The recommended technical option is to extend the existing municipal water main to the Eva Mae Dr. community. The implementation plan for the recommended solution to address the issue of potential substandard private well water quality in the extraterritorial community of Raleigh, NC includes details about the decision to pursue this technical option, the annexation process requirements and approval, water main design and construction requirements,
scheduling, potential technical problems, and long-term maintenance. The preferences of key stakeholders such as the water utility and the community residents should be considered first. Because extension of the existing water main is dependent upon annexation into the City of Raleigh, the annexation process and requirements are considered second. Thirdly, the capacity of the existing water main, design and costs, construction scheduling, and public disturbance are discussed. Lastly, potential technical problems during installation and thereafter as well as long- term maintenance is considered.
Stakeholder Preferences
Firstly, this report should be presented to the community, the water utility, and the City of Raleigh to initiate a discussion between all parties regarding the implementation of the preferred solution. It should be noted that the water main extension through annexation may not be the preferred solution of all or any parties involved. Further insight should be established through additional water quality testing, resident polling, and in-depth exploration of opinions of all stakeholders. If this investigation reveals that the water main extension through annexation is
33
the preferred solution to provide quality water to the residents of the Eva Mae Dr. community, the following details of implementation should be considered.
Annexation Requirements and Approval
If a community located within an extraterritorial jurisdiction desires to have water services, the community must be annexed into the city limits (or the community must compensate the town for the extended services, whether that be from the residentsβ personal financial resources or through grants). For the purposes of this report, water services as a result of annexation is the only scenario considered. Because the median household income of the communityβs census tract (528.06) is $53,828, it is assumed that a majority of the households within the community have an income greater than the poverty threshold and will petition for annexation in accordance with Section 10 of the North Carolina General Assembly (NCGA) Annexation Law or could potentially be involuntarily annexed in accordance with Part 7 (Census Explorer, 2013; NCGA, 2011).
Once the annexation application is reviewed, if the community is annexed into the city, water and sewer service must be provided within 3.5 years of annexation at no cost to the property owners (Bluestein, 2011; NCGA, 2011). However, there must be a submitted request from a majority of the owners within 65 days of receiving notice of the right to water service to avoid assessment fees (Bluestein, 2011; NCGA, 2011). Annexation procedure, whether
voluntary or involuntary, including public informational meetings, contracts with rural fire departments and solid waste collection firms, and recording and reporting should follow all guidelines and requirements of the NCGA Section 2011-396 Annexation Law.
Water Main Design and Construction
After annexation and before project implementation, the City of Raleigh will request bids and civil engineering consulting firms interested in the project will submit bids. The costs
34
detailed in the submitted bids are expected to be similar to those calculated in this report. One consulting firm will be chosen to design, construct, and oversee the water main extension based on the submitted bids.
The water main extension should be designed in accordance with the most recent City of Raleigh Public Utilities Handbook by a designer employed by the consulting firm. The design detailed in this report is only preliminary. A final designer or consulting firm may review the preliminary design presented in this report, create required design drawings and specifications to be submitted to the City of Raleigh for approval, oversee the implementation of the project, and confirm that the project was completed in accordance with design specifications.
Scheduling
The scheduling of this project will ultimately be at the discretion of the City of Raleigh, although water services must be provided within three and one-half years after annexation becomes effective. If the City of Raleigh decides to apply for outside funding such as a
Community Development Block Grant, the application process may delay the completion of the project. The project could take anywhere from a few months to over a year depending upon the bidding process, permitting approval, and the number of groups involved in construction. If permits are not initially approved or if construction drawing submittals have multiple stages of revisions, the time before construction begins may be extended. Extended time during the design and permitting process may also increase the cost of the project. If multiple companies are contracted to complete the construction of the project, scheduling conflicts may contribute to an extension of the time required for construction.
