DOWNTOWN CONSTRUCTION PROJECTS

JUNE 7, 2021 - Committee of the Whole

Wells-Williams Conversion

Downtown Utilities Improvement

(2)

DOWNTOWN CONSTRUCTION

April 2020 - August 2021

Wells - Williams Conversion Project

February 2021 - March 2023

Downtown Utility Improvement Project

November 2020 - April 2021

Downtown Core Streetscape Improvements

June - September 2021

Houser Way Project

rentonwa.gov/dcp

There are also ongoing private development and franchise utility relocations downtown

(3)

WELLS - WILLIAMS

CONVERSION PROJECT

Project Manager

Public Works, Transportation Division

KEITH WOOLLEY

(4)

WELLS-WILLIAMS: PROJECT GOALS

• Convert to Two-way Traffic

• Improve Mobility and Safety

• Update Urban Design and Streetscape

• Encourage Economic Development

Project Goals

(5)

NEPA

• National Environmental Protection Act

• Federal Funding Requirement

Organizations Visited

• City Center Advisory Board

• Downtown Partnership

• North Renton Neighborhood Assoc

Summary of Comments

• Supportive

• Concerns – Trees, Left Turns

CONTACT THE PROJECT

Open House #1 (June 2018)

• Project Overview

• Located at Farmer’s Market

Open House #2 (January 2019)

• Project Construction Impacts

• Located at Downtown Library

Door-to-Door

• Before Each Open House

• Mailers to All of Downtown

Public Outreach - Design Phase (pre-2020)

(6)

Phone Calls to All Business

• 196 Businesses in April

• 22 Businesses Specifically re: Closures

Zoom One-on-One Mtgs

• Businesses with Sidewalk Work

• Phone Calls / E-mails As Needed

Bi-Weekly Zoom Open Office Hours

• Hosted by Project Manager

CONTACT THE PROJECT

Business Zoom Mtgs (2)

• May 7, 2020

• July 28, 2020

Bi-Weekly Construction Flyers

• Approximately 840 subscribers

• Also Posted to Project Webpage

Weekly E-mails

• Approximately 840 subscribers

• 160 Businesses – Closure Specific

Public Outreach – Construction Phase (2020-2021)

(7)

Parking Downtown

(8)

PRELIMINARY CONSTRUCTION PHASING

Construction Phases

• Utility Work

― S 3 rd St - Water, Storm

― S 2 nd St - Water, Sewer

• New Traffic Signals

• S 3 rd Street Intersections / Sidewalks

S 2 nd Street Intersections / Sidewalks

• Paving and Two-Way Conversion

• (Substantial Completion)

(9)

PRELIMINARY CONSTRUCTION PHASING

Utility Work S 3 rd Street

Seattle Water Line (2x) 12” Water Line

12” Stormwater Line Stormwater Structure

(10)

PRELIMINARY CONSTRUCTION PHASING

Utility Work S 2 nd Street

12” Water Line 12” Water Line

12” Sewer Line Under Comm 72” Sewer Structure

(11)

Signal Work

Conduit Poles / Foundations

Controller and Service Cabinets Wiring Install

(12)

S 3 rd Street Intersections – March/April 2021

Wells Ave S

Raised

Concrete

Intersections

(13)

S 3 rd Street Intersections

Pouring

Concrete

(14)

S 3 rd Street Sidewalks –

May/June

2021

(15)

S 3 rd Street – Nature of Sidewalk Work Challenges

Roof Drains Signal Conduit Fiber Conduit Irrigation

Buried Sidewalks “Coal Chutes” Abandoned Foundations Franchise Utilities

(16)

S 2 nd Street – South Halves – Mid June 2021

S 2nd St S 2nd St

ONE WAY ONE WAY

Stop

Stop

Stop

(17)

S 2 nd Street – North Halves – Late June 2021

S 2nd St S 2nd St

ONE WAY ONE WAY

Stop

Stop

Stop

(18)

S 2 nd Street

Partially Completed Driveways/Curb/Gutter

(19)

Final Paving and Two-Way

Conversion

• HMA Asphalt

• Signing, Striping

• Signal Activation

• All-Way Stops:

S 5 th St

N & S Riverside

(20)

Schedule Next Three

Months

June (early)

• S 3 rd St Sidewalk

June (mid-late)

• S 2 nd St Southside Intx

June/July

• S 2 nd St Northside Intx

July

• S 2 nd St Sidewalks

• HMA Asphalt

August

• Striping

• Street Furnishings

• Landscaping

• Signing

• Two-Way Conversion

(21)

Houser Way Project June – Sept 2021

• New Sidewalks

• New Asphalt Intersections

• 12” Waterline in Williams

(Casing Already Installed Under BNSF)

• Revised Storm System

(Already Installed Under BNSF)

• Lighting, Landscaping

(22)

DOWNTOWN UTILITIES IMPROVEMENT PROJECT

Project Manager Public Outreach Liaison

Public Works,

Utilities Division

ANN FOWLER, PE

(23)

Approximately 3,300 feet of new domestic

(drinking) water lines

WATER

Approximately 8,000 feet of new and rehabilitated sewer

pipes

WASTEWATER

Approximately 5,600 feet of new

stormwater pipes

SURFACEWATER

The replacement of curbs, gutters, sidewalks and ramps

where impacted by new utilities

CURB & GUTTER

G E N E R A L P R O JE C T D E T A IL S

(24)

PROJECT TIMELINE

Project Bid

Nov 2020

Construction Contract Award to SCI Construction, Inc.

Award Construction

Management Agreement to Murraysmith

Utility Coordination

Jan 2021

Pre-Construction Meeting

Contractor Submittals

Contractor Mobilization

Construction Survey

Utility Locates

Layout

Feb 2021

Start of Construction

Mar 2021

Construction Planned to be complete per

contractor's schedule *

Sept/Oct 2022

Contract

Completion Date

Mar 2023

We are here

* Contractor's schedule subject to change

(25)

PUBLIC OUTREACH

Continuous project updates​

⚬ Weekly construction updates on webpage​

⚬ Weekly email updates on project information and construction progress​

⚬ Quarterly newsletters of overall project progress and next steps​

Additional webinars will be announced throughout project milestones​

One-on-one meetings can be scheduled with project staff​

Dedicated on-site office hours to connect with City Staff​

Project hotline for general concerns, questions and immediate issues​

Signage to direct people to businesses located within and surrounding the work zones.​

BEING THE BEST NEIGHBOR WE CAN BE

M A R A P R M A Y J U N J U L F A L L 2 0 2 2

OUTREACH ENGAGEMENT

3/1/2021

INITIAL PROJECT MAILER

3/11/2021 FIRST PROJECT WEBINAR

3/26/2021 WALK & KNOCK INITIAL PROJECT INTRO

4/15/2021 WALK & KNOCK SHATTUCK AVE S

4/28/2021 CLOCK TOWER MOVE NOTICE

ONGOING WEEKLY NEWSLETTER UPDATES COORDINATED WITH THE WELLS-WILLIAMS PROJECT UPDATES 3/15/2021

BUILDING SURVEY NOTICE

Virtual Office Hours every other Friday

from 1-1:30 p.m.

Next scheduled date 06/18/2021

EARLY JUNE

UPDATED PROJECT MAILER

5/17/2021 RDP BOARD PRESENATION

5/18/2021

LUTHER'S TABLE BOARD MTG

5/21/2021

UPDATED CLOCK TOWER POSTER

(26)

WHAT TO EXPECT

CONSTRUCTION IMPACTS DURING UTILITY WORK • 7am-6pm construction hours

• Limited overnight or earlier start times work is expected in limited circumstances

⚬ During the Farmer's Market, work hours on Tuesdays are from 5am - 12pm for work near the Market

⚬ Overnight work is expected for the sewer tie-in at the intersection of Rainier Ave S and S 3rd St

• Equipment will stay in work zones overnight

WORK HOURS

• While we are installing multiple utilities in the same street, the work cannot occur at the same time.

