Typical Low Wall Return
3 THE DESIGN PROCESS
3.2 DEVELOPING THE USER REQUIREMENTS SPECIFICATION (URS)
2563 2564
3.2.1 Introduction 2565
2566
User requirements provide key information that defines the processes, 2567
activities, and environments needed for an operating facility.
2568
lowest Total Cost of Ownership(TCO).
2573 2574
Decisions and commitments made in the early phase of project planning 2575
are often too costly to change as the project advances to final design 2576
significant portion of a facilities cost.
2581 2582
It is important to ensure that user requirements are well understood 2583
and properly applied.
2584 2585
For HVAC systems in a pharmaceutical environment, user requirements are 2586
Quality – Regulatory guidance and quality principles to guide decision 2593
making on HVAC parameters that can have product impact.
2594 2595
Operations – Proper environment for the working conditions that impact 2596
the HVAC design.
2597 2598
Maintenance – Provide input on critical aspects of the HVAC design that 2599
would ensure a low TCO 2600
2601
User requirements have often been associated with qualification, that 2602
is, critical HVAC parameters (e.g., temperature, humidity, differential 2603
pressure, air quality) are segregated from non critical HVAC 2604
parameters. Critical HVAC parameters are part of direct impact systems 2605
while non-critical HVAC parameters are either indirect or no impact 2606
systems. In either case, all HVAC systems are commissioned following 2607
GEP while direct impact systems are further qualified.
2608 2609
User requirements can either be in the form of performance based 2610
information that describes an operation and sets expectations or strict 2611
criteria where critical HVAC parameters are well defined, e.g., 2612
Temperature, Relative Humidity, etc.
2613 2614
In the case of performance based information, the HVAC designer would 2615
gather relevant information and propose the necessary criteria that 2616
would meet the user requirements. It is accepted practice to copy HVAC 2617
criteria from one facility to another (similar) facility – as long as 2618
the rationale for the original criteria is well understood. For 2619
example, determining temperature and relative humidity criteria in an 2620
aseptic environment is dependent on, type of process (closed or open, 2621
powder or liquid), local regulatory expectations, gowning procedures, 2622
environmental monitoring procedures, the level and type of activity in 2623
the area, and alert and alarm limits,. The HVAC designer should 2624
carefully consider each of these variables when proposing criteria and 2625
avoid using "industry norms" or "accepted industry practices" without 2626
an understanding of the variables involved.
2627 2628
Once user requirements are established, the HVAC designer should begin 2629
to consider design strategies and impact. It is desirable to segregate 2630
HVAC parameters that are critical and non-critical under different HVAC 2631
systems rather than mix critical and non-critical HVAC parameters under 2632
the same system. Although there may not be any restrictions from a 2633
process viewpoint, segregating HVAC system components between direct 2634
and indirect impact adds to the complexity of commissioning and 2635
qualification. It could unnecessarily drive up qualification and on-2636
going maintenance costs.
2637 2638
The flow diagrams shown below are a simple model segregating critical 2639
HVAC parameters with separate HVAC systems versus combining critical 2640
and non-critical HVAC parameters, by virtue of a single HVAC system.
2641
Both design approaches would meet user requirements but it illustrates 2642
the potential complexity when using a single HVAC system to serve 2643
direct and indirect/no-impact areas.
2644 2645
The impact assessment methodology evaluates the HVAC system at the 2646
component level to separate out critical and non-critical components, 2647
thus making it possible to have a single HVAC system. Well defined and 2648
accepted procedures should be in-place or agreed upon when defining the 2649
user requirements that would allow the single HVAC system to have a 2650
lower total cost of ownership. If these concepts are not well 2651
understood or established procedures or practices do not recognize this 2652
methodology, the HVAC design may increase the total cost of ownership.
2653
2654
Figure 3-1 User Requirements drive HVAC critical parameters 2655
2656
3.2.2 References for User Requirements 2657
2658
ISPE Baseline Guides provide a framework to understand the different 2659
products and processes within pharmaceutical and biopharmaceutical 2660
manufacturing facility. The baseline guides that would apply to this 2661
section include the following:
2662 2663
Bulk Pharmaceutical Chemicals 2664
Oral Solid Dosage Forms 2665
Sterile Manufacturing Facilities 2666
Biopharmaceuticals 2667
Packaging, Labeling & Warehousing Operations (under development) 2668
Laboratories (draft) 2669
2670
(Include a chart with a timeline and activities to illustrate?.... no) 2671
2672
The following section describes HVAC parameters as covered in the 2673
Baseline Guides listed above and the importance of each parameter in 2674
each type of facility.
2675 2676
3.2.3 HVAC Parameters 2677
2678
HVAC parameters that may have impact on product generally include:
2679 2680
Temperature 2681
Relative Humidity 2682
Airborne contamination (viable and non-viable particles), which is 2683
affected by:
2684 2685
Room Relative Pressure 2686
Airflow patterns 2687
Air Changes 2688
Air Filtration 2689
2690
Within the context of the baseline guides listed, some parameters are 2691
common to all facility types while other parameters only apply to 2692
specific facilities. The following chart depicts at-a-glance the 2693
typical HVAC parameters that would generally apply to each facility 2694
type.
