• No results found

PPC and Reasons

In document Tesis Doctoral Ballard (Page 71-82)

CHAPTER FIVE: CASE ONE-CCSR PROJECT

5.2 PPC and Reasons

Several kinds of data were collected: PPC and reasons, auxiliary documents such as phase and master schedules, and the observations of the

researcher. PPC and reasons data was collected each week from 12/24/97 through 3/3/98, during the wettest season in the San Francisco area in recorded history. Although the project had taken weatherizing precautions to minimize weather-related delays, such as type of fill material and drainage systems, nonetheless rain was

20 A phase was conceived in terms of a relatively independent facility system. For

by far the most frequently cited reason for failing to completed assignments on weekly work plans

Table 5.1

I.

CCSR-Weekly Planning Cycle

Table 5.2

CCSR Weekly Planning Cycle

GC and subs meet to: 1) status this

week's plan, identify reasons for

failing to complete planned tasks, and agree on actions to prevent repetition, and 2) finalize the

lookahead

* The short interval schedule covers the construction tasks required to achieve a schedule

milestone (e.g. slab-on-grade by 2/28/97) and the design and supplier tasks providing needed information and materials. The team develops

a detailed schedule for each phase of the job at least 4 weeks before starting that phase. The phase schedule

then becomes the control schedule for short interval scheduling each week.

* Subs status tasks for these constraints:

contract, design, submittals, matls, prerequisite work, tools & eqpt, space,

labor, other. A/E statuses tasks by specifying the information or decision

needed.

*Both subs and A/E are answering the

questions: 1) If constraints are in your

control, are you confident they will be removed in time? 2) If constraints are not in your control, what help

do you need from others?

Guidelines: 1) Schedule for next

week (Wed thru Tu) only tasks that

have no constraints or have

only constraints you know can be removed in time. 2)

Schedule in the 2nd and 3rd weeks

only tasks you are confident can be

made ready in time. The goal is

100% plan well the team is

achieving its

* GC reviews the phase schedule and master schedule for needed adjustment.

Table 5.2

Wills

II. I D

Activity Start Contract Design Sub mitta

950 Tunnel Lobby -Walls Rebar

3/4/98 1040 Footings 6 & 7

Dowels

3/4/98 1220 Footings 6 & 7

Between A and H Dowels, and Footings E & G Dowels

Between 4.5 and 8

3/4/98

630 Line 4 Wall and Line C

ID Activity Start Contract Design Sub mitta

PPC was measured as shown in Figure 5.1, ranging from an initial measurement of 56%

during the week of 12/24/97 to 70% in the week of 3/3/98. Rain was cited as the reason for 18 plan failures (see Figure 5.2) and

frequently cited reasons were lack of prerequisite work (14), availability or quality of design information (8), and submittals (6).

Removing rain as a reason, weekly PPC would have been as shown in Figure 5.3, with a mean PPC for the research period of 71% (149 of 211

assignments completed), which compared favorably to work flow reliability achieved through previous application of the Last Planner system to projects which were not subcontracted.21

Figure 5.1

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

12/24/97 12/31/97 1/6/98 1/14/98 1/18/98 1/25/98 2/3/98 2/10/98 2/17/98 2/24/98 3/3/98 Week

% Completed

CCSR-Weekly PPC

21 Ballard et al., 1996; Ballard and Howell, 1997

Table 5.3

Week 12/24/97 12/31/97 1/6/98 1/14/98 1/18/98 1/25/98 2/3/98 2/10/98 2/17/98 2/24/98 3/3/98

PPC 56% 86% 57% 67% 73% 75% 50% 53% 74% 44% 70%

Tasks Completed

5 6 8 10 11 18 7 10 23 19 14

Tasks Planned

9 7 14 15 15 24 14 19 31 43 20

Rain 1 1 3 6 2 2 1 2 18

Pre-Requisite 2 2 1 7 2 14

Design 1 1 4 2 8

Submittal 2 2 2 6

Other 1 1 1 1 4

Space 1 2 3

Equipment 2 2

Labor 1 1 2

Materials 1 1

Contract 0

CCSR-PPC and Reasons Data

Figure 5.2

0 5 10 15 20 25

Rain Pre-Requisite Design Submittal Other Space Equipment Labor Materials Contract

Reason

Number Of Ocurrences

CCSR-Reasons for Noncompletion

Figure 5.3

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

12/24/9712/31/97 1/6/98 1/14/98 1/18/98 1/25/98 2/3/98 2/10/98 2/17/98 2/24/98 3/3/98

Weekly PPC Mean PPC

CCSR-PPC without rain

As shown in Table 5.4, reasons for plan failure were categorized as either an Execution Failure or a Plan Failure22. Of the 57 total failures23, 28 were determined to have resulted from some defect in planning, while 29 were attributed to some defect in execution. The 18 failures caused by rain were categorized as execution failures. Disregarding rain, Plan Failures would have amounted to 28 of 38, or 74%, further evidence that to a substantial degree, our fate is in our own hands as regards planning and work flow. In even extreme weather conditions, fully half of noncompletions resulted from poor planning.

22 This distinction was introduced into the Last Planner system in Ballard (1994).

23 Note the absence of detailed information for failures in the week of 12/24/97. Their inclusion would add 4 noncompletions to the total.

