1
PROJECT REPORT
on
PLANNING AND DESIGN OF NET ZERO ENERGY
RESIDENTAL BUILDING
Submitted in partial fulfillment for the award of the degree
of
BACHELOR OF TECHNOLOGY
inCIVIL ENGINEERING
byKARTHIK V
(1010910090)
SASIDHAR K.V (1010910092)
NEERAJ PORWAL (1010910118)
ABHINAV N (1010910119)
Under the guidance of
Mrs. VASANTHI.P
Assistant Professor (O.G)DEPARTMENT OF CIVIL ENGINEERING
FACULTY OF ENGINEERING AND TECHNOLOGY
SRM UNIVERSITY
2
(Under section 3 of UGC Act, 1956)
SRM Nagar, Kattankulathur- 603203
Kancheepuram District
MAY 2013
PROJECT REPORT
on
PLANNING AND DESIGN OF NET ZERO ENERGY
RESIDENTAL BUILDING
Submitted in partial fulfillment for the award of the degree
of
BACHELOR OF TECHNOLOGY
inCIVIL ENGINEERING
byKARTHIK V
(1010910090)
SASIDHAR K.V (1010910092)
NEERAJ PORWAL (1010910118)
ABHINAV N (1010910119)
Under the guidance of
Mrs. VASANTHI.P
Assistant Professor (O.G)3
DEPARTMENT OF CIVIL ENGINEERING
FACULTY OF ENGINEERING AND TECHNOLOGY
SRM UNIVERSITY
(Under section 3 of UGC Act, 1956)
SRM Nagar, Kattankulathur- 603203
Kancheepuram District
MAY 2013
BONAFIDE CERTIFICATE
Certified that this project report titled “PLANNING AND DESIGN OF
NET ZERO ENERGY RESIDENTAL BUILDING” is the bonafide
work
of
KARTHIK.V(1010910090),
SASIDHAR
REDDY.K.V(1010910092),
NEERAJ
PORWAL
(1010910118),
ABHINAV. N (1010910119) who carried out the research under my
supervision. Certified further, that to the best of my knowledge the work
reported herein does not form part of any other project report or dissertation
on the basis of which a degree or award was conferred on an earlier
occasion or any other candidate.
4
Signature of the Guide Signature of the HOD
Mrs. VASANTHI .P Dr. R. ANNADURAI
Assitant Professor (O.G) Professor & Head Department of Civil Engineering Department of Civil
Engineering
SRM University SRM University
Kattankulathur- 603203 Kattankulathur- 603203
INTERNAL EXAMINER
EXTERNAL
EXAMINER
DATE:
ABSTRACT
The proposed Net zero residential building is located at
Urapakkam. The NZERB has G+1 floor. The total land surface covered by
the Net zero energy residential building is 99 square meters. A complete
design shall be done for the proposed NZERB using Indian standard
codes. There are three main phases in a construction project which are
planning, designing and estimation. The first stage in a project is planning,
in which preparation of layout of plot has to be done. To conclude the
project a detailed estimate of the residential building has also been prepared.
5
ACKNOWLEDGEMENT
The author wish to acknowledge my indebtedness to alma mater for congenial cooperation and granting me permission to accomplish a work on “PLANNING AND
DESIGN OF NET ZERO ENERGY RESIDENTIAL BUILDING”
The author is grateful and records his sincere thanks to Dr. T. P.
GANESAN
Pro Vice Chancellor (P&D) and Dr. C. MUTHAMIZHCHELVAN, Director, (E&T), SRM UNIVERSITY for providing all the necessary facilities for carrying out this work.
6
The author expresses his sincere thanks and Gratitude to HOD Dr. R.
ANNADURAI, Department of Civil Engineering, for his valuable suggestions and
advice in carrying out this thesis work.
The author expresses his sincere thanks to Department Coordinator/Civil
Dr.K.GUNASEKARAN, Professor, Department of Civil Engineering, for initiative and
motivation during the course of this work.
The author hereby acknowledges with deep sense of gratitude the valuable guidance given by the Guide Mrs.VASANTHI P, Assistant Professor, Department of Civil Engineering, for initiative and motivation during the course of this work.
The
author is extremely grateful tothe
valuble advices given by the class incharge Mr.K.PRASANNA, Assistant professor,Department of Civil Engineering, for constant support.The author is grandly indebted to all the Faculty Members of Department of
Civil Engineering, for their valuable help rendered during the course of study.
Finally, the author expresses his hearty thanks to Friends for their kind help and encouragement throughout the course of this thesis work.
TABLE OF CONTENTS
CHAPTER TITLE PAGE
7 ACKNOWLEDGEMENT v LIST OF TABLES ix LIST OF FIGURES x ABBREVATIONS xi 1 OVERVIEW 1 1.1 OBJECTIVE 1 1.2 NECESSITY 1 1.3 SCOPE 2 1.4 METHODOLOGY 2
1.5 MAJOR DESIGN EXPERIENCE 2
1.6 REALISTIC DESIGN CONSTRAINTS 3
1.7 REFERENCE TO CODES AND STANDARS 3
1.8 APPLICATION OF EARLIER COURSE WORKS 4
1.9 MULTIDISCIPLINARY AND TEAM WORK 4
1.10 SOFTWARE USED 5 1.11 CONCLUSION 5 1.12 FUTURE SCOPE 5 2 INTRODUCTION 6 2.1 GENERAL 6 2.2 LITERATURE REVIEW 7
2.3 DEVELOPMENT CONTROL RULES FOR CHENNAI
METROPOLITAN AREA, 2004 8
2.3.1 Primary Residential Use Zone 8
2.4 CONFORMATION TO NATIONAL BUILDING
CODE OF INDIA 9
2.4.1 Fire Safety, Detection And Extinguishing
8
2.4.2 Security Deposits 10
3 OBJECTIVE AND SCOPE 11
3.1 OBJECTIVE 11
3.2 SCOPE 12
3.3 MATERIALS AND METHODOLOGY 12
4 RESULTS AND DISCUSSIONS 13
4.1 PLANNING 13
4.1.1 Selection of Site 13
4.1.2 Plot Layout 14
4.1.3 Plan of the Building 15
4.2 DESIGNS 16 4.2.1 Design of Hall 16 4.2.2 Design of Bedroom 20 4.2.3 Design of Bedroom 23 4.2.4 Design of Bathroom 27 4.2.5 Design of Portico 30 4.2.6 Design of Kitchen 33
4.2.7 Design of Dining Room 37
4.2.8 Design of Wall 40
4.2.9 Design of Footing 44
4.2.10 Design of Hollow Brick Wall 44
4.2.11 Design of Footing (Hollow Brick) 49
9
4.3 DESIGN OF SOLAR PANEL AND ITS COMPONENTS 54 4.3.1 Solar power system components
54 4.3.2 Working of Solar Panel 55
4.3.3 Description of Individual Solar Panel components 55
4.3.3.1 Solar Panels 55
4.3.3.2 Solar Regulator 55
4.3.3.3 Power Inverter 56
4.3.3.4 Solar Batteries 56
4.3.4 Designing of Solar Panel 57
4.4 RATE ANALYSIS OF SOLAR PANELS 59
4.5 INFRARED THERMOMETER 60
4.6 HOLLOW BRICK 62
4.6.1 Parameters of Hollow Brick 62
4.6.2 Advantages of Hollow Bricks 64
4.7 ESTIMATION 65
4.7.1 Abstract Estimate of Conventional Building 65 4.7.2 Abstract Estimate of NZERB
67 4.7.3 Rate Analysis 70 5 CONCLUSION 72 5.1 CONCLUSION 72 5.2 FUTURE SCOPE 72 REFERENCES 73
10
LIST OF TABLES
TABLE TITLE PAGE 1.1 Codes Used
3
1.2 Earlier Course Work Used
11 2.1 Front Setback 8 2.2 Rear Setback 9 2.3 Side Setback 9
4.1 Values of slenderness ratio 48
4.2 Stress reduction factor for slenderness ratio 48
4.3 Calculation of permissible stress 49
4.4 Safe allowable load
49
4.5 Calculations of loads
57
4.6 Abstract Estimate of Conventional Building 65
4.7 Abstract Estimate of NZERB
67
4.8 Rate Analysis of Proposed Conventional Building 70
4.9 Rate Analysis of Proposed NZERB 71
12
LIST OF FIGURES
FIGURE TITLE PAGE
4.1 Plot Layout 13
4.2 Ground Floor Plan 14
4.3 First Floor Plan 15
4.4 Footing Design 51
4.5 Working of Solar Panels 54
4.6 Infrared Thermometer 60
13
ABBREVIATIONS
deff - Effective depth
c.c - Clear cover
D - Total depth
b - Width
Mu,lim - Ultimate limiting moment of resistance
fck - Characteristic compressive strength of concrete
Mu - Ultimate moment
Pt - Percentage of tension reinforcement
Pc - Percentage of compression reinforcement
Ast - Area of steel in tension zone
14
Sv - Spacing of stirrups
fy - Yield stress of steel
Asv - Total cross sectional area of stirrup legs
kt - Modification factor for tension reinforcement
