P
P
ROJECT
ROJECT
R
R
IIS
SK
K
M
M
ANAGEMENT
ANAGEMENT
H
H
ANDBOOK
ANDBOOK
First Edition
First Edition
Revision 0
Revision 0
June 26, 2003
June 26, 2003
Office of Project Management Process Improvement
Office of Project Management Process Improvement
Office of
Office of Project Management Process ImprovementProject Management Process Improvement 1120 N Street, Mail Station 28
1120 N Street, Mail Station 28 Sacramento, CA95814
Sacramento, CA95814
www.dot.ca.gov/hq/projmgmt www.dot.ca.gov/hq/projmgmt
Project Risk Management Handbook Project Risk Management Handbook June 26, 2003
June 26, 2003 Rev 0
Project Risk Management
Project Risk Management HandbookHandbook iiiiii
Preface
Preface
This handbook provides an overview of risk management at the California This handbook provides an overview of risk management at the California Department of
Department of Transportation (Department).Transportation (Department). This version is effective as of July 1, 2003. This version is effective as of July 1, 2003.
The project team thanks all individuals within the regions, districts and The project team thanks all individuals within the regions, districts and headquarters for their support and contributions to
headquarters for their support and contributions to the production of thethe production of the Project Risk Management Handbook
Project Risk Management Handbook..
Purpose
Purpose This document describes the basic concepts and processes that guide riskThis document describes the basic concepts and processes that guide risk management planning and implementation during
management planning and implementation during project development.project development.
Audience
Audience Department project managers, functional managers, and staff engaged inDepartment project managers, functional managers, and staff engaged in the delivery of capital projects.
the delivery of capital projects.
Background
Background The purpose of this handbook is The purpose of this handbook is to make the present policy/subject matterto make the present policy/subject matter more useful and easier to understand.
more useful and easier to understand.
Revisions
Revisions Revision 0 represents the original version of the Revision 0 represents the original version of the 11ststedition.edition.
Conventions
Conventions Titles of books and other documents appear inTitles of books and other documents appear initalicsitalics.. Web site URLs appear in
Web site URLs appear inbold italicsbold italics..
Like this example.
Project Risk Management
Project Risk Management HandbookHandbook vv
C
C
C
C
ON TEN T S
ON TEN T S
P
Prefacereface ... iiiiii
Purpose...iii Purpose...iii Audience...iii Audience...iii Background...iii Background...iii Revisions Revisions ... iiiiii Conventions...iii
Conventions...iii
Figures Figures ... viivii Overview ...1
Overview ...1
Why Why Risk Risk ManagemenManagement?t? ... 22 Definition Definition ... 22 Objective... Objective... 22 Process Overview...3 Process Overview...3 Flow Flow... 44 Tasks
Tasks and and Outputs...Outputs... 55 Key
Key ResponsibilResponsibilitiesities ... 66 Process
Process StepsSteps ... 77 Risk
Risk ManagemenManagement t PlanningPlanning ... 88 Risk
C o n t e n t s C o n t e n t s
Qualitative
Qualitative Risk Risk AnalysisAnalysis ... 1010
Quantitative Risk Analysis...11
Quantitative Risk Analysis...11
When to Use Quantitative Analysis...11
When to Use Quantitative Analysis...11
Risk Response Planning...12
Risk Response Planning...12
Risk Risk MonitorinMonitoring g and and ControlControl ...1313 Appendices...15
Appendices...15
Appendix A: Sample Risk List...16
Appendix A: Sample Risk List...16
Technical Risks...16
Technical Risks...16
External External RisksRisks ...1717 Environmental Risks...17
Environmental Risks...17
Organizational Risks...18
Organizational Risks...18
Project Project ManagemeManagement nt RisksRisks ...1818 Right of Way Risks...19
Right of Way Risks...19
Constructio Construction n RisksRisks ... 1919 Regulatory Risks...19
Regulatory Risks...19
Appendix B: Sample Risk Management Plan Spreadsheet...20
Appendix B: Sample Risk Management Plan Spreadsheet...20
Appendix Appendix C: C: Risk Risk ProbabilProbability ity RankingRanking ...23.23 Appendix Appendix D: D: ReferencesReferences ... 2525 Glossary Glossary ...27....27 Acronyms...29 Acronyms...29 Index ...31 Index ...31
C o n t e n t s C o n t e n t s
Project Risk Management
Project Risk Management HandbookHandbook viivii
Figures
Figures
Figure
Figure 1. 1. Risk Risk management management process process flowcharflowchart...t... 44 Figure
Figure 2. 2. Risk Risk management management plan plan spreadsheet spreadsheet samplesample ... 2121 Figure
Project Risk Management
Project Risk Management HandbookHandbook 11
1
1
O
O
VERVI EW
VER VI EW
This chapter defines: This chapter defines:
Project risk and risk Project risk and risk managementmanagement
W h y
W h y R i s k R i s k M a n a g e m e n t ? M a n a g e m e n t ? O v e r v i e wO v e r v i e w
Why Risk Management?
Why Risk Management?
The Capital Project Risk Management Process, described in this handbook, The Capital Project Risk Management Process, described in this handbook, is intended to result in
is intended to result in the effective management of project risks andthe effective management of project risks and opportunities. The project manager, project sponsor, and
opportunities. The project manager, project sponsor, and project teamproject team members jointly develop a written plan that enables them to identify, members jointly develop a written plan that enables them to identify, assess, quantify, prepare a response to,
assess, quantify, prepare a response to, monitor, and control capital projectmonitor, and control capital project risks.
risks.
Definition
Definition Project risk Project riskis an uncertain event or condition that, if it occurs, has ais an uncertain event or condition that, if it occurs, has a positive or a negative effect on a
positive or a negative effect on a project objective. A risk has a cause project objective. A risk has a cause and, if and, if it occurs, a consequence.
it occurs, a consequence.11 Risk management
Risk management is the systematic process of is the systematic process of planning for, identifying,planning for, identifying, analyzing, responding to, and monitoring project risk. It involves analyzing, responding to, and monitoring project risk. It involves processes, tools, and techniques that will
processes, tools, and techniques that will help the project managerhelp the project manager maximize the probability and consequences of positive events and maximize the probability and consequences of positive events and
minimize the probability and consequences of adverse events. Project risk minimize the probability and consequences of adverse events. Project risk management is most effective when first performed early in the life
management is most effective when first performed early in the life of theof the project and is a
project and is a continuing responsibility throughoucontinuing responsibility throughout the project.t the project.
