• No results found

Phasing out not started on time

3.3 Problem knot

3.3.3 Phasing out not started on time

When the phasing out process is not started on time, there is not enough time for the stock to sell out or at least decrease to an acceptable level, based on the demand process. There are three causes for this problem, namely: the collection end time is not known, the collection end time is not monitored, and it is not known when to switch to PS. To assure that the phasing out process, i.e., switch the MRP type to PS, is started on time, it must be known when to start the phasing out process. This is mainly determined by the collection end time. When the end time is known, but not monitored, the decision whether to switch to PS or not is prompted. Finally, when both the collection end time is known and monitored, but no criteria regarding the MRP type change are stated (e.g., switch to PS two years before collection end time), the phasing out process is still not started on time. Another complication of this problem is that when the planners cannot see the β€˜switch to PS date’, they continue to order according to the current MRP type policy, while it can be sensible to postpone an order that is prompted a month before the MRP switch date. An example of this problem can be seen in Figure 3-4, where an order, that was placed end 2010 under PR, was delivered when the article was already switched to PS. To reduce the obsolete risk, actions such as postponing the order or ordering a smaller but costlier run could be have undertaken, if, however, it was known when the article would be switched to PS.

3.4

C

ONCLUSION

In this chapter, the scope is quantified. It has been shown that the decorative window covering products have the highest impact on the stock reservations, mainly caused by the product lines Roller Blinds, Venetian Blinds, and PlissΓ© Shades. Next to that, only make to stock items are responsible for stock reservations. With this scope, the research focusses on 65% of the total reservations made. Following, a problem knot was made to identify the main causes of the high obsolete costs. These are a high minimum order quantity, amongst others caused by an inaccurate forecast, faulty (production/purchase) orders, and the fact that the phasing out process is not started on time. In the next chapter, the literature review regarding these subjects is presented.

PR PI PS PR PU PO 0 200 400 600 800 1000 1200 1400 1600 Qu an tity in m ete rs

Swing 1.98 m Pink/Orange

29 | M a s t e r T h e s i s – M . K . v a n d e r H o e v e n

LITERATURE REVIEW

In this chapter the relevant literature is described. There are four main categories introduced, namely demand uncertainty (Section 4.1), lot sizing (Section 4.2), intermittent demand (Section 4.3), and obsolescence (Section 4.4).

4.1

DEMAND UNCERTAINTY

Inventory control takes an important part in production systems. An improper policy of inventory control leads either to shortages, which generate expenses, or to needless stocks, which decrease capital assets (Dolgui & Prodhon, 2007). This is especially true when uncertainties occur. Koh, Saad, & Jones (2002) classify them in two main categories: input (as external supply or demand reliability) and process (as machine breakdown, etc.). To minimize the influence of these uncertainties, enterprises implement safety stocks, but stock is expensive. So the problem is to control inventories and to avoid stockout while maintaining a high level of service (Dolgui & Prodhon, 2007).