kc - Modification factor for compression reinforcement
kf - Reduction factors for flanged beams
Pu - Ultimate load
τc - Permissible shear stress
Ag - Gross area of cross section
Ly - Length in y direction
Lx - Length in x direction
Wu - Ultimate load
αx - Bending moment coefficient for short span
αY - Bending moment coefficient for long span
Mx - Moment in short span direction
My - Moment in long span direction
dreq - Required depth
dprov - Provided depth
Mu,max - Maximum ultimate moment
Ast( reqd) - Area of steel required
Ast (min) - Area of minimum steel required
ast - Area of 1 bar
D.L - Dead Load
L.L - Live Load
Φ - Angle of internal friction
NC , NY, Nq - Bearing capacity factors
CMDA - Chennai metropolitian development authority PWD - Public works department
15
KKNP - Kudankulam Nuclear Power Plant W.h - Watt hour
A.h - Ampere hour
16
OVERVIEW
1.1 OBJECTIVE
i. Design a building with Net zero energy concept.
ii. To eliminate the necessity of active energy loads on the building. iii. Comparing the net zero energy building with conventional building.
1.2 NECESSITY
The basic necessities of such a building are:
i. As the country is developing day by day the consumption of power is also very high. ii. Now if we are going for NZERB building we can save energy locally
which mean to save energy in global level.
iii. The use of this technology used in residential buildings has shown huge amount savings in the electricity bill.
iv. The proper design and alignment of the building can make the building cheaper than that of the conventional type of buildings.
v. Usage of hollow bricks and avoidance of columns and beams will result in lowering of temperature inside the building
vi. To achieve sustainability.
1.3 SCOPE
17
ii. Design of load bearing structure using hollow bricks iii. Design of solar panels
iv. Comparison of room temperature between NZERB and conventional building
v. Comparison of energy consumption between NZERB and conventional building.
1.4 METHODOLOGY
This entire project is an planning and design in nature and the methodology followed in this project is listed as below.
i. Selection of site where renewable energy is available ii. Study the climate conditions of area
iii. Aligning the building to utilize maximum amount of renewable resources iv. Planning and design of proposed NZERB building
v. Comparison of the NZERB building with other conventional building
1.5 MAJOR DESIGN EXPERIENCE
Design experience in the following areas has been gained during the course of the project
i. Design of slabs ii. Design of footings
iii. Design of wall using Hollow bricks iv. Design of solar panels
18
i. Economic: Building shall be designed such that the entire energy requirements are met by solar energy only due to shortage of conventional energy.
ii. Sustainability Constraints: The design shall be such that the requirement of cooling do not fluctuate throughout the year.
iii. Economic Constraint: The materials adopted for construction are economical compared to conventional materials.
1.7 REFERENCE TO CODES AND STANDARDS
The codes for design of buildings and structures, Design co-efficient, Limit state design method and Fixing of dimensions are shown in Table 1.1
Table 1.1 Reference to codes and standards
Codes /Standards Context
IS 875 :1987 -1,2 Design loads for buildings and structures (Dead load , Imposed load )
IS 456 :2000 Design co-efficient, Limit state design method used for slab and footing IS 2572-1963(R 1997) Design of Hollow bricks
IS 1905 :1987 Structural use of Unreinforced Masonry SP 20 :1991 Handbook of Masonry design and
19
1.8 APPLICATION OF EARLIER COURSE WORK
The codes for Computer aided building drawing, layout and planning and Byelaws, Setbacks, Open space, Floor area ratio are shown in Table 1.2
Table 1.2 Application of earlier course work Course Code and Name Context
CE 0104- Computer aided building
drawing Computer aided building drawing CE0102- Elements of building science
and Architecture layout and planning
CE0209- Building technology Byelaws, Setbacks, Open space, Floor area ratio
CE0303-Structural Design II R.C.C Design CE0304-Structural Design III R.C.C Design
1.9 MULTIDISCIPLINARY COMPONENT AND TEAM WORK
i. This project involves in multidisciplinary team work and helps interacting with the builders who deal with the non conventional building
methods and use of waste and cost effective building materials.
ii. It also involves interaction with software people to learn about the function and operation of the software‟s used in this project for the design, analyse and estimation of the parts of the structure.
1.10 SOFTWARE USED
i. Auto CAD ii. MS EXCEL iii. MS WORD
20
1.11 CONCLUSION
The two types of buildings are analyzed with respect to cost, time, availability of skilled labour and ease in construction.
COST ELECTRICITY AVAILABILITY OF RESOURSES NORMAL CONVENTIONAL BUILDING Low It requires an active source Easily Available NZERB High Produced on its own Difficult
1.12 FUTURE SCOPE OF THE PROJECT
The building is designed as a NET ZERO ENERGY BUILDING which produces its own electricity, thus we can save a huge amount in electricity bill.
21
CHAPTER 2
INTRODUCTION
2.1 GENERAL
Fast rate of urbanization and increase in the consumption of electricity has become a major problem in Tamil Nadu. Due to increase in consumption of electricity the Tamil Nadu electricity board is unable to fulfill the requirements of the public and industrial sectors .In Tamil Nadu, This is the major problem faced. Officials were banking on a number of projects, which would generate 14,000 MW of power, from thermal, nuclear and other power projects. Most of these should have been completed by 2012. But the projects have got delayed, with the KKNP turning out to be a big challenge .Hence requirement has brought in new building technologies by utilizing the renewable energy resources.
In housing aspects it is necessary to design the material adopted structurally in a proportion with reference standard codes. Designing of building is the most essential work to be proposed in any projects. Before starting the project it is necessary to prepare layout and plan in a plot as per the Government Rules and Regulation for getting an approval without any delay and to execute the project. Overall cost of the project should be economical so estimation of building is very important. As a whole we have incorporated all the needs for a building to be built with efficient, eco-friendly and economic, also abiding by the Government Rules.
22
This project envisages the preparation of a Residential layout by incorporating the Tamil Nadu Government rules and the preparation of a plan for a residential building in a plot by using software AutoCAD. Finally this project will end up with the preparation of an estimation of the prepared plan (Ref 1).
2.2 LITERATURE REVIEW
Anna Joanna,
Aalborg University, Department of Civil Engineering,
According to ANNA, “With energy conservation arrangements, such as high-insulated constructions, solar heating system. Extra Energy supply for the electric installations in the house is taken from the municipal mains” (Ref 2).
