AOP08 Implement Airport Airside Capacity Planning Method

In document European Single Sky ImPlementation (Page 92-96)

ESSIP Plan Edition 2012

Safety : Capacity planning can be organised to prevent traffic overload and contributes therefore to safety of operations.

Capacity : Provision of a plan in time to adapt local capacity to demand.

Cost-effectiveness : Optimisation of remedial actions to local capacity constraints in function of costs. Compared to possible shortfalls in

capacity and thus generating huge costly delays this capacity planning method itself is cost efficient.

Environment : Allows remedial actions to be considered in relation to environmental aspects. Efficient capacity planning contributes to

environmental benefits.

Security : N/A

Detailed SloA descriptions

AOP08-ASP01 Contribute to AOP08-APO01 to 03 as part of the stakeholder team to the five

year rolling capacity planning process. Start:06/2006 Finish:12/2015

Action by : ANS Providers

Description & purpose : Participate to the round-table exercise and share of ANSP expertise in order to target constraints and look for remedial actions.

Supporting material(s) : EUROCONTROL - Airside Capacity Enhancement (ACE) Implementation Manual - Edition 1.0 / 14-10-2003 EUROCONTROL - Enhancing Airside Capacity - the Complete Guide - Edition 2.0 / 15-09-2003

Url : http://www.eurocontrol.int/airports/public/standard_page/ace_library.html

Finalisation criteria : Proven record that ANSP contribute to the annual round-table exercise to determine capacity requirements and identify constraints and remedial actions.

AOP08-APO01 Conduct annual baseline capacity assessment with a view to update the 5-year

rolling capacity planning period Start:01/2006 Finish:12/2015

Action by : Airport Operators

Description & purpose : Assess airside capacity for capacity planning purposes, at least once a year to determine baseline capacity potential. This should be done in accordance with the assessment method described in AOP01.2. With a view to reduce costs either one of the two capacity assessments undertaken in the context of EC regulation 793/04 may be used.

Supporting material(s) : EUROCONTROL - Airside Capacity Enhancement (ACE) Implementation Manual - Edition 1.0 / 14-10-2003 EUROCONTROL - Enhancing Airside Capacity - the Complete Guide - Edition 2.0 / 15-09-2003

Url : http://www.eurocontrol.int/airports/public/standard_page/ace_library.html

EUROCONTROL - Measurement of Pilot Reaction Times and Runway Occupancy Times - The complete Guide - Edition 1.0 / 14-10-2003

Url : http://www.eurocontrol.int/airports/public/standard_page/ace_library.html

Finalisation criteria : - Annual baseline capacity assessment completed in accordance with method described in AOP01.2. - Capacity constraints are identified and remedial actions agreed upon with airport partners.

- Contribution of the airport partners recorded.

AOP08-APO02 Conduct annual assessment of future capacity requirements Start:01/2006 Finish:12/2015

Action by : Airport Operators

Description & purpose : Determine on a rolling 5 year basis what demand and consequently what capacity is required to cater for the identified demand.

Supporting material(s) : EUROCONTROL - Airside Capacity Enhancement (ACE) Implementation Manual - Edition 1.0 / 14-10-2003 EUROCONTROL - Enhancing Airside Capacity - the Complete Guide - Edition 2.0 / 15-09-2003

Url : http://www.eurocontrol.int/airports/public/standard_page/ace_library.html

EUROCONTROL - Measurement of Pilot Reaction Times and Runway Occupancy Times - The complete Guide - Edition 1.0 / 14-10-2003

Url : http://www.eurocontrol.int/airports/public/standard_page/ace_library.html

Finalisation criteria : Annual assessment of future capacity requirements completed.

AOP08-APO03 Apply Airside Capacity Planning method for a five year rolling period. Start:06/2006 Finish:12/2015

Action by : Airport Operators

Description & purpose : Apply the step by step structured method that leads to identifying constraints for future growth, remedial activities versus cost and capacity improvements of each of the mitigation actions

AOP08

Implement Airport Airside Capacity Planning Method

ESSIP Plan Edition 2012

Supporting material(s) : EUROCONTROL - Airside Capacity Enhancement (ACE) Implementation Manual - Edition 1.0 / 14-10-2003 EUROCONTROL - Enhancing Airside Capacity - the Complete Guide - Edition 2.0 / 15-09-2003

Url : http://www.eurocontrol.int/airports/public/standard_page/ace_library.html

EUROCONTROL - Measurement of Pilot Reaction Times and Runway Occupancy Times - The complete Guide - Edition 1.0 / 14-10-2003

Url : http://www.eurocontrol.int/airports/public/standard_page/ace_library.html

Finalisation criteria : Airside capacity planning method applied.

