ISO CERTIFICATION

In document Precommissioning Procedure (Page 37-68)

ATTACHMENT # 5 OCS NATA Certification

NATA is Australia’s government-endorsed laboratory accreditor, and a leader in accreditation internationally.

National Association of Testing Authorities, Australia

(ABN 59 004 379 748)

has accredited

Offshore Construction Specialists Pte Ltd Singapore

following demonstration of its technical competence to operate in accordance with

ISO/IEC 17025

This facility is accredited in the field of

MECHANICAL TESTING

for the tests, calibrations and measurements shown on the Scope of Accreditation issued by NATA

Jennifer Evans

Chief Executive Officer

Date of accreditation:15 July 2013

Accreditation number:19122

ATTACHMENT # 6 OCS Personnel CVs

Offshore Construction Specialists Pte. Ltd.

Sayed Dedy Mahdy

Career Summary

• 4 Months University Field Practical, Tunu Field Development “Tunu Phase 8 EPSC 3 Project”- TotalFinaElf Indonesie.

• 9 Months as Field Engineer for PT. McConnell Dowell Indonesia.

• 1 year and 8 months working with PT McDermott Indonesia

• Currently working with Offshore Construction Specialists Pte. Ltd.

Experience

Field Engineer

June 2009 - January 2010

Amerada Hess Ujung Pangkah Phase 2, Indonesia Offshore Construction Specialists Pte Ltd

• Responsible for all Offshore Pigging Operation, Hydrotesting and Leak test of 3 subsea flowlines, 6”, 12” and 16” between WHP B and WHP A.

• Manage the offshore operation at site, together with the barge supt & the other field engineers. Work included the wellhead platform, WHP B installation, 6”, 12” and 16”

flowline installation between WHP B and WHP A. Post trenching of 6”, 12” and 16”

flowline.

Field Engineer Sept 2008 – May 2009

Asia Petroleum Development (APD) - Glagah Kambuna Project, Indonesia Offshore Construction Specialists Pte Ltd

• Responsible for all Offshore Pigging Operation, Hydrotesting and Leak test of 42 km 14” gas export pipeline from the Kambuna platform offshore North Sumatera to a landfall north east of Medan.

• Manage the offshore operation at site, together with the barge supt & the other field engineers. Work included 5 km beach approach, Pre and Post trenching of 13 km of the pipeline to a cover of 2.0 metres. Topsides installation and Hook up.

• Responsible for all Offshore Pigging Operation, Hydrotesting and Leak test of 800mtr pipeline, Flexible risers and spools.

• Manage the offshore operation at site, together with the barge supt & the other field engineers. 1 jacket(sidelift & upend) + 1 deck + 2 pipeline (10 in) + 1 SPC + 1PLEM + 4 sp tie in (10 in) + 2 flexible riser (6 in) + 1 mooring hawser

Field Engineer

November 2006 – October 2007

Project : Kerisi Field Development Phase II CPP Jacket and Deck Installation PT. McDERMOTT INDONESIA

Working with procedures and instruments preparation for 12”∅and 16”∅ spools hydrotesting. Responsible for almost all load out preparation for 3 material barges, 4 nos of Central Processing modules over 1000MT and 8 Legs Jacket load out for Central Processing Platform

Field Engineer

November 2006 – October 2007

Project : Angel Project – Substructure Installation and Pipelay PT. McDERMOTT INDONESIA

Manage and supervise technical on field for fabrication of 5 sections Articulated Stinger and refurbishment 3 sections Articulated Stinger.

Field Engineer

January 2007 – August 2007 Project : SSB T&I

PT. McDERMOTT INDONESIA

Manage and supervise technical on field for structural modification 5 sections Articulated Gulf Of Mexico Stinger and refurbishment 3 sections Articulated Stinger and 1 section truss stinger.

Field Engineer

August 2006 – September 2006

Project : Kerisi Field Development Phase I PT. McDERMOTT INDONESIA

Manage and supervise readiness of marine installation on field in subcontractor yard of 1420 MT Wellhead Platform and 1113 MT Jacket load out.

Field Engineer

July 2006 – August 2006

Project : PM3 Camau – Gas Pipeline PT. McDERMOTT INDONESIA

As-built for survey for over 289 KM from Bunga Raya (Malaysian Area) to GDS (Vietnamese

Offshore Construction Specialists Pte. Ltd.