Saitoh, (1988) (JAPAN)
According to SAITOH, “… a multi-purpose natural energy autonomous house will meet almost all the energy demands for solar panel and cooling as well as
supply of hot water. For this purpose, solar energy, the natural underground coldness and sky radiation cooling are utilized.”
i. Solar panels are designed to harness.
ii. Solar energy in buildings include systems that capture heat (such as Solar water heating systems and passive heating).
iii. It converts solar energy into electrical energy, its done with the help of photovoltic (PV) systems (Ref 3).
23
2.3 DEVELOPMENT CONTROL RULES FOR CHENNAI METROPOLITAN AREA, 2004
2.3.1 Primary Residential Use Zone
In this primary residential use zone, buildings shall be permitted only for the following purposes and accessory uses.
(a) Professional consulting offices of the residents and incidental uses there to occupy a floor area not exceeding 40 square meters.
(b) Petty shops dealing with daily essentials including retail sale of provisions, soft drinks, cigarettes, newspapers, tea stalls, mutton stall and milk kiosks, cycle repair shops and tailoring shops.
(c) Nursery, primary and high school.
(d) Parks and playgrounds occupying an area not exceeding 2 hectares. (e) Taxi stands and car parking.
Front setback according to the CMDA code is shown in Table 2.1.
Table 2.1 Front Set Back
Abutting Road Width Front Set Back
Above 30m 6.0m
Above 15m but less than 30m 4.5m
Above 10m but less than 15m 3.0m
Below 10m 1.5m
Rear setback according to Chennai Metro Development Authority (CMDA) code is shown in Table 2.2.
24
Table 2.2 Rear Set Back
Depth of Plot Rear Set Back
Up to 15m 1.5m
Between 15m to 30m 3.0m
Above 30m 4.5m
Side setback according to CMDA code is shown in Table 2.3.
Table 2.3 Side Set Back
Width of Plot Side Set Back
Not more than 6m 1.0m on one side
More than 6m but not more than 9m 1.5m on one side
More than 9m 1.5m on either side
2.4 CONFORMATION TO NATIONAL BUILDING CODE OF INDIA
In so far as the determination of sufficiency of all aspects of structural designs,
building services, plumbing, fire protections, construction practice and safety are concerned the specifications, standards and code of practices recommended in the National Building Code of India (Ref.4), shall be fully confirmed to any breach thereof shall be deemed to be a breach of the requirements under these rules.
Every multi-storied development erected shall be provided with (i) Lifts as prescribed in National Building Code; (ii) a stand-by electric generator of adequate capacity for running lift and water pump, and a room to accommodate the generator; (iii) a room of not less than 6 meters by 4.5 meters in area with a minimum head room of 3 meters to accommodate electric transformer in the ground floor; and (iv) at least one meter room of size 2.4 meters by 2.4 meters for every 10 consumers or three floor whichever is less. The meter room shall be provided in the ground floor.
25
2.4.1 Fire Safety, Detection and Extinguishing Systems
All building in their design and construction shall be such as to contribute to and ensure individually and collectively and the safety of life from fire, smoke, fumes and also panic arising from these or similar other causes.
In building of such size, arrangement or occupancy than a fire may not itself provide adequate warning to occupants automatic fire detecting and alarming facilities shall be provided where necessary to warn occupants or the existence of fires, so that they may escape, or to facilitate the orderly conduct of fire exit drills. Fire protecting and extinguishing system shall conform to accepted standards and shall be installed in accordance with good practice a recommended in the National Building Code of India, and for the satisfaction of the Director of Fire Services by obtaining a no objection certificate from him (Ref.4).
2.4.2 Security Deposits
The applicant shall deposit a sum at the rate of Rs.100 per square meters of floor area as a refundable non-interest earning security and earnest deposit. The deposit shall be refunded on completion of development as per the approved plan as certified by CMDA, if not, it would be forfeited.
26
CHAPTER 3
OBJECTIVE AND SCOPE
3.1 OBJECTIVE
i. Design a building with Net zero energy concept.
Net-zero energy buildings start with energy-conscious design A zero-energy residential building is a building with zero net energy consumption A net-zero energy (NZE) building is one that relies on renewable sources to produce as much energy as it uses, usually as measured over the course of a year.
ii. To eliminate the necessity of active energy loads on the building.
Solar panels is one of the technologies used to achieve net-zero status. To eliminate the necessity of active energy loads solar techniques are used which include the use of photovoltaic panels and solar thermal collectors to harness the energy.
iii. Comparing the net zero energy building with conventional building.
The comparison of NZERB and conventional building is shown in Table 3.1
Table 3.1 Comparison of NZERB and Conventional Building
Sl.no NZERB CONVENTIONAL
1 Brick Material Hollow brick Normal brick
2 Temperature 4 to 5 degree less compared
To conventional building More than NZERB 3 Electricity Produced on its own It requires an active
source
4 Initial Cost High Less compared to
NZERB 5 Solar Panels 250 w panels Provided in NZERB Not provided
27
3.2 SCOPE
i. Functional planning of G+1 Residential building. ii. Design of load bearing structure using hollow bricks. iii. Design of solar panels.
iv. Comparison of room temperature between NZERB and conventional building.
v. Comparison of energy consumption between NZERB and conventional building.
3.3 METHODOLOGY
This entire project is an planning and design in nature and the methodology followed in this project is listed as below.
i. Selection of site where renewable energy is available
Urappakam has a tropical wet and dry climate. The weather is hot and humid for most of the year. The hottest part of the year is late May to early June. Hence solar energy is available on the site which makes the site suitable to harness solar energy
ii. Study the climate conditions of area
The city lies on the thermal equator and is also on the coast, which prevents extreme variation in seasonal temperature. The weather is hot and humid for most of the year. maximum temperatures is around 35– 40 °C (95–104 °F). The highest recorded temperature is 45 °C (113 °F)
iii. Aligning the building to utilize maximum amount of renewable resources
Elongated east-west and oriented to astronomic south (Ref 5). South-facing windows harvest solar energy.
iv. Planning and design of proposed NZERB building
28
CHAPTER 4
RESULTS AND DISCUSSIONS
4.1 PLANNING
The key plan of the residential building is drawn by considering the alignment of the building with respect to the CMDA.
The key plan of the site is shown in Figure 4.1
29
The ground floor of the building consist of one hall, two bedrooms, one dinning, one kitchen. The allocations of the rooms in the plan has been done with due consideration of sun diagram as per the requirement of zero energy building. The plan has been prepared using Auto CAD software.
The Ground Floor plan is shown in Figure 4.2
30
The first floor of the building consist of one hall, two bedrooms, one dinning, one kitchen. The allocations of the rooms in the plan has been done with due consideration of sun diagram as per the requirement of zero energy building. The plan has been prepared using Auto CAD software.
The First Floor plan is shown in Figure 4.3
31
4.2 ANALYSIS AND DESIGNS SLAB DESIGN (Ref 6)
The analysis and designs of the slab for Hall, Bedroom, Bathroom, Dinning, Kitchen, Stair case, Portico are done with proper considerations as per IS 456:2000.
4.2.1 Design of Hall
Using M 20 Concrete Fe 415 steel
Live Load = 2 (Ref 7)
1. Effective Span
Lx = 3.26 m
Ly = 5.1 m
Aspect ratio = = 1.56<2 Hence Two Way Slab
2. Load Calculation
Assuming Slab Thickness
Assume 10 bar, Clear Cover 20mm
Actual Depth (d) = 130-5-20 = 105 mm
Assume Floor Finish = 40 mm
Weight of Floor Finish = 0.04 × 24 = 0.96 Imposed Load = 2 (Ref 8)
32 Factored Load (Wu) = 1.5 × 6.21 = 9.315
Consider 1m width of slab
Load per meter Length = 9.127
3. Finding Design Bending Moment
Refer Table 26, Page No.91 of IS456 Two adjacent edges are discontinuous (already found out )
Refer Table 26
Short Span αx = 0.068
Long Span αy = 0.037
[Note that Lx only to be taken, where it is long span or short span only coefficient varies].