The safety stock is calculated in the following way (Fotopoulos, Wang, & Rao, 1988): 𝐺𝐺𝐺𝐺=𝑧𝑧𝛼𝛼×�𝑅𝑅(𝐿𝐿)𝜎𝜎𝐷𝐷2+ (𝑅𝑅(𝐷𝐷))2𝜎𝜎𝐿𝐿2 Where: 𝐺𝐺𝐺𝐺=𝐺𝐺𝑀𝑀𝑃𝑃𝑅𝑅𝑅𝑅𝐼𝐼𝐺𝐺𝑅𝑅𝐺𝐺𝑖𝑖𝑠𝑠 𝑧𝑧𝛼𝛼=π‘€π‘€π‘€π‘€πΌπΌπ‘…π‘…πΊπΊπΊπΊπ‘…π‘…πΊπΊπ‘ƒπ‘ƒπ‘…π‘…β„Žπ‘…π‘…π‘€π‘€πΊπΊπΊπΊπ‘–π‘–π‘€π‘€π‘™π‘™π‘–π‘–π‘…π‘…π‘–π‘–π‘…π‘…π‘™π‘™π‘€π‘€π‘…π‘…π‘€π‘€πΌπΌπ‘…π‘…πΉπΉπ‘€π‘€πΊπΊπ‘…π‘…πΊπΊπ‘€π‘€π‘™π‘™π‘…π‘…π‘…π‘…π‘€π‘€πΊπΊπ‘€π‘€πΊπΊπ‘ƒπ‘ƒπΊπΊπ‘…π‘…πΊπΊπΌπΌπ‘€π‘€π‘–π‘–π‘…π‘…π‘™π‘™π‘…π‘…πΌπΌπ‘…π‘…π‘™π‘™π›Όπ›Ό 𝑅𝑅(𝐿𝐿) =𝑅𝑅𝐹𝐹𝑒𝑒𝑅𝑅𝑖𝑖𝑅𝑅𝑅𝑅𝐹𝐹𝑙𝑙𝑅𝑅𝑀𝑀𝐹𝐹𝑅𝑅𝑀𝑀𝑖𝑖𝑅𝑅 𝜎𝜎𝐷𝐷2=𝐼𝐼𝑀𝑀𝐺𝐺𝑀𝑀𝑀𝑀𝑀𝑀𝑖𝑖𝑅𝑅𝐺𝐺𝑃𝑃𝐹𝐹𝑅𝑅𝑖𝑖𝑀𝑀𝑀𝑀𝐹𝐹 𝑅𝑅(𝐷𝐷) =𝑅𝑅𝐹𝐹𝑒𝑒𝑅𝑅𝑖𝑖𝑅𝑅𝑅𝑅𝐹𝐹𝐹𝐹𝑅𝑅𝑖𝑖𝑀𝑀𝑀𝑀𝐹𝐹 𝜎𝜎𝐿𝐿2=𝐼𝐼𝑀𝑀𝐺𝐺𝑀𝑀𝑀𝑀𝑀𝑀𝑖𝑖𝑅𝑅𝐺𝐺𝑃𝑃𝑙𝑙𝑅𝑅𝑀𝑀𝐹𝐹𝑅𝑅𝑀𝑀𝑖𝑖𝑅𝑅

A reorder point is than calculated in the following way: 𝑅𝑅𝑅𝑅𝑃𝑃=𝑅𝑅(𝐿𝐿) ×𝑅𝑅(𝐷𝐷) +𝐺𝐺𝐺𝐺

Demand uncertainty is linked to the predictability of the demand for the product (Lee, 2002). Lee (2002) also states that when a company faces the pressure of excessive inventory, degraded customer service, escalating costs, its supply chain is out of control. A simple but powerful way to characterize a product when seeking to devise the right supply chain strategy is the β€œuncertainty framework” (see Figure 4-1).

30 | M a s t e r T h e s i s – M . K . v a n d e r H o e v e n

Figure 4-1: Uncertainty framework (Lee, 2002)

Demand for functional products is much easier to forecast, while demand for innovative products is highly unpredictable. Due to the differences in product lifecycle and the nature of the product, functional products tend to have lower product profit margins, but the cost of obsolescence is low; whereas innovative products tend to have higher product profit margins, but the cost of obsolescence is high. Figure 4-2 shows the two kinds of strategies that improve supply chain performance through uncertainty reductionβ€”demand uncertainty reduction and supply uncertainty reduction.

Figure 4-2: Uncertainty reduction strategies (Lee, 2002)

In many cases, the bullwhip effect is one of the causes of demand uncertainty. The bullwhip effect is an amplification of order variability as one goes upstream along a supply chain (Lee, Padmanbhan, & Whang, 1997). Only through information sharing and tight coordination can one regain control of supply chain efficiency. Sharing of demand information and synchronized planning across the supply chain are crucial for this purpose. Lee (2002) states that given the different nature of demand and supply uncertainties of different products, different supply chain strategies are needed for different products. With highly unpredictable demand, excessive inventory may result. The cost of inventory for innovative products can be significant, since the product lifecycles are short. Companies with such products should pursue strategies with a responsive supply chain. Rather than focusing on accurate

31 | M a s t e r T h e s i s – M . K . v a n d e r H o e v e n

forecasting and inventory planning, companies with a very stable process and product technology can make use of the concept of postponement to pursue aggressive build to order strategies.

