Not Used
3. PART 3 – EXECUTION
3.1. COOPERATION WITH TESTING LABORATORIES AND INSPECTORS
3.1.1. Inspectors and representatives of the testing laboratory shall have access to the work.
Provide facilities for such access in order that the testing, inspection and the obtaining of samples may be done properly.
3.2. CONTRACTOR PROVIDED SAMPLE
3.2.1. Contractor shall deliver material specimens to the District’s testing lab, which must by terms of the Contract be tested prior to inclusion in the Project, at least 30 days prior to scheduled delivery to the job site.
3.2.2. Material shipped by the Contractor from the source of supply prior to having satisfactorily passed such testing and inspection or prior to the receipt of notice from said representative that such testing and inspection will not be required shall not be incorporated in the job.
3.3. FIELD SPECIMENS
3.3.1. Field specimens and samples for testing, unless otherwise provided in these Contract Documents, shall be selected and taken by the testing laboratory or Inspector and not the Contractor. Sampling equipment and personnel will be provided by the testing laboratory. Deliveries of specimens and samples to the testing laboratory will be performed by the testing laboratory.
3.4.1. Establishing Schedule:
3.4.1.1. By advance discussion with the testing laboratory selected by the District, determine the time required for the laboratory to perform tests and to issue each of its findings.
3.4.1.1.1. Provide required time within the construction schedule.
3.4.2. Revising Schedule: When changes of construction schedule are necessary during construction, coordinate such changes of schedule with the testing laboratory as required.
3.4.3. Adherence to Schedule: When the testing laboratory is ready to test according to the determined schedules, but is prevented from testing or taking specimens due to incompleteness of the work, extra charges for testing attributable to the delay may be back-charged to the Contractor and will be deducted by the District from the Contract amount.
3.5. REQUIRED TESTING
Tests and inspections for the following items will be required in conformance with the Uniform Building Code, State of California Amendments, Title 24, Part 2, of the California Code of Regulations, and Interpretations of Regulations of the California State Structural Safety Interpretive Manual:
A. FOUNDATIONS (Chapters 18) Earth fill compaction
3.5.1.1.1.1 Soil Fill Compaction – 3317.3, 3318.2 and 3318.1 3.5.1.1.1.2 Excavation and Fills – 3301.1, 3317.3, 3318.2 and
3318.1
3.5.1.1.1.3 Cast-in-place Concrete Piles – 1809A.7 3.5.1.1. CONCRETE (Chapter 19)
3.5.1.1.1. Materials:
3.5.1.1.1.1. Portland Cement Tests – 1929A.1, 1903A.2 3.5.1.1.1.2. Concrete Aggregates – 1903A.3
3.5.1.1.1.3. Reinforcing Bars – 1903A.5, 1928A.2 3.5.1.1.1.4. Batch Plant Inspection – 1929A.4
3.5.1.1.1.5. Waiver of Batch Plant Inspection and Tests – 1929A.5 and 1929A.6
MT.SANANTONIOCOLLEGE TESTING AND INSPECTION -01450 3.5.1.1.2.1. Proportions of Concrete – 1904A, 1905A.1,
1905A.2, 1905A.3, 1905A.4 and 1905A.1.5 3.5.1.1.2.2. Strength Tests of Concrete – 1905A.6 3.5.1.1.2.3. Splitting Tensile Strength – 1905A.1.4 and
1905A.1.5
3.5.1.1.2.4. Composite Construction Cores – 1929A.8 3.5.1.1.3. Concrete Inspection
3.5.1.1.3.1. Job Site Inspection – 1929A.7
3.5.1.1.3.2. Batch Plant or Weighmaster Inspection – 1929A.4 & 1929A.5
3.5.1.1.3.3. Waiver of Batch Plant – 1929A.9
3.5.1.1.3.4. Reinforcing Bar Welding Inspection – 1929A.12 3.5.1.1.4. Anchors in Concrete
3.5.1.1.4.1. Drilled-in-Expansion Bolts or Epoxy-Type Anchors in Concrete – 1929A.3.5
3.5.1.2. MASONRY (Chapter 21A) 3.5.1.2.1. Materials
3.5.1.2.1.1. Masonry Units – 2102A.2, Items 4, 5 & 6 3.5.1.2.1.2. Portland Cement – 2102A.2, Item 2
3.5.1.2.1.3. Mortar and Grout Aggregates – 2102A.2, Item 1; 2103A.3; 2103A.4
3.5.1.2.1.4. Reinforcement – 2102A.2, Item 10; 1903A.5;
1929A.2 3.5.1.2.2. Masonry Quality
3.5.1.2.2.1. Portland Cement Testing – 1903A.2, 1929A.1 3.5.1.2.2.2. Mortar and Grout Testing – 2105A.3.4, Item 2 3.5.1.2.2.3. Masonry Prism Testing – 2105A.3.2,