Project : EMEPMI Seligi A- To Tapis Pump Pipeline Replacement PT. McDERMOTT INDONESIA

Prepared and manage of fabrication and refurbishment for engineering installation aid for 18”∅ crude pipeline installation, assisting in procedures and instruments preparation associated with pigging and hydrotesting. Over 60 days was spent offshore time on board DB30 to manage 21,2 KM 18”∅ crude pipeline installation, riser and two sub sea spool trough the commissioning stage.

Field Engineer

December 2005 – January 2006

Contract Value USD 2.5m – PT. NewMont NTT. Batu Hijau-Scavenger Maintenance Phase I PT. McCONNELL DOWELL INDONESIA

Performance as Project Planner for Scavenger Shut Down Project on PT. NewMont NTT.

Project Mobilization coordinator and controlling material take off.

Field Engineer

April 2005 – December 2005

Contract Value USD 4.6m + USD 1,2m Variation – Kaltim Prima Coal Service Wharf and Shiploader Jetty Refurbishment.

PT. McCONNELL DOWELL INDONESIA

Employed with PT McConnell Dowell Indonesia to manage the shiploader jetty and service wharf rehabilitation works contract. Contract involves the partial demolition and reinstatement of 15years old reinforced concrete service wharf at KPC and rehabilitation of Structural steel shiploader jetty paintwork.

Field Practical April 2002 - June 2002

Contract Value – USD 3.5m - Tunu Field Development Phase 8-EPSC 3, Aerial Pipe Installation

PT. CITRA PANJI MANUNGGAL

• Preparing Pilling Equipment that Needed for Pilling Activities

• Responsible for daily Report

• Assisting Surveying

• Liaise with third Party Inspector Badan Kualifikasi Indonesia (BKI)

• Assisting with application of work Permit

• Assisting with safety procedures

Diponegoro University, 2004

On Job Training and Courses

HUET – MSTS ASIA SDN. BHD, Johor Malaysia, 2006 Sea Survival – MSTS ASIA SDN. BHD, Johor Malaysia, 2006 Fire Fighting – MSTS ASIA SDN. BHD, Johor Malaysia, 2006

Wire Rope Inspector - Carl Stahl Evita Ltd, Batam Indonesia, February 2007 Field Engineer training 1st Module : General Topics, Singapore, 2007 Field Engineer training 2nd Module : Structural Installation, Singapore 2007

Incident Investigation training, Batam, Indonesia 2007 Task Risk Assessment training, Batam, Indonesia 2007

Firms

Nov 2007 Offshore Construction Specialist Jan 2006 to 8 Oct 2007 PT McDermott Indonesia

Apr 2005 to Dec 2005 PT Mc Connell Dowell Indonesia

Personal Details

Date of Birth : November 29, 1979

Age : 34

Nationality : Indonesian Citizenship

Languages : Bahasa Indonesia – oral & written English – oral & written

Contacts : Mobile +62-8127011155

Page 1 of 2

PERSONAL DATA

Name : Roni

DOB : 20 August 1975

Place / DOB : Belawan

Sex : Male

Marital Status : Married Nationality : Indonesia Religion : Moslem

DOCUMENT

No Document Number Date Of Issued Date Of Expiry Place Of Issued 1 Passport W 259674 30 Nov 2010 30 Nov 2015 Batam

CERTIFICATE OF COMPETENCY

No Certificate Number Date OF issued

Date Of Expiry

Place Of Issued 1. BOSIET & Travel Safely

by Boat

- 24 Nov 2010 23 Nov 2014

Batam

WORK EXPERIENCES Pre-Comm Supervisor

August 2013 to present

Offshore Construction Specialists Pte Ltd

Responsible for the maintaining High Pressure pumps and Flooding Pumps in good condition after project and prepare, function test of High Pressure pumps and Flooding Pumps before offshore work.

Operate and ensure High Pressure Pumps and Flooding pump working in good condition for Pre-commissioning work.

Completed Project:

No Company Project position Location Client Vessel Name Periode 1. Neptune SONSUB Grouting

Chinese SAIPEM MERMAID OFFSHORE

Malaysia PETRONAS ROCK WATER 2

Supervisor Brunei BSP SHELL ONSHORE 25 Mar 20013 16 May 2013

Page 1 of 5

NAME: KRISBEL SIMANJUNTAK

DATE OF BIRTH 4 May 1963

NATIONALITY Indonesian

MARITAL STATUS Married EDUCATION/TRAINING :

 May 07, 2007. Basic Offshore Safety Induction & Emergency Training Including Additional OLF Modules (OPITO Approved)

 February 06, 2007. Confine Space Entry and Rescue.