Objective
Objective The project risk management process helps project sponsors and projectThe project risk management process helps project sponsors and project teams to make informed decisions
teams to make informed decisions regarding project alternatives. Riskregarding project alternatives. Risk management encourage
management encourages the s the project team to take appropriate measures toproject team to take appropriate measures to minimize:
minimize:
Adverse impacts to project scope, cost, and scheduleAdverse impacts to project scope, cost, and schedule
Management by crisisManagement by crisis
1
Project Risk Management
Project Risk Management HandbookHandbook 33
2
2
P
P
R OCES S
R OCES S
O
O
VERVI EW
VER VI EW
This chapter describes process tasks, their outputs, and key responsibilities This chapter describes process tasks, their outputs, and key responsibilities of project participants.
F l o w
F l o w P r o c e s s P r o c e s s O v e r v i e wO v e r v i e w
Flow
Flow
The project team completes the risk management plan before the project The project team completes the risk management plan before the project initiation document (PID) component ends. The team updates the plan in initiation document (PID) component ends. The team updates the plan in each subsequent lifecycle component and continues to monitor and each subsequent lifecycle component and continues to monitor and control risks throughout the life of the project.
control risks throughout the life of the project.
What type of What type of environmental document environmental document
is expected? is expected?
STEP 1: Risk Management Planning STEP 1: Risk Management Planning
The PDT members assign project
The PDT members assign project team membersteam members to create a project risk management plan. to create a project risk management plan.
STEP 2: Risk
STEP 2: Risk IdentificationIdentification
The assigned project team members identify risks The assigned project team members identify risks
and create a project risk list through and create a project risk list through brainstorming, interviews, and sample risk lists. brainstorming, interviews, and sample risk lists.
STEP 3: Qualitative Risk Analysis STEP 3: Qualitative Risk Analysis
The assigned project team members assess the The assigned project team members assess the importance of the identified risks and probability importance of the identified risks and probability
of occurrence. of occurrence.
STEP 4: Quantitative Risk Analysis STEP 4: Quantitative Risk Analysis
The Value Analysis team, assisted by an expert, The Value Analysis team, assisted by an expert, develops statistical data on the probability and develops statistical data on the probability and
impact of major risks. impact of major risks.
STEP 5: Risk Response Plan STEP 5: Risk Response Plan
For each identified risk, the PDT decides whether to For each identified risk, the PDT decides whether to avoid the risk, mitigate the risk, or accept the risk. avoid the risk, mitigate the risk, or accept the risk.
STEP 6: Risk Monitoring and Control STEP 6: Risk Monitoring and Control
Risk monitoring and control is an ongoing process Risk monitoring and control is an ongoing process for the life of the project. Assigned team members for the life of the project. Assigned team members monitor the risks as the project matures, new risks monitor the risks as the project matures, new risks
develop, or anticipated risks di
develop, or anticipated risks di sappear.sappear.
Risk management plan is optional Risk management plan is optional
Project has Project has only a only a Categorical Categorical Exemption or Exemption or Categorical Categorical Exclusion Exclusion Project has environmental
Project has environmental document (ND, FONSI, EIS, or EIR) document (ND, FONSI, EIS, or EIR)
Is Value Analysis Is Value Analysis required for the required for the
project? project? Yes Yes No No Figure 1.
P r o c e s s
P r o c e s s O v e r v i e w O v e r v i e w T a s k s T a s k s a n d a n d O u t p u t sO u t p u t s
Project Risk Management
Project Risk Management HandbookHandbook 55
Tasks and Outputs
Tasks and Outputs
This matrix shows the two main process tasks,
This matrix shows the two main process tasks, the four subtasks, and all of the four subtasks, and all of the deliverables associated with project risk
the deliverables associated with project risk management.management.
Process
Process Tasks Tasks Task Task Outputs Outputs (deliverables)(deliverables) Risk
Risk management management planning planning Risk Risk management management planplan Risk
Risk identification identification Project Project risk risk list list Qualitative
Qualitative risk risk analysis analysis Prioritized Prioritized list list of of risks risks classified classified as as high, high, moderate,moderate, or low.
or low. Quantitative risk analysis
Quantitative risk analysis (Only if the project (Only if the project includes Value Analysis) includes Value Analysis)
An analysis of the project’s
An analysis of the project’s likelihood of achievinglikelihood of achieving its cost and time objectives
its cost and time objectives Risk
Risk response response planning planning Risk Risk response response plan, plan, including including one one or or more more of of thethe following: residual risks, secondary risks, change following: residual risks, secondary risks, change control, contingency reserve (amounts of time or control, contingency reserve (amounts of time or budget needed), and inputs to a revised project budget needed), and inputs to a revised project plan
plan Risk
Risk monitoring monitoring and and control control Workaround Workaround plans, plans, corrective corrective actions, actions, project project change requests (PCR), and updates to t change requests (PCR), and updates to t he riskhe risk response plan and to risk identification checklists response plan and to risk identification checklists for future projects
K e y
K e y R e s p o n s i b i l i t i e s R e s p o n s i b i l i t i e s P r o c e s s P r o c e s s O v e r v i e wO v e r v i e w
Key Responsibilities
Key Responsibilities
This matrix shows the six process
This matrix shows the six process tasks and the responsibilities of thetasks and the responsibilities of the project manager and stakeholders.
project manager and stakeholders.
Role Role Process Tasks Process Tasks Sponsor District Sponsor District Division Chief Division Chief for Program for Program and Project and Project Management Management Project Project Manager Manager Assistant Assistant Project Project Manager/ Manager/ Project Project Management Management Support Unit Support Unit Functional Functional Manager Manager Task Task Manager Manager Risk management Risk management planning planning S S S S R R S S S S SS Risk
Risk identification identification S S S S A A S S R R RR
Qualitative risk Qualitative risk analysis analysis R S R S S S SS Quantitative risk Quantitative risk analysis (Performed analysis (Performed only as part of Value only as part of Value Analysis) Analysis) A S A S R R RR Risk response Risk response planning planning S S S S R, R, A A SS
Risk monitoring and Risk monitoring and control control R R R R R, R, A A S S R R RR Legend: Legend: R = responsibleR = responsible S = supportS = support A = approveA = approve
Project Risk Management
Project Risk Management HandbookHandbook 77
3
3
P
P
R OCES S
R OCES S
S
S
T EPS
T EP S
This chapter identifies and explains the six tasks
R i s k
R i s k M a n a g e m e n t M a n a g e m e n t P l a n n i n g P l a n n i n g P r o c e s s P r o c e s s S t e p sS t e p s
Risk Management Planning
Risk Management Planning
Before starting project Before starting project studies, the project
studies, the project manager establishes a manager establishes a PDT in accordance with PDT in accordance with Department policy. For Department policy. For
details, see the “PDT details, see the “PDT Formation” sub-section of Formation” sub-section of
the
theProject DevelopmentProject Development Procedures Manual Procedures Manual..
