PIPELINE PRE-COMMISSIONING
PRE-QUALIFICATION DOCUMENT
Offshore Construction Specialists (OCS)
20 Toh Guan Road
CJ GLS Building #07-02
Singapore 608839
Tel: +65 6567-9080
Fax: +65 6567-8082
Web: http://www.offshore-ocs.com/index.html
Contact Information
Contact Company Position Email Address.
Keith Jackson Managing and Technical Director [email protected]
Seto Jian Operations Manager [email protected]
William Wijaya Project Manager [email protected]
Loke Kah Poh Project Manager [email protected]
Rakul Remanan Engineering Manager [email protected]
Henry Chuy Subcontracts & Procurement Manager [email protected]
Alastair Wong Senior Project Engineer [email protected]
TABLE OF CONTENTS
1. INTRODUCTION ... 3
2. OCS ORGANISATION CHART ... 4
3. TYPICAL PRECOMMISSIONING ORGANISATION CHART... 6
4. PIPELINE PRECOMMISSIONING ACTIVITIES ... 7
5. SAFETY AND SAFE WORKING PRACTICES. ... 7
6. ENGINEERING AND PROCEDURES. ... 8
7. PROCUREMENT. ... 8
8. FABRICATION. ... 8
9. PIPELINE FLOODING, CLEANING AND GAUGING. ... 8
10. PIPELINE INTELLIGENT AND CALLIPER PIGGING. ... 8
11. PIPELINE HYDROTESTING ... 8
12. PIPELINE BULK DEWATERING ... 8
13. PIPELINE AIR DRYING. ... 8
14. PIPELINE VACUUM DRYING ... 8
15. NITROGEN PACKING ... 8
16. EXISTING AND PAST CLIENTS ... 9
17. COMPLETED PROJECTS ... 10
18. EQUIPMENT DATA SHEETS ... 18
1. INTRODUCTION
Offshore Construction Specialists (OCS) was formed in 2007 from a core group of marine construction engineers to provide construction management, engineering and strategic support equipment services primarily to the offshore oil and gas sector.
Our key personnel come from previous careers at J.Ray McDermott in the marine operations department. Our managing and technical director Mr Keith Jackson worked for 17 years in the group the last 5 years as the marine division manager.
As a matter of policy under Mr Jackson J.Ray McDermott would execute work peripheral to that being undertaken by the major work vessel (normally executed using third party subcontractors) using in-house resources. Pipeline pre-commissioning, pre and post trenching, flexible flowline / umbilical lay are examples of work that was routinely carried out in-house and not subcontracted. One of the main reasons for doing this was that it prevented the activities of the subcontractor impinging on the work of the high cost marine spread. The work was always planned with maximum operational synergy in mind
In JRM large pipeline pre-commissioning projects such as the 650 km West Natuna gas gathering pipeline network and many other major projects were planned and executed in-house. OCS has taken the model developed in JRM and applied it to our own activities. Our equipment is managed and operated by people who come from the same background as the main marine contractor. We help the marine contractor plan the work such that the pre-commissioning has the least impact on operations. We are proactive in highlighting potential issues and ensuring both parties win. Our engineering capabilities are very sophisticated and significantly more advanced than our competitors.
OCS has now completed a range of pre-commissioning projects for many different customers with great success. OCS is certified by Nata for pipeline hydrotesting which is the preeminent qualification for pre-commissioning contractors. The OCS organisation has also been qualified to IS0 9001 since 2009.
Our in-house equipment spread has grown significantly and is described in detail in this document. OCS is equipped to handle the full range of pre-commissioning activities including flooding, cleaning, gauging, hydrotesting, dewatering, drying and nitrogen packing. We work with established intelligent and caliper pig suppliers to complement our service. We have established long term relationships with key Singapore and overseas vendors.
OCS is equipped to handle large projects or discrete project elements depending on the specific needs of the customer.
The company has grown steadily since incorporation and now employs 60 personnel of whom 30 are civil/structural and mechanical engineers working with our pre-commissioning technicians. The company office in Toh Guan Rd, Singapore has been leased until 2014 and has room for additional expansion. The office can accommodate customer representatives for liaison as necessary.
2.
OCS ORGANISATION CHART
KEY PERSONNEL CONTACTS
Keith Jackson Managing and Technical Director [email protected]
Seto Jian Operations Manager [email protected]
William Wijaya Project Manager [email protected]
Loke Kah Poh Project Manager [email protected]
Rakul Remanan Engineering Manager [email protected]
Henry Chuy Subcontracts & Procurement Manager [email protected]
Alastair Wong Senior Project Engineer [email protected]
PROJECT & CONSTRUCTION MANAGEMENT PROCUREMENT & SUBCONTRACTS SETO JIAN OPERATIONS MANAGER KP LOKE PROJECT MANAGER NG BEE KIM
ACCOUNTS, HR & ADMIN LEAD
CHUY CHUN FEI
SUBCONTRACTS & PROCUREMENT MANAGER CONSTRUCTION ENGINEERING FIELD CONSTRUCTION OPERATIONS SAYED DEDY PRE-COMM ENGINEER DRAFTING PRAVIN THORAT SENIOR STRUCTURAL ENGINEER SUDHAKAR ANDY K. PRIYA PANJIROSA ZIA AL AKBAR STRUCTURAL ENGINEERS CHANIN SRIYAPORN SNR. DRAFTING ALASTAIR WONG SNR PROJECT ENGINEER/ PRE-COMM MANAGER FERY WIJAYA PROJECT MANAGER BODIE MALLET SETTHA Y. IVAN CHAI (OPERATIONS/ SNR. FIELD ENGINEER) LENI TALAVERA RECEPTIONIST CUM ADMIN CLERK
KRISBEL BUDIMAN ZACK INDRA IDHAM TECHNICIANS MECHANICS OPERATIONS ADMINISTRATION GILBERT GREJALDO ACCOUNT EXECUTIVE UDAY SARATHY MOHAN CHAND SENIOR PIPELINE ENGINEER JOYCE LIM SUBCONTRACT / PROCUREMENT ADMINISTRATOR MONICA ZHANG ACCOUNTANT JULIANNE OOI HR ADMINISTRATOR ARYO PRAKOSO SNR. DRAFTSMAN CHARLESTAN BUYER / EXPEDITOR ACCOUNTS PLANT & EQUIPMENT ADI CAHYA AARON LIAN TRACY EE ZHONG ZHIYUAN DAVID SHAW CHEAH WIN LOONG CHATCHAI W. SEAN SIA TIN WEI DANIEL CAO FIELD ENGINEERS ENGINEERING RAMIL ZAPANTA VINOTH KUMAR DRAFTSMAN RAKULREMANAN ENGINEERING MANAGER OPERATIONS STRATEGIC EQUIPMENT
TEAM CONSTRUCTION FIELD SUPERVISION TEAM JAMIE JACOBSEN LEON COAD DAVID WOOD FIELD FOREMANS JAMES CARROLL FIELD
SUPERINTENDENT TRACY TEEURISA L
DOCUMENT CONTROLLER EQUIPMENT MANAGEMENT WILLIAM WIJAYA EQUIPMENT MANAGER *ADMINITRATION *ADMINITRATION SUPPORT TEAM: TRACY & URISA
JAW LE E & M COORDINATOR RONI GROUTING SUPERVISOR TOOLAYA R IT ENGINEER REMARK: HERYANTHO Y L TAUFAN S. SAINUL ABID SAVOY AMITH PRASAD NAVAL ARCHITECT
3. TYPICAL
PRECOMMISSIONING ORGANISATION CHART
OCS Pre-commissioning Team offshore ONSHORE OFFSHORE CLIENT KP LOKE WILLIAM WIJAYA PROJECT MANAGERS RAKUL REMANAN ENGINEERING MANAGER PRAVIN THORAT HERY LEMBANG SUDHAKAR SUBRAMANIAM UDAYSARATHY MOHAN ZIA AKBAR TAUFAN SIREGAR PRIYA PANJIROSA AMITH PRASAD SAVOY SAINUL ABID CONSTRUCTION SUPPORT ENGINEERS CHANIN SRIYAPORN ARYO PAKOSO RAMIL ZAPANTA VINOTH DRAFTING ALASTAIR WONG FERY WIJAYA PROJECT ENGINEERS SAYED DEDY MAHDI ADI CAHYA BODIE MALLET SETTHA Y. IVAN CHAI CHONG CHIA YAN AARON LIAN DAVID SHAW CHEAH WIN LOONG CHATCHAI SEAN SIA FIELD ENGINEERS HENRY CHUY SUBCONTRACTS & PROCUREMENT MANAGER JOYCE LIM EXPEDITOR/ BUYER CHARLES TAN BUYER/ SUBCONTRACTS EXECUTIVE
4. PIPELINE
PRECOMMISSIONING
ACTIVITIES
OCS experience embraces the full range of pipeline pre-commissioning activities from the initial flooding, cleaning, gauging and hydrotesting to dewatering, drying and nitrogen purging and packing.