Mu = Wu × Co-efficient × Lx2 (4.1)
Mu is calculated by equation 4.1
Where,
Mu = Moment in short span direction
Wu= Ultimate load
Lx = Length in x direction
Mu(+) Short = 0.068 × 9.315 × 3.262 = 6.731 kN.m (Ref.9)
Mu(+) Long = 0.037 × 9.315 × 3.262 = 3.662 kN.m
Take the Highest Moment and check for adequacy of the section. Mu,lim=
* + (4.2)
(or) = 0.138fckb d2
Mu,lim is calculated by equation 4.2
33
Mu,lim = Ultimate limiting moment of resistance
fck = Characteristic compressive strength of concrete
b = Width d =Effective depth = 0.138 × 20 × 1000 × 1052 =30.42 kN.m (Mu Limit) > (Mu Short) Hence its ok 4. Calculation of Steel Ast(+) Short = [1 - 1-4.598 ] (4.3) Ast(+) Short is calculated by equation 4.3
Where,
Ast(+) Short =Area of steel required
b = Width
d = Effective depth
fck = Characteristic compressive strength of concrete
fy = Yield stress of steel
R = = 6.731 × = 0.6105 Ast(+) Short = 1000 × 105 × ( ) × 415 [1 - 1-4.598 = 184.27 mm2 Minimum Steel = 0.12% × D × B Ast,min = ( )× 130 × 1000 = 156 mm 2
Ast(+) Short <Ast,min
5. Check for maximum Spacing
i. 3d = 3 × 105 = 315 mm
ii. 300
34 d for long span bars
d = D – Clear Cover – - = 130 – 20 – - 10 = 95 mm
6. Calculation of Ast for Long Span Ast(+)Long [1 - 1- 4.598 ] Same as equation 4.3 R = d2 = × 952 = 0.4057 Ast(+)Long = 1000 × 95 × ( )× 415 [1 – 4.598 × ] = 109.37 mm2
Ast(+)Long<Ast,min
7. Spacing for all Steel
i. 3d = 3 × 95 = 285 mm ii. 300
Spacing = 285 mm
8. Check for Deflection
Short Span Lx = 3260 mm Ast(+) Short = 116.37 mm2 Basic Value = 20 Fs = 0.58 × 415× =240.2 Pt ( ) = ( ) = 0.175% Modification Factor = 1.62
Modified Basic Value = 20 × 1.62 = 32.8
35 31.047 < 32.8
Hence its ok
4.2.2 Design of Bed Room
Using M20 Concrete Fe415 steel Live Load = 2 1. Effective Span Lx = 3 m Ly = 3.5 m
Aspect ratio = = Hence Two Way Slab
2. Load Calculation
Assuming Slab Thickness Assume 10 bar, Clear Cover = 20mm
Actual Depth (d) = 125-5-20 = 100 mm
Self Weight of a Slab = Assume 40 mm Floor Finish
Weight of Floor Finish = 0.04 X 24 = 0.96
Imposed Load = 2
Total Load = 6.08
Factored Load (Wu) = 1.5× 6.96 = 9.127
Consider 1m width of slab
Load per meter Length = 9.127
36 Refer Table 26, Page No.91 of IS456 Two adjacent edges are discontinuous ( already found out )
Refer Table 26
Short Span αx = 0.043
Long Span αy = 0.035
[ Note that Lx only to be taken, where it is long span or short span only coefficient varies ].
Mu = Wu× Co-efficient × Lx2
Same as equation 4.1
Mu(+) Short = 0.043 × 9.13 × 3.232 = 4.09 kN.m
Mu(+) Long= 0.035 × 9.13 × 3.232 = 3.33 kN.m
Take the Highest Moment and check for adequacy of the section. Mu,lim= * + (or) Mu,lim = 0.138 fckbd2 Same as equation 4.2 Mu,lim = 0.138 × 20 × 1000 × 1002 Mu,lim = 27.6 (Mu Limit) > (Mu Short) Hence its ok 4. Calculation of Steel Ast(+) Short = [1 - 1-4.598 ] Same as equation 4.3
37 R = = 4.1 × × 1000 = 0.41 Ast(+) Short = [1 - 1-4.598 × ] = 116.37 mm2 Minimum Steel = 0.12% × D × B Ast,min = × 125 × 1000 = 150 mm 2
Ast(+) Short <Ast,min
5. Check for maximum Spacing
i. 3d = 3 X 100 = 300 mm ii. 300
Max Spacing = 300 mm d for long span bars d= D – Clear Cover – - d= 125 – 20 – 10/2 - 10 d= 90 mm
6. Calculation of Ast for Long Span Ast(+)Long [1 - 1- 4.598 ] Same as equation 4.3 R = = 3.33 × = 0.33 Ast(+)Long = 1000 × 100 × * – + = 93.2 mm2
Ast(+)Long<Ast,min
7. Spacing for Steel
38 Ast(+)Short = × 1000 = 674.5 mm Ast(+)Long = × 1000 = 842.27 mm
8. Check for Deflection
Short Span Lx = 3230 mm Ast(+) Short = 116.37 mm2 Basic Value = 20 Fs = 0.58 × 415 × =240. Pt ( ) = (1.22 X 10-3) ×100 = 0.122% Modification Factor = 1.7
Modified Basic Value = 20 × 1.7 = 34
32.3 < 34 Hence its ok
4.2.3 Design of Bed Room
Using M20 Concrete Fe415 steel Live Load = 2 1. Effective Span Lx = 3.85 m Ly = 3.95 m Aspect ratio = = = 1.027<2
Hence Two Way Slab
2. Load Calculation
39 d = 120.31mm = 120 mm Assume 10 bar, Clear Cover 20 mm D = 120+ +20 = 145mm = 150 mm Actual Depth (d) = 150-5-20 = 125 mm Self Weight of a Slab = × 25 = ×25 = 3.75 Assume 40 mm Floor Finish
Weight of Floor Finish = 0.04 × 24 = 0.96 Imposed Load = 2
Total Load = 6.75
Factored Load (Wu) = 1.5 × 6.75 = 10.125
Consider 1m width of slab
Load per meter Length = 10.125
3. Finding Design Bending Moment
Refer Table 26, Page No.91 of IS456 Two adjacent edges are discontinuous = 1.027 (already found out)
Refer Table 26
Short Span αx = 0.048
Long Span αy = 0.047
[ Note that Lx only to be taken, where it is long span or short span only coefficient varies ].