LANGUAGES Bahasa Indonesian (written and spoken)

English (Fair Spoken)

Career Summary

Over 26 years experience in maintain heavy equipment, engines, High Pressure pumps and flooding pumps, pipe fittings, operating related machinery.

Work Experience

Mechanic

Mar 2009 to present

Offshore Construction Specialists Pte Ltd

Responsible for the maintaining High Pressure pumps and Flooding Pumps in good condition after project and prepare, function test of High Pressure pumps and Flooding Pumps before offshore work.

Operate and ensure High Pressure Pumps and Flooding pump working in good condition for Pre-commissioning work.

Completed Projects

Oct 2013 – Nov 2013

Offshore Construction Specialists Pte Ltd Project : Leighton Offshore

Location : Jakarta - Cirebon

S513 Main Oil Line from X-Ray Field to Balongan Plant Project

Post Trenching, Free Span Correction, and Pre-commissiong Services

Task Description Jetting Technician April 2013 – May 2013

Offshore Construction Specialists Pte Ltd

Project : Brunei Shell Petroluem – Domgas Pipeline Installation Project Location : Bulan Bulan Field Development - Brunei

Jetting services for the Pile Refusal Remedial Project Task Description

Jetting Technician responsible for operating of jetting spread, monitoring the performance of equipment and troubleshooting the jetting equipment in the event of equipment breakdown.

Jetting Technician

August 2012 – January 2013

Offshore Construction Specialists Pte Ltd

Project : Chevron (Australia) – Domgas Pipeline Installation Project Location : Domgas Field Development, North West Coast of Australia

Jetting services for the 6” & 20” pipeline 1.5 km and 5.9km CW-DW and PPP-DW installation Task Description

Jetting Technician responsible for operating of jetting spread, monitoring the performance of equipment and troubleshooting the jetting equipment in the event of equipment breakdown.

Mechanic

April 2012 to May 2012

Offshore Construction Specialists Pte Ltd

Project : Conoco Philips Indonesia – Develop the Bawal Field Location : Bawal Field – Natuna Sea

Offshore Pigging and Hydrotesting work for 14” newly laid pipeline to connect the two Bawal wells (BW1 and BW2) to inline Tee and valve assemblies on the new pipeline, using rigid spools.

Mechanic

October 2011 – November 2011

Offshore Construction Specialists Pte Ltd

Project : Korea Development Company LTD. – Gas Lift Compression Project.

Location : Poleng Field – Gresik, West Java, Indonesia.

Offshore Pigging and Hydrotesting work for newly laid pipeline 6” Gas Lift Pipeline DW-PP and 6” Gas Lift DW-PP in total length 6.3 Km.

Mechanic

September 2011 – October 2011

Offshore Construction Specialists Pte Ltd

Project : Kangean Energy Indonesia Ltd. –Pre-Commissioning Services for Subsea Facilities

Page 3 of 5

Location : TSB Field, Kangean Block – Bali Sea Indonesia.

Offshore Pigging and Hydrotesting work on DSV.Crest Odyssey of 25.745km x 18” Rigid Pipeline and 2 nos of 5.2km x 20” Rigid Pipelines

Mechanic

February 2011 – July 2011

Offshore Construction Specialists Pte Ltd

Project : CHEVRON 2011 INSTALLATION CAMPAIGN.

PLATFORMS AND PIPELINES INSTALLATION Location : Chevron Thailand Oil and Gas Fields, Gulf of Thailand

Flooding and gauging work of newly laid pipelines:

16” NPPLL, 5.4 Km Long Pipeline 10” FUPLP, 5.9 Km Long Pipeline 10” PDPLB, 6,7 Km Long Pipeline 10” KPPLG, 2.7 Km Long Pipeline 10” ERPLZC, 2.4 Km Long Pipeline

As well leak testing of spools before subsea tie in of:

NPWL Platform (3 ea x 16” Spools) FUWP Platform (2 ea x 10” Spools) PDWB Platform (5 ea x 10” Spools) KPWG Platform (2 ea x 10” Spools) ERWZC Platform (2 ea x 10” Spools) Mechanic

January 2010 – March 2010

Offshore Construction Specialists Pte Ltd

Project : Hess (Indonesia – Pangkah) Ltd. – Ujung Pangkah Development Project.