Specific activities undertaken by OCS:
No. Description
1 Flooding, Cleaning and Gauging. 2 Calliper and Intelligent Pigging. 2 Hydrotesting 3 Dewatering/ Swabbing 4 Air Drying 5 Vacuum Drying 6 Nitrogen Purging 7 Nitrogen Packing
OCS provides a cradle to grave pipeline pre-commissioning services including complete engineering, procurement, fabrication and execution services. Our in-house inventory is extensive and our personnel are well trained.
5.
SAFETY AND SAFE WORKING PRACTICES
OCS is acutely aware of the dangers involved in the marine construction industry in general and in pipeline pre-commissioning particularly where high pressure water and air and heavy equipment, chemicals etc combine to create a range of potential hazards if not managed properly.
All OCS activities on specific projects are the subject of hazids and risk assessments to ensure levels of risk are reduced to as low as reasonably practical. These risk assessments are ideally attended by the main contractor and the ultimate client.
Other specific safety and operational measures that are taken:
i) All OCS personnel have appropriate Bosiet offshore sea survival training ii) OCS technicians are Nata qualified and well trained for their specific duties iii) All OCS equipment is provided with a specific safety passport.
iv) Offshore hazardous areas are barricaded as required and unauthorized personnel are excluded.
v) All installation aids are properly engineered and subject to structural checks by the OCS CSE group.
6.
ENGINEERING AND PROCEDURES
OCS prepares project specific engineering and procedures for each job undertaken. What sets OCS apart from other pre-commissioning contractors is our engineering skills base which means that all structural, mechanical, hydrodynamic and aerodynamic considerations are addressed in-house. OCS procedures will address:
i) Project specific procurement requirements.
ii) Equipment specification requirements and preparations.
iii) Designs of Pig launchers and receivers for Flooding, Cleaning and Gauging. iv) Designs of Hydrotest heads.
v) Designs of Pig Launchers and Receivers for Dewatering and Drying. vi) Pig Requirements and Designations.
vii) Intelligent and Calliper Pigging requirements. viii) Chemical injection requirements.
ix) Hydrotesting pressurization, strength and leak tests.
x) Bulk Dewatering.
xi) Drying Procedures using Air or Vacuum drying techniques. xii) Nitrogen Packing.
7. PIPELINE PRE-COMMISSIONING PROCEDURES
PLEASE REFER TO APPENDIX 1
8. FABRICATION
9.
PIPELINE FLOODING, CLEANING AND GAUGING
10. PIPELINE INTELLIGENT AND CALLIPER PIGGING
11. PIPELINE
HYDROTESTING
12. PIPELINE
BULK
DEWATERING
13. PIPELINE
AIR
DRYING
14. PIPELINE VACUUM DRYING
15. NITROGEN
PACKING
8 EXISTING AND PAST CLIENTS
OCS has built up a significant customer base during four (4) years of operations. OCS past and present clients are listed below. References can be provided on request.
No. Client Name
1 Star Petroleum ( Indonesia) 2 HESS ( Indonesia)
3 Asia Petroleum Developments (Salamander) ( Indonesia)
4 Kangean Energy ( Indonesia) 5 NuCoastal ( Thailand)
6 Chevron (Thailand)
7 EMAS ( Singapore)
8 Larsen & Toubro ( Malaysia/ India)
9 SapurasAcergy ( Malaysia)
10 TLO SapuraCrest ( Malaysia)
11 Heerema (Holland)
12 NorCe ( Singapore)
13 Offshore Marine Contractors
14 Vietsovpetro (VSP) (Vietnam)
15 Timas Suplindo ( Indonesia)
16 Nippon Steel (Indonesia)
17 Newfield Peninsula Malaysia ( Malaysia)
18 Franklin Offshore ( Singapore)
19 M3 Energy ( Malaysia)
20 Sarku ( Malaysia)
21 Hako Offshore ( Singapore)
22 Global Industries ( Malaysia)
23 Sea Drill ( Singapore)
24 Origin Energy (Australia)
25 Swiber ( Singapore)
26 Galoc ( Philipines)
9. COMPLETED
PROJECTS
Year Project Title Client Pipeline
Dia (“)
Length
(km) Scope Of Work Location
2007 GFI EOCP EMAS
offshore Construction and Production 10” 6” Flexible 0.8 0.1 Flood, Clean, Gauge and Hydrotest/Leak test Gulf of Thailand 2008 Galoc Development Project EOCP EMAS offshore Construction and Production 6 “ Spool 6” Flexible
0.7 Leak Test 65km off
North West Coast of Palawan Island 2008 Nexus Australia- Bass Strait
Nexus PLEM &
Startup Heads
- Leak Test Singapore
2009 Asia Petroleum
Development (APD) – Glagah
Kambuna Field Development
PT Timas 14 “ 42 Flood, Clean,
Gauge and Hydrotest From the Kambuna platform offshore North Sumatera to a landfall Northeast of Medan 2009 Star Petroleum Kakap Field Redevelopment PT Timas 10” 6” 6” 11.2 2 2.3 Flood, Clean, Gauge and Hydrotest Kakap Field located in the Indonesian West Natuna Sea 2009 M3nergy JDA Sdn Bhd/ Carigali-PTTEPI-JDA Block B-17 Franklin Offshore
11” Flexible 0.24 Leak Test Offshore Malaysia 2010 HESS Ujung Pangkah Development PT Timas 6” 12” 16” 5.5 5.5 5.5 Flood, Clean, Gauge, Hydrotest, Dewater, Air &
Vacuum Dry and Nitrogen Packing Ujung Pangkah, Gresik in Surabaya Indonesia
Year Project Title Client Pipeline Dia (“)
Length
(km) Scope Of Work Location
2011 Kangean Energy Indonesia Limited – TSB Development PT Timas 18” 20” 20” 25 5.5 5.5 Flood, Clean, Gauge and Hydrotest, Dewater, Dry and Nitrogen Packing Bali Sea, approximately 120km from Pagerubgan Island
2011 Kodeco Project PT Timas 6” 7 km &
6km Flood, Clean, Gauge and Hydrotest Java Sea 2011 Chevron (Thailand) EMAS 10” 16” 35 km & 35 km Flood, Clean, Gauge and Hydrotest Gulf Of Thailand 2011 TSB Kangean PT Timas 18” 20” 25.745 km & 5.2km Flood, Clean, Gauge and Hydrotest, Dewater, Dry and Nitrogen Packing Java Sea
2012 Bawal PT Timas 14” 40 km Flood, Clean,
Gauge and Hydrotest
Natuna Sea
2012 Bien Dong DOF Subsea 6” flexible 400m LeakTest Vietnam
2013 Zawtika L&T 18” 18” 11.3 km & 9.7km Flood, Clean, Gauge and Hydrotest Myanmar 2013 PTTEP Bongkot Riser Replacement
DOF Subsea 6” 80m LeakTest Gulf Of
Thailand 2013 Pertamina EP MOL Project Leighton Offshore 12” 28km Flood, Clean, Gauge, Hydrotest and Dewater Java Sea 2012 Pertamina UL Project
PT Timas 12” 12 km Flood, Clean,
Gauge and Hydrotest Java Sea 2012 Pertamina EP L-Parigi PT Timas 20’ / 14” 500m/3.3 km Flood, Clean, Gauge, Hydrotest Java Sea
2014 Petronas Ketapang
PT Timas 12” 111 km Flood, Clean,
Gauge, Hydrotest, Dewater, Dry, N2 Pack. 2014 Petronas Ketapang PT Timas 8/12”/16” 700 m each Flood, Clean, Gauge, Hydrotest, .