35 Public Disturbance
Vehicle traffic will most likely be disrupted during the construction process. Vehicle detour signs should be placed in proper areas during construction along Bethel Road and Eva Mae Dr. Precautions should be taken not to block any community residents from leaving the neighborhood and at least one lane should be available to the residents at all times for entering and exiting the neighborhood. The construction should be implemented in sections so as to disturb the least amount of land area each day. As there are no sidewalks in the neighborhood, pedestrian traffic disruption will be limited. Construction noise may also be considered a disruption to residents in the Eva Mae Dr. community and surrounding communities. Technical Problems
Unexpected technical problems may also have the potential to increase the time required to complete the project and could possibly increase construction costs. Unpredicted or
incorrectly assumed factors such as weather conditions, soil type, or construction accidents are examples of possible technical issues. Adverse weather could delay the construction process by inhibiting transportation to the worksite or preventing the safe use of equipment on site. The interruption of construction is not likely to increase costs significantly. Although construction cost estimates include the possibility of bedrock in some portions of the soil, the presence of more or less bedrock than predicted may increase or decrease the cost of the project. Accidents during construction should also be considered as an accident involving tools and equipment, damage to existing infrastructure, or injury of a worker can increase the cost of the project as well as delay the project completion.
Long-term Maintenance
The City of Raleigh Public Utilities Department will be responsible for the routine maintenance of the installed water mains. Maintenance of the plumping infrastructure supplying
36
the municipal water to the household will be the responsibility of the household residents. Additionally, the supply of quality drinking water to the municipal water network is the
obligation of the City of Raleigh Public Utilities Department and payment to the Public Utilities Department for water services is the duty of each household.
37
CHAPTER 6: CONCLUSION
Residents residing in the extraterritorial jurisdictions of municipalities are often not supplied with municipal water service and rely on self-supplied water systems. Self-supplied water, often from wells, is not regulated by the Environmental Protection Agency and may potentially increase health risks to household residents. The costs of ensuring standard water quality and potential resulting health benefits to residents relying on self-supplied well water in a census block located within the extraterritorial jurisdiction of Wake County were evaluated. Three options were evaluated as solutions to this problem: extending the existing water
infrastructure as a result of annexation into the City of Raleigh, periodic testing and treatment of the community's well water by the residents, and no action. Although none of the technical options is optimal for all attributes of importance considered, the extension of the existing water main through annexation is recommended to improve the quality of water to the census block evaluated in the extraterritorial jurisdiction of Raleigh, NC based on monetary costs, potential health benefits, and implementation feasibility.
38
APPENDICES
APPENDIX A: EVA MAE DRIVE COMMUNITY LOCATION
Figure 7. Location of Eva Mae Dr. community in Wake County, North Carolina.
Figure 8. View north from southern border of community on Bethel Rd. (Eva Mae Dr. Raleigh, NC, 2015).
39
Figure 9. View south from southern border of community on Bethel Rd. (Eva Mae Dr. Raleigh, NC, 2015).
The green sign on the right shows the Raleigh city limit boundary and the solid waste collection roll carts demonstrate the availability of these services to residents within the city limits.
40
APPENDIX B: WATER MAIN EXTENSION: INPUT CALCULATIONS FOR EXISTING CITY OF RALEIGH MASTER WATER MODEL
The average daily demand (ADD) of the entire community was calculated on the basis of the 2013 per capita water demand, 96 gallons per capita day (gpcd), provided in the 2013 City of Raleigh Water Resources Assessment Plan (Waldroup, Wheeler, Buchan, & Tant, 2013)
(Equation 3). This value was translated to maximum daily demand (MDD) using a peaking factor of 1.4, the peaking factor generally used by the City of Raleigh (Davis, Telephone, 2015) (Equation 4). The MDD at each node was calculated using Equation 5 where π»π represents the total number of households in the community (30) and π»π represents the number of households assigned to node X based on proximity to the node (Figure 10). The calculated MDD at each node (Table 9) was entered into the existing City of Raleigh Master Water Model by Todd Davis.
