• No results found

pile-design.xls

N/A
N/A
Protected

Academic year: 2021

Share "pile-design.xls"

Copied!
9
0
0

Loading.... (view fulltext now)

Full text

(1)

LARSEN & TOUBRO LIMITED

CONSTRUCTION GROUP

PROJECT:

IOCL-PANIPAT EXPANSION PROJECT(EPCC-V)

DOCUMENT NO. DATE

8/Feb/17

500 Dia Driven Cast-in-situ Pile

DESIGNED CHECKED PAGE

STRUCTURE: KKG 1

STRUCTURAL DESIGN OF WORKING PILE (FIXED HEAD)

1. DESIGN FOR VERTICAL LOAD WITH BENDING:

Diameter Pile D = 500.0 mm

Design Load ( Vertical) P = 70.0 MT Design Load ( Horizontal) 3.50 MT

Length of Fixity 5.37 m

Length of Pile above GL 0.00 m Total Moment Capacity of Pile

9.40 T.m

Actual Moment Capacity of Pile

Moment Correction Factor m = 0.82 ( As per IS 2911 (I - Sec 2 ) - 1979)

7.706 T.m Grade of Concrete M 35 35.0 N/mm2

Grade of Steel = Fe415

Nominal Cover d' = 75.0 mm Main Reinforcement: = 0.120 = 0.0264 d' / D = 0.15 From Chart 57 of SP 16 = 0.011 Percentage of Steel p = 0.39

* Area of Steel Required 7.559 Qg = Lf = L1 = Mf = Qg x (Lf + L1)/2 Mf = Ma = Mf x m Ma = Fck = Pu / FckB D Mu / FckB D2 p / Fck Asc = Cm2

(2)

500 Dia Driven Cast-in-situ Pile

STRUCTURE: KKG 2

2. DESIGN FOR TENSION WITH BENDING:

Design Tension Capacity N = 12.0 MT Actual Moment Capacity of Pile M = 7.71 T.m Main Reinforcement:

( As per "HAND BOOK FOR LSD OF REINFORCED CONCRETE MEMBERS" By V. K. GHANEKAR & J. P. JAIN )

Assume 1.5

Cross Sectional Area of Pile 196349.5 0.0262 0.0336

d' / D = 0.15

From Chart 2.1-F3 Pg 338:- 0.200 But

* Area of Steel Required

33.12

Hence Provide 11 - 20 tor bars as main reinforcement .

Lateral Ties:

Provide 8 tor ties at a spacing of least of the following:

a) 16 times the dia of main bar =16 x 20 = 320 mm b) 48 times the dia of lateral tie = 48 x 8 = 384 mm c) Least Lateral dimension of pile = 500 mm

Provide 8 tor ties at a spacing of 300mm c/c



= (c /1.5) x (Nu / Fck.Ac)



= (c /1.5) x (Mu / Fck.Ac.D) c = Ac= mm2



=



=

=

= (c /1.5) x (Atot * Fy / Fck.Ac) Atot =x Ac x Fck / ((c / 1.5) * Fy) Atot = Cm2

(3)

LARSEN & TOUBRO LIMITED

CONSTRUCTION GROUP

PROJECT:

EIRP FOR IOCL AT PARADIP

DOCUMENT NO. DATE

8/Feb/17

1000 DIA BCIS VETICAL LOAD TEST PILE

DESIGNED CHECKED PAGE

STRUCTURE: KBR 1

STRUCTURAL DESIGN PILE:

VERTICAL LOAD TEST PILE:

Diameter Pile D = 1000.0 mm

Design Load ( Vertical) P = 225.0 MT

Test Load 2 x P MT

450.0 MT

Grade of Concrete M 20 20.0 N/mm2

Grade of Steel = Fe415

Nominal Cover d' = 75.0 mm

Main Reinforcement:

= 0.225 = 0.0

d' / D = 0.075

From Chart 55 & 56 of SP 16 = 0.000

Percentage of Steel p = 0.000

* Area of Steel Required 0.000

Provide 12- 20 tor bars as main reinforcement (minimum)

Lateral Ties:

Provide 8 tor ties at a spacing of least of the following:

a) 16 times the dia of main bar =16 x 20 = 320 mm

b) 48 times the dia of lateral tie = 48 x 8 = 384 mm

c) Least Lateral dimension of pile = 1000 mm

Provide 8 tor ties at a spacing of 300mm c/c Pu = Pu = Fck = Pu / FckB D Mu / FckB D2 p / Fck Asc = Cm2

(4)
(5)

LARSEN & TOUBRO LIMITED

CONSTRUCTION GROUP

PROJECT:

EIRP FOR IOCL AT PARADIP

DOCUMENT NO. DATE

8/Feb/17

1000 DIA BCIS LATERAL LOAD TEST PILE

DESIGNED CHECKED PAGE

STRUCTURE: KBR 1

STRUCTURAL DESIGN OF PILE:

HORIZONTAL LOAD TEST PILE:

Diameter Pile D = 1000.0 mm

Design Load ( Horizontal) 4.50 MT (Free Head)

Test Load

9.00 MT

Length of Fixity 7.15 m (Free Head)

Length of Pile above GL 0.00 m

Total Moment Capacity of Pile

64.350 T.m

Grade of Concrete M 20 20.0 N/mm2

Grade of Steel = Fe415

Nominal Cover d' = 75.0 mm

Main Reinforcement:

= 0.00 = 0.032

d' / D = 0.075

From Chart 55 & 56 of SP 16 = 0.030

Percentage of Steel p = 0.60

* Area of Steel Required 47.124

Provide 6 - 25 + 6 - 20 tor bars as main reinforcement .