Location : Ujung Pangkah oil & gas field, East Java. Indonesia

Pigging, Hydrotesting and Leak test work of 3 subsea flowlines, 6”, 12” and 16” between WHP B and WHP A.

Mechanic

August 2009 to November 2009

Offshore Construction Specialists Pte Ltd

Project : Star Energy Ltd. – Kakap Gas Development Project.

Location : Kakap Field West Natuna, Indonesia.

Offshore Pigging and Hydrotesting work for newly laid pipeline:

 6” gas flowline, 2.3 Km long, KG-West 1 subsea wellhead to KG Platform,

 6” gas flowline, 2 Km long, Lukah-1X subsea wellhead to KG Platform

 10” pipeline 11.2 Km long. KG Platform to KF Platform Mechanic and Project Leader Man

March 2009 - June 2009

Offshore Construction Specialists Pte Ltd

Project : Serica Energy – Asia Petroleum Development Project

Location : Gelagah Kambua Field Development, Malacca Strait, North Sumatra, Indonesia

Diameter 14” 42 Km long Pipeline installations from WHP Kambuna A to onshore receiving facilities, 5km beach pull preparation operation (trenching Work), 10km jetting operation, lowering pipeline 2mtr TOP. Pre-commissioning of laid pipeline

Task Description

Mechanic & Leader man on 5KM trenching work from near shore to shore for beach pull operation, ensure the generator, air compressor and 2 unit of excavator running in good condition for 24hrs trenching operation. Maintain 24hrs operation on 5 unit jetting pumps during jetting operation and pre-commissioning job including pigging operation and hydrotesting of Dia. 14”, 42 KM pipeline.

Mechanic 1

February 2002 – August 2008 J.Ray McDermott,

Location : Batam, Indonesia

Marine onshore facility maintenance and projects preparation.

Task Description

Maintain all running heavy equipments in marine onshore facilities to ensure working in best performance. Refurbish and prepare including function test of marine E&M equipment before send to offshore for project including forklift, loader, Skagit Winch, Hydraulic Hammer, Generators, Compressors.

Special in preparing flooding pumps and high pressures pumps for offshore use.

Mechanic and Project Leader Man March 2006 – July 2006

J.Ray McDermott

Project : PM3-Camau (Offshore Gas Pipeline Installation) Location : Vietnam

Dia.16” 300KM long Pipeline installation. Beach pull preparation, 6KM trenching from near shore to shore operation to buried pipeline in various depth from 4mtr near shore to 6mtr at offshore

Task Description

Mechanic & Leader man on 6KM trenching work from near shore to shore for beach pull operation, ensure the generator, air compressor and 2 unit of excavators running in good condition for 24hrs trenching operation. Maintain 24hrs operation on 6 unit jetting pumps during jetting operation.

Mechanic 1

May 1990 – July 1999 PT. McDermott Indonesia Location : Batam, Indonesia

Fabrication yard facility maintenance Task Description

Maintain all running heavy equipments and engines in Batam fabrication yard including: fork lift, hydraulic crane, loader, generators and compressors.

Page 5 of 5

Mechanic Helper

August 1987 – June 1989 PT. Barakaz Lumber Coy Location : Riau, Indonesia Logging Operation

Task Description

Helping mechanic in maintain heavy equipment including Bulldozer, Low Vehicle Trailer, Fork Lift, Compressors and Generators.

Mohd Zakaria Bin Abdul Aziz

Mechanic / Technician Nationality: Malaysian

Date of Birth: 11-March-1986 Marital Status: Single

Languages: English and Bahasa Melayu

Education / Training

 High School Graduate

 Basic Offshore Safety Induction & Emergency Training Including Additional OLF Modules and Travel Safety By Boat (OPITO Approved)-Validity 06-Jan-2015

Career Summary

Eight years of experience in offshore construction and engineering as a technician commissioning team. Specialists in Pipeline Pigging, Flooding, Hydro Test, Dewatering, Drying, Nitrogen Purging, Commissioning & Decommissioning

He start his career in November 2004 in Oil and Gas Pipeline Installation and commissioning and he’s project completion and work experience in Malaysia and Singapore.

During his time as a technician, he gained much experience in the offshore jobs for Cleaning, Hydro Testing, Dewatering, Drying and Nitrogen Packing.