GFI (Thailand) Pigging and Hydrotesting Photos (Nov 2007 to Jan 2008)
Flexible Riser Leak For M3nergy JDA Sdn Bhd / Carigali-PTTEPI - JDA Block B-17, Offshore Malaysia. ( Sep 2009) Photos
Star Energy (KAKAP) Pipeline Project– Pigging & Hydrotest (Oct 2009) Photos
Asia Petroleum Development (APD) Pigging and Hydrotesting. - Glagah Kambuna Field Development Project (Mar 2009) Photos
HESS (UJUNG PANGKAH) Pipeline Project–
Pigging, Hydrotest, Dewatering, Drying & N2 Pack (Jan – Feb 2010) Photos
Chevron Thailand Project
Kangean Project
Pigging, Hydrotest, Dewatering, Air drying and N2 packing (Aug- Nov 2011) Photos
Kodeco Project
Zawtika Project, 2013
18. EQUIPMENT DATA SHEETS
OCS operates a comprehensive range of pre-commissioning equipment. Each piece of equipment has it own equipment passport which is maintained from project to project. This helps ensure that only appropriately maintained equipment is supplied to projects.
A sample of our equipment passport is included below.
7.1. FLOODING PUMP SERIES 1
FLOODING PUMP - 03 Nos.
Capacity 320 Cu.m / Hr
Maximum Head 171 meters
Engine Make Detroit Diesel 8V-92TA 450BHP
7.2. FEED PUMP
FLOODING PUMP - 02 Nos.
Capacity 1590 Cu.m / Hr
Maximum Head 25 meters
Engine Make Detroit Diesel 8V-92TA 450BHP
7.3. DIESEL DRIVEN FLOODING / JETTING PUMP SERIES 2
(HIGH PERFORMANCE)
FLOODING PUMP - 02 Nos.
Capacity 335 Cu.m / Hr
Maximum Head 260 meters
Engine Make Detroit Diesel 12V-149TI 1130BHP
7.4. DIESEL DRIVEN HIGH PRESSURE PUMP SERIES 2 (HIGH
PERFORMANCE)
HIGH PRESSURE DISEL DRIVEN
PUMP - 01 Nos.
Capacity 180 liters / Minute
Maximum Pressure 7250 psig
Engine Make Johndeere 160kw 6 cylinder diesel engine
Pump Make Woma 2502 P40
7.5. HIGH PRESSURE DISEL DRIVEN PUMP SERIES 1
HIGH PRESSURE DISEL DRIVEN
PUMP - 01 Nos.
Capacity 35-37 liters / Minute
Maximum Pressure 8000 psig
Engine Make Isuzu 50 HP-4 cylinder (turbocharged & water cooled)
Pump Make Den-Jet CD 40-550
7.6. HIGH PRESSURE AIR DRIVEN PUMP
HIGH PRESSURE AIR DRIVEN
PUMP - 01 Nos.
Capacity 20 liters / Minute
Maximum Pressure 7,500 psig
Maximum Air Supply Pressure 125 psig
HIGH PRESSURE AIR DRIVEN
PUMP - 04 Nos.
Capacity 4 liters / Minute
Maximum Pressure 600 psig
Maximum Air Supply Pressure 120 psig
7.7. DEAD WEIGHT TESTER DEAD WEIGHT TESTER + WEIGHT
SET - 02 Nos.
Make DH –BUDENBERG MODEL 580 DX
Range 0-700 bar
Accuracy 0.025 %
7.8. PRESSURE/TEMPERATURE RECORDER
PRESSURE RECORDER - 03 Nos.
Make BARTON
Range 0-5000 psi
Accuracy ± 1 % FS
TEMPERATURE RECORDER - 02 Nos.
Make SCOTECH Range 0-50o C Accuracy ± 1 % FS PRESSURE-TEMPERATURE DUAL RECORDER - 02 Nos. Make BARTON Range 0-5000 psi/0-100o C Accuracy ± 1 % FS
7.9. 8 X 10 FT BREAK TANK (18 Cu.m Capacity) - 01 Nos
7.10. VACUUM PUMP
VACUUM PUMP - 01 Nos.
Capacity 1020 Cu.m / Hr
Booster Make Edwards mechanical booster Model EH1200, Hydrokinetic Drive
Pump Make Edwards high vacuum pump Serial 220. EIM 275
7.11. PRESSURE TRANSDUCER & READOUT)
- 03 Nos.
Type 750C, ABSOLUTE PRESSURE TRANSDUCER
Make/ Range MKS
Accuracy/ Input/ Output
10 MILLIBAR , 100 MILLIBAR , 1000 MILLIBAR
1% OF FULL SCALE
+13 TO +32 VDCINPUT, 0-10VDC O/P
- 02 Nos.
Type DIGITAL SUPPLY AND READOUT
Make/ Range MKS
Input Power
7.12. HEATED REGENERATIVE DESICCANT AIR DRYER & AIR COOLED AFTER COOLER
Regenerative compressed air dryer use desiccant to absorb water vapour from the compressed airstream. In the twin tower design, one tower dries the air from the After-cooler while the dessicant in the other tower is being regenerated to provide continuous operation. A heater is added to heat the purge air. It not only benefits the regeneration effect but also decreases regeneration purge loss.
Desiccant: activated alumina + molecular sieve Purge air: <3 ~ 6%
Working pressure: 24 barg Inlet oil content: < 0.1 mg/m3
Pressure dew point: - 40oC to - 50oC Inlet temperature: - 0oC to 45oC Capacity: 150 Nm3/min
Heater: 50 kW
Dimension: 2.9 x 2.2 x 3.5m Weight: 5.9 mT
Lifting skid are mounted.
Air Cooled After Cooler is auxiliary equipment of air compressor, after which the high temperature and high pressure air is cooled. Most of the vapour is condensated and discharged out of compressor in order to meet the working conditions of downstream drying equipment. The medium of cooling is air.
Capacity: 150 Nm3/min Power requirement: 2.5 kW Dimension: 2.9 x 2.2 x 3.5m Weight: 5.9 mT
7.13. LIQUID N2 CONVERTER
1. Operating parameters:
Design temperature load bearing/pressure retaining –20 Deg to + 50 Deg C. Design temperature machinery –20 Deg to + 50 Deg C.
2. Diesel Engine
Detroit Diesel model 8V 71T
Rated to produce 420 BHP @ 2100 RPM. (Continuous) 3.. Gearbox
Marco 3 pad hydraulic pump drive gearbox
Marco Gearbox will be enclosed coupled on engine flywheel 4. Start System
Air starter 5 . Hydraulic System
Twin Commercial hydraulic pumps for Low and High pumping rate, motors and relief valves. heat exchanger.
6. Cryogenic High Pressure System Paul triplex.
Max. Pressure: 10,000 psi. Flow Rate: 3,000 SCFM. Discharge Temperature: 70o
F. 7. Control Panel
A stainless steel control panel 8. Skid/Frame
ATTACHMENT # 5 OCS NATA Certification
NATA is Australia’s government-endorsed laboratory accreditor, and a leader in accreditation internationally.
National Association of Testing Authorities, Australia
(ABN 59 004 379 748)
has accredited
Offshore Construction Specialists Pte Ltd
Singapore
following demonstration of its technical competence
to operate in accordance with
ISO/IEC 17025
This facility is accredited in the field of
MECHANICAL TESTING
for the tests, calibrations and measurements shown on the
Scope of Accreditation issued by NATA
Jennifer Evans
Chief Executive Officer
Date of accreditation:15 July 2013
Accreditation number:19122
ATTACHMENT # 6 OCS Personnel CVs
Offshore Construction Specialists Pte. Ltd.
Sayed Dedy Mahdy
Career Summary
• 4 Months University Field Practical, Tunu Field Development “Tunu Phase 8 EPSC 3 Project”- TotalFinaElf Indonesie.
• 9 Months as Field Engineer for PT. McConnell Dowell Indonesia.