AOP08-USE01 Contribute to AOP08-APO01 to 03 as part of the stakeholder team to the five

year rolling capacity planning process. Start:06/2006 Finish:12/2015

Action by : Airspace Users

Description & purpose : Participate to the round-table exercise and share of aircraft operator's expertise in order to target constraints and look for remedial actions.

Supporting material(s) : EUROCONTROL - Airside Capacity Enhancement (ACE) Implementation Manual - Edition 1.0 / 14-10-2003 EUROCONTROL - Enhancing Airside Capacity - the Complete Guide - Edition 2.0 / 15-09-2003

Url : http://www.eurocontrol.int/airports/public/standard_page/ace_library.html

EUROCONTROL - Measurement of Pilot Reaction Times and Runway Occupancy Times - The complete Guide - Edition 1.0 / 14-10-2003

Url : http://www.eurocontrol.int/airports/public/standard_page/ace_library.html

Finalisation criteria : On annual basis, capacity requirements are identified and fed to the local Airport Authority

PAGE LEFT INTENTIONALLY BLANK

SESAR Active APT

AOP09

Implement Optimised Dependent Parallel Operations

REG ASP MIL APO USE INT IND

ESSIP Plan Edition 2012

Description & purpose

The purpose of this operational change is to increase utilisation of the parallel runway operations. It aims at reducing dependencies between the runways by implementing more accurate surveillance techniques and controller tools as well as associated procedures. Capacity gains can be achieved by increased utilisation of the combined runways. Dependencies between multiple runways determine the practical runway capacity which in most cases is lower than the combined single runway capacities.

Applicable area(s) Operational capability dates FOR THIS OBJECTIVE

Initial operational capability: 12/2012 Refer to the airports list

Full operational capability: 12/2015

References

European ATM Master Plan relationship

OI step - [AO-0403]-Optimised Dependent Parallel Operations

Applicable legislation

Council Decision of 30 March 2009 endorsing the European Air traffic Management Master Plan of the Single European Sky ATM Research (SESAR) project (2009/320/EC)

Commission Implementing Regulation (EU) N° 1034/201 1 of 17 October 2011 on safety oversight in air traffic management and air navigation services and amending Regulation (EU) N° 691/2010 1 8-10-2011

Applicable ICAO Annexes and other references

ICAO Annex 10 - Telecommunications ICAO Annex 14 - Aerodromes

EUROCONTROL - ESARR 4 - Risk Assessment and Mitigation in ATM

Stakeholder Lines of Action (SloA )

SloA ref. Title Start Finish

AOP09-REG01 Approve the procedures for optimised dependant parallel operations 01/2012 12/2015

AOP09-REG02 Conduct safety oversight of the changes 01/2012 12/2015

AOP09-REG03 Certify and deliver operational approval 01/2012 12/2015

AOP09-ASP01 Upgrade and put into service surveillance systems to support optimised dependent parallel operations

01/2012 12/2015

AOP09-ASP02 Upgrade and put into service ATS systems to support optimised dependent parallel operations

01/2012 12/2015

AOP09-ASP03 Develop and validate procedures for optimised dependant parallel operations

01/2012 12/2015

AOP09-ASP04 Develop safety assessment for the changes 01/2012 12/2015

AOP09-ASP05 Train operational and technical staff 01/2012 12/2015

AOP09-ASP06 Revise and publish Aeronautical Information documents 01/2012 12/2015

AOP09-USE01 Obtain airworthiness certification 01/2012 12/2015

AOP09-USE02 Obtain operational approval 01/2012 12/2015

AOP09-USE03 Update training manual and train crew 01/2012 12/2015

▲ Applicable to the military.

Description of finalised SLoAs is available on the EIPR website at http://www.eurocontrol.int/articles/essip-plan/