Mu = Wu× Co-efficient × Lx2
Same as equation 4.1
40
Mu(+) Long = 0.047 × 10.125 × 3.852 = 7.063 kN.m
Take the Highest Moment and check for adequacy of the section. Mu,lim= * + (or) = 0.138fckb d2 Same as equation 4.2 = 0.138 × 20 × 1000 × 1252 = 43.125 kN.m (Mu Limit) > (Mu Short) Hence its ok 4. Calculation of Steel Ast(+) Short = [1 - 1-4.598 ] Same as equation 4.3 R = = 7.203 × 106 = 0.460 Ast(+)Short = 1000 × 125 × ( ) × 415 [1 - 1-4.598 × ] = 164.08 mm2 Minimum Steel = 0.12% × D × B Ast,min = ( )× 150 × 1000 = 180 mm2
Ast(+) Short <Ast,min
5. Check for maximum Spacing
i. 3d = 3 × 125 = 375 mm ii. 300
Max Spacing = 300 mm d for long span bars d= D – Clear Cover – - d= 150 – 20 – - 10
41 d= 115 mm
6. Calculation of Ast for Long Span Ast(+)Long [1 - 1- 4.598 ] Same as equation 4.3 R = = = 0.553 Ast(+)Long = 1000 × 115 × ( ) × 415 [1 – 4.598 × ] = 181.11 mm2
Ast(+)Long<Ast,min
7. Spacing for all Steel
i. 3d = 3 × 115 = 345 mm ii. 300
Spacing = 300 mm
8. Check for Deflection
Short Span Lx = 3850 mm Ast(+)Short = 181.11 mm2 Basic Value = 20 Fs = 0.58 × 415 × =240.2 Pt ( ) = ( ) = 0.157% Modification Factor = 1.8
Modified Basic Value = 20 × 1.8 = 36
= = 30.8 30.8 < 35.6 Hence its ok
42 4.2.4 Design of Bathroom Using M20 Concrete Fe415 steel Live Load = 2 1. Effective Span Lx = 2.38 m Ly = 4.28 m Aspect ratio = = = 1.798<2 Hence Two Way Slab
2. Load Calculation
Assuming Slab Thickness
d = = 74.375 mm = 80 mm Assume 10 bar, Clear Cover 20 mm
Actual Depth d = 110-5-20 = 85 mm
Self Weight of a Slab = = 2.75
Assume 40 mm Floor Finish
Weight of Floor Finish = 0.04 × 24 = 0.96 Imposed Load = 2
Total Load = 5.75
Factored Load (Wu) = 1.5 × 5.75 = 8.625
Consider 1m width of slab
43
3. Finding Design Bending Moment
Refer Table 26, Page No.91 of IS456 Two adjacent edges are discontinuous
= 1.798 (already found out)
Refer Table 26
Short Span αx = 0.085
Long Span αy = 0.047
[ Note that Lx only to be taken, where it is long span or short span only coefficient varies ].
Mu = Wu× Co-efficient × Lx2
Same as equation 4.1
Mu(+) Short = 0.085 × 8.625 × 2.382 = 4.127 kN.m
Mu(+) Long = 0.047 × 8.625 × 2.382 = 2.29 kN.m
Take the Highest Moment and check for adequacy of the section. Mu,lim= * + (or) = 0.138fckb d2 Same as equation 4.2 = 0.138 × 20 × 1000 × 852 =19.94 kN.m (Mu Limit) > (Mu Short) Hence its ok 4. Calculation of Steel Ast(+) Short = [1 - 1-4.598 ] Same as equation 4.3 R = = 4.1527 ×( ) = 0.574 Ast(+) Short = 1000 × 85 × ( ) × 415 [1 - 1-4.598 × ]
44 = 139.92 mm2 Minimum Steel = 0.12% × D × B Ast,min= ( ) × 110 × 1000 = 132 mm 2
Ast(+) Short <Ast,min
5. Check for maximum Spacing
i. 3d = 3 × 855 = 255 mm
ii. 300
Max Spacing = 255 mm d for long span bars d= D – Clear Cover – - d= 110 – 20 – - 10 d= 75 mm
6. Calculation of Ast for Long Span Ast(+)Long [1 - 1- 4.598 ] Same as equation 4.3 R = = = 0.4082 Ast(+) Long = 1000 × 75 × ( ) × 415 [1 – 4.598 × = 86.88 mm 2
Ast(+) Long <Ast,min
7. Spacing for all Steel
i. 3d = 3 × 75 = 225 mm
ii. 300
MaxSpacing = 225 mm
8. Check for Deflection
Short Span Lx = 2380 mm
45 Basic Value = 20 Fs = 0.58 × 415 × = 240.2 Pt ( ) = ( ) ( ) = 0.1646% Modification Factor = 1.9
Modified Basic Value = 20 × 1.9 = 38
= = 28 28 < 38 Hence its ok 4.2.5 Design of Portico Using M20 Concrete Fe415 steel Live Load = 2 1. Effective Span Lx = 3.78 m Ly = 6.93 m Aspect ratio = = 1.83<2
Hence Two Way Slab
2. Load Calculation
Assuming Slab Thickness
d = 118.124 mm = 120 mm Assume 10 bar, Clear Cover 20 mm D = 120 = 150 mm
Actual Depth (d) = 150-5-20 = 125 mm Self Weight of a Slab = ×25
46 = 3.75 Assume 40 mm Floor Finish
Weight of Floor Finish = 0.04 × 24 = 0.96 Imposed Load = 2
Total Load = 6.75
Factored Load (Wu) = 1.5 × 6.75 = 10.125
Consider 1m width of slab
Load per meter Length = 10.125
3. Finding Design Bending Moment
Refer Table 26, Page No.91 of IS456 Two adjacent edges are discontinuous (already found out)
Refer Table 26
Short Span αx = 0.087
Long Span αy = 0.047
[ Note that Lx only to be taken, where it is long span or short span only coefficient varies ].
Mu = Wu× Co-efficient × Lx2
Same as equation 4.1
Mu(+) Short = 0.087 × 10.125 × 3.782 = 12.58 kN.m
Mu(+) Long = 0.047 × 10.125 × 3.782 = 6.79 kN.m
Take the Highest Moment and check for adequacy of the section. Mu,lim= * + (or) = 0.138fckb d2 Same as equation 4.2
47 = 0.138 × 20 × 1000 × 1252 = 43.125 kN.m (Mu Limit) > (Mu Short) Hence its ok 4. Calculation of Steel Ast(+) Short = [1 - 1-4.598 ] Same as equation 4.3 R = = = 0.805 Ast(+) Short = 1000 × 125 × [1 - 1-4.598 × ] = 184.27 mm2 Minimum Steel = 0.12% × D × B Ast,min = ( )× 130 × 1000 = 156 mm2
Ast(+) Short <Ast,min
5. Check for maximum Spacing
i. 3d = 3 ×105 = 315 mm
ii. 300
Max Spacing = 300 mm d for long span bars d= D – Clear Cover – - d= 130 – 20 – 10/2 - 10 d= 95 mm
6. Calculation of Ast for Long Span Ast(+)Long
[1 - 1- 4.598 ] Same as equation 4.3
48 = = 0.4057 Ast(+)Long = 1000 × 95 × ( )× 415 [1 – 4.598 × ] = 109.37 mm2
Ast(+)Long<Ast,min
7. Spacing for all Steel
i. 3d = 3 × 95 = 285 mm ii. 300
Spacing = 285 mm
8. Check for Deflection
Short Span Lx = 3260 mm Ast(+) Short = 116.37 mm2 Basic Value = 20 Fs = 0.58 × 415× = 240.2 Pt ( ) = ( ) = 0.175% Modification Factor = 1.62 Modified Basic Value = 20 × 1.62 =32 = = 31.047 31.047 < 32.8 Hence its ok 4.2.6 Design of Kitchen Using M20 Concrete Fe415 steel Live Load = 2 1. Effective Span
49 Lx = 2.23 m
Ly = 3.73 m
Aspect ratio Hence Two Way Slab
2. Load Calculation
Assuming Slab Thickness d = = 65 mm
Assume 10 bar, Clear Cover 20 mm D = 65+ +20 = 90 mm
Actual Depth (d) = 90-5-20 = 65 mm Self Weight of a Slab =
= 2.25 Assume Floor Finish = 40 mm
Weight of Floor Finish = 0.04 × 24 = 0.96 Imposed Load = 2
Total Load = 5.25
Factored Load (Wu) = 1.5 × 5.25 = 7.875
Consider 1m width of slab
Load per meter Length = 7.875 Finding Design Bending Moment Refer Table 26, Page No.91 of IS456 Two adjacent edges are discontinuous = 1.67 (already found out)
Refer Table 26
50 Long Span αy = 0.035
[ Note that Lx only to be taken, where it is long span or short span only coefficient varies ].