2695 2696
HVAC Parameter
Facility Type Temperature
Relative Humidity
Room Relative Pressure
Airborne Particles
Air Changes Bulk Pharmaceutical
Chemicals
Oral Solid Dosage Forms
Air
direction Sterile
Manufacturing Facilities
Biopharmaceuticals Pack., Labeling &
Warehousing Laboratories 2697
Table 3-1 Typical HVAC Critical Parameters by facility type 2698
2699
Hatched areas represent the HVAC parameter used to set criteria that 2700
normally would have product impact or is required for creature comfort.
2701
Non-shaded areas are HVAC parameters that do not normally have product 2702
impact and are not used to set criteria. However, there may be other 2703
requirements such as local codes or regulations that may require 2704
certain parameters be considered in the design. For example, room 2705
relative pressure may not have product impact in a Bulk Pharmaceutical 2706
facility, but due to governing codes, the design may implement room 2707
pressurization controls in order to sustain certain safety requirements 2708
due to the high presence of flammable liquids or vapors.
2709 2710
Individual HVAC parameters are discussed in the following section with 2711
an emphasis on establishing the minimum requirements to achieve 2712
"compliance", the importance of the parameter, the impact on design, 2713
and the challenges faced in determining these requirements.
2714
Temperature requirements will vary depending on the application, 2720
product impact, and operator comfort. ………
2721 2722
This looks to be light… why discuss just temperature?
2723 2724
3.2.4 Critical Parameters 2725
2726
Provide typical critical HVAC parameters under a given process or 2727
classification; i.e., Product Type, Solvent Issues, Environmental 2728
Classification, Open/Closed processes, Terminally Sterilized, Oral 2729
Solid Dosage Forms. Discuss assumptions or clarifications 2730
will require additional attention via qualification and may require 2734
higher levels of redundancy to avoid business impact.
2735
be provided in the form of a matrix in which the individual components 2742
the other axis.
2746 2747
Managing HVAC Parameters (Monitoring) – Accountability for alerts and 2748
alarms. Methodology in determining appropriate alarm delays. Guidance 2749
on how to monitor - BAS, procedural means or manual monitoring.
2750
Determining what should be monitored – every room or select rooms.
2751 2752
Table 3-2 (HVAC System Impact Matrix) See Appendix for graphic 2753
2754
3.2.5 Programming and Layout Considerations 2755
project programmer must coordinate their knowledge and experience to 2760
avoid future problems in the construction, verification, operation and 2761
maintenance of the facility. The impact of HVAC on programming and 2762
layout will vary by the type of facility, generally increasing as the 2763
complexity of the facility increases from general administrative office 2764
It is important to establish User Requirements before beginning layout 2768
and design. It is especially important to identify critical parameters 2769
versus controlled parameters, as this is a major factor determining 2770
environmental cleanliness classifications. In general, the larger the 2771
classified area and the more stringent the environmental cleanliness 2772
class the more complex and costly the HVAC system, both first cost and 2773
the ongoing operating cost. Determine if there are there special 2774
requirements for temperature or RH for specific rooms (freezers, chill 2775
rooms, stability storage chambers, R&D suites, etc.).
2776 2777
The flow of materials, equipment and people (unidirectional flow;
2778
gravity flow, etc.) must be understood by the HVAC engineer in 2779
determining area classifications, pressurization strategies, airlock 2780
strategies (the use of airlocks to separate areas of different 2781
requirements for cleanliness, pressure, temperature, and/or RH) and 2782
their classification, HVAC system zoning, etc.
2783 2784
Area functionalities and adjacencies (both horizontal and vertical) 2785
2786
Determine functional/relational adjacencies (i.e., don‘t put large air 2787
compressors adjacent to a laboratory with vibration-sensitive precision 2788
projects employing prefabricated modular construction.
2792 2793
The locations and considerations for HVAC and utilities equipment, 2794
ducting/piping routing, supply/exhaust/return diffusers/grilles.
2795
docks and other loading/unloading facilities. Will major equipment be 2799
located in basement, penthouse, roof or elsewhere? Building 2800
configuration (H x W x L) may affect the location of central services 2801
and how they are distributed.
2802 2803
Understand the requirements for maintenance, testing, repair and/or 2804
replacement. This includes the locations for access doors/panels for 2805
HVAC system inspection, testing and maintenance, including HEPA filter 2806
pathways, hoists/elevators, etc.). Identify the locations and need for 2813
access to BMS/EMS data and control, and what local indications and/or 2814
control features are needed. What are the maintenance philosophies for 2815
the facility (i.e., maintain from inside or outside of room)?
