• No results found

DSP Data and System Planning

N/A
N/A
Protected

Academic year: 2021

Share "DSP Data and System Planning"

Copied!
23
0
0

Loading.... (view fulltext now)

Full text

(1)

DSP – Data and System Planning

Rotterdam 10th June 2015

10:30 12:00

Marco Fehmer, DSP General Manager

PROCESS AUTOMATION PROJECT: DRIVERS OF THE CHANGE AND RISK

MANAGEMENT TO MAKE THEM SUCCESSFUL

(2)

Nice to meet you

Marco Fehmer

DSP - General Manager

Since 1986, DSP provides IT solutions and business operations consultancy for the shipping industry.

DSP is a certified NAVIS Implementation Partner and First Line Support Centre

DSP is active on international TOS projects and collaborates with industry key players

(3)

Nice to meet you

NAVIS TOS Professional Services

 Project Management

 Data migration

 Installation and Configuration

 Product Training and Best Practice

 Go-Live assistance

Field Development

 Operations Shadowing

 First line Maintenance & Support  NAVIS SPARCS Optimisation: Prime

Route, Expert Decking,

Autostow

Automation Integration

EDIconfiguration

Operations Consultancy

 Business Process Analysis (BPM)

ROI evaluation of innovation projects

Project Auditing

Software Engineering & IT Services

Gap Analysis

SAP management  Software solutions  Hardware Sizing

(4)

Drivers for process automation

SAFETY

COST SAVING

STANDARDISATION

PRODUCTIVITY

PROCESS CONTROL

EFFICIENCY

DAMAGE REDUCTION

SECURITY

VISABILITY OF ASSETS

(5)

Automation is not (yet) a standard

Equipment Fleet

Solution and Architecture

Products

Process

Drivers

(6)

Return of investment .. a matter of time

Hidden Cost

shall be discovered

Project

Budget

are different, sometimes a small investment returns

the highest value

Time plays an important role as technology is evolving extremely fast

Requirements

and

Drivers

can change during the project lifecycle Automation could cross multiple functions and increase the number of

(7)

Multi Discipline Project Team

Automation • Project Manager • Solutions Consultant • Field Engineers • Product Developers TOS • Project Manager • Consultants • Product developers Terminal • Project Manager • Process Analyst

• Operations Key Users • IT Engineers • Technical Engineers Equipment • Project Manager • Field Engineers • Product developers

(8)

Approach

1

Requirements

2

Consolidation

3

Integration

4

Go Live

End-to-end process tests Training Procedures approval Soft Go Live Collect Functional and

Technical Requirements Design of Business Process Exeptions Handling Vehicle Survey Asset Survey Wi-Fi Coverage Configuration Development of solution Installation Cabling

Purchase and Delivery

Tuning of

operations process Tuning of solution Handover to

(9)

Main Challenges

Day by day business. Automation Process is often applied to

working

terminal

Automation may require deployment of

new IT architectures

(i.e. Wi-Fi)

Automation

Firmware

compliancy with terminal infrastructure (i.e.

network) shall be verified

Fleet of

Equipment

(TT, RTG, SC, QC, …) could be not

homogenous and some could be de-scope from project

TOS configuration can be affected by automation and new business

process

shall be designed and tested

Project Governance shall be clearly identified as well as delivery

interdependency

(10)

ICTSI Tecplata

LSCT La Spezia Container Terminal

(11)

Click to edit Master title style

TecPlata, Argentina

450.000

TEU 600 m quay

4

Quay Gantry Cranes

9

RTG

18

Terminal Tractors

5

Reach Stackers

Sparcs

N4

2.5.8

E

xpert

D

ecking

(12)

Operational Targets

12

 Automatic confirmation of the container position

 Automatic identification of the Lift – Set  Auto Job Promotion of the WI

 Real time actualisation of NAVIS Prime Route

 Real time position of all the Terminal equipment and external trucks

* SmartLift * SmartStack * SmartPath * SmartMap

(13)

Click to edit Master title style

11 June 2015 13

 Achieve safe and seamless Terminal

operations

 Increase operational efficiency by reducing time in every single automated process

 Provide a secure integrated solution which will practically eliminate risk of pilferage or fraud