Lateral Ties:

Provide 8 tor ties at a spacing of least of the following:

a) 16 times the dia of main bar =16 x 20 = 320 mm

b) 48 times the dia of lateral tie = 48 x 8 = 384 mm

c) Least Lateral dimension of pile = 1000 mm

Provide 8 tor ties at a spacing of 300mm c/c

Qg = Qgu = 2 x Qg Qgu = Lf = L1 = Mf = Qgu x (Lf + L1) Mf = Fck = Pu / FckB D Mu / FckB D2 p / Fck Asc = Cm2

(6)

1000 DIA BCIS TENSION TEST PILE

STRUCTURE: kbr 1

STRUCTURAL DESIGN OF PILE:

TENSION LOAD TEST PILE:

Diameter Pile D = 1000.0 mm

Design Load ( Tension) T = 45.0 MT

Test Load 2 x T

90.0 MT

Grade of Concrete M 20 20.0 N/mm2

Grade of Steel = Fe415

Nominal Cover d' = 75.0 mm

Main Reinforcement:

Area of Steel Required

Allowable tensile stress 230.0

39.130

Hence Provide 13 - 20 tor bars as main reinforcement .

Lateral Ties:

Provide 8 tor ties at a spacing of least of the following:

a) 16 times the dia of main bar =16 x 20 = 320 mm

b) 48 times the dia of lateral tie = 48 x 8 = 384 mm

c) Least Lateral dimension of pile = 1000 mm

Provide 8 tor ties at a spacing of 300mm c/c

Tu = Tu = Fck = Ast = Tu / ft ft = N/mm2 Ast = Cm2

(7)

LARSEN & TOUBRO LIMITED

CONSTRUCTION GROUP

PROJECT:

IOCL-PANIPAT EXPANSION PROJECT(EPCC-V)

DOCUMENT NO. DATE

8/Feb/17

450 Dia Driven Cast-in-situ Pile

CHECKED PAGE

STRUCTURE: KKG 1

DETERMINATION OF LENGTH OF FIXITY (For Fixed Head Pile)

Diameter of Pile D= 500.0 mm

Grade of Concret M20 Fck= 35.00

E= 5000xsqrt( Fck) E= 295804

Moment of Inertia of Pile I= 306796

Length of Pile above GL 0.00 m

Safe Horizontal Capacity of Pile 3.50 MT

Lateral Deflection of Pile @ GL

Y=

12 x E x I

Allowable Deflection Y= 5.00 mm

Length of Fixity

537.49 Cm

Length of Fixity of Fixed head Pile 5.37 m

DESIGNE D N/mm2 N/mm2 Kg/Cm2 Cm4 L1= Qg= Qg x (L1 + Lf )3 Lf = ((Y x 12 x E x I) / Qg)1/3 - L 1 Lf = Lf =

(8)

450 Dia Driven Cast-in-situ Pile

STRUCTURE: KKG 1

DETERMINATION OF LENGTH OF FIXITY (For Fixed Head Pile)

Diameter of Pile D= 0.0 mm

Grade of Concret M20 Fck= 20.00

E= 5000x10 x Fck E= 223607

Moment of Inertia of Pile I= 0

Length of Pile above GL 0.00 m

Safe Horizontal Capacity of Pile 2.50 MT

Lateral Deflection of Pile @ GL

Y=

3 x E x I

Allowable Deflection Y= 5.00 mm

Length of Fixity

0.00 Cm

Length of Fixity of Fixed head Pile 0.00 m

D N/mm2 Kg/Cm2 Kg/Cm2 Cm4 L1= Qg= Qg x (L1 + Lf )3 Lf = ((Y x 3 x E x I) / Qg)1/3 - L 1 Lf = Lf =

(9)

LARSEN & TOUBRO LIMITED

CONSTRUCTION GROUP

PROJECT: DOCUMENT NO. DATE

DESIGNED CHECKED PAGE STRUCTURE:

References

Related documents

These statements are subject to many risks and uncertainties, including an adverse development of global economic conditions, in particular a decline of demand in our most

It was found that irradiation of austenitic stainless steels with nitrogen ions can be considered an effective way to increase the hardness and yield strength of steels in the

Each record represents one health service code claim by a specific primary care physician for a specific patient and provides information on the specific health service code

Electoral systems and agricultural support in OECD countries.” Paper presented at the 70th Annual Conference of the Midwest Political Science Association, April 12 – 15, 2012,

On the negative side, in Section 6, we show that there does not exist any asymptotic polynomial-time approximation scheme (APTAS) for the multiprocessor partitioned packing problem

Cilj optimizacije skladišnih procesa je povećati učinkovitost rada unutar skladišta, postići racionalniju pohranu robe na skladišne lokacije, te smanjiti troškove koji

Furthermore, when the interpolant has a linear denominator, we obtain a formula for the barycentric weights which is simpler than the one found by Berrut and Mittelmann [Matrices

Using a multiple case study approach, the qualitative research provided detailed information on allocation practices and understanding of how Impact Aid is used by school districts