As part of
As part of workplan development, project development team (PDT)workplan development, project development team (PDT) members assign project team
members assign project team members to create a project risk managmembers to create a project risk managementement plan.
plan.
At this point, the assigned
At this point, the assigned project team members begin to create the riskproject team members begin to create the risk management plan. The risk management plan identifies and establishes in management plan. The risk management plan identifies and establishes in the project plan the activities of risk
the project plan the activities of risk management for the project.management for the project. If the project will undergo a
If the project will undergo a value analysis (VA), the VA team assists value analysis (VA), the VA team assists inin preparing the risk management plan. If the risk management plan is preparing the risk management plan. If the risk management plan is prepared with a VA study, the
prepared with a VA study, the risk management plan is included in the VArisk management plan is included in the VA study report.
study report.
To prepare the risk management plan, the assigned project team members To prepare the risk management plan, the assigned project team members use a spreadsheet that shows the
use a spreadsheet that shows the risks and responses in an risks and responses in an abbreviatedabbreviated form. For a sample of
form. For a sample of what this spreadsheet might contain, see “what this spreadsheet might contain, see “AppendixAppendix B: Sample Risk Management Plan Spreadsheet
B: Sample Risk Management Plan Spreadsheet” on page” on page 20.20. An electronicAn electronic version of the sample spreadsheet is available on
version of the sample spreadsheet is available on the project managementthe project management guidance Web site at
guidance Web site at
http://www.dot.ca.gov/hq/projmgmt/guidance.htm http://www.dot.ca.gov/hq/projmgmt/guidance.htm
P r o c e s s
P r o c e s s S t e p s S t e p s R i s k R i s k I d e n t i f i c a t i o nI d e n t i f i c a t i o n
Project Risk Management
Project Risk Management HandbookHandbook 99
Risk Identification
Risk Identification
Risk identification involves identifying potential project risks and Risk identification involves identifying potential project risks and documenting their characteristics. Risk identification results in a documenting their characteristics. Risk identification results in a deliverable — the project risk list.
deliverable — the project risk list.
The assigned team members identify the
The assigned team members identify the potential risks and potential risks and opportunities,opportunities, using:
using:
The sample risk list provided on The sample risk list provided on pagepage 1616
Their own knowledge of the projectTheir own knowledge of the project
Consultation with others who have significant knowledge of theConsultation with others who have significant knowledge of the
project or its
project or its environmentenvironment
Techniques for Techniques for identifying risks and identifying risks and opportunities are taught in opportunities are taught in the Department’s Value the Department’s Value Analysis courses. Analysis courses.
The team considers: The team considers:
Risks — what might go wrongRisks — what might go wrong
Opportunities — better methods of achieving the Opportunities — better methods of achieving the project’s purposeproject’s purpose
and need and need
Triggers — symptoms and warning signs that indicate whether eachTriggers — symptoms and warning signs that indicate whether each
risk is likely to occur risk is likely to occur
Q u a l i t a t i v e
Q u a l i t a t i v e R i s k R i s k A n a l y s i s A n a l y s i s P r o c e s s P r o c e s s S t e p sS t e p s
Qualitative Risk Analysis
Qualitative Risk Analysis
Qualitative risk analysis assesses the importance of the identified risks Qualitative risk analysis assesses the importance of the identified risks andand develops prioritized lists of these risks for
develops prioritized lists of these risks for further analysis or directfurther analysis or direct mitigation. The team assesses each identified risk for its
mitigation. The team assesses each identified risk for its probability of probability of occurring and its impact on project objectives. Sometimes experts or occurring and its impact on project objectives. Sometimes experts or functional units assess the risks in
functional units assess the risks in their respective fields and share thesetheir respective fields and share these assessments with the team.
assessments with the team.
Team members sort the identified risks into high, moderate, and low Team members sort the identified risks into high, moderate, and low riskrisk categories for each project objective (time, cost, scope). They rank
categories for each project objective (time, cost, scope). They rank risks byrisks by degrees of probability and impact, and include their assessment rationale. degrees of probability and impact, and include their assessment rationale. For more information and a sample, see “
For more information and a sample, see “Appendix C: Risk Appendix C: Risk ProbabilityProbability Ranking”
Ranking” on pageon page 23.23.
Team members revisit qualitative risk analysis
Team members revisit qualitative risk analysis during the project’s lifecycle.during the project’s lifecycle. When the team repeats qualitative analysis for individual risks, trends may When the team repeats qualitative analysis for individual risks, trends may emerge in the results. These trends can
emerge in the results. These trends can indicate the need for more or lessindicate the need for more or less risk management action on particular risks, or whether a risk
risk management action on particular risks, or whether a risk mitigationmitigation plan is working.
P r o c e s s
P r o c e s s S t e p s S t e p s Q u a n t i t a t i v e Q u a n t i t a t i v e R i s k R i s k A n a l y s i sA n a l y s i s
Project Risk Management
Project Risk Management HandbookHandbook 1111
Quantitative Risk Analysis
Quantitative Risk Analysis
Quantitativ
Quantitative risk analysis is e risk analysis is a way of a way of numerically estimating thenumerically estimating the probability that a project will meet its cost
probability that a project will meet its cost and time objectives.and time objectives. Quantitativ
Quantitative analysis is e analysis is based on a simultaneous evaluation of the impactbased on a simultaneous evaluation of the impact of all identified and quantified risks. The
of all identified and quantified risks. The result is a probability distributionresult is a probability distribution of the project’s cost and completion date based on
of the project’s cost and completion date based on the risks in the project.the risks in the project. Quantitativ
Quantitative risk e risk analysis involves statistical techniques that analysis involves statistical techniques that are mostare most easily used with specialized software. The Department has specialists easily used with specialized software. The Department has specialists trained in these techniques and equipped with the necessary
trained in these techniques and equipped with the necessary software. Asoftware. A specialist is assigned to assist
specialist is assigned to assist each value analysis team. The team provideseach value analysis team. The team provides the specialist with the data needed to
the specialist with the data needed to perform the analysis.perform the analysis.
When to Use When to Use Quantitative Quantitative Analysis Analysis
The Department does not require quantitative analysis
The Department does not require quantitative analysis for projects;for projects; however, it strongly recommends that projects requiring VA, or those however, it strongly recommends that projects requiring VA, or those projects with an extremely high risk identified from the qualitative projects with an extremely high risk identified from the qualitative analysis, undergo quantitative risk analysis.
analysis, undergo quantitative risk analysis.
