Philips: Comprehensive Lean Scheduling
LEAN SCHEDULING
Their.investigation.discovered.that.project.teams.used.a.lot.of.different.
ways.to.plan.their.projects.. Some.teams.used.detailed.schedules,.while.
other.groups.only.planned.the.major.milestones..Planning.in.many.cases.
led.to.problems.in.project.execution..The.plans.quickly.got.out.of.date.and.
became.unreliable.as.sources.of.information.about.a.team’s.progress..Since.
project.managers.developed.the.plans,.the.teams.did.not.have.much.vis-ibility.into.how.the.plans.were.developed.and.did.not.take.ownership.for.
living.up.to.the.plan..It.was.no.surprise.that.the.plans.that.did.exist.often.
fell.apart.in.mid-development.
One. key. finding. was. that. product. developers. often. had. to. fight. fires.
because. their. stakeholders. reconsidered. key. decisions.. In. fact,. a. fire. in.
one.place.could.trigger.a.fire.someplace.else,.simply.because.the.team.lost.
focus.on.the.entire.project.and.accidentally.started.a.new.fire.while.they.
put.out.the.original.fire..Suzanne.says,
We. came. to. the. conclusion. that. plans. should. make. sure. that. decisions.
Level 0.is.the.Milestone.Schedule..It.outlines.all.of.the.major.milestones.
and.checkpoints.that.the.project.team.must.hit.if.they.are.going.to.
Level 1.is.an.overview.of.the.Key.Decisions.for.the.project..Unlike.Level.0,.
Level.1.is.built.specifically.for.each.project..Every.Level.1.looks.differ-ent..The.key.decisions.are.defined.and.put.in.a.sequence.and.relation.
to.each.other.to.build.the.development.logic..The.team.will.identify.
the.knowledge.required.to.make.each.of.the.decisions,.leading.to.work.
packages.(sets.of.activity.to.acquire.the.knowledge).at.Level.2.
Level 2.shows.the.Major.Activities.and.Deliverables.over.the.next.two.
to.three.months.that.the.team.needs.to.complete.in.order.to.hit.the.
Philips: Comprehensive Lean Scheduling • 111
updated.once.per.month,.when.the.team.adjusts.the.plans.already.
made.for.the.first.two.months.and.then.adds.the.third.month.
Level 3.is.the.Detailed.Plan,.and.it.only.goes.two.to.three.weeks.out..This.
plan.shows.the.immediate.action.items.that.the.team.is.working.on.
right.now,.in.order.to.finish.the.major.activities.and.deliverables.of.
Level.2.on.time..It.may.be.in.the.form.of.a.gridded.time.line.with.days.
across.the.top.and.sticky.notes.to.represent.tasks,.or.it.may.be.kept.as.
a.simple.list.with.the.action.item,.owner(s),.and.due.date..This.list.gets.
updated.frequently—as.often.as.every.day.and.at.least.once.a.week.
Philips
Level 0Level 1Level 2Level 3
Person A
Decision IPD Milestone
TFC IPP
Lean Scheduling
Person B Person C Person D
FIGURE 9.2
Levels.of.Lean.Schedules.
ViSUAL PRoJect PLAnS
Good.visual.project.plans.have.these.common.elements:
•. Visual.project.plans.have.a.home,.and.all.stakeholders.know.
where.it.is..The.home.is.big.enough.to.keep.the.most.essential.
team.information.visible.without.having.to.open.anything.or.
look.behind.anything..The.home.can.take.many.forms..It.could.
be.a.physical.home.such.as.a.dedicated.conference.room.or.a.
virtual.home.such.as.a.team.website.
•. Visual. project. plans. include. only. the. information. essen-tial. to. running. the. project.. If. a. tool. doesn’t. apply,. it’s. not.
included..This.is.in.direct.conflict.to.most.standard.product.
development. processes. that. consist. of. lists. of. deliverables.
to. be. produced. for. each. phase,. sometimes. ordered. into. a.
prepopulated. Gantt. chart..It.is.amazing. how.much.time. a.
project.manager.can.spend.updating.and.maintaining.these.
deliverables.
•. The.information.flow.of.the.visual.plan.is.evident.in.the.layout.
and.structure.of.the.plan..It.is.clear.how.the.project.goals.will.
accomplish.the.team’s.mission,.and.how.milestones.will.drive.
accomplishment.of.the.goals..Tasks.at.one.level.relate.to.the.
tasks.at.levels.above.and.below..In.a.well-designed.visible.plan,.
a.person.new.to.the.project.can.start.at.one.corner.of.the.plan.
and. follow. the. flow. of. information. to. the. end.. By. the. time.
someone.has.read.the.entire.plan,.he.or.she.also.has.a.good.
grasp.of.the.project.
•. Visual.project.plans.answer. the. “why”. question. as.deeply. as.
they.answer.“what”.and.“how”.questions..This.is.important.for.
keeping.the.team.in.alignment,.especially.as.the.project.enters.
into.its.busiest.phases.when.it.is.easy.to.forget.the.reasons.that.
the.project.was.funded..The.project.team’s.goals.and.objectives.
are. kept. front. and. center. so. that. the. team. has. the. constant.
reminder.that.this.project.is.linked.to.real.business.results..This.
helps.them.make.the.right.decisions.
Philips: Comprehensive Lean Scheduling • 113
One.of.the.major.problems.with.project.planning.in.product.develop-ment.is.that.the.volume.of.changes.is.overwhelming..If.one.attempts.to.
track. a. product. development. program. of. any. complexity. using. Gantt.
charts,.a.weekly.status.update.can.require.hours.of.work.by.the.project.
manager.to.bring.the.Gantt.chart.in.alignment.with.current.reality..Since.
Gantt.charting.software.automatically.adjusts.everything.as.the.schedule.
changes,.milestones.get.moved.that.shouldn’t.be.moved,.sometimes.with-out.the.project.manager.or.the.team.noticing.that.dates.have.changed..This.
encourages. product. development. program. managers. to. avoid. detailed.
planning,.which.makes.it.easy.for.schedule.risks.to.go.unrecognized.until.
it’s.too.late.to.fix.them.
With.this.multilevel.model,.the.detailed.plans.that.change.the.most.
are.the.easiest.to.change:.Simply.move.sticky.notes.around.or.re-sort.
the.activity.list..At.the.same.time,.the.major.milestones.remain.fixed.
in.a. visible.location.. If. the. team. changes. the. schedule. so. much. that.
they.cannot.meet.a.schedule.requirement.in.the.next.tier.up,.they.will.
discover.it.as.soon.as.they.adjust.their.plans..When.low-level.activi-ties.are.broken.into.days,.slippages.and.schedule.risks.have.no.place.
to.hide.