• 1 year and 8 months working with PT McDermott Indonesia
• Currently working with Offshore Construction Specialists Pte. Ltd.
Experience
Field Engineer
June 2009 - January 2010
Amerada Hess Ujung Pangkah Phase 2, Indonesia
Offshore Construction Specialists Pte Ltd
• Responsible for all Offshore Pigging Operation, Hydrotesting and Leak test of 3 subsea flowlines, 6”, 12” and 16” between WHP B and WHP A.
• Manage the offshore operation at site, together with the barge supt & the other field engineers. Work included the wellhead platform, WHP B installation, 6”, 12” and 16” flowline installation between WHP B and WHP A. Post trenching of 6”, 12” and 16” flowline.
Field Engineer
Sept 2008 – May 2009
Asia Petroleum Development (APD) - Glagah Kambuna Project, Indonesia
Offshore Construction Specialists Pte Ltd
• Responsible for all Offshore Pigging Operation, Hydrotesting and Leak test of 42 km 14” gas export pipeline from the Kambuna platform offshore North Sumatera to a landfall north east of Medan.
• Manage the offshore operation at site, together with the barge supt & the other field engineers. Work included 5 km beach approach, Pre and Post trenching of 13 km of the pipeline to a cover of 2.0 metres. Topsides installation and Hook up.
• Responsible for all Offshore Pigging Operation, Hydrotesting and Leak test of 800mtr pipeline, Flexible risers and spools.
• Manage the offshore operation at site, together with the barge supt & the other field engineers. 1 jacket(sidelift & upend) + 1 deck + 2 pipeline (10 in) + 1 SPC + 1PLEM + 4 sp tie in (10 in) + 2 flexible riser (6 in) + 1 mooring hawser
Field Engineer
November 2006 – October 2007
Project : Kerisi Field Development Phase II CPP Jacket and Deck Installation
PT. McDERMOTT INDONESIA
Working with procedures and instruments preparation for 12”∅and 16”∅ spools hydrotesting. Responsible for almost all load out preparation for 3 material barges, 4 nos of Central Processing modules over 1000MT and 8 Legs Jacket load out for Central Processing Platform
Field Engineer
November 2006 – October 2007
Project : Angel Project – Substructure Installation and Pipelay
PT. McDERMOTT INDONESIA
Manage and supervise technical on field for fabrication of 5 sections Articulated Stinger and refurbishment 3 sections Articulated Stinger.
Field Engineer
January 2007 – August 2007 Project : SSB T&I
PT. McDERMOTT INDONESIA
Manage and supervise technical on field for structural modification 5 sections Articulated Gulf Of Mexico Stinger and refurbishment 3 sections Articulated Stinger and 1 section truss stinger.
Field Engineer
August 2006 – September 2006
Project : Kerisi Field Development Phase I
PT. McDERMOTT INDONESIA
Manage and supervise readiness of marine installation on field in subcontractor yard of 1420 MT Wellhead Platform and 1113 MT Jacket load out.
Field Engineer
July 2006 – August 2006
Project : PM3 Camau – Gas Pipeline
PT. McDERMOTT INDONESIA
Offshore Construction Specialists Pte. Ltd. Project : EMEPMI Seligi A- To Tapis Pump Pipeline Replacement
PT. McDERMOTT INDONESIA
Prepared and manage of fabrication and refurbishment for engineering installation aid for 18”∅ crude pipeline installation, assisting in procedures and instruments preparation associated with pigging and hydrotesting. Over 60 days was spent offshore time on board DB30 to manage 21,2 KM 18”∅ crude pipeline installation, riser and two sub sea spool trough the commissioning stage.
Field Engineer
December 2005 – January 2006
Contract Value USD 2.5m – PT. NewMont NTT. Batu Hijau-Scavenger Maintenance Phase I
PT. McCONNELL DOWELL INDONESIA
Performance as Project Planner for Scavenger Shut Down Project on PT. NewMont NTT. Project Mobilization coordinator and controlling material take off.
Field Engineer
April 2005 – December 2005
Contract Value USD 4.6m + USD 1,2m Variation – Kaltim Prima Coal Service Wharf and Shiploader Jetty Refurbishment.
PT. McCONNELL DOWELL INDONESIA
Employed with PT McConnell Dowell Indonesia to manage the shiploader jetty and service wharf rehabilitation works contract. Contract involves the partial demolition and reinstatement of 15years old reinforced concrete service wharf at KPC and rehabilitation of Structural steel shiploader jetty paintwork.
Field Practical
April 2002 - June 2002
Contract Value – USD 3.5m - Tunu Field Development Phase 8-EPSC 3, Aerial Pipe Installation
PT. CITRA PANJI MANUNGGAL
• Preparing Pilling Equipment that Needed for Pilling Activities
• Responsible for daily Report
• Assisting Surveying
• Liaise with third Party Inspector Badan Kualifikasi Indonesia (BKI)
• Assisting with application of work Permit
Diponegoro University, 2004
On Job Training and Courses
HUET – MSTS ASIA SDN. BHD, Johor Malaysia, 2006 Sea Survival – MSTS ASIA SDN. BHD, Johor Malaysia, 2006 Fire Fighting – MSTS ASIA SDN. BHD, Johor Malaysia, 2006
Wire Rope Inspector - Carl Stahl Evita Ltd, Batam Indonesia, February 2007 Field Engineer training 1st Module : General Topics, Singapore, 2007 Field Engineer training 2nd Module : Structural Installation, Singapore 2007
Incident Investigation training, Batam, Indonesia 2007 Task Risk Assessment training, Batam, Indonesia 2007
Firms
Nov 2007 Offshore Construction Specialist
Jan 2006 to 8 Oct 2007 PT McDermott Indonesia
Apr 2005 to Dec 2005 PT Mc Connell Dowell Indonesia
Personal Details
Date of Birth : November 29, 1979
Age : 34
Nationality : Indonesian Citizenship
Languages : Bahasa Indonesia – oral & written
English – oral & written
Contacts : Mobile +62-8127011155
Page 1 of 2
PERSONAL DATA
Name : Roni
DOB : 20 August 1975
Place / DOB : Belawan
Sex : Male
Marital Status : Married
Nationality : Indonesia
Religion : Moslem
DOCUMENT
No Document Number Date Of Issued Date Of Expiry Place Of Issued
1 Passport W 259674 30 Nov 2010 30 Nov 2015 Batam
CERTIFICATE OF COMPETENCY
No Certificate Number Date OF
issued
Date Of Expiry
Place Of Issued 1. BOSIET & Travel Safely
by Boat - 24 Nov 2010 23 Nov 2014 Batam
WORK EXPERIENCES
Pre-Comm Supervisor
August 2013 to presentOffshore Construction Specialists Pte Ltd
Responsible for the maintaining High Pressure pumps and Flooding Pumps in good condition after project and prepare, function test of High Pressure pumps and Flooding Pumps before offshore work. Operate and ensure High Pressure Pumps and Flooding pump working in good condition for Pre-commissioning work.