Deputy District Directors for Project and Program Management are Deputy District Directors for Project and Program Management are responsible for identifying which of their projects will undergo VA
responsible for identifying which of their projects will undergo VA duringduring the following fiscal year, and
the following fiscal year, and for submitting a list of these projects to for submitting a list of these projects to thethe District VA Coordinator. Project managers must arrange for appropriate District VA Coordinator. Project managers must arrange for appropriate resources through the functional mangers, consultants, and design
resources through the functional mangers, consultants, and design centers,centers, and must include VA in the project schedules.
and must include VA in the project schedules. For more information about implement
For more information about implementing VA, see the ing VA, see the following Web site.following Web site. http://www.dot.ca.gov/hq/oppd/pdpm/chap_htm/chapt19/chapt19. http://www.dot.ca.gov/hq/oppd/pdpm/chap_htm/chapt19/chapt19. htm
R i s k
R i s k R e s p o n s e R e s p o n s e P l a n n i n g P l a n n i n g P r o c e s s P r o c e s s S t e p sS t e p s
Risk Response Planning
Risk Response Planning
Risk response planning focuses on
Risk response planning focuses on the high-risk items evaluated in thethe high-risk items evaluated in the qualitative and/or quantitative risk analysis. It identifies and
qualitative and/or quantitative risk analysis. It identifies and assigns partiesassigns parties to take responsibility for each risk
to take responsibility for each risk response. This process ensures that eachresponse. This process ensures that each risk requiring a response has an
risk requiring a response has an owner.owner.
The project manager and the PDT identify which strategy is
The project manager and the PDT identify which strategy is best for eachbest for each risk, and then design specific
risk, and then design specific actions to implement that strategy. Theseactions to implement that strategy. These strategies and actions include:
strategies and actions include:
AvoidanceAvoidance. The team changes the project plan . The team changes the project plan to eliminate the riskto eliminate the risk or to protect the project objectives from its impact. The team might or to protect the project objectives from its impact. The team might achieve this by changing scope, adding
achieve this by changing scope, adding time, or adding resourcestime, or adding resources (thus relaxing the so-called “triple constraint”). These changes may (thus relaxing the so-called “triple constraint”). These changes may require a PCR.
require a PCR.
TransferenceTransference. The team transfers the financial impact of . The team transfers the financial impact of risk byrisk by
contracting out some aspect of the work. Transference reduces the contracting out some aspect of the work. Transference reduces the risk only if the
risk only if the contractor is more capable of taking steps to contractor is more capable of taking steps to reducereduce the risk and does so.
the risk and does so.
MitigationMitigation. The team seeks to . The team seeks to reduce the probability orreduce the probability or
consequences of a risk event to
consequences of a risk event to an acceptable threshold. Theyan acceptable threshold. They accomplish this via many different means that are specific to accomplish this via many different means that are specific to thethe project and the risk. Mitigation steps, although costly and
project and the risk. Mitigation steps, although costly and time- time-consuming, may still be preferable to going forward with
consuming, may still be preferable to going forward with thethe unmitigated risk.
unmitigated risk.
AcceptanceAcceptance. The project manager and the project team decide to. The project manager and the project team decide to
accept certain risks. They do not
accept certain risks. They do not change the project plan to deal change the project plan to deal withwith a risk, or identify any
a risk, or identify any response strategy other than agreeing toresponse strategy other than agreeing to address the risk if and when it occurs.
P r o c e s s
P r o c e s s S t e p s S t e p s R i s k R i s k M o n i t o r i n g M o n i t o r i n g a n d a n d C o n t r o lC o n t r o l
Project Risk Management
Project Risk Management HandbookHandbook 1313
Risk Monitoring and Control
Risk Monitoring and Control
Residual risks are Residual risks are left over from the previous left over from the previous lifecycle component. lifecycle component. Typically, they are not Typically, they are not high risks, but could high risks, but could become so under certain become so under certain conditions.
conditions.
Risk monitoring and control keeps track of
Risk monitoring and control keeps track of the identified risks, residualthe identified risks, residual risks, and new risks. It also ensures the execution of risk response plans, risks, and new risks. It also ensures the execution of risk response plans, and evaluates their effectiveness.
and evaluates their effectiveness. Risk monitoring and contr
Risk monitoring and control continues for the life of tol continues for the life of the project. The listhe project. The list of of project risks changes as the project matures, new risks
project risks changes as the project matures, new risks develop, ordevelop, or anticipated risks disappear.
anticipated risks disappear.
Periodic project risk reviews repeat the tasks of identification, analysis, and Periodic project risk reviews repeat the tasks of identification, analysis, and response planning (see previous tasks).
response planning (see previous tasks). The project manager regularlyThe project manager regularly schedules project risk reviews, and ensures that project risk is
schedules project risk reviews, and ensures that project risk is an agendaan agenda item at all PDT meetings. Risk ratings and
item at all PDT meetings. Risk ratings and prioritization commonlprioritization commonly changey change during the project lifecycle.
during the project lifecycle.
If an unanticipated risk emerges, or a risk’s
If an unanticipated risk emerges, or a risk’s impact is greater than expected,impact is greater than expected, the planned response may not be adequate. The project manager and the the planned response may not be adequate. The project manager and the PDT must perform additional response planning to control the risk. PDT must perform additional response planning to control the risk. Risk control involves:
Risk control involves:
Choosing alternative response strategiesChoosing alternative response strategies
Implementing a contingency planImplementing a contingency plan
Taking corrective actionsTaking corrective actions
Re-planning the projectRe-planning the project
The functional manager assigned to each risk reports periodically to the The functional manager assigned to each risk reports periodically to the project manager and the risk team leader on the effectiveness of
project manager and the risk team leader on the effectiveness of the plan,the plan, any unanticipated effects, and any mid-course correction that the PDT any unanticipated effects, and any mid-course correction that the PDT must take to mitigate the risk.