4.2

L

OT SIZING

According to Dolgui & Prodhon (2007) it is often better to group orders together, instead of ordering by a lot-for-lot rule (LFL), i.e., to order only the net needs for a single period. The LFL permits reducing inventory but does not take into consideration economic aspects and organizational constraints. Sometimes, the ordering cost is very expensive in relation to the holding cost, so lot- sizing is needed. The principal lot-sizing rules are:

- The economic order quantity (EOQ);

- The periodic order quantity (POQ);

- The Wagner-Whitin algorithm (WW).

According to Winston (2003) the assumptions of the EOQ model are:

- Demand is deterministic and occurs at a constant rate;

- If an order of any size (say, q units) is placed, an ordering and setup cost K is incurred;

- The lead time for each order is zero;

- No shortages are allowed;

- The cost per unit/year of holding inventory is h;

- D is the annual demand.

The economic order quantity is: π‘žπ‘žβˆ—=οΏ½2𝐾𝐾𝐷𝐷

β„Ž

This function minimizes the total annual costs which consists of the annual costs of placing orders, annual purchasing costs, and annual holding costs. From the EOQ, it can be deduced the POQ: an optimal constant time between orders is calculated, and from the optimal constant time, the necessary quantity to order for each period is obtained (Dolgui & Prodhon, 2007). The Wagner- Whitin algorithm is a procedure that determines the minimal order cost for a dynamic deterministic demand without capacity constraint. The classical lot sizing model of Wagner and Whitin and its extensions deal with the problem of finding the optimal replenishment plan for an item under the assumption that inventory can be carried for an indefinite number of periods. This assumption cannot be justified if one considers potentially obsolete or perishable product (Jain & Silver, 1994). Dolgui & Prodhon (2007) conclude that with demand and lead time uncertainties, the relative efficiency of lot-sizing rules performances is not stable.

The materials managers of manufacturing firms are facing the task of replenishing high quality components in the right quantities, at the right time, and at the right price (Benton & Park, 1996). Large orders usually lower a unit purchase price through quantity discounts and enhance customer service level as well, but they result in increased inventory cost. Therefore, the buyers should consider the tradeoffs between the costs and the benefits resulting from larger orders and come up with reasonable purchasing decisions (Benton & Park, 1996). Although the recent purchasing strategy has focused on how to acquire flexible resources and high quality components to gain competitive advantages in the current market, lowering cost is still one of the critical competitive priorities to win the market. Consequently, reduction of purchasing cost will be a key concern to the materials managers.

32 | M a s t e r T h e s i s – M . K . v a n d e r H o e v e n

Many companies face the challenge of managing inventory that has the potential to suddenly become obsolete (Emsermann & Simon, 2007). These circumstances render traditional inventory analysis unsuitable for balancing reordering costs with costs of overstocking. Emsermann & Simon (2007) consider the problem of determining the optimal ordering and reordering policy for an inventory in which the entire stock will simultaneously become obsolete at some random future time. They study a continuous-review and stochastic-demand obsolescence inventory model, and calculate its optimal control policy. Emsermann & Simon (2007) show that when the number of weeks since the last obsolescence of a the researched product increases, the optimal order quantity decreases.

4.3

I

NTERMITTENT DEMAND

Syntetos, Boylan & Croston (2005) has proposed the following categorization of demand patterns.

Figure 4-3: Demand pattern categorization matrix (Syntetos et al., 2005)

In the figure above, demand variability is expressed with CV2, which is the squared coefficient of

variation of demand sizes. The demand interval is expressed with p, which is the average inter- demand interval expressed in number of forecast review periods.