Equation 3. Total community average daily demand of water. 96 [ πππππππ
ππππ ππ Γ πππ¦] Γ 66[ππππ πππ ] = 6336 [
πππππππ πππ¦ ] Equation 4. Conversion from ADD to MDD.
6336 [πππππππ πππ¦ ] Γ 1.4 = 8870 [ πππππππ πππ¦ ] Equation 5. MDD at node X. πππ‘ππ ππ·π· [πππππππ πππππππ πππ¦ ] Γ· π»πΓ π»π = ππ·π·π[ πππππππ πππππππ πππ¦ ]
41
Table 9. Calculated MDD (gallons per day) at each connection node. Node Households ADD (gpd) MDD (gpd)
1 5 1056 1478
2 8 1690 2365
3 2 422 591
4 15 3168 4435
Total 30 6336 8870
Figure 10. Household demand assigned to each new connection junction.
The existing water network has ample capacity to support an extension and the resulting maximum day pressures vary between 66 pounds per square inch (psi) and 89 psi (Davis, E-mail, 2015). This meets the requirement of the City of Raleigh to meet a minimum pressure of 20 psi (Public Utilites Handbook, 2014).
42
43
APPENDIX C: WATER MAIN EXTENSION: ARCGIS DATA AND METHOD
A shapefile containing the Eva Mae Dr. community was created from a shapefile containing all ETJ census blocks in Wake County. The Eva Mae Dr. community was selected from the Wake County ETJ attribute table. From this selection, the Eva Mae Dr. community shapefile was created using the βCreate Layer From Selected Featuresβ command (Figure 12).
A shapefile of the 0.75 mile radius surrounding the Eva Mae Dr. community shapefile was created using the ArcGIS βBufferβ tool (Figure 12). The radius shapefile was also used in data requests to Carl Stearns and Layman Ricker to be extracted from county-wide existing water and sewer shapefiles.
The Eva Mae Dr. community shapefile and its radius shapefile were used to trim down other county-sized shapefiles including streets, highways, and property parcels using the βIntersectβ tool (Figure 12, Figure 13).
44
Figure 12. Eva Mae Dr. community shapefile, existing water infrastructure, and streets and highways within a 0.75-mile radius of the study community.
Because the communityβs census block covered portions of four Wake County grid sections (1722, 1723, 1732, 1733), the topography shapefile for each grid section was intersected with the radius shapefile using the βIntersectβ tool (Figure 13). The four resulting trimmed topographic layers were merged using the βMergeβ tool to create one topography shapefile within the 0.75 radius of the ETJ. Once each shapefile was cut down to only include the area of
45
Figure 13. Eva Mae Dr. community property parcels and four surrounding Wake County topographic gird sections within the 0.75 mile radius of the community boundary.
46
APPENDIX D: WATER MAIN EXTENSION: WATERGEMS NETWORK EXTENSION DESIGN
Using the background files created in ArcGIS, the locations of the water main extension pipes were specified. Using Raleigh iMaps as a measurement tool, hydrant locations were determined and placed approximately 400 feet apart, at each intersection, at the end of dead end streets, and no further than 400 feet from each home. Valves were specified at all intersections per the City of Raleigh Public Utilities Handbook. For each βTEEβ intersection of the extension, there are three main line valves. Main line valves were placed between street intersections (Public Utilites Handbook, 2014). Additionally, each hydrant has a 6-inch branch valve, and four air release valves were specified along Bethel Rd. to account for elevation changes greater than 15 feet (Figure 14). Figure 15 through Figure 19 display the pipe elevation profiles along Bethel Rd., Martha St., Poplar Dr., the road connecting Martha St. and Poplar Dr. and Eva Mae Dr.
47
48
Figure 15. Elevation of designed pipes along Bethel Rd. from south to north.
Figure 16. Elevation of designed pipes along Martha St. from east to west.