Project Risk Management
Project Risk Management HandbookHandbook 1515
A
A
A
A
P P EN D I CES
P P END I CES
This chapter provides the
A p p e n d i x
A p p e n d i x A : A : S a m p l e S a m p l e R i s k R i s k L i s t L i s t A p p e n d i c e sA p p e n d i c e s
Appendix A: Sample Risk List
Appendix A: Sample Risk List
The task of risk
The task of risk identification produces a project risk list. The project teamidentification produces a project risk list. The project team then puts the risks into
then puts the risks into categories and assigns each risk to categories and assigns each risk to a team member.a team member. The project team members may use this sample risk checklist to
The project team members may use this sample risk checklist to develop adevelop a specific project risk list. This list is not meant to be all-inclusive; it is just a specific project risk list. This list is not meant to be all-inclusive; it is just a guide. Team members add other risks
guide. Team members add other risks areas from previous project resultsareas from previous project results and as they arise
and as they arise during the project. Such sources might include:during the project. Such sources might include:
Final project reportsFinal project reports
Risk response plansRisk response plans
Organized lessons learnedOrganized lessons learned
The experience of project stakeholders or others in the organizationThe experience of project stakeholders or others in the organization
Published information such as commercial databases or Published information such as commercial databases or academicacademic
studies studies
Technical Risks
Technical Risks Design incompleteDesign incomplete
Right of Way analysis in Right of Way analysis in errorerror
EnvironmentEnvironmental analysis incomplete or al analysis incomplete or in errorin error
Unexpected geotechnical issuesUnexpected geotechnical issues
Change requests because of errorsChange requests because of errors
Inaccurate assumptionInaccurate assumptions on technical issues s on technical issues in planning stagein planning stage
Surveys late and/or surveys in errorSurveys late and/or surveys in error
Materials/geoteMaterials/geotechnical/foundation in chnical/foundation in errorerror
Structural designs incomplete or in Structural designs incomplete or in errorerror
Hazardous waste site analysis incomplete or in errorHazardous waste site analysis incomplete or in error
Need for design exceptionsNeed for design exceptions
Consultant design not up Consultant design not up to Department standardsto Department standards
Context sensitive solutionsContext sensitive solutions
A p p e n d i c e s
A p p e n d i c e s A p p e n d i x A p p e n d i x A : A : S a m p l e S a m p l e R i s k R i s k L i s tL i s t
Project Risk Management
Project Risk Management HandbookHandbook 1717
External Risks
External Risks Landowners unwilling to sellLandowners unwilling to sell
Priorities change on existing programPriorities change on existing program
Inconsistent cost, time, scope, and quality objectivesInconsistent cost, time, scope, and quality objectives
Local communities pose objectionsLocal communities pose objections
Funding changes for fiscal yearFunding changes for fiscal year
Political factors changePolitical factors change
Stakeholders request late changesStakeholders request late changes
New stakeholders emerge and demand new workNew stakeholders emerge and demand new work
Influential stakeholders request additional needs to serve their ownInfluential stakeholders request additional needs to serve their own
commercial purposes commercial purposes
Threat of lawsuitsThreat of lawsuits
Stakeholders choose time and/or cost over qualityStakeholders choose time and/or cost over quality
Environmental Environmental Risks
Risks
Permits or agency actions delayed or take longer Permits or agency actions delayed or take longer than expectedthan expected
New information required for permitsNew information required for permits
EnvironmentaEnvironmental l regulations changeregulations change
Water quality regulation changesWater quality regulation changes
Reviewing agency requires higher-level review than assumedReviewing agency requires higher-level review than assumed
Lack of specialized staff (biology, anthropology, archeology, etc.)Lack of specialized staff (biology, anthropology, archeology, etc.)
Historic site, endangered species, wetlands presentHistoric site, endangered species, wetlands present
EIS requiredEIS required
Controversy on environmental grounds expectedControversy on environmental grounds expected
EnvironmentaEnvironmental analysis on l analysis on new alignments is requirednew alignments is required
Formal NEPA/404 consultation is requiredFormal NEPA/404 consultation is required
Formal Section 7 consultation is requiredFormal Section 7 consultation is required
Section 106 issues expectedSection 106 issues expected
Project in an area of high Project in an area of high sensitivity for paleontologysensitivity for paleontology
Section 4(f) resources affectedSection 4(f) resources affected
Project in the Coastal ZoneProject in the Coastal Zone
Project on a Scenic HighwayProject on a Scenic Highway
Project near a Wild and Scenic RiverProject near a Wild and Scenic River
A p p e n d i x
A p p e n d i x A : A : S a m p l e S a m p l e R i s k R i s k L i s t L i s t A p p e n d i c e sA p p e n d i c e s
Project does not conform to the state implementation plan for airProject does not conform to the state implementation plan for air
quality at the program and plan level quality at the program and plan level
Water quality issuesWater quality issues
Negative community impacts expectedNegative community impacts expected
Hazardous waste preliminary site investigation requiredHazardous waste preliminary site investigation required
Growth inducement issuesGrowth inducement issues
Cumulative impact issuesCumulative impact issues
Pressure to compress the environmental schedulePressure to compress the environmental schedule
Organizational Organizational Risks
Risks
Inexperienced staff assignedInexperienced staff assigned
Losing critical staff at crucial point of Losing critical staff at crucial point of the projectthe project
Insufficient time to planInsufficient time to plan
Unanticipated project manger workloadUnanticipated project manger workload
Internal “red tape” causes delay getting approvals, decisionsInternal “red tape” causes delay getting approvals, decisions
Functional units not available, overloadedFunctional units not available, overloaded
Lack of understanding of Lack of understanding of complex internal funding procedurescomplex internal funding procedures
Not enough time to planNot enough time to plan
Priorities change on existing programPriorities change on existing program
New priority project inserted into New priority project inserted into programprogram
Inconsistent cost, time, scope and quality objectivesInconsistent cost, time, scope and quality objectives
Project Project
Management Risks Management Risks
Project purpose and need is poorly definedProject purpose and need is poorly defined
Project scope definition is poor or Project scope definition is poor or incompleteincomplete
Project scope, schedule, objectives, cost, and deliverables are notProject scope, schedule, objectives, cost, and deliverables are not
clearly defined or understood clearly defined or understood
No control over staff prioritiesNo control over staff priorities
Too many projectsToo many projects
Consultant or contractor delaysConsultant or contractor delays
Estimating and/or scheduling errorsEstimating and/or scheduling errors
Unplanned work that must be Unplanned work that must be accommodatedaccommodated
CommunicatiCommunication breakdown with on breakdown with project teamproject team
A p p e n d i c e s
A p p e n d i c e s A p p e n d i x A p p e n d i x A : A : S a m p l e S a m p l e R i s k R i s k L i s tL i s t
Project Risk Management
Project Risk Management HandbookHandbook 1919
Lack of Lack of coordination/comcoordination/communicationmunication
Lack of upper management supportLack of upper management support
Change in key staffing throughout the projectChange in key staffing throughout the project
Inexperienced workforce/inadequate staff/resource Inexperienced workforce/inadequate staff/resource availabilityavailability
Local agency issuesLocal agency issues
Public awareness/supportPublic awareness/support
AgreementsAgreements
Right of Way Risks
Right of Way Risks Utility relocation may not happen in timeUtility relocation may not happen in time
Freeway agreementsFreeway agreements
Railroad involvementRailroad involvement
Objections to Right of Way appraisal takes more time and/or moneyObjections to Right of Way appraisal takes more time and/or money
Construction Risks
Construction Risks Inaccurate contract time estimatesInaccurate contract time estimates
Permit work windowsPermit work windows
UtilityUtility
SurveysSurveys
Buried man-made objects/unidentified hazardous wasteBuried man-made objects/unidentified hazardous waste
Regulatory Risks
Regulatory Risks Water quality regulations changeWater quality regulations change
New permits or New permits or new information requirednew information required
A p p e n d i x
A p p e n d i x B : B : S a m p l e S a m p l e R i s k R i s k M a n a g e m e n t M a n a g e m e n t P l a n P l a n S p r e a d s h e e t S p r e a d s h e e t A p p e n d i c e sA p p e n d i c e s
Appendix B: Sample Risk Management Plan
Appendix B: Sample Risk Management Plan
Spreadsheet
Spreadsheet
Using the sample risk list
Using the sample risk list (Appendix A), the assigned project team members(Appendix A), the assigned project team members add their specific information to the risk
add their specific information to the risk management plan spreadsheet.management plan spreadsheet. The following illustration shows a sample Excel spreadsheet that represents The following illustration shows a sample Excel spreadsheet that represents one possibility for what a
one possibility for what a risk management plan spreadsheet mightrisk management plan spreadsheet might include.