Intermittent demand is random demand with significant periods of no demand activity (Silver, 1981). Demand that is intermittent is often also β€˜lumpy’, meaning that there is great variability among the nonzero values (Willemain, Smart, & Schwarz, 2004). According to Willemain et al. (2004) accurate forecasting of demand is important in inventory control, but the intermittent nature of demand makes forecasting especially difficult. Intermittent demand is a highly recognized challenge and many models have been created to face this challenge. Three promising models are explained below.

4.3.1 Model of Croston

Exponential smoothing is frequently used for forecasting demand in a routine stock control system when large numbers of products may be involved (Croston, 1972). It has be shown that for some low and intermittent demand items the stock levels of the system appeared to be excessive. Croston (1972) proposes the following model:

33 | M a s t e r T h e s i s – M . K . v a n d e r H o e v e n π‘Œπ‘Œπ‘‘π‘‘:𝐷𝐷𝑅𝑅𝑖𝑖𝑀𝑀𝑀𝑀𝐹𝐹𝑃𝑃𝐺𝐺𝐺𝐺𝑀𝑀𝑀𝑀𝑀𝑀𝑅𝑅𝑅𝑅𝑖𝑖𝑀𝑀𝑀𝑀𝑒𝑒𝑅𝑅𝐺𝐺𝑀𝑀𝐺𝐺𝐹𝐹𝑅𝑅. π‘Œπ‘Œβ€² 𝑑𝑑:𝑅𝑅𝐺𝐺𝑅𝑅𝑀𝑀𝑖𝑖𝑀𝑀𝑅𝑅𝑅𝑅𝐺𝐺𝑃𝑃𝑖𝑖𝑅𝑅𝑀𝑀𝑀𝑀𝐹𝐹𝑅𝑅𝑖𝑖𝑀𝑀𝑀𝑀𝐹𝐹𝑒𝑒𝑅𝑅𝐺𝐺𝑒𝑒𝑅𝑅𝐺𝐺𝑀𝑀𝐺𝐺𝐹𝐹𝑖𝑖𝑀𝑀𝐹𝐹𝑅𝑅𝑀𝑀𝑀𝑀𝑒𝑒𝑅𝑅𝐺𝐺𝑀𝑀𝐺𝐺𝐹𝐹𝑅𝑅𝑃𝑃𝐺𝐺𝐺𝐺𝑒𝑒𝑅𝑅𝐺𝐺𝑀𝑀𝐺𝐺𝐹𝐹𝑅𝑅+ 1 𝑧𝑧′ 𝑑𝑑:𝑅𝑅𝐺𝐺𝑅𝑅𝑀𝑀𝑖𝑖𝑀𝑀𝑅𝑅𝑅𝑅𝐺𝐺𝑃𝑃𝑖𝑖𝑅𝑅𝑀𝑀𝑀𝑀𝐹𝐹𝑅𝑅𝑖𝑖𝑀𝑀𝑀𝑀𝐹𝐹𝐺𝐺𝑀𝑀𝑧𝑧𝑅𝑅𝑀𝑀𝑀𝑀𝑒𝑒𝑅𝑅𝐺𝐺𝑀𝑀𝐺𝐺𝐹𝐹𝑅𝑅. 𝑇𝑇𝑑𝑑:𝐴𝐴𝑖𝑖𝑅𝑅𝑅𝑅𝑀𝑀𝑙𝑙𝐹𝐹𝑅𝑅𝑖𝑖𝑀𝑀𝑀𝑀𝐹𝐹𝑀𝑀𝑀𝑀𝑅𝑅𝑅𝑅𝐺𝐺𝐼𝐼𝑀𝑀𝑙𝑙𝑀𝑀𝑀𝑀𝑒𝑒𝑅𝑅𝐺𝐺𝑀𝑀𝐺𝐺𝐹𝐹𝑅𝑅. 𝑇𝑇′𝑑𝑑:𝑅𝑅𝐺𝐺𝑅𝑅𝑀𝑀𝑖𝑖𝑀𝑀𝑅𝑅𝑅𝑅𝐺𝐺𝑃𝑃𝑖𝑖𝑅𝑅𝑀𝑀𝑀𝑀𝐹𝐹𝑅𝑅𝑖𝑖𝑀𝑀𝑀𝑀𝐹𝐹𝑀𝑀𝑀𝑀𝑅𝑅𝑅𝑅𝐺𝐺𝐼𝐼𝑀𝑀𝑙𝑙𝑀𝑀𝑀𝑀𝑒𝑒𝑅𝑅𝐺𝐺𝑀𝑀𝐺𝐺𝐹𝐹𝑅𝑅. 𝛼𝛼,𝛽𝛽:π‘†π‘†π‘–π‘–πΊπΊπΊπΊπ‘…π‘…β„Žπ‘€π‘€π‘€π‘€π‘€π‘€π‘–π‘–πΊπΊπ‘€π‘€πΊπΊπ‘…π‘…π‘€π‘€π‘€π‘€π‘…π‘…πΊπΊ (0≀ 𝛼𝛼,𝛽𝛽 ≀1).

