization letter for major equipments.   

VI. Bidding  firm  or  alliance  partner  must  have  at  least  one  certified  Technical  consultant for Datacenter.  Certificate copy should be submitted . 

 

VII. The  bidding  firm/company  or  alliance  partner  must  be  having  valid  ISO  9001  or  better certification in this regard at the time of biding.    3.29 Client’s Right to Vary Quantities at Time of Award   At the time the Contract is awarded, the Client reserves the right to increase or decrease the  quantity of Goods and Related Services and vary the Bill of Material listing without any  change in the unit prices or other terms and conditions of the Bid and the Bidding  Documents.                        

(20)

Page 19 of 31 4 Technical Specification 

This  section  provides  information  on  the  technical  requirements/specifications  for  the  required solution s  /service s . 

4.1      Electrical with panel, earthing & light Fittings 

    Your  total  electrical  solution  should  be  based  on  Industry  standard  considering  4  nos.  of  Racks  and  two  nos.  of  Precision  Air  Condition  PAC   System.  Accordingly  total  electrical  solution has to be made in one time. The Electrical System shall be designed in such a fashion  so that in the future redundant UPS can be added.   

 

The building power supply source should be terminated into a dedicated LT panel for data  center. The LT panel should mainly be consisting of required amps MCCB  of popular make   incomers along with required feeders  of popular make  and a TPN bus bar. There should be  different DB for different loads like UPS, AC, lighting & raw power and there has to be a spare  MCB per DB. On the basis of above structure, cables & wire size should be used as per the  requirement. 

  

There  should  be  dedicated  earth  pit  with  copper  plate  and  copper  strip  as  per  standard  proper  grounding  of  Data  Center  equipment,  often  called  network  grounding  or  the  Data  Center  grounding  infrastructure,  defined  by  TIA‐942  Telecommunications  Infrastructure  Standard for Data Centers, and goes beyond the requirements of the National Electrical Code  NEC  to protect equipment and improve system reliability. The bidder shall follow both TIA  and  NEC;  however  whenever  any  aspect  is  not  covered  by  NEC  or  there  is  difference  between the two, TIA/EIA‐942 would prevail.      The design should ensure that the ground resistance will be within the limit. The composite  of all ground electrodes connected together at a single point must have an impedance of less  than 1 ohm to ground. If this impedance exceeds 1 ohm, then additional, driven ground rods  or a chemically assisted grounding electrode must be added to reduce this value to below 1  ohm.        

The  NOC  room  should  be  glared  with  popular/standard  make  FPL  mirror  optics  light  and  down  lighter.  All  light  fittings  should  be  placed  on  the  false  ceiling  of  server  room  &  NOC  room. 

 

4.1.1.     Electrical Work Guidelines   

The  electrical  work  includes  furnishing the  Data Center  area  in  all aspects.  The  furnishing  includes but not limited to the following:    • Cabling  • Wiring  • Conducting  • Earthing    Electrical Cabling‐ Fire retardant cables of rated capacity exceeding the power requirement  of  fully  blown  configuration  of  the  existing  and  proposed  component  should  be  used.  For  expansion  needs  suitable  redundant  power  points  to  be  provided  at  suitable  locations.  All  materials used shall conform to IS standards as per industry practice. 

(21)

Page 20 of 31 Bunching  of  Wires  –  Wires  carrying  current  should  be  so  bunched  in  the  conduit  that  the  outgoing  and  return  wires  are  drawn  into  the  same  conduit.  Wires  originating  from  two  different phases should not run in the same conduit. 

 

Drawing  of  Conductors  –  The  drawing  Aluminum  /  Copper  conductor  wires  should  be  executed with due regards to the following precautions while drawing insulated wires into  conduits. Care should be taken to avoid scratches and kinks, which cause breakages. 

   

Joints  –  All  joints  should  be  made  at  main  switches,  distribution  boards,  socket  outlets,  lighting  outlets  and  switch  boxes  only.  No  joints  should  be  made  inside  conduits  and  junctions boxes. Conductors should be continuous from outlet to outlet. 

 

Mains  &  Sub‐Mains  –  Mains  &  sub‐mains  wires  where  called  for  should  be  of  the  rated  capacity  and  approved  make.  Every  main  and  sub‐main  should  be  drawn  into  an  independent  adequate  size  conduit.  Adequate  size  draw  boxes  should  be  provided  at  convenient locations to facilitate easy drawing of the mains and sub mains. An independent  earth wire of proper rating should be provided. The earth wires should run along the entire  length of the mains and sub‐mains. 