include.
An electronic version of this sample spreadsheet is
An electronic version of this sample spreadsheet is available on the projectavailable on the project management guidance Web site at
management guidance Web site at
http://www.dot.ca.gov/hq/projmgmt/guidance.htm http://www.dot.ca.gov/hq/projmgmt/guidance.htm
A p p e n d i c e s
A p p e n d i c e s A p p e n d i x A p p e n d i x B : B : S a m p l e S a m p l e R i s k R i s k M a n a g e m e n t M a n a g e m e n t P l a n P l a n S p r e a d s h e e tS p r e a d s h e e t
Project Risk Management Handbook
Project Risk Management Handbook 2121 Figure 2.
A p p e n d i c e s
A p p e n d i c e s A p p e n d i x A p p e n d i x C : C : R i s k R i s k P r o b a b i l i t y P r o b a b i l i t y R a n k i n gR a n k i n g
Project Risk Management
Project Risk Management HandbookHandbook 2323
Appendix C: Risk Probability Ranking
Appendix C: Risk Probability Ranking
Using established methods and tools, qualitative risk analysis assesses Using established methods and tools, qualitative risk analysis assesses thethe probability and the consequences of each identified risk to
probability and the consequences of each identified risk to determine itsdetermine its overall importance. Using these tools helps to correct biases
overall importance. Using these tools helps to correct biases that are oftenthat are often presented in a project plan. In
presented in a project plan. In particular, careful and objective definitionsparticular, careful and objective definitions of different levels of probability and impact are the keys to the credibility of of different levels of probability and impact are the keys to the credibility of the results.
the results.
To rank risks by probability and impact:To rank risks by probability and impact:
For more information For more information about risk probability about risk probability ranking, see chapter 11 of ranking, see chapter 11 of the PMBOK.
the PMBOK.
Step 1
Step 1: Set up a : Set up a matrix to match a percentage (probability of risk) to amatrix to match a percentage (probability of risk) to a ranking number. Department project managers often use the matrix ranking number. Department project managers often use the matrix shown below, but they can
shown below, but they can set up a different matrix if it set up a different matrix if it would better suitwould better suit the project.
the project.
Risk Probability Ranking Risk Probability Ranking Ranking
Ranking Probability of Probability of Risk Risk EventEvent
5 80–99% 5 80–99% 4 60–79% 4 60–79% 3 40–59% 3 40–59% 2 20–39% 2 20–39% 1 1–19% 1 1–19% Step 2
Step 2: Set up a matrix to match the objective (time, cost, and scope) to a: Set up a matrix to match the objective (time, cost, and scope) to a defined impact. Department project managers often use the
defined impact. Department project managers often use the impactimpact numbers shown in the matrix below, but they can
numbers shown in the matrix below, but they can choose others if it wouldchoose others if it would better suit the project.
better suit the project.
Evaluating Impact of a Risk on
Evaluating Impact of a Risk on Major Project ObjectivesMajor Project Objectives Impact Impact 1 1 2 2 4 4 8 8 1616 Time Insignificant Time Insignificant schedule schedule slippage slippage Delivery plan Delivery plan milestone delay milestone delay within quarter within quarter Delivery plan Delivery plan milestone delay of milestone delay of one quarter one quarter
Delivery plan Delivery plan milestone delay of milestone delay of more than one more than one quarter quarter Delivery plan Delivery plan milestone delay milestone delay outside fiscal outside fiscal year year Cost Insignificant Cost Insignificant cost increase cost increase <5%
<5% cost cost increase increase 5–10% 5–10% cost cost increase increase 10–20% cost 10–20% cost increase increase >20% cost >20% cost increase increase O O b b j j e e c c t t i i v v e e
Scope
Scope Scope decreaseScope decrease is barely is barely noticeable noticeable Changes in Changes in project limits or project limits or features with <5% features with <5% cost increase cost increase Changes in project Changes in project limits or features limits or features with 5–10% cost with 5–10% cost increase increase
Sponsor does not Sponsor does not agree that scope agree that scope meets the purpose meets the purpose and need
and need
Scope does not Scope does not meet purpose meet purpose and need and need
A p p e n d i x
A p p e n d i x C : C : R i s k R i s k P r o b a b i l i t y P r o b a b i l i t y R a n k i n g R a n k i n g A p p e n d i c e sA p p e n d i c e s
Step 3
Step 3: Combine the data from the two : Combine the data from the two previous steps. Each risk appears inprevious steps. Each risk appears in its own probability and impact (PxI) matrix.
its own probability and impact (PxI) matrix. The PDT uses a PxI matrix to combine each
The PDT uses a PxI matrix to combine each risk’s probability and impact.risk’s probability and impact. These matrices establish whether each risk is high,
These matrices establish whether each risk is high, moderate, or low. Themoderate, or low. The risks can then be displayed by high, moderate, and low groupings for each risks can then be displayed by high, moderate, and low groupings for each of the three objectives (time, cost, and scope).
of the three objectives (time, cost, and scope). Department projectDepartment project managers often use the PxI matrix shown below, but they
managers often use the PxI matrix shown below, but they can set up acan set up a different matrix and assign different scores if it
different matrix and assign different scores if it would better suit thewould better suit the project.
project.
