Next Stage maintained a log of design decisions, numbered similarly to action items and issues, but with a DA prefix for Site/Civil, DB for Structural, etc.

Decision Log

As Of December 02, 1998 Project Progress Meeting Revised: 12.14.98 Date Originated-Item

No. Item Description Decision

By

Decision Date A. Site/Civil

DA07.15.98.01 Retain the services of a TAS Accessibility Specialist.

NS:RT 07.15.98 DA07.15.98.02 There will be multiple collection points for

storm and sanitary drainage around the building (IA07.01.98.03).

CHPA:GP HA:JR

07.15.98

DA07.29.98.01 Specify same site and parking lighting fixtures as Lone Star Park, unless not feasible or too costly.

NS:RT 07.29.98

DA07.29.98.02 Barrier Free Texas selected as Accessibility Specialist.

NS:RT/ELS :KS

07.29.98 DA07.29.98.03 Uncertain timetable does not allow taking

borrow material from existing sewer contractor.

NS:RT 07.29.98 DA08.12.98.01 Use existing lighting for Road D, rewired for

new/joint operation with Lone Star Park.

NS:RT 08.12.98 DA08.12.98.02 Grading permit approval does not require

architectural document submission.

ELS:DF 08.12.98 DA08.26.98.01 Roadway and building relationships are not

affected by the commissary.

HA:JR 08.26.98 DA08.26.98.02 Commissary Scheme A selected (reversal from

Scheme B).

NS:BC 08.26.98 DA08.26.98.03 Roof drain overflow to be piped into primary

drainage system.

CHPA:GP 08.26.98 DA09.09.98.01 Commence geotechnical exploration/drilling of

LSP borrow material.

NS:RT 09.09.98 DA10.07.98.01 Utilize 55 foot light poles in parking area. TEE:CS 10.07.98 DA11.04.98.01 If GPISD material is available at the start of

construction, then will make an offer for subgrade material for automobile parking.

NS:RT 11.04.98

B. Structural

DB07.15.98.01 Cantilever balcony structure is not practical nor feasible; cross aisles raised to make cantilever work.

JA:HW KS:ELS

07.15.98 08.26.98 DB07.29.98.01 Tapered beams will be utilized to support the

balcony.

HW:JA/

ELS:KS

07.29.98 DB08.12.98.01 There will be no electrical point loads in the

structure greater than 500 lbs (AB07.01.98.08).

TEE:CS 08.12.98 DB08.12.98.02 Design criteria for building exterior will be

based upon wind tunnel test results (AB07.01.98.14).

HW:RT 08.12.98

DB08.12.98.03 Resolved audience reduction and box beam loads and location.

ELS:KS / AA:AS

08.12.98 DB08.12.98.04 Proceed with structural design based upon

existing perimeter envelope and seating platform.

NS:RT 08.12.98

DB08.12.98.05 Extend four week steel fabrication schedule from 4 weeks to 6 weeks (IB07.15.98.03 / AB08.12.98.01).

HSC:JK 08.12.98

DB08.12.98.06 Resolved low roof impact on structural design by selecting concession scheme 'B'. Reversed to Scheme A.

NS:BC NS:BC

08.12.98 08.26.98 DB08.12.98.07 Project will not start construction 09.15.98;

and, will not utilize warehouse steel.

NS:RT 08.12.98 DB08.12.98.08 Acceptable construction tolerance on seating is

1/2" per riser, platform to platform.

ELS:KS 08.12.98 DB09.09.98.01 Initial steel mill order must be made 1 month

prior to start of construction.

HSC:JK 09.09.98 DB09.23.98.01 Complete 3D model check; hold-up connection

study, detailing, and, trans-mission of 3-D model until resolution of potential seating layout change.

NS:RT 09.23.98

DB10.07.98.01 Eliminate CMU walls at FOH mechanical rooms due to revised AHU layout.

JHSA:RL 10.07.98 DB12.02.98.01 Revise column locations at rear of stage house

to center the door.

BC:NS 12.02.98

C. Enclosure/Architectural

DC07.01.98.01 Construction/shop drawings not necessary to provide GMP for exterior wall enclosure.

CC:SC 07.01.98 DC07.15.98.01 There is not a food service requirement for

louvers (IC07.01.98.05).

CHPA:GP 07.15.98 DC07.15.98.02 The site has a "quiet area" designation relating

to outside area noise.