 

Color  Code  of  the  Conductors  –  Color  code  should  be  maintained  for  the  entire  wiring  installation, Red, Yellow, Blue for three phases and “OFF” circuit black for neutral and green  for earth  or bare earth . 

 

Fixing  of  the  Conduits  –  Conduits  junction  boxes  should  be  kept  in  position  and  proper  holdfast has to be provided. Conduits should be so arranged as to facilitate easy drawing of  the  wires  through  them.  Adequate  junction  boxes  of  approved  shape  &  size  should  be  provided. All conduits should be installed so as to avoid stream and hot water pipes. After  conduits, junction boxes, outlet boxes & switch boxes are installed in position their outlets  should be properly plugged so that water, mortar, insects or any other foreign matter does  not  enter  into  conduit  system.  Conduits  shall  be  laid  in  a  neat  and  organize  manner  as  directed and approved by the ITL Personnel or person on their behalf. Conductors shall be  planned so as not to conflict with any other service pipe lines/ducts. 

 

Protection –  To  minimize  condensation  or  sweating  inside  the  conductors  all  outlets  of  conduit  system  shall  be  adequately  ventilated  and  approved  by  the  proper  competent  authority. All screwed and socket connections shall be adequately made fully water tight by  use of proper jointing materials. 

 

Switch‐Outlet  Boxes  and  Junction  Boxes  –  All  boxes  shall  conform  to  all  prevailing  Indian  Standards.  The  cover  plates  shall  be  of  best  quality  sheets  or  ISI  grade,  which  should  be  mechanically strong and fire retardant. Proper support shall be provided to the outer boxes  to  fix  the  cover  plates  of  switches  as  required.  Separate  screwed  earth  terminals  shall  be  provided inside the box for earthing purpose.    Inspection Boxes – Rust proof inspection boxes of required size having smooth external and  internal finish shall be provided to permit periodical inspection and to facilitate removal and  replacement of wires when required.  4.2 High Availability of Cooling Solution with PAC & AC  Server room requires precise temperature and humidity control. To address this challenge  the  vendor  must  suggest  two  numbers  of  a  popular  make  6.5TR  precision  controlled  air  condition system.  Basically,  both  PAC  should  be  running  in  sequential  mode.  If  any  of one  fails the other should be activated. Both outdoor unit of PAC should be placed at the ground  level of outer side of the building provided if there is no technical problem. Otherwise, it has 

(22)

Page 21 of 31 to be located somewhere in a suitable area. NOC room needs to be cooled by 2nos of 2TR  split AC. Existing floor should be insulated with PVC foil insulator to protect air leakage.    

Details of Specification of PAC‐ 

The  server  room  shall  be  air‐conditioned  with  2  nos.  1  Working 1  Standby   under  floor  discharge type Precision Air‐conditioning Unit each of Actual 6.5 TR capacity  at 20 deg C  Inside  temperature,  50%  Inside  RH  &  Summer  25oC  outside  ambient  temperature   &  De‐ humidified air quantity of Min 4700 CFM.  

 

The room temperature shall be maintained at 200 C  /‐ 1 Deg C and 50%  /‐ 5% RH and  outside temperature at 250C. The grille outlet temperature should be less than 18 deg C. The  air‐conditioning unit shall be designed specifically for high sensible heat ratio applications,  having Sensible Heat Cooling capability of  95%. 

 

The  system  shall  contain  scroll  compressor,  evaporator  blower  &  coil,  heater,  humidifier,  split  coil  solenoid  shut‐off  type  de‐humidification  cycle,  PID  based  microprocessor  and  thermostatic expansion valve  TXV , all of which shall be contained within the cabinet of the  unit.  The  outdoor  unit  shall  be  comprised  of  condenser  fan  &  motor  and  multi  condenser  coil, suitably sized to match low ambient in winter. 

 

*  *PAC  system  under  this  project  shall  be  supplied  by  certified  NSP.  Proof  of  document  should be submitted at the time of delivery. 

 

As  a  redundant  cooling  system,  the  client  want  to  make  use  of  the  existing  Comfort  AC  installed in the server room. Vendor is required to installed these two comfort ACs  Vendor  will be guided by the client  in the Integrated Data Center.  