Time, Cost, and Scope
Time, Cost, and Scope ObjectivesObjectives Large Aversion to High & Very High Impacts Large Aversion to High & Very High Impacts Probability Probability 5 5 5 5 10 10 20 20 40 40 8080 4 4 44 8 8 16 16 32 32 6464 3 3 3 3 6 6 12 12 24 24 4848 2 2 2 2 4 4 8 8 16 16 3232 1 1 1 1 2 2 4 4 8 8 1616 1 1 2 2 4 4 8 8 1616 Impact Impact Figure 3.
Figure 3. Sample PxI Sample PxI matrixmatrix
Some Department project managers use a
Some Department project managers use a PxI matrix based on PxI matrix based on narrativenarrative probabilities and impacts (very low, low, moderate, high, very
probabilities and impacts (very low, low, moderate, high, very high) ratherhigh) rather than numerical ones. For a sample of this type of matrix, see “
than numerical ones. For a sample of this type of matrix, see “Appendix B:Appendix B: Sample Risk Management Plan Spreadsheet
Sample Risk Management Plan Spreadsheet” on page” on page 2020.. Translate Score Translate Score to Risk Rank to Risk Rank Score Risk Score Risk 1 1 – – 6 6 LowLow 7 7 – – 14 14 ModerateModerate 15 15 – – ++ ++ HighHigh
A p p e n d i c e s
A p p e n d i c e s A p p e n d i x A p p e n d i x D : D : R e f e r e n c e sR e f e r e n c e s
Project Risk Management
Project Risk Management HandbookHandbook 2525
Appendix D: References
Appendix D: References
For more information about risk and
For more information about risk and risk management, see:risk management, see:
Chapter 11 of Chapter 11 of A Guide to Project A Guide to Project Management Body of KnowledgeManagement Body of Knowledge
(PMBOK® Guide), 2000 Edition (PMBOK® Guide), 2000 Edition
Chapter 11 of theChapter 11 of theGovernment Extension to a Government Extension to a Guide to the Project Guide to the Project Management Body of Knowledge
Management Body of Knowledge, 2000 Edition, 2000 Edition
DepartmentDepartment Guide to Capital Project Work Breakdown StructureGuide to Capital Project Work Breakdown Structure,, Release 5.1
Project Risk Management
Project Risk Management HandbookHandbook 2727
G
G
G
G
LOSS A R Y
LOS S AR Y
Contingency Contingency Reserve ReserveThe amount of money or time needed above the estimate to
The amount of money or time needed above the estimate to reduce the riskreduce the risk of overruns of project objectives to a level acceptable to
of overruns of project objectives to a level acceptable to the organization.the organization. Decision Tree
Decision Tree A diagram used to select the A diagram used to select the best course of action in uncertain situations.best course of action in uncertain situations. Environmental
Environmental Document Document
The National Environmental Policy Act (NEPA) and the California The National Environmental Policy Act (NEPA) and the California Environmental Quality Act (CEQA)
Environmental Quality Act (CEQA) require certain environmentalrequire certain environmental
documentation for transportation projects. Types of documents include a documentation for transportation projects. Types of documents include a negative declaration (ND) finding of no significant impact (FONSI), or negative declaration (ND) finding of no significant impact (FONSI), or anan environmental impact study (EIS)/environmental impact report (EIR). environmental impact study (EIS)/environmental impact report (EIR). Impact
Impact Effect or consequence.Effect or consequence. Milestone
Milestone A significant event in the project, usually completion of A significant event in the project, usually completion of a majora major deliverable.
deliverable. Mitigation
Mitigation The act of alleviating a harmful circumstance. Risk mitigation seeks toThe act of alleviating a harmful circumstance. Risk mitigation seeks to reduce the probability and/or impact of a risk
reduce the probability and/or impact of a risk to below an acceptableto below an acceptable threshold.
threshold. Probability
G l o s s a r y G l o s s a r y Project Change Project Change Request Request
Any significant changes to the scope,
Any significant changes to the scope, cost, or schedule of a cost, or schedule of a programmedprogrammed project (STIP, SHOPP, or TCRP) or special program project (toll seismic project (STIP, SHOPP, or TCRP) or special program project (toll seismic retrofit, soundwall) require a revision
retrofit, soundwall) require a revision to the delivery to the delivery commitmentcommitment..22
Project Project
Development Team Development Team
An interdisciplinary team, composed of key members of the project team An interdisciplinary team, composed of key members of the project team as well as
as well as external stakeholders, that acts as a steering committee inexternal stakeholders, that acts as a steering committee in directing the course of studies required to evaluate the various project directing the course of studies required to evaluate the various project alternatives during the early components of the project lifecycle. alternatives during the early components of the project lifecycle. Project Initiation
Project Initiation Document
Document
Concept approval document for candidate projects that contains: Concept approval document for candidate projects that contains:
A defined project scopeA defined project scope
A reliable capital and support cost estimate for each A reliable capital and support cost estimate for each alternativealternative
solution solution
A project schedule (workplan) for A project schedule (workplan) for the alternative recommended forthe alternative recommended for
programming the project programming the project
Project Objective
Project Objective A particular goal of a A particular goal of a project. All projects have these four objectives:project. All projects have these four objectives:
ScopeScope ScheduleSchedule CostCost QualityQuality Risk Officer
Risk Officer A person other than the project manager assigned to monitor andA person other than the project manager assigned to monitor and maintain the project risk management plan.
maintain the project risk management plan. Scope
Scope Encompasses the work that must be done to Encompasses the work that must be done to deliver a product with thedeliver a product with the specified features and functions.
specified features and functions. Value Analysis
Value Analysis A multi-disciplined team systematically applies recognized techniques to:A multi-disciplined team systematically applies recognized techniques to:
Identify the function of a product or Identify the function of a product or serviceservice
Establish a worth for that functionEstablish a worth for that function
Generate alternatives through the use of Generate alternatives through the use of creative thinkingcreative thinking
Reliably provide the needed functions at the lowest overall costReliably provide the needed functions at the lowest overall cost
The term is often interchanged with Value Engineering. The term is often interchanged with Value Engineering.
Value Analysis Team
Value Analysis Team A team that performs value A team that performs value engineering.engineering. Workplan
Workplan A resourced schedule. The workplan identifies the project-specific WBSA resourced schedule. The workplan identifies the project-specific WBS elements and defines the cost, timeline, and requirements for each. The elements and defines the cost, timeline, and requirements for each. The current workplan guides the day-to-day operations
current workplan guides the day-to-day operations of project executionof project execution and project control.
and project control.