Completed Project:
No Company Project position Location Client Vessel Name Periode
1. Neptune SONSUB Grouting
Tech
Thailand PTT BODO
SUPLIER
10 Aug 2004 25 Sept 2004
2. Neptune SAIPEM Grouting
Tech
Chinese SAIPEM MERMAID
OFFSHORE
18 Jun 2006 29 Jul 2006
3. Neptune HYUNDAI Grouting
Tech Indonesia/ Kalimantan TOTAL HYUNDAI OFFSHORE 1 09 Jul 2007 20 Aug 2007
4. Neptune SWIBER Grouting
Tech
Brunei BSP SHELL SARKU 2000 06 Oct 2007 30 Dec 2007
5. Neptune SWIBER Grouting
Tech
Brunei BSP SHELL SWIBER
GLORIOUS
07 May 2008 11 Jul 2008 6. Neptune SUBSEA 7 Grouting
Tech
Malaysia PETRONAS ROCK WATER
2
15 Sept 2008 20 Oct 2008
7. Neptune SWIBER Grouting
Tech
Brunei BSP SHELL SWIBER
RESOLUTE
05 Jan 2009 10 Mar 2009
8. Neptune SWIBER Grouting
Tech
Myanmar SWIBER SWIBER 05 Apr 2010
30 May 2010
9. Neptune HALLIN Grouting
Tech Indonesia/ Aceh EXXON MOBIL PENRITH 27 Nov 2011 18 Jan 2012
10. Neptune CRUEZ Grouting
Tech Indonesia/ Natuna CONOCO PHILLIPS CRUEZ SUPPOTER 08 Sep 2012 28 Oct 2012
11. Neptune HALLIN Supervisor Thailand PTT KENDAL 31 Des 2012
29 Jan 2013
12. Neptune ALESTA Grouting
Tech
Turkey/ Istanbul
DOGTAS DEEP BLUE 06 Feb 2013
04 Mar 2013
13. Neptune Seamat
mattresses
Supervisor Brunei BSP SHELL ONSHORE 25 Mar 20013
Page 1 of 5
NAME: KRISBEL SIMANJUNTAK
DATE OF BIRTH 4 May 1963
NATIONALITY Indonesian
MARITAL STATUS Married
EDUCATION/TRAINING :
May 07, 2007. Basic Offshore Safety Induction & Emergency Training Including Additional OLF Modules (OPITO Approved)
February 06, 2007. Confine Space Entry and Rescue.
LANGUAGES Bahasa Indonesian (written and spoken)
English (Fair Spoken)
Career Summary
Over 26 years experience in maintain heavy equipment, engines, High Pressure pumps and flooding pumps, pipe fittings, operating related machinery.
Work Experience
Mechanic
Mar 2009 to present
Offshore Construction Specialists Pte Ltd
Responsible for the maintaining High Pressure pumps and Flooding Pumps in good condition after project and prepare, function test of High Pressure pumps and Flooding Pumps before offshore work. Operate and ensure High Pressure Pumps and Flooding pump working in good condition for Pre-commissioning work.
Completed Projects
Oct 2013 – Nov 2013
Offshore Construction Specialists Pte Ltd Project : Leighton Offshore
Location : Jakarta - Cirebon
S513 Main Oil Line from X-Ray Field to Balongan Plant Project
Task Description
Jetting Technician
April 2013 – May 2013
Offshore Construction Specialists Pte Ltd
Project : Brunei Shell Petroluem – Domgas Pipeline Installation Project Location : Bulan Bulan Field Development - Brunei
Jetting services for the Pile Refusal Remedial Project
Task Description
Jetting Technician responsible for operating of jetting spread, monitoring the performance of equipment and troubleshooting the jetting equipment in the event of equipment breakdown.
Jetting Technician
August 2012 – January 2013
Offshore Construction Specialists Pte Ltd
Project : Chevron (Australia) – Domgas Pipeline Installation Project Location : Domgas Field Development, North West Coast of Australia
Jetting services for the 6” & 20” pipeline 1.5 km and 5.9km CW-DW and PPP-DW installation
Task Description
Jetting Technician responsible for operating of jetting spread, monitoring the performance of equipment and troubleshooting the jetting equipment in the event of equipment breakdown.
Mechanic
April 2012 to May 2012
Offshore Construction Specialists Pte Ltd
Project : Conoco Philips Indonesia – Develop the Bawal Field Location : Bawal Field – Natuna Sea
Offshore Pigging and Hydrotesting work for 14” newly laid pipeline to connect the two Bawal
wells (BW1 and BW2) to inline Tee and valve assemblies on the new pipeline, using rigid
spools.
Mechanic
October 2011 – November 2011
Offshore Construction Specialists Pte Ltd
Project : Korea Development Company LTD. – Gas Lift Compression Project. Location : Poleng Field – Gresik, West Java, Indonesia.
Offshore Pigging and Hydrotesting work for newly laid pipeline 6” Gas Lift Pipeline DW-PP
and 6” Gas Lift DW-PP in total length 6.3 Km.
Mechanic
September 2011 – October 2011
Offshore Construction Specialists Pte Ltd
Page 3 of 5
Location : TSB Field, Kangean Block – Bali Sea Indonesia.
Offshore Pigging and Hydrotesting work on DSV.Crest Odyssey of 25.745km x 18” Rigid
Pipeline and 2 nos of 5.2km x 20” Rigid Pipelines
Mechanic
February 2011 – July 2011
Offshore Construction Specialists Pte Ltd
Project : CHEVRON 2011 INSTALLATION CAMPAIGN. PLATFORMS AND PIPELINES INSTALLATION Location : Chevron Thailand Oil and Gas Fields, Gulf of Thailand
Flooding and gauging work of newly laid pipelines: 16” NPPLL, 5.4 Km Long Pipeline
10” FUPLP, 5.9 Km Long Pipeline 10” PDPLB, 6,7 Km Long Pipeline 10” KPPLG, 2.7 Km Long Pipeline 10” ERPLZC, 2.4 Km Long Pipeline
As well leak testing of spools before subsea tie in of: NPWL Platform (3 ea x 16” Spools)
FUWP Platform (2 ea x 10” Spools) PDWB Platform (5 ea x 10” Spools) KPWG Platform (2 ea x 10” Spools) ERWZC Platform (2 ea x 10” Spools) Mechanic
January 2010 – March 2010
Offshore Construction Specialists Pte Ltd
Project : Hess (Indonesia – Pangkah) Ltd. – Ujung Pangkah Development Project. Location : Ujung Pangkah oil & gas field, East Java. Indonesia
Pigging, Hydrotesting and Leak test work of 3 subsea flowlines, 6”, 12” and 16” between WHP B and WHP A.
Mechanic
August 2009 to November 2009
Offshore Construction Specialists Pte Ltd
Project : Star Energy Ltd. – Kakap Gas Development Project. Location : Kakap Field West Natuna, Indonesia.
Offshore Pigging and Hydrotesting work for newly laid pipeline:
6” gas flowline, 2.3 Km long, KG-West 1 subsea wellhead to KG Platform, 6” gas flowline, 2 Km long, Lukah-1X subsea wellhead to KG Platform 10” pipeline 11.2 Km long. KG Platform to KF Platform
Mechanic and Project Leader Man
March 2009 - June 2009
Offshore Construction Specialists Pte Ltd
Location : Gelagah Kambua Field Development, Malacca Strait, North Sumatra, Indonesia
Diameter 14” 42 Km long Pipeline installations from WHP Kambuna A to onshore receiving facilities, 5km beach pull preparation operation (trenching Work), 10km jetting operation, lowering pipeline 2mtr TOP. Pre-commissioning of laid pipeline
Task Description
Mechanic & Leader man on 5KM trenching work from near shore to shore for beach pull operation, ensure the generator, air compressor and 2 unit of excavator running in good condition for 24hrs trenching operation. Maintain 24hrs operation on 5 unit jetting pumps during jetting operation and pre-commissioning job including pigging operation and hydrotesting of Dia. 14”, 42 KM pipeline.
Mechanic 1
February 2002 – August 2008
J.Ray McDermott,
Location : Batam, Indonesia
Marine onshore facility maintenance and projects preparation.
Task Description
Maintain all running heavy equipments in marine onshore facilities to ensure working in best performance. Refurbish and prepare including function test of marine E&M equipment before send to offshore for project including forklift, loader, Skagit Winch, Hydraulic Hammer, Generators, Compressors.
Special in preparing flooding pumps and high pressures pumps for offshore use.
Mechanic and Project Leader Man
March 2006 – July 2006
J.Ray McDermott
Project : PM3-Camau (Offshore Gas Pipeline Installation) Location : Vietnam
Dia.16” 300KM long Pipeline installation. Beach pull preparation, 6KM trenching from near shore to shore operation to buried pipeline in various depth from 4mtr near shore to 6mtr at offshore
Task Description
Mechanic & Leader man on 6KM trenching work from near shore to shore for beach pull operation, ensure the generator, air compressor and 2 unit of excavators running in good condition for 24hrs trenching operation. Maintain 24hrs operation on 6 unit jetting pumps during jetting operation.
Mechanic 1
May 1990 – July 1999
PT. McDermott Indonesia Location : Batam, Indonesia
Fabrication yard facility maintenance
Task Description
Maintain all running heavy equipments and engines in Batam fabrication yard including: fork lift, hydraulic crane, loader, generators and compressors.