 

Vendor  is  required  to  quote  only  for  the  installation  and  maintenance  if  required   of  the 

existing comfort ACs         

4.3 Raised Flooring, False ceiling and Partitioning   

4.3.1 Raised  Flooring‐  The  raised  floor  system  to  be  installed  shall  provide  a  minimum  finished floor height of maximum 600mm from the existing floor level.  The system  shall  provide  for  suitable  pedestal  and  understructure  designed  to  withstand  various  static  loads  and  rolling  loads  subjected  to  it  in  server  racks.  The  entire  raised floor system should be able to accept approved laminated floor covering anti‐ static  PVC  /  Anti  Static  Laminate  and  PVC  beading  on  all  sides  of  the  panel.    The  overall system shall be able to withstand a UDL of 1350 kgs per sq mt. and a Point  Load of 450 kgs. The understructure should withstand an Axial load of 2200 kgs.   

4.3.2 Panels‐  Panel  floor  should  be  made  of  steel.    The  bottom  of  the  panel  shall  be  embossed in 64 hemispherical shape of 60 mm dia. The top sheet shall be plain and  resistant  welded  at  various  locations  after  the  top  and  bottom  sheets  have  been  degreased  and  phosphated.    The  above  hollow  panel  shall  have  an  in  fill  of  lightweight  cementious  material.    The  entire  panel  shall  be  coated  with  epoxy  coating  on  the  exposed  surface.    Panels  shall  remain  flat  through  and  stable  unaffected  by  humidity  or  fluctuation  in  temperature  throughout  its  normal  working  lift.    Panels  shall  provide  for  impact  resistance  top  surfaces  minimal  deflection,  corrosion,  resistance  properties  and  shall  not  be  combustible  or  aid  surface spread of flame.  Panels shall be insulated against heat and noise transfer.   Panels shall be 600 x 600 mm and shall have a maximum flange of 12mm on all four  sides  for  resting  on  stringer ,  fully  interchangeable  with  each  other  within  the  range  of  a  specified  layout.    Panels  shall  rest  on  the  grid  formed  by  the  stringers,  which the range of a specified layout.  Panels shall rest on the grid formed by the 

(23)

Page 22 of 31 stringers,  which  are  bolted  onto  the  pedestals.    Panels  shall  be  factory  laminated  Anti‐Static  PVC/Laminate  on  the  top  and  PVC  beading/trimming  along  the  edges.  Ventilated tiles should be placed in front of each rack.  

 

4.3.3 Understructure‐  Understructure  installed  to  support  the  panel  shall  be  suitable  to  achieve a finished floor height of 300mm. Understructure shall be placed at 600mm  distance  c/c  in  both  direction  to  form  a  grid  of  600mm  x  600mm.  The  understructure designed shall confirm speedy assembly and removal and re‐fixing,  maintenance.  Understructure base should be permanently secured to be placed on  the sub floor by effective mechanical fastening / glue, the understructure assembly  shall provide for easy leveling and accurately aligning the panels to ensure lateral  restrain.  Understructure shall support an axial load of 2000 kgs without permanent  deflection and an ultimate load of 3500 kgs.  Understructure head shall be designed  to avoid any rattle or squeaks. It should consist of 100 x 100 x 2mm galvanized base  plate electro‐mechanically welding to a 25mm O.D. 2.0mm thick.  GI/ epoxy coated  pipe to engage the pedestal head assembly.  The pedestal head assembly shall be of  4mm  G.I.  plated  having  4  holes,  welded  to  steel  stud  16mm  O.D.  x  100mm  long  threaded  stud.    The  assembly  shall  provide  a  range  of  height  adjustment  up  to  50mm, with the help of check nut. 

 

4.3.4 Stringers‐ Stringer system should be all steel construction, rectangular channels 575  x  30 x 20 x 1.2 mm thick.  Understructure system shall provide adequate solid, rigid  and  quiet  support  for  access  floor  panels.  The  understructure  shall  provide  a  minimum  clear,  uninterrupted  height  of  90  to  765mm  between  the  bottom  of  the  floor and the bottom of the raised floor for electrical conduit and wiring.    4.3.5 Floor Grill‐ Floor grills of 600x600 mm with air damper should be placed under each  rack.    4.3.6 False Ceiling‐ This ceiling must be made with mineral fiber which should be hanged  from concrete ceiling in LAY‐In system. The surface of tiles is to be coated with 50  micron epoxy polyester powder paint. These tiles, which should be fire rated, grid  system  with  acoustic,  light  reflection,  humidity  resistance  properties.  Acoustic  sound proofing non‐woven fiber fabric should be used.    4.3.7 Partitioning ‐ Partition has to be made with concrete.    4.3.8 Aluminum Doors‐ Doors should be with single leaf along with floor spring covered  with fire rated Teflon glass along with all accessories. Door frame shall be made of  aluminum composite panel.    4.3.9 Windows – Windows should be concealed with gypsum.   