He is also familiar with the Blowing, Flushing and Leak Testing jobs

.

Work Experience

Mechanic

Jan 2010 to present

Offshore Construction Specialists Pte Ltd

Page 2 of 6

Responsible for the maintaining High Pressure pumps and Flooding Pumps in good condition after project and prepare, function test of High Pressure pumps and Flooding Pumps before offshore work.

Operate and ensure High Pressure Pumps and Flooding pump working in good condition for Pre-commissioning work.

Completed Projects:

Mechanic

July 2013 – August 2013

Offshore Construction Specialists Pte Ltd Project : TIMAS-EHMRS

Location : Indonesia – South China Sea

Provision of Engineering Services and Subcontract Equipment associated with the installation of Flexible flowlines for COPI Belanak Project

Precom Technican July 2013

Project: Hess Exploration & Production Malaysia BV. FPSO for FPSO North Malay Basin – Grouting Project

Location: North Malay Basin (Kota Bahru)

Kamelia Field – precommissiong work for Flooding Production, Storage and offloading vessel Lewek Arunothai.

Mechanic

January 2013 – April 2013

Offshore Construction Specialists Pte Ltd

Project : Asian Energy Services – AES VSP Dangdo Thang Long Launch Location : Su Tu Vang Field, Thang Long-Dong Do Field, Vietnam

The preparation, rig up and execution of the jacket launch. The jacket weighed 4100mT was loaded and launch off the launch engineering, procedure preparation, physical barge rig up and site supervision and management of the launch operation, while Asian Energy performed the launch and transportation engineering.

Mechanic

August 2012 – January 2013

Offshore Construction Specialists Pte Ltd

Project : Chevron (Australia) – Domgas Pipeline Installation Project Location : Domgas Field Development, North West Coast of Australia

Jetting services for the 6” & 20” pipeline 1.5 km and 5.9km CW-DW and PPP-DW installation Task Description

Jetting Technician responsible for operating of jetting spread, monitoring the performance of equipment and troubleshooting the jetting equipment in the event of equipment breakdown.

Mechanic

April 2012 to May 2012

Offshore Construction Specialists Pte Ltd

Project : Conoco Philips Indonesia – Develop the Bawal Field Location : Bawal Field – Natuna Sea

Offshore Pigging and Hydrotesting work for 14” newly laid pipeline to connect the two Bawal wells (BW1 and BW2) to inline Tee and valve assemblies on the new pipeline, using rigid spools.

Mechanic

September 2011 – October 2011

Offshore Construction Specialists Pte Ltd

Project : Kangean Energy Indonesia Ltd. –Pre-Commissioning Services for Subsea Facilities of TSB Field Development

Location : TSB Field, Kangean Block – Bali Sea Indonesia.

Offshore Pigging and Hydrotesting work on DSV.Crest Odyssey of 25.745km x 18” Rigid Pipeline and 2 nos of 5.2km x 20” Rigid Pipelines

Mac 2011 – May 2011

Offshore Construction Specialists Pte Ltd

Project : Dai Hung Field Development VSP -WHP DH2 JACKET LAUNCH Project Location : VietsovPetro, Vung Tau, Vietnam

Commence reeving of port side sheave blocks using a messenger to pull 56mm wire through 500T construction blocks back to 70t hydraulic winch. ‘Straight’ lace configuration. Launched with VSP-05 (WD ~100m)

 EMAS - Chevron Offshore (Thailand) Ltd.

 HESS (Indonesia-Pangkah) Ltd Phase II Transportation and Installation Location - Surabaya, East Java Sea, Indonesia

Transport of CPP Deck, AUP Deck and LQ, Compression module, Bridges and flare boom

CPP and AUP Jackets were installed during the first campaign in the 4th Quarter 2010 utilizing the DLB QP 2000. CPP and AUP jackets are 4 legged jackets with an approximate unit weight of 300 tonne and 48” diameter steel pile foundations. The piles were driven with a MHU270T to 95 meter penetration.

HESS Ujung Pangkah –Phase 1 Location - East Java Sea, Indonesia

Transporation and Installation of one 8 legged Well Head platform (WHP-B) and 3 pipelines (6”

Gas lift, 12” Oil and 16” Gas) x ~5.5km between WHP-B and WHP-A (existing) including pre-commissioning.