Page 5 of 5
Mechanic Helper
August 1987 – June 1989
PT. Barakaz Lumber Coy Location : Riau, Indonesia Logging Operation
Task Description
Helping mechanic in maintain heavy equipment including Bulldozer, Low Vehicle Trailer, Fork Lift, Compressors and Generators.
Mohd
Zakaria
Bin
Abdul
Aziz
Mechanic / Technician
Nationality: Malaysian
Date of Birth: 11-March-1986
Marital Status: Single
Languages: English and Bahasa Melayu
Education / Training
High School Graduate
Basic Offshore Safety Induction & Emergency Training Including Additional OLF Modules and Travel Safety By Boat (OPITO Approved)-Validity 06-Jan-2015
Career Summary
Eight years of experience in offshore construction and engineering as a technician commissioning team. Specialists in Pipeline Pigging, Flooding, Hydro Test, Dewatering, Drying, Nitrogen Purging, Commissioning & Decommissioning
He start his career in November 2004 in Oil and Gas Pipeline Installation and commissioning and he’s project completion and work experience in Malaysia and Singapore.
During his time as a technician, he gained much experience in the offshore jobs for Cleaning, Hydro Testing, Dewatering, Drying and Nitrogen Packing.
He is also familiar with the Blowing, Flushing and Leak Testing jobs
.
Work Experience
Mechanic
Jan 2010 to present
Page 2 of 6
Responsible for the maintaining High Pressure pumps and Flooding Pumps in good condition after project and prepare, function test of High Pressure pumps and Flooding Pumps before offshore work. Operate and ensure High Pressure Pumps and Flooding pump working in good condition for Pre-commissioning work.
Completed Projects:
Mechanic
July 2013 – August 2013
Offshore Construction Specialists Pte Ltd
Project : TIMAS-EHMRS
Location : Indonesia – South China Sea
Provision of Engineering Services and Subcontract Equipment associated with the installation of Flexible flowlines for COPI Belanak Project
Precom Technican July 2013
Project: Hess Exploration & Production Malaysia BV. FPSO for FPSO North Malay Basin – Grouting Project
Location: North Malay Basin (Kota Bahru)
Kamelia Field – precommissiong work for Flooding Production, Storage and offloading vessel Lewek Arunothai.
Mechanic
January 2013 – April 2013
Offshore Construction Specialists Pte Ltd
Project : Asian Energy Services – AES VSP Dangdo Thang Long Launch
Location : Su Tu Vang Field, Thang Long-Dong Do Field, Vietnam
The preparation, rig up and execution of the jacket launch. The jacket weighed 4100mT was loaded and launch off the launch engineering, procedure preparation, physical barge rig up and site supervision and management of the launch operation, while Asian Energy performed the launch and transportation engineering.
Mechanic
August 2012 – January 2013
Offshore Construction Specialists Pte Ltd
Project : Chevron (Australia) – Domgas Pipeline Installation Project Location : Domgas Field Development, North West Coast of Australia
Jetting services for the 6” & 20” pipeline 1.5 km and 5.9km CW-DW and PPP-DW installation
Task Description
Jetting Technician responsible for operating of jetting spread, monitoring the performance of equipment and troubleshooting the jetting equipment in the event of equipment breakdown.
Mechanic
April 2012 to May 2012
Offshore Construction Specialists Pte Ltd
Project : Conoco Philips Indonesia – Develop the Bawal Field Location : Bawal Field – Natuna Sea
Offshore Pigging and Hydrotesting work for 14” newly laid pipeline to connect the two Bawal
wells (BW1 and BW2) to inline Tee and valve assemblies on the new pipeline, using rigid
spools.
Mechanic
September 2011 – October 2011
Offshore Construction Specialists Pte Ltd
Project : Kangean Energy Indonesia Ltd. –Pre-Commissioning Services for Subsea
Facilities of TSB Field Development
Location
: TSB Field, Kangean Block – Bali Sea Indonesia.
Offshore Pigging and Hydrotesting work on DSV.Crest Odyssey of 25.745km x 18” Rigid
Pipeline and 2 nos of 5.2km x 20” Rigid Pipelines
Mac 2011 – May 2011
Offshore Construction Specialists Pte Ltd
Project : Dai Hung Field Development VSP -WHP DH2 JACKET LAUNCH Project
Location : VietsovPetro, Vung Tau, Vietnam
Commence reeving of port side sheave blocks using a messenger to pull 56mm wire through 500T construction blocks back to 70t hydraulic winch. ‘Straight’ lace configuration. Launched with VSP-05 (WD ~100m)
EMAS - Chevron Offshore (Thailand) Ltd.
HESS (Indonesia-Pangkah) Ltd Phase II Transportation and Installation
Location - Surabaya, East Java Sea, Indonesia
Transport of CPP Deck, AUP Deck and LQ, Compression module, Bridges and flare
boom
CPP and AUP Jackets were installed during the first campaign in the 4th Quarter 2010
utilizing the DLB QP 2000. CPP and AUP jackets are 4 legged jackets with an
approximate unit weight of 300 tonne and 48” diameter steel pile foundations. The piles
were driven with a MHU270T to 95 meter penetration.
HESS Ujung Pangkah –Phase 1Location - East Java Sea, Indonesia
Transporation and Installation of one 8 legged Well Head platform (WHP-B) and 3 pipelines (6” Gas lift, 12” Oil and 16” Gas) x ~5.5km between WHP-B and WHP-A (existing) including pre-commissioning.
Page 4 of 6
Kakap Field KG Gas Development Project – Provision of EPCI of KG Gas Development ProjectServices including pre-commissioning.
Project:
REINSTATEMENT TEST FOR CAKERAWALA
TOP SIDE N2 HE LEAK TEST FOR BULAN A
Client:
Pertonas Carigali
Year:
(Dec) 2007
Scope of work:
Leak testing.
Project:
EPCC of Segamat Compressor Station Expansion Project
Client:
PETRONAS GAS
Year:
(July)
2007
Scope of work:
Blowing,Flushing,Hydrotesting and Nitrogen Packing
Project:
EPCC of Nutral Gas Disiribution to Semenyih
FL stage 1/05 Jalan Persekutuan 1 Semenyih-Beranang
Client:
Gas Malaysia
Year:
(Mar) 2007
SCOPE OF WORK: CLEANING, HYDRO TEST, DEWATERING, DRYING, NITROGEN
PACKING.
Project:
EPCC of Nutral Gas Disiribution to Kundang
FL DL stage 1/05 Kundang Sungai Buloh Selangor.
Client:
Gas Malaysia
Year:
(Jan) 2006
Scope of work:
Cleaning,Hydro Test,Dewatering,Drying,Nitrogen Packing
Project:
EPCC of Nutral Gas Disiribution to Setiawan
FL stage 2/05 Setiawan Perak.
Client:
Gas Malaysia
Year:
(Feb)2006
Scope of work:
Cleaning,Hydro Test,Dewatering,Drying,Nitrogen Packing.
Project:
EPCC of Nutral Gas Disiribution to Kapar
FL stage 1/05,Kapar Klang Selangor.
Client:
Gas Malaysia
Year:
(Jan) 2006
Project:
EPCC of Nutral Gas Distribution System to Sungai Buloh
FL Stage 3/05, Sungai Buloh selango
Client:
Gas Malaysia.
Year:
(Dec)2005
Scope of work:
Cleaning, Hydro Test, Dewatering, Drying and Nitrogen Packing.
Project:
EPCC of GPRW at Road B15 From SKVE to KVDT Precint 11,
Putrajaya Selangor.
Client:
Gas Malaysia.
Year:
(Dec)2005
Scope of Work:
Cleaning, Hydro Test, Dewatering, Drying and Nitrogen Packing.
PROJECT:
EPCC OF NUTRAL GAS DISTRIBUTION SYSTEM TO NORTH PORT
FL DL STAGE 1/05, PORT KLANG SELANGOR.
Client:
Gas Malaysia.
Year:
(Nov)2005
Scope of Work:
Cleaning, Hydro Test, Dewatering, Drying and Nitrogen Packing.