The model: Explanation:

πΌπΌπ‘ƒπ‘ƒπ‘Œπ‘Œπ‘‘π‘‘ = 0 π‘…π‘…β„Žπ‘…π‘…π‘€π‘€ If there is no demand in period t then

𝑇𝑇′𝑑𝑑 =π‘‡π‘‡β€²π‘‘π‘‘βˆ’1 Estimate of mean demand interval stays the same

𝑧𝑧′𝑑𝑑 =π‘§π‘§β€²π‘‘π‘‘βˆ’1 Estimate of mean demand size stays the same

π‘Œπ‘Œβ€²π‘‘π‘‘ =π‘Œπ‘Œβ€²π‘‘π‘‘βˆ’1 Estimate of mean demand per period stays the same

πΌπΌπ‘ƒπ‘ƒπ‘Œπ‘Œπ‘‘π‘‘ > 0 If there is demand in period t then

𝑇𝑇′𝑑𝑑 =π‘‡π‘‡β€²π‘‘π‘‘βˆ’1+𝛽𝛽(π‘‡π‘‡π‘‘π‘‘βˆ’ π‘‡π‘‡β€²π‘‘π‘‘βˆ’1) Update estimate of mean demand interval by smoothing constant Ξ²

𝑧𝑧′𝑑𝑑 =π‘§π‘§β€²π‘‘π‘‘βˆ’1+𝛼𝛼(π‘Œπ‘Œπ‘‘π‘‘ βˆ’ π‘§π‘§β€²π‘‘π‘‘βˆ’1) Update estimate of mean demand size by smoothing constant Ξ±

π‘Œπ‘Œβ€²π‘‘π‘‘ =𝑧𝑧′𝑑𝑑/𝑇𝑇′𝑑𝑑 Update mean demand / period with mean demand size and interval

Croston’s estimator relies upon separate exponentially smoothed estimates of the interval between consecutive demands and the size of demands. The estimates are updated only in periods with positive demand.

4.3.2 Model of Willemain et al.

The model of Willemain et al. (2004) adopts bootstrapping to forecast intermittent data. A summary of the steps in the bootstrap approach is:

Step 0: Obtain historical demand data in chosen time buckets (e.g. days, weeks, months). Step 1: Estimate transition probabilities for two-state (zero vs. nonzero) Markov model.

Step 2: Conditional on last observed demand, use Markov model to generate a sequence of zero/nonzero values over forecast horizon.

Step 3: Replace every nonzero state marker with a numerical value sampled at random with replacement from the set of observed nonzero demands.

Step 4: Jitter the nonzero demand values.

Step 5: Sum the forecast values over the horizon to get one predicted value of lead time demand. Step 6: Repeat step 2β€”5 many times.