Figure 17. Elevation of designed pipes along Poplar Dr. from west to east.
Intersection with Martha St. Intersection with connecting street Intersection with connecting street
49
Figure 18. Elevation of pipes along the connecting street between Martha St. and Poplar Dr. from south to north.
Figure 19. Elevation of designed pipes along Eva Mae Dr. from north to south.
Intersection with
Poplar Dr. Intersection with
50
APPENDIX E: WATER MAIN EXTENSION: ESTIMATION OF COSTS TO THE UTILITY
Hypothetical Construction Bid
The calculation of the construction costs of the water main extension are detailed in Table 10. The unit cost of each item includes material and installation costs. The unit cost for each item of Table 10 was estimated from three example bids from similar projects in Wake County (Appendix F). When available, unit cost per item from each example bid was averaged to calculate the unit cost to be used in the construction cost opinion calculation for each item. For Item 1, 2% of the subtotal of the project was calculated. For Items 2 through 11 and Item 15, quantity of units were determined from existing ArcGIS shapefiles and the project design in WaterGEMS. Items 12, 20, 24, and 25 were estimated based on example bids of projects with similar overall pipe lengths and diameters. Items 13 and 14 are equal to the number of
households in the community to be connected to the constructed water main. Items 16 and 23 were estimated based on the length of pipe to be installed and existing topography. Items 17 through 19 were estimated based on aerial images of driveways along the eastern and northern sides of roads where installation will take place (iMAPS, 2015). Item 21 was estimated based on the type of soil along roadways and potential bedrock below ground elevation (Figure 20). Louisburg Loamy Sand (LoB) is classified as typically having bedrock at approximately 40 inches below ground elevation (Soil Map, 2015). Item 22 was set equal to Item 21. Item 26 was calculated as 15% of the total cost of piping.
51
Table 10. Hypothetical bid for Eva Mae Dr. community water main extension.
Eva Mae Dr. Community
ITEM DESCRIPTION QUANTITY UNIT UNIT COST CONSTRUCTION
COST OPINION
1 Bonds, Insurance, Mobilization, 2% Max 1 LS $ 14,555.00 $ 14,555.00
2 6-inch DI Water Main, Class 350 30 LF $ 45.43 $ 1,363.01
3 8-inch DI Water Main, Class 350 2,400 LF $ 49.80 $ 119,520.00
4 12-inch DI Water Main, Class 350 1,550 LF $ 50.98 $ 79,019.00
5 12"x8" Tapping Sleeve and Valve Assembly 2 EA $ 5,298.75 $ 10,597.50
6 8"x8" Tapping Sleeve and Valve Assembly 2 EA $ 4,100.00 $ 8,200.00
7 6-inch Gate Valve Assembly 12 EA $ 1,912.20 $ 22,946.40
8 8-inch Gate Valve Assembly 11 EA $ 1,804.60 $ 19,850.60
9 12-inch Gate Valve Assembly 6 EA $ 3,357.00 $ 20,142.00
10 New Fire Hydrant Assembly* Includes tapping sleeves 12 EA $ 4,167.00 $ 50,004.00
11 Connection to Existing Water Main 4 EA $ 2,903.40 $ 11,613.60
12 Ductile Iron Fittings 1,600 LBS $ 7.60 $ 12,160.00
13 3/4-inch Water Service 30 EA $ 2,210.60 $ 66,318.00
14 3/4-inch Water Service Curb Stop 30 EA $ 386.00 $ 11,580.00
15 Existing Blowoff and Manhole Removal 3 EA $ 2,122.00 $ 6,366.00
16 Asphalt Roadway Patching 4,000 SY $ 33.38 $ 133,500.00
17 Gravel Driveway Repair 115 SY $ 15.75 $ 1,811.25
18 Asphalt Driveway Repair 15 SY $ 88.50 $ 1,327.50
19 Concrete Driveway Repair 47 SY $ 78.75 $ 3,675.00
20 Miscellaneous Concrete 75 CY $ 181.00 $ 13,575.00
