• No results found

G LOSS A R Y LOS S AR Y

G

G

G LOSS A R Y LOS S AR Y

Contingency Contingency Reserve Reserve

The amount of money or time needed above the estimate to

The amount of money or time needed above the estimate to reduce the riskreduce the risk of overruns of project objectives to a level acceptable to

of overruns of project objectives to a level acceptable to the organization.the organization.

Decision Tree

Decision Tree A diagram used to select the A diagram used to select the best course of action in uncertain situations.best course of action in uncertain situations.

Environmental Environmental Document Document

The National Environmental Policy Act (NEPA) and the California The National Environmental Policy Act (NEPA) and the California Environmental Quality Act (CEQA)

Environmental Quality Act (CEQA) require certain environmentalrequire certain environmental

documentation for transportation projects. Types of documents include a documentation for transportation projects. Types of documents include a negative declaration (ND) finding of no significant impact (FONSI), or negative declaration (ND) finding of no significant impact (FONSI), or anan environmental impact study (EIS)/environmental impact report (EIR).

environmental impact study (EIS)/environmental impact report (EIR).

Impact

Impact Effect or consequence.Effect or consequence.

Milestone

Milestone A significant event in the project, usually completion of A significant event in the project, usually completion of a majora major deliverable.

deliverable.

Mitigation

Mitigation The act of alleviating a harmful circumstance. Risk mitigation seeks toThe act of alleviating a harmful circumstance. Risk mitigation seeks to reduce the probability and/or impact of a risk

reduce the probability and/or impact of a risk to below an acceptableto below an acceptable threshold.

threshold.

Probability

Probability Likelihood of the occurrence of any event.Likelihood of the occurrence of any event.

G l o s s a r y

Any significant changes to the scope,

Any significant changes to the scope, cost, or schedule of a cost, or schedule of a programmedprogrammed project (STIP, SHOPP, or TCRP) or special program project (toll seismic project (STIP, SHOPP, or TCRP) or special program project (toll seismic retrofit, soundwall) require a revision

retrofit, soundwall) require a revision to the delivery to the delivery commitmentcommitment..22 Project

Project

Development Team Development Team

An interdisciplinary team, composed of key members of the project team An interdisciplinary team, composed of key members of the project team as well as

as well as external stakeholders, that acts as a steering committee inexternal stakeholders, that acts as a steering committee in directing the course of studies required to evaluate the various project directing the course of studies required to evaluate the various project alternatives during the early components of the project lifecycle.

alternatives during the early components of the project lifecycle.

Project Initiation Project Initiation Document

Document

Concept approval document for candidate projects that contains:

Concept approval document for candidate projects that contains:

A defined project scopeA defined project scope

A reliable capital and support cost estimate for each A reliable capital and support cost estimate for each alternativealternative solution

solution

A project schedule (workplan) for A project schedule (workplan) for the alternative recommended forthe alternative recommended for programming the project

programming the project Project Objective

Project Objective A particular goal of a A particular goal of a project. All projects have these four objectives:project. All projects have these four objectives:

Risk Officer A person other than the project manager assigned to monitor andA person other than the project manager assigned to monitor and maintain the project risk management plan.

maintain the project risk management plan.

Scope

Scope Encompasses the work that must be done to Encompasses the work that must be done to deliver a product with thedeliver a product with the specified features and functions.

specified features and functions.

Value Analysis

Value Analysis A multi-disciplined team systematically applies recognized techniques to:A multi-disciplined team systematically applies recognized techniques to:

Identify the function of a product or Identify the function of a product or serviceservice

Establish a worth for that functionEstablish a worth for that function

Generate alternatives through the use of Generate alternatives through the use of creative thinkingcreative thinking

Reliably provide the needed functions at the lowest overall costReliably provide the needed functions at the lowest overall cost The term is often interchanged with Value Engineering.

The term is often interchanged with Value Engineering.

Value Analysis Team

Value Analysis Team A team that performs value A team that performs value engineering.engineering.

Workplan

Workplan A resourced schedule. The workplan identifies the project-specific WBSA resourced schedule. The workplan identifies the project-specific WBS elements and defines the cost, timeline, and requirements for each. The elements and defines the cost, timeline, and requirements for each. The current workplan guides the day-to-day operations

current workplan guides the day-to-day operations of project executionof project execution and project control.

and project control.