4.3.10 Ramp‐  If  required  a  suitable  ramp  shall  be  placed  at  Data  Center  entrance  which  should be elevated from main entrance to Data Center’s raised floor. This ramp must  be capable of carrying more than 300kg load.              4.4 Access Control Systems  IP based Biometric with i‐class card reader along with inbuilt controller shall be installed as  security access to the Data Center. It should be installed on the main doors of Data Center. It  has  to  be  sealed  in  rugged,  weatherized,  polycarbonate  enclosure  designed  to  withstand  harsh  environment  and  provide  vandal  resistance.  The  access  control  system  must  be  complemented  with  time  attendance  software.  An  access  control  system  consisting  of 

(24)

Page 23 of 31 intelligent  controllers,  biometric  with  i‐class  readers,  power  supplies,  cards,  and  all  associated accessories is required to make a fully operational online access control system.          4.5 Fire Alarm Systems      We already have complete set of fire detection system in the 2  separate server room.  The  Client wishes the Vendor to make use of these existing systems to be deployed in data center  and NOC room depending on your methodology of partition    4.6  Monitoring System  For security purpose IP based surveillance camera shall be placed to monitor server room &  NOC room and, the whole system must be connected through LAN.       Detailed specification of Surveillance system:   

Sl.No  Product Description  Compliance

   IP based Camera     1  1/3" CCD Image sensor 540 tvl    2  Signal System PAL.     3  Auto IRIS DC Drive along with 2.8 ‐ 11 mm Lens. Angle viewing of 97 Deg.     4  Day /Night IR cut filter with auto switch.    5  Bit rate of 32 Kbps to 8 Mbps.    6  IR range of 10 to 20 Meters     7  Temperature 10 degree to 60 Degree    8  Protocols :‐TCP/IP     9  Electronic shutter rate 1/25 1/30  S  1/100000 S    10  Maximum image resolution PAL‐ 704 x 576   

11  Intelligent  Alarm  Motion  Detection,  Video  Loss,  Network  Disconnect,  IP 

address conflict, Storage exception   

12  Power Supply DC12V 10%/PoE  AC24V optional   

13  Power Consumption 5.5W MAX ‐I: 7W MAX 7.5W MAX with ICR working     

14  Digital Noise Reduction Yes    

15  Video Compression H.264/MJPEG   

16  Communication Interface 1 RJ45 10M / 100M self‐adaptive Ethernet interface, 

1 RS‐485 interface    

17  Image  Settings  Saturation,  Brightness,  Contrast  adjustable  through  client 

software or web browser     18  Auto Iris DC Drive     19  Adjustment Range Pan0~360°, Tilt0~75°, Rotation0~360°    20  Certification‐ UL Listed        

(25)

Page 24 of 31 4.7 Rodent Repellent  The entry of rodents and other unwanted pests shall be controlled using non‐chemical, non‐ toxic   devices. Ultrasonic pest repellents shall be provided in the false flooring and ceiling to  repel the pests without killing them.     4.8 Bill of Materials 

No.  Item Description  Specification/ Description QTY*

1.  PAC  1 6.5 TR Precision Environment Control System for  Server Room ‐ with complete accessories, installation  and setup. 2 nos    2 10 TR Precision Environment Control System for  Server Room ‐ with complete accessories, installation  and setup.

