• No results found

2. Chapter

3.3. Modelling methodology

3.3.1. Notation

See Section 2.5.1., for a list of Notation associated with this chapter.

3.3.2. The delay-time model development

As illustrated in Figure 3.1, delay-time modelling describes the evolution of defects in industrial equipment in two separate, but linked stages. The first stage is the time lapse from new (or as new) until a defect (fault) arrives. This is the time-to-defect arrival, U. Equivalently, it is the sojourn in the good state. The second stage is the time lapse from defect arrival to the point at which this defect causes the equipment to fail. This is the delay-time, H. Equivalently, it is the sojourn in the defective state. This second stage is the window of opportunity for inspection, identification of defects, and remedial maintenance intervention (repair or component replacement) before a defect causes failure of operational function. Thus, the β€˜change point’ from the good state to the defective state occurs at a random time, failure occurs some random time later, and the time of transition from the good to defective state is unobservable. Nonetheless, using failure times and counting instances of defects found at inspection, the distributions of time of defect arrival and delay-time may be estimated (Baker and Wang, 1992).

Consider now the complex or multi-component plant maintenance modelling scenario in this study, shown in Figure 3.2, with the associated notations and assumptions shown in Section 3.3.1. Here, multiple concurrent defects are possible. The β€˜first to fail’ determines the failure time, and thus a series system is assumed. Failures are repaired immediately but not instantaneously, so that a downtime of 𝑑𝑓 time units is incurred at a cost of 𝐢𝑠 per unit time.

Inspections are carried out every 𝑇 time units, requiring 𝑑𝑠 time units and costing 𝐢𝑠 per unit time, where 𝑑𝑠<< 𝑇. All defects identified at inspection are repaired during the inspection process, I. During the failure stoppage process, the system is returned to the operational state, but any defects present are not removed. During inspection and failure stoppage (repair) processes, plant components are assumed to be in a state of suspension, so that the system is then not ageing, and thus defects and failures can only arise whilst plant is operating, and defects are not β€˜growing’. It is assumed that the plant has operated sufficiently long to be considered working under a steady state condition.

Figure 3.1. The delay-time concept, depicting the arrival of a defect and its evolution into: (a) failure; or (b) not, as inspection intervenes.

Figure 3.2. Defect arrivals, failures, failure repair F, and inspection I in this complex system of multiple components.

u h Time

Time I

a) Defect developing into failure

b) Defect found at inspection, I Defect arrival Failure u T T d d s f

I

F

F

I

h Initial Time,

These assumptions represent a relatively simple inspection problem in the class reported by Christer (1999), whom under these assumptions, gives the expected number of failure breakdowns over the interval (0, 𝑇), 𝐸𝑁𝑓(𝑇), and the expected downtime per unit time, 𝐷(𝑇). Provided that πΉπ‘ˆ(𝑒) and 𝐹𝐻(β„Ž) can be estimated, either through the consideration of data or subjective, expert opinion or both, 𝐷(𝑇) and 𝐢(𝑇) equivalently can be calculated and then the 𝑇 that minimises 𝐷(𝑇) or 𝐢(𝑇) can be determined. It is this optimisation step that links the inspection frequency to the defect arrival and failure rates, and the cost and downtime parameters. However, these models are only applicable to the maintenance activities for single- line plant. Hence, there are many practical industrial situations, like this one with multiple lines, where their use is limited. For example, for a production system consisting of a two-out-of-three set up with an inventory buffer (storage) facility, the mathematical analysis is very difficult and may be intractable. Thus a different approach is considered in this study.

3.3.3. Modelling multi-line production systems

The main objective of this research is to determine the downtime per unit time and thus the optimum inspection policy for a multi-line production system. In this case, downtime is defined as the duration of a stoppage to the downstream and/or the upstream processes. Consider the three-line scenario with no standby line in Figure 3.3. Under our definition, downtime occurs only when the individual stoppages coincide (period of length z in that figure). In other situations, upstream and downstream downtime may have different consequences and upstream and/or downstream inventory buffers may exist. For example, in a production system with a two-out-of-three line set up (see e.g. Smith and Dekker, 1997, or De Smidt-Destombes et al., 2007, for a general discussion of k-of-out-n systems) and one line used as standby (Figure 3.4), the definition of downtime should depend on the way the management operates the facility.

Figure 3.3. Plant downtime in a simple multi-line production system,

indicating downtime for M1 of duration x, downtime of M2 that is concurrent with M1 of duration y, and complete system downtime of duration z.

Figure 3.4. A multi-line production system with a two-out-of-three line set up and inventory buffer.

There are two principal ways in which inspection can be performed for the system in Figure 3.4, namely, simultaneous (concurrent) inspection of all parallel lines, or consecutive inspection, inspecting each in sequence. If inspection is performed simultaneously, assuming that the required resources (spares, personnel) are available, then the inspection time itself is downtime (similar to a single-line scenario), and the long-run cost per unit time (cost-rate) for the realisation shown in Figure 3.5(a) is:

πΆπ‘ π‘–π‘š(𝑇) = (3( 𝑑𝑠 + 𝑑𝑓 )𝐢𝑠+ (𝑑𝑠+ 𝑑𝑣)𝐢𝑑)/𝑇. (1)

With consecutive inspection, the cost-rate for the realisation shown in Figure 3.5(b) is: πΆπ‘π‘œπ‘›(𝑇) = (3( 𝑑𝑠 + 𝑑𝑓 )𝐢𝑠+ (𝑑𝑣′+ 𝑑𝑣)𝐢𝑑)/𝑇 < πΆπ‘ π‘–π‘š(𝑇) . (2)

Upstream

Process

Downstream

Process

X Y Z M1 M2 M3

Upstream

Process

Downstream

Process

Line 1 Standby Line 3 Inventory Buffer Line

since 𝑑𝑣′ < 𝑑𝑠 and 𝑑𝑣 < 𝑑𝑓. In practice, it may be possible to reduce the cost of downtime further by modifying the policy so that if a failure occurs while another line is being inspected, the inspection is suspended until the failed line becomes operational. Then for the realisation shown in Figure 3.5(c), for example, the cost-rate is:

πΆπ‘šπ‘œπ‘‘(𝑇) = (3( 𝑑𝑠 + 𝑑𝑓 )𝐢𝑠+ 𝑑𝑣 𝐢𝑑)/𝑇 < πΆπ‘π‘œπ‘›(𝑇). (3)

(a)

(b)

(c)

Figure 3.5. Policy schematic for two-out-of-three line system

(inspection I; failure repair F; concurrent occurrence of two failure stoppages 𝑑𝑣; concurrent occurrence of a failure stoppage and an inspection 𝑑𝑣′):

(a) simultaneous inspection; (b) consecutive inspection; and (c) consecutive inspection prioritising failure repair.