Project:
EPCC of Nutral Gas Disiribution to Bukit Rambai
FL DL Stage 1/05 Bukit Rambai Melaka
Client:
Gas Malaysia
Year:
(Oct) 2005
Scope of work:
Cleaning,Hydro Test,Dewatering,Drying,Nitrogen Packing
Project:
EPCC of Nutral Gas Disiribution to Tangga Batu
FL DL Stage 1/05 Tangga Batu Area Melaka.
Client:
Gas Malaysia
Year:
(Sept)2005
Scope of work:
Cleaning, Hydro Test, Dewatering, Drying, Nitrogen Packing.
Project:
EPCC of Nutral Gas Disiribution System to Ayer Keroh
FL DL Stage 1/04, Industri Area Ayer Keroh Melaka.
Client:
Gas Malaysia.
Year:
(Sept)2005
Scope of work:
Cleaning, Hydro Test, Dewatering, Drying and Nitrogen Packing.
Project:
EPCC of Nutral Gas Disiribution to Ijok
FL Stage 1/05, Ijok, Kuala Selangor
Client:
Gas Malaysia
Page 6 of 6
SCOPE OF WORK: CLEANING, HYDRO TEST, DEWATERING, DRYING, NITROGEN
PACKING.
Project:
EPCC of Nutral Gas Disiribution System to Pasir Gudang
FL DL Stage 1/05, Pan Century Edible Oils Sdn Bhd.
Client:
Gas Malaysia.
Year:
(Sept)2005
Scope of work:
Cleaning, Hydro Test, Dewatering, Drying and Nitrogen Packing.
Project:
EPCC of Nutral Gas Disiribution to Pulau Indah-Westport
FL Stage 1/05, Pulau Indah Port Klang, Selangor.
Client:
Gas
Malaysia
Year:
(May)2005
NAME: INDRA JAYA DATE OF BIRTH 24 February 1979
NATIONALITY Indonesian
MARITAL STATUS Married
EDUCATION/TRAINING :
• Technical High School, Dabo Singkep
• Alkon, “Pressure vessel training”
• JRM, In-house, “Confined Space Entry And Rescue Training”
• JRM, In-house, “PTW Performing Training”
• JRM, In-house, “Pressure Vessel Training”
• JRM, In-house, “Dead Weight Tester Operating Training”
• AST, “ Over Head Crane Training”
• JRM, In-house, “BBSM”
LANGUAGES Bahasa Indonesian (written and spoken) English (Fair Spoken)
Career Summary
Over 7 years experience in repair and maintain instrumentation for pressure, temperature and flow measurement device i.e. Dead Weight Tester, Pressure Recorder, Pressure Gauge, Temperature Gauge, Temperature Recorder, Turbine Flow Meter, Pinger Detector, Subsea Temperature device, for offshore pre-commissioning work including in-house calibration check, pipe fittings, familiar with rigging certification system and operating related machinery.
Instrument Technician
March 2012 to present
Offshore Construction Specialists Pte Ltd
Responsible for the maintaining small flow High Pressure pumps, Pressure, Temperature and Flow measurement device for Pigging and hydrotesting operation and grouting for the following projects in Indonesia, Brunei and Myammar.
Page 2 of 3 Current Project:
Work Experience
Technician/Mechanic
Oct 2013 – Nov 2013
Offshore Construction Specialists Pte Ltd
Project : Leighton Offshore
Location : Jakarta - Cirebon
S513 Main Oil Line from X-Ray Field to Balongan Plant Project
Post Trenching, Free Span Correction, and Pre-commissiong Services
Task Description
Sep to Oct 2013
Offshore Construction Specialists Pte Ltd
Project : Su Tu Vang North East Development Project
Location : Vietnam
Task Description
Responsible for performing the cleaning, gauging, flooding, hydrostatic testing of pipelines Hydrotesting & Precommissioning.
April 2013 – May 2013
Offshore Construction Specialists Pte Ltd
Project : Swiber Shell - Air Lift Jetting
Location : Bulan Bulan Field Development - Brunei Jetting services for the Pile Refusal Remedial Project Task Description
Jetting Technician responsible for operating of jetting spread, monitoring the performance of equipment and troubleshooting the jetting equipment in the event of equipment breakdown.
Mechanic
January 2013 – April 2013
Offshore Construction Specialists Pte Ltd
Project : PTTEPI – Installation of WP1, 2 and 3 well platforms and Intrafield Sealines Location : Zawtika Field Development Project Phase I - Myamar
Offshore Pigging and Hydrotesting work on LTS 3000 for installation of WP1, 2, 3 Well Platforms including Jackets, Piles, jacket appurtenances and decks and WP2-ZPQ and WP3-ZPQ infield pipelines.
Mechanic
April 2012 to May 2012
Offshore Construction Specialists Pte Ltd
Project : Conoco Philips Indonesia – Develop the Bawal Field
Location : Bawal Field – Natuna Sea
Offshore Pigging and Hydrotesting work for 14” newly laid pipeline to connect the two Bawal wells (BW1 and BW2) to inline Tee and valve assemblies on the new pipeline, using rigid spools.
Hydrotesting Instrument Technician
26 January 2006 to 28 Feb 2012 PT. McDermott Indonesia
Responsible for the maintaining all hydrotesting instrumentations and related equipment and gears in good condition for onshore and offshore pre-commissioning work. Preparation of all related instrumentation and hydrotesting gears, work side by side with field engineer for offshore work. Maintenance of all JRM stinger for all air lines and water lines and tanks in good and water tight condition. Project Involved : • Camau Project • Kerisi Project • Esso Project • SUTUVANG Project • Sutuden Project • Rubi Project • Guntong A Project • Guntong B Project
• Dai Hung Project
• Bien Dong Project
• TGT Project
• Angel Project
• Chevron Project
• Sakhalin Project
Page 1 of 5
NAME: BUDIMAN SAGALA DATE OF BIRTH 16 Jul 1983
NATIONALITY Indonesian
MARITAL STATUS Single
MOBIL :+6281370977227 +6281372223565
EDUCATION/TRAINING :
• May 03, 2008 (MSTS) Tropical Basic Offshore Safety Induction & Emergency with EBS
• May 18, 2007 (J.Ray McDermott) Permit To Work
• December 21, 2006 (J.Ray McDermott) Confined Space Entry And Rescue
• November 27, 2006 (Indonesia Labor Department) Hoist Crane Operator
• May 2006, (DH. Budenberg) Dead Weight Tester Usage and Maintenance
• April, 2004 (Carl Stahl Evita Ltd), Level 1, Wire Rope Inspector
LANGUAGES Bahasa Indonesian (written & spoken) English (fair spoken)
Career Summary
Over 12 years experience in repair and maintain instrumentation for pressure, temperature and flow measurement device i.e. Dead Weight Tester, Pressure Recorder, Pressure Gauge, Temperature Gauge, Temperature Recorder, Turbine Flow Meter, Pinger Detector, Subsea Temperature device, for offshore pre-commissioning work including in-house calibration check, pipe fittings, familiar with rigging certification system and operating related machinery.
Work Experience
Instrument Technician
March 2009 to present
Offshore Construction Specialists Pte Ltd
Responsible for the maintaining small flow High Pressure pumps, Pressure, Temperature and Flow measurement device for Pigging and hydrotesting operation for the following projects in Indonesia, Thailand and Myammar.
Completd Project: Technician
Jul 2013 – Sep 2013
Offshore Construction Specialists Pte Ltd
Project : PERTAMINA EP - REROUTE GAS PL L-PARIGI-CILAMAYA
Location : PT TIMAS SUPLINDO,INDONESIA
Provision of Engineering Services associated with the Provision of Hot Tap and pipeline Lima complex by pass, perform the pipeline pre-commissioning on the assumption that the scope is as Flooding and gauging, hydrotesting, bulk dewatering and nitrogen packing to 5 psi pressure.