Mu = Wu× Co-efficient × Lx2
Same as equation 4.1
Mu(+) Short = 0.06 × 7.88 × 2.232 = 2.35 kN.m
Mu(+) Long = 0.035 × 7.88 × 2.232 = 1.373 kN.m
Take the Highest Moment and check for adequacy of the section. Mu,lim= * + (or) Mu,lim = 0.138 fckb d2 Same as equation 4.2 = 0.138 × 20 × 1000 × 652 =11.66 kN.m (Mu Limit) > (Mu Short) Hence its ok 3. Calculation of Steel Ast(+) Short = [1 - 1-4.598 ] Same as equation 4.3 R = = 2.735 × = 0.55 Ast(+) Short = 1000 × 65 × × 415 [1 - 1-4.598 × ] = 103.56 mm2 Minimum Steel = 0.12% × D × B Ast,min × 90 × 1000 = 108 mm2
Ast(+) Short <Ast,min
51
i. 3d = 3 × 65 = 195 mm
ii. 300
Max Spacing = 195 mm d for long span bars d= D – Clear Cover – - d= 90 – 20 – - 10 d= 55 mm
5. Calculation of Ast for Long Span Ast(+)Long [1 - 1- 4.598 ] Same as equation 4.3 R = = 1.373 × = 0.115 Ast(+) Long =1000 × 55 × × 415 [1 – 4.598 × ] = 71.05 mm2
Ast(+) Long <Ast,min
6. Spacing for all Steel
Ast = × 102 = 78.5 mm2 Ast(+) Short = × 1000 = 758.01 mm Ast(+) Long = × 1000 = 1104.8 mm
7. Check for Deflection
Short Span Lx = 2230 mm Ast(+) Short = 103.56 mm2 Basic Value = 20 Fs = 0.58 × 415 × = 240.7 Pt ( ) = = 0.16%
52 Modification Factor = 1.8
Modified Basic Value = 20 × 1.8 = 36
34.3 < 36 Hence its ok
2.4.7 Design of Dinning Room
Using M20 Concrete Fe415 steel Live Load = 2 1. Effective Span Lx = 2.6 m Ly = 3.73 m Aspect ratio Hence Two Way Slab
2. Load Calculation
Assuming Slab Thickness d =
Assume 10 bar, Clear Cover 20 mm D
Actual Depth (d) = 105-5-20 = 80 mm
Self Weight of = 2.625
Assume Floor Finish = 40 mm
Weight of Floor Finish = 0.04 × 24 = 0.96 Imposed Load = 2
53 Total Load = 5.62
Factored Load (Wu) = 1.5 × 5.62 = 8.43
Consider 1m width of slab
Load per meter Length = 8.43
3. Finding Design Bending Moment
Refer Table 26, Page No.91 of IS456 One edge discontinuous
= 1.43 (already found out)
Refer Table 26
Short Span αx = 0.049
Long Span αy = 0.028
[ Note that Lx only to be taken, where it is long span or short span only coefficient varies ].
Mu = Wu× Co-efficient × Lx2
Same as equation 4.1
Mu(+) Short = 0.049 × 8.43× 2.62 = 2.79 kN.m
Mu(+) Long = 0.028 × 8.43 × 2.62 = 1.595 kN.m
Take the Highest Moment and check for adequacy of the section. Mu,lim= * + (or) Mu,lim = 0.138fckb d2 Same as equation 4.2 Mu,lim = 0.138 × 20 × 1000 × 802 Mu,lim =17.66 kN.m (Mu Limit) > (Mu Short) Hence its ok 4. Calculation of Steel
54 Ast(+) Short = [1 - 1-4.598 ] Same as equation 4.3 R = = 2.79 × = 0.435 Ast(+) Short = 1000 × 80 × 415 [1 - 1-4.598 ] = 99.15 mm2 Minimum Steel = 0.12% × D × B Ast,min= × 105 × 1000 = 126 mm2 Ast(+) Short <Ast,min
5. Check for maximum Spacing
i. 3d = 3 × 80 = 240 mm ii. 300
Max Spacing = 240 mm d for long span bars d= D – Clear Cover – - d= 105 – 20 – - 10 d= 70 mm
6. Calculation of Ast for Long Span Ast(+)Long [1 - 1- 4.598 ] Same as equation 4.3 R = = 1.595 × = 0.325 Ast(+) Long =1000 × – 4.598 × ] = 64.34 mm2
55 Ast(+) Long <Ast,min
7. Spacing for Steel
Ast = × 102 = 78.5 mm2 Ast(+) Short = 1000 = 791.7 mm Ast(+) Long = × 1000 = 1200.08 mm
8. Check for Deflection
Short Span Lx = 2600 mm Ast(+) Short = 99.15 mm2 Basic Value = 20 Fs = 0. Pt ( ) = = 0.14% Modification Factor = 1.8
Modified Basic Value = 20 × 1.8 = 36
= 32.5 32.5 < 36 Hence its ok 4.2.8 Design of Wall Design of a wall 1.Calculation of Loads
Maximum short span = 3.60 m Width of corridor = 1.50 m Height of the storey = 3 m
Live load = 2
56 Height of the Plinth from ground = 0.5 m Height of the Plinth above Footing = 1 m Height of the Parapet Wall = 1 m Thickness of Roof Slab =110 mm
Brick Size = 230 × 115 × 75
3. Slenderness Ratio and Stress Factor
Ground Floor + First Floor
H = 3+0.115+0.5+3+0.115+1 = 7.73 m
Effective Height (h) = 0.75H = 0.75 × 7.73 = 5.797 m Slenderness Ratio
4. Shape modification factor:
Crushing Strength of Modular Brick = 5
Shape Modification Factor = Kp = 1 ( From table 10 of IS: 1905-1987)
5. Area reduction factor:
Area Reduction Factor
Ka = 0.7 + 1.5 A = 0.7 + 1.5X0.3 = 1.15
A > 0.2 m2
Ka = 1 ( From clause 5.4.1.2)
6. Stress Reduction Factor:
ks = 0.46 ( from table 9)
7. Permissble Stress
Fc = Ks × Ka × Kp× Basic compressible stress (4.4)
Fc is calculated by equation 4.4
Where,
Ks= Stress reduction factor
Ka= Area reduction factor
57 Fc = 0.44 × 0.48 × 1 × 1 = 8. Safe Load Q = ( ) = = 63 9. Wall Area
Outer wall = Total Perimeter x 3(floor height) = ((11.31×2) + (8.93×2))×3
= 40.83 m3
Inner wall = (4.87×3) + (4.87×3) + (3.5×2×3) = 29.22 + 21 = 50.22 m3
Total wall volume = 91.05 m3
10. Deductions: Outer Deductions = 1.098+1.089+2.226+1.089+1.4884+1.4884+1.4884+ 1.4884+1.4884+1.098 = 14.042 m3 Inner Deductions = 1.89+1.89+2.496+1.746+1.746 = 9.768 m3 Total Deduction =23.81 m3
Total wall volume – Total Deductions = 91.05 -23.81 = 67.25 m3 % Opening =
= 35.4 %
Thickness = 1 Brick thick wall (using nomograms)
11. For Hall : Wu= × {3- ( ) 2 } (4.5) Wu is calculated by equation 4.5
58 Where,
Wu= Factored load
W=Load from the slab Lx=Short span Ly=Long span Wu =( ( )) * } Wu = 13.11 103
For bed room: Wu=
* ( ) }
= (9.127 × ( )) × {3- * + } = 11.055 103
For dinning room: Wu= × {3- *( )+2 } = ( ( )) × {3- [( )( )]2} = 9.81 103 Total : 13.11 + 11.055 + 9.81 = 33.98 103 63>33.98
Hence the design is ok
4.2.9 Design of Footing
Load from Walls = 126.7
59 1. Area of Footing =
Assume SBC = 150 A = = 0.47 m2 Consider 1m Length room
Breadth of the Footing Required = = 0.47 2. Minimum Width = (2w+300)mm
= (2x230+300) = 760 mm Provide Width of P.C.C= 760 mm
It is customary to provide 150 to 300 mm P.C.C thickness Provide = 300 mm
The Projection of P.C.C beyond the brick work should not be more than ½ of the thickness of P.C.C
Projection = = 150 mm
Actual work of Brick work = 760 – 300 = 460 mm Brick work projection beyond the wall
1.Depth of the Brick work = 115 × 2 = 230 mm
These depth has to be Provided by means of series steps The thickness of each step is given by modular brick = 200 mm The offset in the brick is also given as modular = 100 mm
4.2.10 Design of Hollow Brick Wall Step 1: Calculation of loads
Maximum short span = 3.6 m Height of the storey = 3 m Live load = 2
60 Height of the Plinth from ground = 0.5 m Height of the Plinth above Footing = 1 m Height of the Parapet Wall = 1 m Thickness of Roof Slab = 0.120 m
Hollow Brick Size = 0.40 × 0.20 ×0. 20 m
EFFECTIVE LENGTH OF WALL
(From Table 5 of IS 1905-1987)