Page 4 of 6

Kakap Field KG Gas Development Project – Provision of EPCI of KG Gas Development Project Services including pre-commissioning.

Project: REINSTATEMENT TEST FOR CAKERAWALA TOP SIDE N2 HE LEAK TEST FOR BULAN A Client: Pertonas Carigali

Year: (Dec) 2007

Scope of work: Leak testing.

Project: EPCC of Segamat Compressor Station Expansion Project

Client:

PETRONAS GAS

Year: (July) 2007

Scope of work: Blowing,Flushing,Hydrotesting and Nitrogen Packing

Project: EPCC of Nutral Gas Disiribution to Semenyih

FL stage 1/05 Jalan Persekutuan 1 Semenyih-Beranang Client: Gas Malaysia

Year: (Mar) 2007

SCOPE OF WORK: CLEANING, HYDRO TEST, DEWATERING, DRYING, NITROGEN PACKING.

Project: EPCC of Nutral Gas Disiribution to Kundang

FL DL stage 1/05 Kundang Sungai Buloh Selangor.

Client: Gas Malaysia Year: (Jan) 2006

Scope of work: Cleaning,Hydro Test,Dewatering,Drying,Nitrogen Packing

Project: EPCC of Nutral Gas Disiribution to Setiawan FL stage 2/05 Setiawan Perak.

Client: Gas Malaysia

Year: (Feb)2006

Scope of work: Cleaning,Hydro Test,Dewatering,Drying,Nitrogen Packing.

Project: EPCC of Nutral Gas Disiribution to Kapar

FL stage 1/05,Kapar Klang Selangor.

Client: Gas Malaysia Year: (Jan) 2006

Scope of work: Cleaning,Hydro Test,Dewatering,Drying,Nitrogen Packing.

Project: EPCC of Nutral Gas Distribution System to Sungai Buloh FL Stage 3/05, Sungai Buloh selango

Client: Gas Malaysia.

Year: (Dec)2005

Scope of work: Cleaning, Hydro Test, Dewatering, Drying and Nitrogen Packing.

Project: EPCC of GPRW at Road B15 From SKVE to KVDT Precint 11, Putrajaya Selangor.

Client: Gas Malaysia.

Year: (Dec)2005

Scope of Work: Cleaning, Hydro Test, Dewatering, Drying and Nitrogen Packing.

PROJECT: EPCC OF NUTRAL GAS DISTRIBUTION SYSTEM TO NORTH PORT

FL DL STAGE 1/05, PORT KLANG SELANGOR.

Client: Gas Malaysia.

Year: (Nov)2005

Scope of Work: Cleaning, Hydro Test, Dewatering, Drying and Nitrogen Packing.

Project: EPCC of Nutral Gas Disiribution to Bukit Rambai FL DL Stage 1/05 Bukit Rambai Melaka

Client: Gas Malaysia Year: (Oct) 2005

Scope of work: Cleaning,Hydro Test,Dewatering,Drying,Nitrogen Packing

Project: EPCC of Nutral Gas Disiribution to Tangga Batu

FL DL Stage 1/05 Tangga Batu Area Melaka.

Client: Gas Malaysia

Year: (Sept)2005

Scope of work: Cleaning, Hydro Test, Dewatering, Drying, Nitrogen Packing.

Project: EPCC of Nutral Gas Disiribution System to Ayer Keroh FL DL Stage 1/04, Industri Area Ayer Keroh Melaka.

Client: Gas Malaysia.

Year: (Sept)2005

Scope of work: Cleaning, Hydro Test, Dewatering, Drying and Nitrogen Packing.

Project: EPCC of Nutral Gas Disiribution to Ijok

FL Stage 1/05, Ijok, Kuala Selangor

Client: Gas Malaysia

Year: (Jun) 2005

Page 6 of 6

SCOPE OF WORK: CLEANING, HYDRO TEST, DEWATERING, DRYING, NITROGEN

PACKING.

Project: EPCC of Nutral Gas Disiribution System to Pasir Gudang FL DL Stage 1/05, Pan Century Edible Oils Sdn Bhd.

Client: Gas Malaysia.

Year: (Sept)2005

Scope of work: Cleaning, Hydro Test, Dewatering, Drying and Nitrogen Packing.

Project: EPCC of Nutral Gas Disiribution to Pulau Indah-Westport

Project: EPCC of Nutral Gas Disiribution to Pulau Indah-Westport