Technician
Nov – Dec 2013
Offshore Construction Specialists Pte Ltd
Project : PT Timas Suplindo
Location : Jakarta UL Project
Pre-commissiong Services
Task Description
Oct 2013 – Nov 2013
Offshore Construction Specialists Pte Ltd
Project : Leighton Offshore
Location : Jakarta - Cirebon
S513 Main Oil Line from X-Ray Field to Balongan Plant Project
Post Trenching, Free Span Correction, and Pre-commissiong Services
Task Description
Jan 2013 – Apr 2013
Offshore Construction Specialists Pte Ltd
Project : PTTEP MYANMAR – L&T-Zawtika Grouting Project
Location : PTTEP INTERNTIONAL LIMITED, Gulf of Moattama, Myanmar
Zawtika Field Development Project Phase 1A EPCI for WP1, WP2, WP3 and Intrafield Sealines – Flooding, Gauging and Hydrotesting of pipeline.
Technician
November 2012
Offshore Construction Specialists Pte Ltd
Project : Galoc Ph 2 Development – Leak Testing for 6” Flexible pipeline Project
Location : Bien Dong Development Field - Vietnam
Leak test for flexible riser and flowlines for 1 off 3” Fuel Gas Riser (347.5 m length, 76.2 mm ID) + 3” Fuel Gas Flowline (2060 m length, 76.2 mm ID)
Page 3 of 5
2 off 7” condensate riser (355.7 m and 365.5 m length, 177.8 mm ID) + 7” condensate flowline (2060 m length, 177.8 mm ID).
Task Description
Leak test for flexible riser and flowlines for 1 off 3” Fuel Gas Riser (347.5 m length, 76.2 mm ID) + 3” Fuel Gas Flowline (2060 m length, 76.2 mm ID) and 2 off 7” condensate riser (355.7 m and 365.5 m length, 177.8 mm ID) + 7” condensate flowline (2060 m length, 177.8 mm ID).
Technician
October 2011 – November 2011
Offshore Construction Specialists Pte Ltd
Project : Korea Development Company LTD. – Gas Lift Compression Project.
Location : Poleng Field – Gresik, West Java, Indonesia.
Offshore Pigging and Hydrotesting work for newly laid pipeline 6” Gas Lift Pipeline DW-PP and 6” Gas Lift DW-PP in total length 6.3 Km.
Technician
September 2011 – October 2011
Offshore Construction Specialists Pte Ltd
Project : Kangean Energy Indonesia Ltd. –Pre-Commissioning Services for Subsea Facilities
of TSB Field Development
Location : TSB Field, Kangean Block – Bali Sea Indonesia.
Offshore Pigging and Hydrotesting work on DSV.Crest Odyssey of 25.745km x 18” Rigid Pipeline and 2 nos of 5.2km x 20” Rigid Pipelines
Technician
February 2011 – July 2011
Offshore Construction Specialists Pte Ltd
Project : CHEVRON 2011 INSTALLATION CAMPAIGN. PLATFORMS AND PIPELINES INSTALLATION
Location : Chevron Thailand Oil and Gas Fields, Gulf of Thailand Flooding and gauging work of newly laid pipelines:
16” NPPLL, 5.4 Km Long Pipeline 10” FUPLP, 5.9 Km Long Pipeline 10” PDPLB, 6,7 Km Long Pipeline 10” KPPLG, 2.7 Km Long Pipeline 10” ERPLZC, 2.4 Km Long Pipeline
As well leak testing of spools before subsea tie in of: NPWL Platform (3 ea x 16” Spools)
FUWP Platform (2 ea x 10” Spools) PDWB Platform (5 ea x 10” Spools) KPWG Platform (2 ea x 10” Spools) ERWZC Platform (2 ea x 10” Spools)
Technician
Offshore Construction Specialists Pte Ltd
Project : Hess (Indonesia – Pangkah) Ltd. – Ujung Pangkah Development Project.
Location : Ujung Pangkah oil & gas field, East Java. Indonesia
Pigging, Hydrotesting and Leak test work of 3 subsea flowlines, 6”, 12” and 16” between WHP B and WHP A.
Technician
August 2009 to November 2009
Offshore Construction Specialists Pte Ltd
Project : Star Energy Ltd. – Kakap Gas Development Project.
Location : Kakap Field West Natuna, Indonesia.
Offshore Pigging and Hydrotesting work for newly laid pipeline:
• 6” gas flowline, 2.3 Km long, KG-West 1 subsea wellhead to KG Platform,
• 6” gas flowline, 2 Km long, Lukah-1X subsea wellhead to KG Platform 10” pipeline 11.2 Km long. KG Platform to KF Platform
Technician
November 2008 – June 2009
Offshore Construction Specialists Pte Ltd Project : Gelagah Kambuna Field Development Location : Malacca Strait, North Sumatra, Indonesia
Diameter 14” 42 Km long Pipeline installations from WHP Kambuna A to onshore receiving facilities, 5km beach pull preparation operation (trenching Work), 10km jetting operation, lowering pipeline 2mtr TOP. Pre-commissioning of laid pipeline
Task Description
Preparation of pre-commissioning equipments for Pigging and Hydrotesting operation. Set up offshore flooding and pigging operation for Diameter 14” 42 Km long newly laid Pipeline ensure sea water chemical treatment composition against sea water as per company spec. Set up hydrotesting of Diameter 14” 42 Km long newly laid Pipeline, operating Dead weight tester, monitor pressure and volume indicator on hydrotesting operation on site under supervision of Pre-commissioning/Project Engineer.
Technician
November, 2008 – June, 2009 J.Ray McDermott
Project : Shell Malaysia
Location : Terengganu, Malaysia Task Description
Preparation of pre-commissioning equipments for Pigging and Hydrotesting operation. Ensure all required fittings to be complete for Pigging and hydrotesting set up. Set up offshore flooding and pigging operation for Diameter 14” 10km long pipeline and Diameter 28” 9km long pipeline, ensure sea water chemical treatment composition against sea water as per company spec. Set up hydrotesting of Diameter 14” 10km long pipeline and Diameter 28” 9km long pipeline, operating Dead
Page 5 of 5
weight tester, monitor pressure and volume indicator on hydrotesting operation on site under supervision of Pre-commissioning/Project Engineer.
Instrumentation Technician
July 2001 – October 2008 J.Ray McDermott
Marine Instrumentation and Rigging Certification Division Task Description
Prepare of instrumentation for offshore pre-commissioning work. Ensure all pressure and temperature measurement device i.e. Dead Weight Tester, Pressure Gauges, Temperature Gauge, Pressure Recorder, Temperature Recorder, Holiday Detector, Pinger, Pinger Detector, Turbine Flowmeter and etc. in valid certificate and in-house checking all the mentioned instrumentation after project for maintenance.
Responsible of Leak test for offshore project installation aid fabricated in marine workshop i.e. Pig Launcher, Pig Receiver, Spool Pipe and Test Header and etc.
Function test all the J.Ray McDermott Asia Pacific Stinger after maintenance in Batam, Marine facility before attached to all J.Ray McDermott Pipe Lay Barge.
Responsible as well for ensure all rigging and lifting gears to be color coded and ensure all rigging to be with valid certificate before send to offshore project.
NAME: IDHAM JAWAHIR DATE OF BIRTH 1 Jul 1972
NATIONALITY Indonesian
MARITAL STATUS Married
LANGUAGES Bahasa Indonesian (written & spoken)
English (fair spoken)
Career Summary
Over 8 years’ of experience in offshore construction and engineering as a technician commissioning team. Specialists in Pipeline Pigging, Flooding, Hydro Test, Dewatering, Drying, Nitrogen Purging, Commissioning & Decommissioning.
Work Experience
Grouting/Pre-com
March 2012 to present
Offshore Construction Specialists Pte Ltd
Responsible for the maintaining High Pressure pumps and Flooding Pumps in good condition after project and prepare, function test of High Pressure pumps and Flooding Pumps before offshore work. Operate and ensure High Pressure Pumps and Flooding pump working in good condition for Pre-commissioning work.
Completed Project:
Precom Supervisor
September to October 2013
Offshore Construction Specialists Pte Ltd Oct 2013 – Nov 2013
Offshore Construction Specialists Pte Ltd
Project : Leighton Offshore
Location : Jakarta - Cirebon
S513 Main Oil Line from X-Ray Field to Balongan Plant Project
Post Trenching, Free Span Correction, and Pre-commissiong Services
Task Description