2816
2817
What are the materials to be used in the process (i.e., potent, 2818
solvents, cytotoxic, sterile) and the approaches & technologies for 2819
product containment and for clean/sterile processing. The use of mini-2820
environments (barrier isolators, RABS, biosafety cabinets, etc.) will 2821
usually reduce both the required amount and grade of classified space 2822
compared to traditional ‗ballroom‘ cleanroom processing. The location 2823
of hazardous equipment & ductwork and the need to maintain them may 2824
affect the facility layout.
2825 2826
Issues related to codes and standards:
2827 2828
What codes and standard apply to this jurisdiction? (ADA, Fire, 2829
OSHA, Energy, IMC, etc.) 2830
Egress and other safety considerations 2831
Must understand risks associated with various layout and programming 2832
issues (i.e., area electrical classification, blowout panels, SISPQ 2833
risks…) 2834
Special considerations with hydrogen operations 2835
2836
The requirements of local codes and standards may need special 2837
attention in the design and construction of prefabricated modules.
2838
When facility modules are fabricated in a different jurisdiction than 2839
the location of the facility, this may become a major problem if not 2840
identified early in the design process.
2841 2842
Within the room: Consider the locations of people, processes and 2843
product with respect to HVAC supplies and exhaust/returns. Consider the 2844
equipment heat loads (where is heat generated and how is it cooled or 2845
extracted?) Consider the location of utilities connection with respect 2846
to the operations to be performed. Room HVAC system must be designed as 2847
3.2.6 Architectural Considerations 2853
previously identified issues for consideration in the programming and 2858
project architect must also coordinate their knowledge and experience 2862
to avoid future problems in the construction, verification, operation 2863
and maintenance of the facility.
2864
sanitization chemicals, suitable for the environment, and be 2870
wear/bump resistant.
2871
2872
Flooring: The same considerations as for Room Finishes. Selection of 2873
performance in a specific application.
2878
differential is important. If RH is important, then address reducing 2885
moisture migration through unsealed penetrations, door seals, and 2886
porous wall materials. Considerations in the door specifications 2887
need to address seals, windows, interlocks, construction of the 2888
door, actuation and hardware.
2889 2890
Consider a commissioning test to verify room tightness (i.e., room 2891
leakage test or room integrity test).
2892 2893
The use of prefabricated modular construction techniques might 2894
impose additional restrictions on the HVAC design (design might be 2895
limited to equipment vendors with which the module contractor has an 2896
established relationship; the size of AHUs might be limited to the 2897
size of a standard module; etc.) 2898
2899
Impact of HVAC on programming and layout will vary by the type of 2900
facility. (some of this is redundant) 2901
Area functionalities and adjacencies (both horizontal and vertical) 2905
Determine functional/relational adjacencies (i.e., don‘t put large 2906
air compressors adjacent to a laboratory with vibration-sensitive 2907
precision analytical equipment.
2908
Locations and considerations for HVAC and utilities equipment, 2909
ducting/piping routing, supply/exhaust/return diffusers/grilles.
2910
Major equipment in basement, penthouse, roof or ????
2911
Requirements for testing, repair and/or replacement (i.e., HEPA 2912
filter scan testing and maintenance) 2913
wheels, coils, filters, 2917
Environmental cleanliness classifications 2918
Materials to be used in the process: Potent, solvents, cytotoxic, 2919
sterile?
2920
Determining User Requirements (critical parameters versus controlled 2921
parameters) 2922
What codes and standard apply? (ADA, Fire, OSHA, ??) 2923
Egress and other safety considerations 2924
Building configuration (H x W x L) may affect the location of 2925
central services and how they are distributed.
2926
Approaches and technologies for product containment.
2927
Routing of ductwork & utilities 2928
Location of Hazardous equipment and ductwork 2929
Manifolded exhaust systems versus one fan per hood.
2930
In general, the larger the classified area and the higher the 2931
environmental cleanliness class, the more complex and costly the 2932
HVAC system, both first cost and the ongoing operating cost.
2933
Room HVAC system must be designed as an integrated system in rooms 2934
with fume hoods, biosafety cabinets (BSCs), LEV systems and process 2935
equipment HVAC systems.
2936
Must understand risks associated with various layout and programming 2937
issues (i.e., area electrical classification, blowout panels, SISPQ 2938
risks…) 2939
Special considerations with hydrogen operations 2940
Location of HVAC inlet air and exhaust stacks 2941
Special temperature (or RH) rooms (freezers, chill rooms, stability 2942
storage chambers, R&D suites, etc.) 2943
Use of airlocks to separate areas of different requirements 2944
(cleanliness, pressure, temperature, RH) and their classification 2945
Location and need for access to BMS/EMS data and control; what local 2946
indications and/or control features are needed 2947
Access to field instruments (calibration, testing, and repair) 2948
Special considerations for prefabricated modular construction 2949
Locations of people, processes and product within the space with 2950
respect to HVAC supplies and exhaust/returns 2951
Consideration of equipment heat loads (where is heat generated and 2952
how is it cooled or extracted?) 2953
Location of utilities connection 2954
2955