34 | M a s t e r T h e s i s – M . K . v a n d e r H o e v e n

4.3.3 Model of Teunter et al.

The model of Teunter et al. (2011) (TSB, after Teunter, Syntetos, and Babai) links the forecasting of intermittent demand to obsolescence. The method uses separate simple exponentially smoothed estimates of the demand probability and the demand size. The estimate of the probability of occurrence is updated every time period. The estimate of the demand size is only updated at the end of periods with positive demand (Teunter, Syntetos, & Zied Babai, 2011).

Teunter et al. (2011) introduces the following notation: π‘Œπ‘Œπ‘‘π‘‘:𝐷𝐷𝑅𝑅𝑖𝑖𝑀𝑀𝑀𝑀𝐹𝐹𝑃𝑃𝐺𝐺𝐺𝐺𝑀𝑀𝑀𝑀𝑀𝑀𝑅𝑅𝑅𝑅𝑖𝑖𝑀𝑀𝑀𝑀𝑒𝑒𝑅𝑅𝐺𝐺𝑀𝑀𝐺𝐺𝐹𝐹𝑅𝑅. π‘Œπ‘Œβ€² 𝑑𝑑:π‘…π‘…πΊπΊπ‘…π‘…π‘€π‘€π‘–π‘–π‘€π‘€π‘…π‘…π‘…π‘…πΊπΊπ‘ƒπ‘ƒπ‘–π‘–π‘…π‘…π‘€π‘€π‘€π‘€πΉπΉπ‘…π‘…π‘–π‘–π‘€π‘€π‘€π‘€πΉπΉπ‘’π‘’π‘…π‘…πΊπΊπ‘’π‘’π‘…π‘…πΊπΊπ‘€π‘€πΊπΊπΉπΉπ‘€π‘€π‘…π‘…π‘…π‘…β„Žπ‘…π‘…π‘…π‘…π‘€π‘€πΉπΉπΊπΊπ‘ƒπ‘ƒπ‘’π‘’π‘…π‘…πΊπΊπ‘€π‘€πΊπΊπΉπΉπ‘…π‘…π‘ƒπ‘ƒπΊπΊπΊπΊπ‘’π‘’π‘…π‘…πΊπΊπ‘€π‘€πΊπΊπΉπΉπ‘…π‘…+ 1. 𝑧𝑧𝑑𝑑:𝐴𝐴𝑖𝑖𝑅𝑅𝑅𝑅𝑀𝑀𝑙𝑙𝐹𝐹𝑅𝑅𝑖𝑖𝑀𝑀𝑀𝑀𝐹𝐹𝐺𝐺𝑀𝑀𝑧𝑧𝑅𝑅𝑀𝑀𝑀𝑀𝑒𝑒𝑅𝑅𝐺𝐺𝑀𝑀𝐺𝐺𝐹𝐹𝑅𝑅. 