2
2 Project Change Requests, memo dated September 21, 2002, Project Change Requests, memo dated September 21, 2002, Number 006Number 006
http://pm.dot.ca.gov/ProjectOffice/ProcessGuidance_Directives/Guidance_DirectivesHome.asp http://pm.dot.ca.gov/ProjectOffice/ProcessGuidance_Directives/Guidance_DirectivesHome.asp
Project Risk Management
Project Risk Management HandbookHandbook 2929
A
A
A
A
CR ON YM S
CR ON YM S
CEQA
CEQA California Environmental Quality ActCalifornia Environmental Quality Act EIR
EIR EnvironmentaEnvironmental Impact l Impact ReportReport EIS
EIS EnvironmentaEnvironmental l Impact StudyImpact Study FONSI
FONSI Finding of No Significant ImpactFinding of No Significant Impact ND
ND Negative DeclarationNegative Declaration NEPA
NEPA National Environmental Policy ActNational Environmental Policy Act PCR
PCR Project Change RequestProject Change Request PDT
PDT Project Development TeamProject Development Team PID
PID Project Initiation DocumentProject Initiation Document PMBOK
PMBOK Project Management Body of KnowledgeProject Management Body of Knowledge PSR
PSR Project Study ReportProject Study Report PxI
PxI Probability and ImpactProbability and Impact SHOPP
A c r o n y m s A c r o n y m s
STIP
STIP State Transportation Improvement ProgramState Transportation Improvement Program TCRP
TCRP Traffic Congestion Relief ProgramTraffic Congestion Relief Program VA
VA Value AnalysisValue Analysis WBS
Project Risk Management
Project Risk Management HandbookHandbook 3131
I
I
II
N D EX
N DEX
A
A
acceptance...12 acceptance...12 assessment... assessment... 10, 10, 2323 avoidance avoidance ... 1212C
C
categoriescategories of of riskrisk ... 10, 10, 1616 change
change requestrequest ...SeeSeePCR.PCR. component... component... 4, 4, 13, 13, 2828 consequence...2, 12, 23, 27 consequence...2, 12, 23, 27 construction risks...19 construction risks...19 contractor/consu contractor/consultantltant ...11, 12, 16, 18...11, 12, 16, 18 controlling
controlling riskrisk... 5, 5, 6, 6, 1313
D
D
degrees
degrees of of riskrisk ... 1010 deliverables...
deliverables... 5, 5, 9, 9, 2727 deputy district director for project and
deputy district director for project and
program management...11 program management...11
district division chief for program and district division chief for program and
project
project managementmanagement ...6...6 district VA
district VA coordinatorcoordinator ...11...11
E
E
environmental risks...17 environmental risks...17 expert...
expert...SeeSeespecialist.specialist. external risks...17 external risks...17
F
F
flowchart, ri
flowchart, risk management sk management processprocess ...4...4 functional
functional managermanager ... 6, 6, 11, 11, 1313 functional unit...10, 18 functional unit...10, 18 funding...17, 18 funding...17, 18
II
identifying ridentifying riskisk ...5, 6, 9, ...5, 6, 9, 13, 1613, 16 impact...10, 11, 12, 13, 23, 24, 27 impact...10, 11, 12, 13, 23, 24, 27
I n d e x I n d e x
L
L
lifecycle lifecycle ...4, 10, ...4, 10, 13, 13, 2828 list...list...SeeSeerisk list.risk list.
M
M
mitigation
mitigation ...10, 12, ...10, 12, 13, 2713, 27 monit
monitorinoring g riskrisk ... 5, 5, 6, 6, 1313
N
N
numer
numeric analysisic analysis ...SeeSeequantitative analysis.quantitative analysis.
O
O
objec
objectivestives .. 2, 5, 10, 11, 122, 5, 10, 11, 12, 17, 18, 23, 24, 27, 17, 18, 23, 24, 27, 28, 28 organizational
organizational risksrisks ... 1818 outputs outputs ... 55
P
P
PCR...5, 12, 16, 28 PCR...5, 12, 16, 28 PDT...8, 12, 13, 24, 28 PDT...8, 12, 13, 24, 28 PID... PID... 4, 4, 2828 probability...10, 11, 12, 23, 27 probability...10, 11, 12, 23, 27 probabilityprobability and iand impact mpact matrixmatrix ... 2424 project
project change rchange requestequest ...SeeSeePCR.PCR. project
project development development teamteam ...SeeSeePDT.PDT. project initiation document...
project initiation document...SeeSeePID.PID. project
project management management risksrisks ... 1818 project
project management management support support unitunit ... 66 proj
project manageect managerr ... 2, 6, 8, 2, 6, 8, 11, 12, 1311, 12, 13 project
project sponsor...sponsor... 2, 6, 2, 6, 2323 proj
project teamect team ... 2, 4, 8, 12, 16, 18, 202, 4, 8, 12, 16, 18, 20
PxI matrix...24
PxI matrix...24
Q
Q
qualitative qualitative analysis...analysis... 5, 6, 5, 6, 1010 quantitative quantitative analysisanalysis ... 5, 5, 6, 6, 1111R
R
ranking ranking risk prisk probabilityrobability ...23...23references...25
references...25
regulatory regulatory risksrisks ...19...19
residual residual risksrisks ... 5, 5, 1313 response response plan...plan... 5, 8, 5, 8, 13, 1613, 16 response response planningplanning ... 5, 5, 6, 12, 6, 12, 1313 responsibilities...6
responsibilities...6
right of way risks...19
right of way risks...19
risk risk categories...10, 16 categories...10, 16 definition...2 definition...2 degrees...10 degrees...10 identification...5, 6, 9, 13, 16 identification...5, 6, 9, 13, 16 list list... 5, 5, 9, 9, 13, 13, 1616 manag management planement plan ... 4, 5, 4, 5, 8, 208, 20 management management planning...planning... 5, 6, 5, 6, 8, 208, 20 management process flowchart...4
management process flowchart...4
monitoring monitoring and contand controllingrolling ... 5, 6, 5, 6, 1313 qualitative qualitative analysisanalysis... 5, 6, 5, 6, 1010 quantitative quantitative analysisanalysis ... 5, 5, 6, 6, 1111 response response planningplanning... 5, 6, 5, 6, 12, 1312, 13 roles roles ...6...6
S
S
secondary risks...5 secondary risks...5 specialist specialist ... 10, 10, 1111 sponsor sponsor ... 2, 2, 6, 6, 2323 spreadsheet, spreadsheet, risk marisk management nagement planplan ... 8, 208, 20 stakeholder stakeholder ... 6, 6, 16, 16, 1717T
T
task manager...6 task manager...6 tasks tasks ... 5, 5, 6, 6, 1313 technical technical risksrisks ...16...16transference transference ...12...12
trends...10
I n d e x I n d e x
Project Risk Management
Project Risk Management HandbookHandbook 3333
V
V
value an
value analysisalysis ... 5, 6, 5, 6, 8, 9, 8, 9, 11, 2811, 28
W
W
workplan