2.  Fiber Patch Cord  LC‐LC patch code  1m 10 nos

3.  Power Module  Power Module for APC Symmetra UPS  4kVA 1 no

4.  Rack  9 U Rack 2 nos

5.  Serge Protection Device   Make ‐TVSS 1 no

6.  IP based 

surveillance  Refer section 4.6 1 no

7.  Power Cables  Make – Royal Cables

8.  MCB  Make‐ Havels

9.  Automatic Transfer 

Switch ATS   NA 1 no

10.  Raised floor panel lifter  1 Single cup raised floor panel lifters 1 no 2 Double cup raised floor panel lifters 11.  Rodent Repellent  System  Refer Section 4.7  12.  Electrical Works  Light fitting  along with dedicated LT panel for server  room 13.  Civil work   painting & Interior 14.  Access control  systems  Refer Section 4.4 15.   Raised flooring   Refer section 4.3.1

(26)

Page 25 of 31 16.  False Ceiling   Refer section 4.3.6

17.   Aluminum Doors  Refer section 4.3.8 18.  Concrete partition  Refer section 4.3.7

19.  Safe box  Fire proof safe box medium 1 no

 

(27)

Page 26 of 31 5 Vendor Profile  

 

This  section  is  intended  to  provide  the  Client  with  sufficient  information  to  enable  an  evaluation of your company’s stability and ability to provide the service s  described in the  response. Please include the following information: 

5.1 Company Size, Organization and Location 

Provide  brief  profile  of  your  company  detailing  the  description  of  corporate  ownership,  number of employees, number of divisions and/or product lines, number and description of  location s  etc. 

5.2 Number of Customers/Related Sites 

List organization where similar service s  have been provided,  in a chronological sequence  of platform or services provided, as appropriate.   

5.3 Client References 

Names of at least three  3  client references similar in size, industry, scope, and complexity  to  the  Royal  Monetary  Authority  and  which  have  purchased  the  vendor’s  proposed  service s /solution s  for a comparable environment. Information must include these points  at a minimum:      Contact Name, Organization, Title, Address and Telephone Number      Contact Date      Solution /Service provided       Role of the Service Provider in Implementation and Support      Contract Size       Size of Project Team 

A complete set of Reference  as stated above  must be provided for each Bid area as outlined  in Section 4.   5.4 Implementation Timeline     Vendors are required to provide a logical implementation plan  and state possible delivery  date barring all unforeseen circumstances  to be adopted.  Please note that for each bid area, the Client expects the successful Vendor s  to complete  implementation within the timeframe outlined below which is subject to finalization during  contract negotiation.      Civil Works  - Walls / partitions - Doors  - Thermal insulation  - Raised floor  - Access ceiling  - Ramp  - Shifting of servers, racks, ACs, UPS and others        

(28)

Page 27 of 31 Electro‐mechanical Works - Power distribution system - Lighting system  - Air conditioning system  - Fire detection system - Surveillance & security system     Precision AC  Comfort AC  Fire Detection  Addressable Smoke Detection System Access Control  Surveillance system  Rodent Repellant system   5.5 Support Information    Specify the number of support sites you have. Which support site will be responsible for the  Client? 

  Outline  the  support  structure  of  your  organization  in  Bhutan   i.e.  the  number  of  staff  allocated to customer support, development and maintenance 

  Include evidence of support agreement  s  with sub‐contractors and OEM partners    Back‐to‐back Agreements 

  Back‐to‐back Support Agreements  in the event of sub contractors     Service Level Agreements and Principal Support Agreements 

  What  are  your  standard  terms  for  support?  Please  specify  what  service  level  agreements  SLA  are available.  e.g. 4hrs, 24hrs response, etc   

  What facilities do you have, or do you plan to implement for problem resolution including:    Hot line?    Expert assistance?    Direct contact with owner/developers?    Escalation procedures?  5.6 Strategic Alliances and Partnerships 

Submit  relevant  documentation  on,  and  describe  all  technical  partnerships  and  strategic  alliances the company is involved in. 

5.7 Industry Awards and Certifications 

Please  provide  necessary  information  on  significant  awards  /  certifications  possessed  by  your organization or its employees that is relevant to the successful delivery of this project   

(29)

Page 28 of 31 5.8 Training and documentation 

Vendors  are  expected  to  provide  comprehensive  training  and  documentation  on  all  configurations, design and operations to client’s IT team. Please outline a description of the  training plans  venue, timeframe, resource etc  proposed for technical users to enhance in‐ house support. 