• In general, installation must occur from deepest utility to shallowest utility due to trench widths/depths (i.e. sewer, storm, water)

⚬ Generally sewer is deepest and installed first

• Sewer and storm are installed from the downstream elevation to the upstream elevation (i.e. deep to shallow)

⚬ Sewer and storm do not always follow the same flow. It is dependent upon the connection point or outfall. For example, in S 3rd St:

■ Sewer flows from west (upstream) to east (downstream)

■ Storm flows from east (upstream) to west (downstream)

MULTIPLE UTILITIES

(27)

TRAFFIC IMPACTS

• Block by block sections of S 3rd Street will be closed to vehicle access during the working day

⚬ Closure of each section is expected to last approximately 2-4 weeks

⚬ Traffic detours will be in place directing traffic south on Shattuck Ave S and east on S 4th St

⚬ Businesses along S 3rd St can be accessed via Morris Ave S and Smithers Ave S

• Where possible, a minimum of 1-lane of traffic will be open at all times

⚬ During construction hours, detours will be established when traffic cannot safely proceed through the work zones

⚬ Additional lanes may be open after construction hours when possible and safe

⚬ Detour and traffic signs will signal vehicle re-routes and access

TRAFFIC MANAGEMENT

S 3RD ST ROAD CLOSURE

CLOCK TOWER

Detour Route - Bypass Traffic Business Access Routes

Current Street Closure Upcoming Street Closure

(28)

SEQUENCE OF WORK (2021)

SPRING - SUMMER

Dewatering Wells on S 3rd St

Storm install on Shattuck Ave S between S 3rd St and S 2nd St

SUMMER - FALL

Sewer Install on S 3rd St from Burnett Ave S to Rainier Ave S

Sewer Install by Safeway

SPRING

Work between Houser Way S and Bronson Way S on Mill Ave

Storm work on Shattuck between S 4th Pl and S 3rd St

Sewer install on S 2nd St between Burnett Ave S and Logan Ave S

Storm install on S 3rd St between Rainier Ave S and Shattuck Ave S

SUMMER

Rainier Ave S & S 3rd St Intersection Work

Storm install on S 2nd St

FALL

Sewer work on Shattuck Ave S , Whitworth Ave S and Morris Ave S

Sewer work on S 2nd St

*

UTILITY WORK COMPLETE -

RESTORATION TO BE COMPLETED Arrow Indicates general direction *

of construction flow for the utility

*

*

(29)

SEQUENCE OF WORK (2022)

WINTER - SPRING

Trenchless Sewer throughout project area (low impact)

WINTER - SUMMER

Water work on S 2nd St, S 3rd St, Shattuck Ave S, and Whitworth Ave S

SUMMER - FALL

Grind and Overlay, Channelization FALL 2021 - WINTER

Storm work on S 3rd St between Smithers Ave S and Shattuck Ave S

Storm work on Whitworth Ave S and Morris Ave S

(30)

COMMENTS OR QUESTIONS

WEBSITES

rentonwa.gov/dcp rentonwa.gov/ww rentonwa.gov/duip

EMAILS

[email protected] [email protected]

PHONE

(425) 363-1007 Project hotline

SURVEY

rentonwa.gov/duips1

(31)

DOWNTOWN RENTON CONSTRUCTION

rentonwa.gov

(32)

S 2nd St – Detours (Half Intersection Closures)

References

Related documents

In summary, the evidence suggests that the increase in the proportion of female single parent households with children can help explain the labor market phenomenon (higher labor

Office of the Attorney General at the California Department of Justice Career opportunities and information about internship programs.. Federal

did not inspect this property during construction and that VA assistance with construction complaints will be limited to defects in equipment, material and workmanship reported

isključivo za proizvodnju električne energije. U svjetskoj su proizvodnji električne energije.. hidroelektrane najveći proizvođač među obnovljivim izvorima energije. S oko 20

The work of mechanical engineers includes, but is not limited to, the following areas: machinery design and construction, design and analysis of thermal systems,

construction of a variety of projects, such as laminates and small furniture construction. Projects may include, but are not limited to: bowl making, designer boxes, advanced pen

If you submit your Accelerated Nursing application before admission to the University, it is essential that you notify [email protected] of your UW Oshkosh student ID number and