JHSA:RL 07.15.98 DC07.15.98.03. GMP for roof can be provided without having

the roof design completed.

PC:TZ 07.15.98

DC08.12.98.01 Walls to be rated R20 & Roof R30 Insulation (IC07.15.98.01 / AC08.12.98.02).

CHPA:GP LCC:BP

08.12.98 DC08.26.98.01 R30 Roof and R20 Wall will be the thermal

transmission ratings used.

08.26.98 DC08.26.98.02 Roof design by Pacific to follow Crown Corr

drawings.

PC:TZ 08.26.98 DC10.07.98.01 Can specify custom metal panel colors based

upon nominal price increase.

NS:RT 10.07.98

D. Mechanical/Electrical/Plumbing/Fire Protection

DD07.15.98.01 TEE:CS to participate in evaluating online project management approach.

TEE:CS 07.15.98 DD07.29.98.01 FE:WMcD to participate in evaluating online

project management approach.

FE:WMcD 07.29.98 DD08.12.98.01 The raceway loads will not affect structural

point loading (AD07.01.98.13).

TEE:CS HW:RT

08.12.98 DD08.12.98.02 Location of main electrical room and electronics

storage will maintain existing relationship.

TEE:CS LCC:MI

08.12.98 DD08.12.98.03 The back of the house will be a no smoking

area.

NS:BC 08.12.98 DD08.12.98.04 Utilize 75 KVA as added electrical load from

commissary.

TEE:CS 08.12.98 DD08.26.98.01 Proceed with concession/commissary MEP design based on

current 08.26.98 consultant concept/interim design criteria.

08.26.98 DD08.26.98.02 HVAC design is to be per ASHRAE standards,

as shown in current Project System Description.

CHPA:GP 08.26.98 DD08.26.98.03 Provide individual climate control in suites. NS:BC 08.26.98 DD09.09.98.01 Smoking area includes suites and select

concession areas (Rooms 123,124)

NS:BC 09.09.98 DD09.23.98.01 Proceed with 21,000 cfm lobby smoke exhaust

as opposed to a house/lobby rated separation.

NS:BC,ELS :KS CHPA:GP

09.23.98

E. Theatrical/Interiors

DE07.01.98.01 NC 25 accepted as design criteria. JHSA:CJ 07.01.98 DE07.29.98.01 Provide suite level public toilet rooms; eliminate

toilet rooms in suites, but provide infrastructure MEP.

NS:RT 07.29.98

DE07.29.98.02 Provide expanded commissary kitchen and support areas.

NS:RT 07.29.98 DE08.26.98.01 Sound and lighting control house mix position

cannot be moved into rear aisle due to

handicapped seating quota. This room requires the size shown on sketch current as of 08.26.98.

JHSA:DR ELS:KS

08.26.98

DE09.23.98.01 Box Booms will be rigged. NS:BC 09.23.98 DE10.07.98.01 Change seating configuration to curved format. NS:RT 10.07.98 DE10.07.98.02 Provide proscenium deluge system with opaque

curtain.

NS:RT ELS:KS

10.07.98 DE10.07.98.03 There will not be a front balcony projection

position.

NS:BC 10.07.98 DE10.07.98.04 Eliminate the rigging pit due to revised

counterweight design.

AA:AS 10.07.98 DE10.21.98.01 Utilize Video/TV/Broadcast scope prepared by

AA/JHSA to define building infrastructure to be provided.

NS:BC 10.21.98

DE12.02.98.01 Approximately 95% of speakers will be rigged or stacked on stage; all lighting and sound support will be within 60 Feet of stage.

NS:BC AA:AS

12.02.98

F. Project Support

DF07.01.98.01 It is not necessary to follow Factory Mutual design criteria.

NS:RT 07.01.98 DF07.01.98.02 Project progress meetings will utilize "Last

Planner" style.

NS:RT 07.01.98 DF07.15.98.01 Design process to maintain 21 month value

stream production schedule.

NS:RT 07.15.98 DF07.15.98.02 Multiple submissions will be made to the City to

satisfy the needs of obtaining multiple permit approvals.

NS:RT 07.15.98

DF09.23.98.01 Keep the design process progressing toward an 11.30.98 construction start; the only reason to hold up progress of the drawings is if it is not efficient for the design to proceed.

NS:LL 09.23.98

End of Decisions