21 Rock Excavation by Mechanical Methods 450 CY $ 184.25 $ 82,912.50
22 Select Backfill 450 CY $ 25.53 $ 11,488.50
23 Temporary Ditch Liner 2,000 SY $ 3.60 $ 7,200.00
24 Erosion Control Measures Maintenance and Removal*
Includes silt fencing 1 LS $ 9,083.38 $ 9,083.38
25 3rd Party Testing Allowance 1 LS $ 5,000.00 $ 5,000.00
26 Clean Up and Seeding (Min. 15% of total cost of piping) 1 LS $ 29,985.30 $ 29,985.30
Note: CY=Cubic Yards, EA=Each, LBS=Pounds, LF=Linear Feet, LS=Lump Sum, SY= Square Yard
Total Bid Price $ 753,793.54
739,238.54 $
52
Figure 20. Soil composition of construction area (Soil Map, 2015). Permitting Costs
All permitting costs were determined by the City of Raleigh Development Fee Schedule and North Carolina Department of Environment and Natural Resources (NCDENR). A stream buffer permit was required as a riparian stream buffer crosses areas of construction on Martha St. and Poplar Dr. (Figure 21).
53
Figure 21. Riparian stream buffer intersecting construction area in community.
The extension project disturbs less than one acre of land and therefore is exempt from an Erosion Control permit from NCDENR Division of Land Quality (Navarrette, 2015). The permitting costs included in cost calculations are detailed in Table 11.
Table 11. Permitting costs of water main extension.
Permit Quantity Unit Unit Cost Estimated Cost
Street Right-of-Way 1 LS $ 289.00 $ 289.00
Engineering Field Inspection for a Public Water Main 4000 LF $ 1.16 $ 4,632.00
Pavement Cut Fee 4000 LF $ 51.00 $ 204,000.00
Right-of-Way (per Driveway) 24 EA $ 81.00 $ 1,944.00
Water/Sewer Plan Review 1 LS $ 200.00 $ 200.00
Stream Buffer Impact 1 LS $ 240.00 $ 240.00
54
APPENIX F: WATER MAIN EXTENSION: CONSTRUCTION BID REFERENCES FROM WAKE COUNTY
All project bids from which cost estimates were calculated were retrieved from Eileen Navarrete, Construction Projects Administrator of the City of Raleigh Public Utilities
Department. Portions of each of the three bids used are demonstrated by Figure 22, Figure 23, and Figure 24.
55
56
Figure 23. Portion of Highfill Infrastructure Engineering, P.C., Water Line Replacement Project Bid, 2012 (Navarrette, 2015).
57
Figure 24. Portion of Withers & Ravenel Water Main Replacement Project, 2011 (Navarrette, 2015).
58
APPENDIX G: WATER MAIN EXTENSION: ESTIMATION OF COSTS AND BENEFITS TO THE EVA MAE DRIVE COMMUNITY
One-time fees paid to the City of Raleigh
The cost of a capital facilities fee, meter installation fee, and utility billing account initiation fee were totaled for each household. The total cost to the homeowner, $2,500.00, would be due upon connection to the newly constructed water main extension. The capital facilities fee and the meter installation fee both vary with pipe connection size (Table 13). In this estimation, a connection pipe size was assumed to be ΒΎ-inch. The assessment fee was assumed to be $0.00 in accordance with the General Assembly of North Carolinaβs Session Law 2011- 396. An assessment fee may be charged to the household requesting services after the 65-day allotted request duration. However, this analysis assumes that all households will request water services in a timely manner in accordance with City of Raleigh standards.
Table 12. Costs to community members as a result of municipal water supply extension.
One-time Fees: (Development Fee Schedule, 2014)
Capital Facilities Fee: for connecting with the water
system (3/4 in. meter)
$2,238.00
Well Abandonment Fee (NW Poole, 2015) $1,600.00