Wall A = 3.82×0.9=3.438 m (continuous on one end & discontinuous on other end)
Wall B = 3.23×0.8=2.584 m (continuous on both ends & supported by cross wall)
Wall C = 3.7×0.9 =3.33 m (continuous on one end & discontinuous on other end) Wall D = 3.2×0.9 =2.88 m (continuous on one end & discontinuous on other end) Wall E = 2.57×0.8=2.056 m (continuous on both ends & supported by cross wall) Wall F = 2.8×0.9 =2.52 m (continuous on one end & discontinuous on other end) Wall G = 3.7 m (discontinuous on both ends and braced by cross wall)
Wall H = 3.23×0.9 =2.907 m (continuous on one end & discontinuous on other end)
Wall I = 3.82 × 0.9=3.438 m (continuous on one end & discontinuous on other end)
Wall J = 3.438 m (continuous on one end & discontinuous on other end) Wall K = 3.72 × 0.8=2.976 m (continuous on both ends & supported by cross wall)
Wall L = 2.15 × 0.9 =1.935 m (continuous on one end & discontinuous on other end)
61
Step 3: Slenderness ratio and stress factor
Ground floor:
H = 2.6+0.6+1 = 4.2 m
Effective height = 0.75 × H = 3.15 m Slenderness ratio = = = 15.75
Step 4: Shape modification factor
Crushing Strength of Hollow Brick= 4.1
= =1
Shape Modification Factor = Kp =1.2( From table 10 of IS: 1905-1987)
Step 5: Stress Reduction Factor
ks = 0.74( From table 9)
Step 6: Area reduction factor
Gross area = 200 × 1000 = 200000 mm2 A = 0.2 m2
Ka= 1( From clause 5.4.1.2)
Step 7: Permissible stress
Fc= 0.74 × 1.2 × 1× 0.44 = 0.39
Safe allowable load per meter length is q = 0.39 × 2 × 105 = 78
Step 7: Slenderness ratio and stress factor
First floor:
62 Effective height = 0.75 × H = 2.55 m Slenderness ratio = = = 12.75
Step 8: Shape modification factor
Crushing Strength of Hollow Brick = 4.1
= =
=
1
Shape Modification Factor = Kp =1.2
Step 9: Stress Reduction Factor
ks = 0.81
Step 10: Area reduction factor
Gross area = 200 × 1000 = 200000 mm2 A = 0.2 m2
Ka= 1
Step 11: Permissible stress
Fc= 0.81 × 1.2 × 1 × 0.44 = 0.427
Safe allowable load per meter length is q = 0.427 × 2 × 105 = 85
The values of slenderness ratio for effective length and height of the building is given in Table 4.1
Table 4.1 Values of slenderness ratio (Ref 10)
63 H L S.R H L S.R A 3.15 3.44 15.75 2.55 3.44 12.75 B 3.15 2.58 12.92 2.55 2.58 12.75 C 3.15 3.33 15.75 2.55 3.33 12.75 D 3.15 2.88 14.4 2.55 2.88 12.75 E 3.15 2.056 10.28 2.55 2.056 10.28 F 3.15 2.52 12.6 2.55 2.52 12.6 G 3.15 3.7 15.75 2.55 3.7 12.75 H 3.15 2.90 14.5 2.55 2.9 12.75 I 3.15 3.44 15.75 2.55 3.44 12.75 J 3.15 3.44 15.75 2.55 3.44 12.75 K 3.15 2.976 14.88 2.55 2.976 12.75 L 3.15 1.935 9.7 2.55 1.935 9.675 M 3.15 5.07 15.75 2.55 5.07 12.75
The values of stress reduction factor for slenderness ratio of the building is given in Table 4.2
Table 4.2 Stress reduction factor for slenderness ratio
Wall type Ground floor First floor
A 0.74 0.81 B 0.81 0.81 C 0.74 0.81 D 0.75 0.81 E 0.89 0.89 F 0.83 0.83 G 0.74 0.81 H 0.75 0.81 I 0.75 0.81 J 0.74 0.81 K 0.75 0.81 L 0.88 0.88
The calculation of permissible stress of the building is given in the Table 4.3
64
Fc=ks×kp×ka× basic compressive stress
Wall type Permissible stress- ground floor(N/mm2)
Permissible stress- first floor(N/mm2) A 0.528×0.74=0.390 0.528×0.81=0.427 B 0.528×0.81=0.427 0.528×0.81=0.427 C 0.528×0.74=0.390 0.528×0.81=0.427 D 0.528×0.75=0.396 0.528×0.81=0.427 E 0.528×0.89=0.469 0.528×0.89=0.469 F 0.528×0.83=0.4382 0.528×0.83=0.4382 G 0.528×0.74=0.390 0.528×0.81=0.427 H 0.528×0.75=0.396 0.528×0.81=0.427 I 0.528×0.75=0.396 0.528×0.81=0.427 J 0.528×0.74=0.390 0.528×0.81=0.427 K 0.528×0.75=0.396 0.528×0.81=0.427 L 0.528×0.88=0.4646 0.528×0.88=0.4646 M 0.528×0.75=0.390 0.528×0.81=0.427
The values of safe allowable load for the building is given in Table 4.4
Table 4.4 Safe allowable load Wall type q = fc×2×10 5 kN/m(ground floor) q = fc×2×105 kN/m(first floor) A 78 85.4 B 85 85.4 C 78 85.4 D 79.2 85.4 E 93 93.8 F 87.6 87.6 G 78 85.4 H 79.2 85.4 I 79.2 85.4 J 78 85.4 K 79.2 85.4 L 92 92 M 78 85.4
65 Load from Wall = 78
Load from wall (critical wall M) +10% for the weight of the Building + weight of slab (hall, bed room & dining) + floor finish
= 78 + 7.8 + 4.6575 + 4.125 + 4.5635 + 1 =100.236 =100 Factored load= 1.25 × 100=125 1. Area of Footing = = = 0.833 m2 Assume SBC = 150
Consider 1m Length room
2. Minimum Width = (2w+300) mm
= (2 x 200+300) = 700 mm Provide Width of P.C.C = 700 mm
It is customary to provide 150 to 300 mm P.C.C thickness Provide = 300 mm
The Projection of P.C.C beyond the brick work should not be more than ½ of the thickness of P.C.C
= = 150 mm
Actual work of Brick work = 700 – 300 = 400 mm Brick work projection beyond the wall
Depth of the Brick work = 200 x 2 = 400 mm
66
The thickness of each step is given by hollow brick = 200 mm The footing design is shown in the Figure 4.4
Fig.4.4 Footing Design 4.2.12 Design of Stair Case:
Length = 4 m Live load = 2
Rise = 150 mm
Thread = 250 mm Using M20 Concrete and Fe415
Step1: Calculation of self weight
Assume waist slab thickness = = 200 mm D = 200 mm
Self weight =
×
× 2 = 5.83 (4.6) Self weight is calculated by equation 4.6
67 D =Diameter
R =Rise T =Thread
Step 2: Calculation of load on waist slab
1. Assume 40 mm Floor finish Floor Finish = × 24 = 1 2. Weight of steps= × R × T × × 25 = 1.875 3. Live load = 3 4. Self weight = 5.83 Wu = 11.075 Wu=1.5 × 11.075 =17.55 Step3: Calculation of Mu Mu = = 35 kN.m Mu,lim = * + 35 × 106= 0.36 × 0.48(1-0.42 × 0.48) × 1000 × d2 × 20 d=113 mm
Assume Clear cover 20 mm Diameter of bar = 20 mm D= 113+20+10 = 143 mm D= 150mm (approximately) d= 150-20-10 = 120 mm
68 R = = 2.43 Ast = = 970.6 mm 2 Number of Bars = = 4 bars Ast actual = 4 × × 202 = 1256 mm2 Pt = × 1000 = × 1000 = 1.04%
Step 5: Check for deflection
Basic value = 20 Fs = 0.58fy = 0.58 × 415 × = 185.89
For Pt =1.04% , Modification factor = 1.2 (Fig 4 of IS 456-2000)
drequired = = = 104.166 mm dactual = 120 mm
Step 6: Providing distribution steel
Astmin= × = 480 mm 2 Spacing of 8mm diameter = × × 82 = 270 mm Main steel = 4No.s 20 bars
69
4.3 DESIGN OF SOLAR PANEL AND ITS COMPONENTS 4.3.1 Solar Power System Components
Brief revision of the major components found in a basic solar power system. A basic solar powered system is shown in Figure 4.5
Fig.4.5 Working of solar panels
The solar panel consists of solar regulator it is connected to DC storage battery and then DC is converted to AC by an inverter. AC can be directly used for the
appliances.