 Have a very positive impact in our service delivery

(14)

Hardware installation

 TECPLATA hired Cargotec Argentina for the installation

 KALMAR created installation guides of every sensor installed

 RTLS and DGPS infrastructure installed

 Sensors and CrossCore were installed on RTGs, RS, EH & TT

 Kalmar consultant on-site assisting in the process Software installation

 Kalmar consultant made initial server installationo n-site, completed remotely

 First SW installation on CHEs was made by Kalmar consultant on-site, remaining CHEs have been made by TECPLATA

resource

 Fine SW tuning on CHEs was made remotely by Kalmar Finland

(15)

Click to edit Master title style

Hardware Commissioning

 Hardware installation/configuration verified

 Integration of CHEs & MTS

 Tested all CHEs

 Result analysed and adjusted

 TECPLATA acceptance

System Integration

 Integration SmartPort – TOS N4

 Kalmar consultant worked closely with Navis

 Soft Go Live, moving real containers in production enviroment

 Variation detected and repaired

 Integration final test

(16)

 Kalmar provided on-site support for the Go-Live

 The complete solution was tested to ensure that the system operated properly and

accurately

 Trained TECPLATA personnel and shadow

assistance as the users begun to use the systems

 Split into one week of preparation and one week of production support.

 After the Go Live was completed, Kalmar

support team started to assist the Terminal

(17)

Learned Lessons

 Automation is not a plug & play

Same team

of consultants during the project lifecycle is an advantage

 The integration between

KALMAR-NAVIS was the key factor of the

decision of TECPLATA. The solution has been customized to fulfill

TECPLATA expectations

 Working with local partner

(Cargotec-Argentina) for completion of installation on all CHE was

(18)

Lessons Learned

 Before installation of the solution, the

operations team should be familiar with the use of EC and PrimeRoute

 The implementation team should be a mix of operations, IT and maintenance

Project Manager:

 70/80% of his time

 Being part of Ops staff and with an operation mindset was an advantage

 The PM should know and understand the process to be automated

 During the Project, the training of the

operators consumed a considerable amount of hours

(19)

La Spezia Container Terminal, Italy

1.2

Million TEU

Over 2000 m quay

11

Quay Gantry Cranes and

7

Mobile Cranes

12 RTG

8

RMG

(20)

Postion Detection System

Automated since ‘90s

Transponder, sensors TOS DGPS RMG RTG

(21)

Targets and Benefit

 Increase reliability of container locations – no more lost containers!

 Speed up of rehandling operations under RMG/RTG with no manual input of

container numbers and/or positions

 The effective return is coming from the TOS that shall apply the right and desired business logic.

 Expert decking manages automatic rehandling decking

(22)

Lessons Learned

 Keep it

simple

: requirements and technology

 This was mainly an operations and technical project

Training:

all drivers shall be trained and made aware of the new procedure

(23)

Thank you for your attention!

Contact us:

www.dspservices.ch

[email protected]

References

Related documents

This course will examine selected legal issues relating to the evolving area of electronic commerce, including legal aspects of information management in an electronic environment..

The assumption informing this paper is that if professionals’ code of ethics is founded on Afro-Kantian ethics then our society can hope to have responsible and

The consultant will work with a Planning Committee, made up of members of the Board, BSP leadership team, and the Executive Director, on the details of the strategic planning process,

Together this indicates that the representation of gender was based on both grammatical and stereotypical information as the female stereotyped role names heightened the agreement

If the aircraft is required at any time during its flight to have a minimum reserve fuel of 30°/0 of trip fuel remaining, the minimum fuel amount after 2hr is:?. The Route MORA

Mapping Tools Consultant Fees FTPS Software Encryption Software Software Certificate X-12 Ver?. 3040 Mapping Tools Consultant Fees Consultant Fees Consultant

Mapping Tools Consultant Fees FTPS Software Encryption Software Software Certificate X-12 Ver.. 3040 Mapping Tools Consultant Fees Consultant Fees Consultant

Mapping Tools Consultant Fees FTPS Software Encryption Software Software Certificate X-12 Ver.. 3040 Mapping Tools Consultant Fees Consultant Fees Consultant Fees