Table 5.4 Week 12/31

Activity Reason Type Of Failure

item 6 - Sump Pit Lid Form

Other: Low Priority Plan

Week 1/6

Activity Reason Type Of Failure

item 3 - Underground Plumbing

Rain Execution

Item 13 - East Wall Forms

Design: RFI Execution

Item 32 - Elevator Wall Forms

Pre-Requisite: Not Identified

Plan Item 43 - 2&3 Line

Excavation

Equipment: Backhoe Execution Item 44 - A,C & 4 Line

Excavation

Equipment: Backhoe Execution Item 45 - 2&3 Line Rebar No Excavation Plan Week 1/14

Activity Reason Type Of Failure

item 26 - Elevator 1&2 SOG Pour

Floor Drain Submittals Plan Item 44 - Elevator Pour

Up to Tunnel Level

Shop Drawings Plan

Item 43 - Form South East Quadrant

Waiting Rebar Fabrication

Plan Item 29 - Rebar J Line Waiting On Excavation Plan

Item 7 - Access Panel Submittal Plan

Week 1/18

Activity Reason Type Of Failure

210 - Design Change Rebar Submittals

Not Back Plan

270 - Interior Wall Rebar Submittals

Not Back Plan

A,C, & 4 Line Excavation Productivity/Rain Execution A,C, & 4 Line Rebar No Excavation Plan Week 1/25

Activity Reason Type Of Failure

Excavate Line F and 7 (MidWest)

Rain Execution

Interior Wall Forms Rain Execution

N,Q,L Lines Rebar Installation

Rain Execution

Reveals Location Waiting On Architect Plan RFI Line 7 (Cupertino) Answer Incomplete Plan

Tunnel Piping Submittal Approval Plan

Week 2/3

Activity Reason Type Of Failure

Excavate F Line Rain Execution

Backfill Sump pit Rain Execution

Template Footings A and 4 Line

Rain Execution

Electrical Conduit Elevator 5

Rain Execution

Small and Large Walls Single Form

Rain Execution

Wall Double up @ Tunnel Lobby

Waiting For Inspection Plan

Backfill N-E/S-E Quad. Rain Execution

Week 2/10

Activity Reason Type Of Failure

Plumbing between lines J

& M

Rain Execution

Plumbing Line 6.5 Rain Execution

Small Interior Walls Form Eleveator Jack Drilling / Rain

Execution Small Interior Walls

Double Up

Eleveator Jack Drilling / Rain

Execution Large Interior Walls Form Eleveator Jack Drilling /

Rain

Execution Large Interior Walls

Double Up

Eleveator Jack Drilling / Rain

Execution Small Wall Rebar Eleveator Jack Drilling /

Rain

Execution Line L wall Rebar Eleveator Jack Drilling /

Rain

Execution E & G Line Rebar from 2

to 5

Eleveator Jack Drilling / Rain

Execution

Week 2/17

Activity Reason Type Of Failure

Elevator Wal Backfill Rain Execution

Line J Excavation Backfill

Plumbing/Rain/Mud

Execution Line 6.5 Excavation After 6 & 7 Line Concrete Plan Small Interior Wall Forms Design Change Plan

Small Walls Double Up Design Change Plan

Small Walls Rebar Design Change Plan

Perimeter Wall Line 2 Rebar

Design Change Plan

Footings 6 & 7 Rebar Rain Execution

Week 2/24

Activity Reason Type Of Failure

Planter Excavation Space Plan

Interior Small Walls Rebar Change/Permit Plan

Tunnel lobby SOG Sequence Change Plan

Line L Wall Rebar Change/Permit Plan

Line J Footing Rain Execution

Wall Line 2 From A-D Man Power Plan

Week 3/3

Activity Reason Type Of Failure

Footings E&G Excavation Space For Crane Plan

Line J Concrete Rain Execution

Footings 6&7 Concrete Rain Execution

Court Yard Planter Crane Reach Plan

Small Interior Walls Man Power Plan

Pipe Ties In @ Tunne Waiting On Stanford Info Plan

CCSR-Reasons for Noncompletion (detailed and categorized)

5.3 Observations

Subcontractors were not selected based on their understanding or willingness to participate in the Last Planner production control system. They were selected based on traditional criteria such as financial soundness and bid price. Subcontractor personnel

responsibilities within it after coming to the site. Not surprisingly, some were more capable and enthusiastic about participating than others. Even so, the project superintendent continued to use the Last Planner system and reported that eventually all foremen were participating and that they began to hold each other accountable for keeping their weekly work plan commitments. Nonetheless, it would have been preferable both to incorporate participation in the production control system in the selection criteria and subcontracts, and also to have devoted more time and effort to education and training.

Shortly after introducing the system, it became apparent that more active involvement of others besides the site foremen was needed. Subcontractor project managers were invited to attend the weekly meetings and were better able to understand what was going on, and specifically better able to provide status information regarding constraints such as submittals, design issues, fabrication, and deliveries. There was also efforts made to involve the architect and design engineers on the project. Unfortunately, those efforts failed, in part because of the stage of design completion and the fact that the production architect/engineer was on a lump sum contract and concerned lest they run out of money before they ran out of work.

Analysis of constraints was a key element introduced into the Last Planner system on CCSR. Efforts to collect constraints information from subcontractors prior to the coordination meeting were mostly unsuccessful, perhaps in large part because there is no tradition in our industry for such activities. Consequently, much of meeting time was dedicated to data collection rather than planning and problem solving.

5.4 Learnings

Learnings for future projects included:

q Incorporate production control requirements into subcontracts.

q Select subcontractors for their ability and willingness to participate in the production control system.

q Involve owner, architect, and engineers in the production control process; preferably from the beginning of design.

q Send to subcontractor project managers by email or fax each week constraint reports with the next 5-6 weeks scheduled activities listed and ask them to status their activities and report back. Make sure this happens so meeting time can be used for planning and problem solving as opposed to data collection.

q Use team planning techniques to produce schedules for each phase of work, with participation by foremen, superintendents, and designers.

q Incorporate reasons identification, analysis, and corrective action into weekly coordinating meetings. Otherwise, there is a danger that incompletions become accepted as unavoidable.

In document Tesis Doctoral Ballard (Page 71-82)