2

2 Project Change Requests, memo dated September 21, 2002, Project Change Requests, memo dated September 21, 2002, Number 006Number 006

http://pm.dot.ca.gov/ProjectOffice/ProcessGuidance_Directives/Guidance_DirectivesHome.asp http://pm.dot.ca.gov/ProjectOffice/ProcessGuidance_Directives/Guidance_DirectivesHome.asp

Project Risk Management

Project Risk Management HandbookHandbook 2929

 A  A

A

A CR ON YM S CR ON YM S

CEQA

CEQA California Environmental Quality ActCalifornia Environmental Quality Act EIR

EIR EnvironmentaEnvironmental Impact l Impact ReportReport EIS

EIS EnvironmentaEnvironmental l Impact StudyImpact Study FONSI

FONSI Finding of No Significant ImpactFinding of No Significant Impact ND

ND Negative DeclarationNegative Declaration NEPA

NEPA National Environmental Policy ActNational Environmental Policy Act PCR

PCR Project Change RequestProject Change Request PDT

PDT Project Development TeamProject Development Team PID

PID Project Initiation DocumentProject Initiation Document PMBOK

PMBOK Project Management Body of KnowledgeProject Management Body of Knowledge PSR

PSR Project Study ReportProject Study Report PxI

PxI Probability and ImpactProbability and Impact SHOPP

SHOPP State Highway Operation & State Highway Operation & Protection ProgramProtection Program

A c r o n y m s A c r o n y m s

STIP

STIP State Transportation Improvement ProgramState Transportation Improvement Program TCRP

TCRP Traffic Congestion Relief ProgramTraffic Congestion Relief Program VA

VA Value AnalysisValue Analysis WBS

WBS Work Breakdown StructureWork Breakdown Structure

Project Risk Management

Project Risk Management HandbookHandbook 3131

 I 

assessment... 10, 10, 2323 avoidance

change requestrequest ......SeeSeePCR.PCR.

component...

component... 4, 4, 13, 13, 2828 consequence...2, 12, 23, 27 consequence...2, 12, 23, 27 construction risks...19 construction risks...19 contractor/consu

contractor/consultantltant ...11, 12, 16, 18...11, 12, 16, 18 controlling deputy district director for project and

deputy district director for project and

program management...11 program management...11

district division chief for program and district division chief for program and

project

project managementmanagement ...6...6 district VA

district VA coordinatorcoordinator ...11...11

E E

environmental risks...17 environmental risks...17 expert...

expert...SeeSeespecialist.specialist.

external risks...17 external risks...17

F F

flowchart, ri

flowchart, risk management sk management processprocess ...4...4 functional

I n d e x

list...SeeSeerisk list.risk list.

M

numeric analysisic analysis ........SeeSeequantitative analysis.quantitative analysis.

O O

objec

objectivestives .. 2, 5, 10, 11, 122, 5, 10, 11, 12, 17, 18, 23, 24, 27, 17, 18, 23, 24, 27, 28, 28 organizational

organizational risksrisks ...... 1818 outputs probability...10, 11, 12, 23, 27 probability...10, 11, 12, 23, 27 probability

probability and iand impact mpact matrixmatrix ...... 2424 project

project change rchange requestequest ......SeeSeePCR.PCR.

project

project development development teamteam ......SeeSeePDT.PDT.

project initiation document...

project initiation document...SeeSeePID.PID.

project

project management management risksrisks ...... 1818 project

project management management support support unitunit ...... 66 proj qualitative analysis...analysis... 5, 6, 5, 6, 1010 quantitative quantitative analysisanalysis ...... 5, 5, 6, 6, 1111

R R

ranking ranking risk prisk probabilityrobability ...23...23

references...25

references...25

regulatory regulatory risksrisks ...19...19

residual

right of way risks...19

right of way risks...19

risk

identification...5, 6, 9, 13, 16 identification...5, 6, 9, 13, 16 list list...... 5, 5, 9, 9, 13, 13, 1616 manag management planement plan ................. 4, 5, 4, 5, 8, 208, 20 management management planning...planning... 5, 6, 5, 6, 8, 208, 20 management process flowchart...4

management process flowchart...4

monitoring monitoring and contand controllingrolling ...... 5, 6, 5, 6, 1313 qualitative qualitative analysisanalysis...... 5, 6, 5, 6, 1010 quantitative spreadsheet, risk marisk management nagement planplan ...... 8, 208, 20 stakeholder technical risksrisks ...16...16

transference transference ...12...12

trends...10

trends...10

I n d e x I n d e x

Project Risk Management

Project Risk Management HandbookHandbook 3333

V V

value an

value analysisalysis ...... 5, 6, 5, 6, 8, 9, 8, 9, 11, 2811, 28

W W

workplan

workplan ...... 8, 8, 2828

Related documents