70
4.3.2 Working of solar panels
The solar panel converts sunlight into DC power or electricity to
charge the battery.
i. This DC electricity (charge) is controlled via a solar regulator which ensures the battery is charged properly and not damaged and that power is not lost/(discharged).
ii. DC appliances can then be powered directly from the battery.
iii. AC appliances need a power inverter to convert the DC electricity into 220 Volt AC power.
4.3.3 Description of individual solar power components
4.3.3.1 Solar Panels
Solar panels are classified according to their rated power output in Watts. Different geographical locations receive different quantities of average peak sun hours per day. As an example, in Tamil Nadu, the annual average is around 6am sun hours per day. This means that an 80W solar panel based on the average figure of 6 sun hours per day, would produce a yearly average of around 480W.H per day. Solar panel output is affected by the cell operating temperature. Panels are rated at a nominal temperature of 25 degrees Celcius. The output of a solar panel can be expected to vary by 0.25% for every 5 degrees variation in temperature.
4.3.3.2 Solar Regulator
The purpose of solar regulators, or charge controllers as they are also called, is to regulate the current from the solar panels to prevent the batteries from
overcharging. Overcharging causes gassing and loss of electrolyte resulting in damage to the batteries. A Solar regulator is used to sense when the batteries are fully charged and to stop, or decrease, the amount of current flowing to the battery. Most solar regulators also include a Low Voltage Disconnect feature, which will switch off the supply to the load if the battery voltage falls below the cut-off voltage. This prevents the battery from permanent damage and reduced life expectancy. Solar regulators are rated by the amount of current they are able to receive from the solar panel or panels.
71
4.3.3.3 Power Inverter
The power inverter is the main component of any independent power system which requires AC power. The power inverter will convert the DC power stored in the batteries and into Ac power to run conventional appliances. There are three waveforms produced by modern solid state power inverters. The simplest, a square wave power inverter, used to be all that was available. Today, these are very rare, as many appliances will not operate on a square wave. True Sine wave inverters provide AC power that is virtually identical to, and often cleaner than, power from the grid. Power inverters are generally rated by the amount of AC power they can supply continuously. Manufacturers generally also provide 5 second and ½ hour surge figures. The surge figures give an idea of how much power can be supplied by the inverter for 5 seconds and ½ an hour before the inverter‟s overload protection trips and cuts the power.
4.3.3.4 Solar Batteries
Deep cycle batteries are usually used in solar power systems and are designed to be discharged over a long period of time (e.g. 100 hours) and recharged hundreds or thousands of times, unlike conventional car batteries which are designed to provide a large amount of current for a short amount of time. To maximize battery life, deep cycle batteries should not be discharged beyond 50% of their capacity. i.e. 50 % capacity remaining. Discharging beyond this level will significantly reduce the life of the batteries. Deep cycle batteries are rated in Ampere Hours (Ah). This rating also includes a discharge rate, usually at 20 hours. This rating specifies the amount of current in Amps that the battery can supply over the specified number of hours. As an example, a battery rated at 120A.H at the 100 hour rate can supply a total of 120A.H over a period of 100 hours. This would equate to 1.2A per hour for 100 hours.
4.3.4 Designing of Solar Panel
Power rating of each appliance that will be drawing power from the system. Calculation of Loads
72
Table 4.5 Calculation Of Loads (Ref 12) PARTICULA RS ITEMS UNITS USAGE IN HRS VOLTA GE W CONSUM PTION INVER TORS HALL CFL (Ref 13) 4 5 20 400 80 FAN 2 5 50 500 100 T.V 1 5 80 400 80 BED ROOM 1 CFL 2 3 15 90 30 FAN 1 10 50 500 50 BED ROOM 2 CFL 2 3 15 90 30 FAN 1 10 50 500 50 KITCHEN OVEN 1 1 900 900 900 CFL 3 4 15 180 45 EXHAUS T 1 4 50 200 50 Mixer 1 1 450 450 450 DINING ROOM AUTO-FRIDGE 1 18 150 2700 195 CFL 3 4 15 180 45 FAN 1 3 50 150 50 TOILET 1 CFL 1 1 15 15 15 TOILET 2 HEATER 1 1 150 150 150 CFL 1 2 15 30 15 WATER PUMP 1 1 750 750 750 WASHING MACHINE 1 2 90 180 90 8365 3175
Power Invertor Sizing
Appliance total power draw = 3175 W
To provide a small buffer or margin your minimum size inverter choice should be around 3500W.
A modified sine wave inverter with a 3500W continuous power rating will therefore be your obvious choice in this specific solar system design.
Determining the Size And Number Of Solar Panels
Divide the total daily power requirement by the number of charge hours for that geographic region eg. (8365×1.2)\6=1673 WATTS
250 Watt Solar Panel
Total watt/ 250 watt solar panel =
=7 PANELS
= 7 x 250 W panels.
Number of Batteries
250W panels produce 4.8Amps, thus 14x 4.8 A = 67.2A x 6 Hrs = 403.2.Ah
105Ah batteries, should be discharged to no more than 50%, thus we divide total amps by 105A x 50% = 50A.h
= 8.08 x 105Ah batteries.
For ease of possible 24V or 48V configuration, this would mean 3 in series of 3 batteries.
Size of Regulators
Let‟s say we had 20A regulators at our disposal. One 250W panel produces around 4.8Amps. The regulators are put in series
14 x 4.8A=67.2
So 14 solar panels would need 4 x 20 A solar regulators .
Complete the solar power system Well we have the following:
i. 7x2x 250W solar panels ii. 4 x 20A solar regulators