5.9 Project Team  

Provide  detail  structure  of  the  overall  project  team,  the  number  of  staff  and  the  profile  qualification, experience, individual role in the project  of those that will be involved in the  execution of the various solutions as stated in section 4.0  

  Explain the roles and responsibilities of sub‐contractors  if any  that would be engaged on  the project  see section 3.19  

5.10 Procurement Tracking Process 

Vendors  are  expected  to  provide  information  on  their  procurement  tracking  process  especially  for  items  which  are  being  imported.  Please  provide  an  overview  of  your  procurement schedule.  The schedule should contain the following key information: 

  Average  cycle  time  in  days  from  order  to  receipt,  shipment,  local  transportation  arrangement etc  5.11 Financial Statement   Include copies of the audited financial statement.  E.g. balance sheet, profit & Loss, Cash flow  statement for the past 3 years      

(30)

Page 29 of 31 6 Response Format 

The  objective  of  the  section  is  to  enable  a  final  comparison  to  be  made  between  each  vendor’s offerings. Only bids adhering to the response structure will be considered.  When  responding  to  questions,  each  item  should  be  answered  in  a  separate  section,  in  the  sequence given and should include the reference number. 

The  required  structure,  numbering  and  content  of  each  section  of  vendors’  responses  is  detailed below. All proposals must include the following sections in order to be considered:  1. Executive Summary 

This is to contain a brief summary of all the key aspects of the proposal including but not  limited to: 

  Statement of agreement  or exceptions if any  with terms and conditions stated in sections 3  of this RFP    Overall description of your approach to meeting the Client’s requirements    Details of Key Contact Person as required in section 3.2    Any other important/critical factors     Integrated Project Plan covering all bid areas    Integrated Cost Sheet covering all bid areas    Vendor Profile See Section 5 for details   This section should contain information about the vendor’s organization and its capability to  support the solution. Please respond to all the enquiries in Section 5 including information  on  Company  Size,  Organization  and  Location,  Client  References,  Support  Information,  Strategic  Alliances  &  Partnerships  and  comprehensive  sub‐contractor  information  if  sub‐ contractors are involved .   

  Proposed Solution s  & Pricing Information 

Please provide a description of how your solution s  components will support the Clients’  requirements  as  described  in  Section.  4.0.  Vendors  are  expected  to  state  clearly  the  Bid  Area s  being responded.    For each Bid Area, the following information must be provided:    Recommended products, technology and service    Explanation of the proposed solution components and why it is appropriate    Price/Quotation    Implementation/Installation Plan    Delivery Timeline  All price responses should be documented in line with format specified in Section 3.7 & 3.12  and should include:    Bill of Material, Price Quotation, Billing Schedule, and corresponding Warranty 

  Vendors  must  give  price  quotation  separately  for  each  of  Bid  area  being  responded  to  as  shown in the table below: 

(31)

Page 30 of 31 7 Appendix 

   

SERVERS AND NETWORK COMMUNICATION EQUIPMENTS  

Sl. No  Rack Details  Application Server Numbers

1  BFS Server Rack ‐ 42u   BFS Servers 8 2  Storage 1 3  SAN switch 1 4  Tape 1 5  KVM   switch 1 6  Network Equipment 4 7  Valrack ‐  42u   Internal Application Servers 9 8  Network Equipment 6 9  KVM   switch 1 10  Valrack ‐   42u   EFTCS Servers 3 11  Network Equipment 2 12  KVM   switch 1 13  Standard Server Rack ‐   42u   Servers  3 14  Workstation PCs 2 15  KVM   switch 1 16  No Rack  RCH Servers 4 17  Workstation PCs 1                                          

References

Related documents

The projected gains over the years 2000 to 2040 in life and active life expectancies, and expected years of dependency at age 65for males and females, for alternatives I, II, and

There are infinitely many principles of justice (conclusion). 24 “These, Socrates, said Parmenides, are a few, and only a few of the difficulties in which we are involved if

19% serve a county. Fourteen per cent of the centers provide service for adjoining states in addition to the states in which they are located; usually these adjoining states have

Standardization of herbal raw drugs include passport data of raw plant drugs, botanical authentification, microscopic & molecular examination, identification of

The most important contributions of this paper are (i) the proposal of a concern mining approach for KDM, what may encourage other groups to start researching on

In general, this equation, with or without some modification, applies to all other type of osmotic systems. Several simplifications in Rose-Nelson pump were made by Alza

This essay asserts that to effectively degrade and ultimately destroy the Islamic State of Iraq and Syria (ISIS), and to topple the Bashar al-Assad’s regime, the international

National Conference on Technical Vocational Education, Training and Skills Development: A Roadmap for Empowerment (Dec. 2008): Ministry of Human Resource Development, Department