2105A.3.3, 2105A.3.4, 2105A.3.5 3.5.1.2.2.4. Masonry Core Testing – 2105A.3.1 3.5.1.2.2.5. Masonry Unit Testing – 2105A.3.4, Item 1 3.5.1.2.2.6. Reinforcement Testing – 1929A.2
3.5.1.2.3.1. Reinforced Masonry – 2115A.1, 2105A.7 3.5.1.2.3.2. Inspection of Welded Reinforcing Bars –
1929A.12
3.5.1.3. STRUCTURAL STEEL AND COLD FORMED STEEL (Chapter 22) 3.5.1.3.1. Materials
3.5.1.3.1.1. Structural Steel and Cold Formed Steel – 2203A.1
3.5.1.3.1.2. Material Identifiction – 2203A.1 3.5.1.3.2. Inspection and Tests of Structural Steel
3.5.1.3.2.1. Tests of Structural & Cold Formed Steel – 2231A.1
3.5.1.3.2.2. Tests of High Strength Bolts, Nuts and Washers – 2231A.2
3.5.1.3.2.3. Tests of End Welded Stud – 2231A.3 3.5.1.3.2.4. Shop Fabrication Inspection – 2231A.3 3.5.1.3.2.5. Welding Inspection – 2231A.5
3.5.1.3.2.6. Nelson Stud Welding – 2231A.3
3.5.1.3.2.7. High Strength Bolt Inspection – 2231A.6 3.5.1.3.2.8. Non-Destructive Weld Testing –2231A.5 3.5.1.4. WOOD (Chapter 23)
3.5.1.4.1. Materials
3.5.1.4.1.1. Lumber and Plywood Grading – 2303A.1.1, 2303A.1.4
3.5.1.4.1.2. Glued-Laminated Members – 2303A.1.2, 2316A.5.4.6
3.5.1.4.2. Wood Inspection
3.5.1.4.2.1. Timber Connectors – 2318A.2 3.5.1.4.2.2. Truss Joists – 2337A.3
3.5.1.4.2.3. Glu-Laminated Fabrication – 2337A.1
MT.SANANTONIOCOLLEGE TESTING AND INSPECTION -01450
___________________________________________________________________________________________
PART 1 - GENERAL 1.1 GENERAL
A. Mobilization shall include the obtaining of all bonds, insurance, and permits; moving onto the site of all plant and equipment; and the furnishing and erecting of all plant, temporary buildings, and other construction facilities; all as required for the proper performance and completion of the Work. Mobilization shall include but not be limited to the following principal items:
1. Moving onto the site of all Contractors’ plant and equipment required for first month’s operations.
2. Establishing fire protection system.
3. Providing on-site communications facilities.
4. Furnishing, installing, and maintaining all storage yards, buildings or sheds required for temporary storage of products equipment, or materials that have not yet been installed in the Work. All such storage shall meet manufacturer’s specified storage requirements, including temperature and humidity control as recommended by the manufacturer.
5. Furnishing and maintaining all security measures and systems.
6. Obtaining and pay for all required permits.
7. Posting all OSHA required notices and establishment of safety programs.
8. Posting all prevailing wage rates applicable to the Work.
9. Submittal of a Preliminary Schedule of Values in accordance with the requirements of Section 01310 within 7 days of issue of the Notice to Proceed.
10. Contractor(s) shall be responsible for providing and maintaining on-site trailers/jobsite office, limited to no more than 300 sq. ft., including all required utilities.
Locations will be as directed by the Project Manager. Contractor(s) shall include the costs of relocation of his office/changing/storage areas and temporary utilities to allow the work of other trades to proceed.
B. Staff Names: Submit a list of the Contractor’s principal staff assignments before commencement of Work for review and approval by the Project Manager, including the Superintendent and other personnel in attendance at the site; identify individuals, their duties and responsibilities; list their addresses and telephone numbers.
1. Post copies of the list as required by the Project Manager.
C. Limitations. Contractor recognizes and acknowledges that, as certain areas of the Project are executed and completed, such areas may be designated restricted areas to which access by the Contractor may be limited or prohibited. Contractor also recognizes and acknowledges that such designated areas may interfere with the orderly plan and schedule of its operations and performance of the Work. Accordingly, Contractor shall not assume there will be unrestricted access to or use of any areas and must, prior to commencement of the Work and as the Work progresses, assure to its satisfaction the access and other conditions affecting the Work.