𝑧𝑧′ 𝑑𝑑:π‘…π‘…πΊπΊπ‘…π‘…π‘€π‘€π‘–π‘–π‘€π‘€π‘…π‘…π‘…π‘…πΊπΊπ‘ƒπ‘ƒπ‘–π‘–π‘…π‘…π‘€π‘€π‘€π‘€πΉπΉπ‘…π‘…π‘–π‘–π‘€π‘€π‘€π‘€πΉπΉπΊπΊπ‘€π‘€π‘§π‘§π‘…π‘…π‘€π‘€π‘…π‘…π‘…π‘…β„Žπ‘…π‘…π‘…π‘…π‘€π‘€πΉπΉπΊπΊπ‘ƒπ‘ƒπ‘’π‘’π‘…π‘…πΊπΊπ‘€π‘€πΊπΊπΉπΉπ‘…π‘…. 𝑒𝑒𝑑𝑑:𝐷𝐷𝑅𝑅𝑖𝑖𝑀𝑀𝑀𝑀𝐹𝐹𝐺𝐺𝑖𝑖𝑖𝑖𝑅𝑅𝐺𝐺𝑅𝑅𝑀𝑀𝑖𝑖𝑅𝑅𝑀𝑀𝑀𝑀𝐹𝐹𝑀𝑀𝑖𝑖𝑀𝑀𝑅𝑅𝐺𝐺𝐺𝐺𝑃𝑃𝐺𝐺𝐺𝐺𝑒𝑒𝑅𝑅𝐺𝐺𝑀𝑀𝐺𝐺𝐹𝐹𝑅𝑅,πΊπΊπΊπΊπ‘…π‘…β„Žπ‘€π‘€π‘…π‘…: 𝑒𝑒𝑑𝑑 =οΏ½0 1 πΊπΊπ‘…π‘…β„Žπ‘…π‘…πΊπΊπ‘’π‘’π‘€π‘€πΊπΊπ‘…π‘…π‘€π‘€π‘ƒπ‘ƒπΉπΉπ‘…π‘…π‘–π‘–π‘€π‘€π‘€π‘€πΉπΉ 𝐺𝐺𝑖𝑖𝑖𝑖𝑅𝑅𝐺𝐺𝐺𝐺𝑀𝑀𝑅𝑅𝑅𝑅𝑀𝑀𝑖𝑖𝑅𝑅𝑅𝑅 (𝑀𝑀.𝑅𝑅.π‘Œπ‘Œπ‘‘π‘‘ > 0) 𝑒𝑒′𝑑𝑑:π‘…π‘…πΊπΊπ‘…π‘…π‘€π‘€π‘–π‘–π‘€π‘€π‘…π‘…π‘…π‘…πΊπΊπ‘ƒπ‘ƒπ‘…π‘…β„Žπ‘…π‘…π‘’π‘’πΊπΊπΊπΊπ‘™π‘™π‘€π‘€π‘™π‘™π‘€π‘€π‘™π‘™π‘€π‘€π‘…π‘…πΌπΌπΊπΊπ‘ƒπ‘ƒπ‘€π‘€πΉπΉπ‘…π‘…π‘–π‘–π‘€π‘€π‘€π‘€πΉπΉπΊπΊπ‘–π‘–π‘–π‘–π‘…π‘…πΊπΊπΊπΊπ‘…π‘…π‘€π‘€π‘–π‘–π‘…π‘…π‘€π‘€π‘…π‘…π‘…π‘…β„Žπ‘…π‘…π‘…π‘…π‘€π‘€πΉπΉπΊπΊπ‘ƒπ‘ƒπ‘’π‘’π‘…π‘…πΊπΊπ‘€π‘€πΊπΊπΉπΉπ‘…π‘…. 𝛼𝛼,𝛽𝛽:π‘†π‘†π‘–π‘–πΊπΊπΊπΊπ‘…π‘…β„Žπ‘€π‘€π‘€π‘€π‘€π‘€π‘–π‘–πΊπΊπ‘€π‘€πΊπΊπ‘…π‘…π‘€π‘€π‘€π‘€π‘…π‘…πΊπΊ (0≀ 𝛼𝛼,𝛽𝛽 ≀1).

The method: Explanation:

𝐼𝐼𝑃𝑃𝑒𝑒𝑑𝑑 = 0 π‘…π‘…β„Žπ‘…π‘…π‘€π‘€ If there is no demand in period t then

𝑒𝑒′

𝑑𝑑 =π‘’π‘’β€²π‘‘π‘‘βˆ’1+𝛽𝛽�0βˆ’ π‘’π‘’β€²π‘‘π‘‘βˆ’1οΏ½ Negatively update the chance of demand with smoothing constant Ξ²

𝑧𝑧′

𝑑𝑑 =π‘§π‘§β€²π‘‘π‘‘βˆ’1 Estimate of mean demand size stays the same

π‘Œπ‘Œβ€²

𝑑𝑑 =𝑒𝑒′𝑑𝑑𝑧𝑧′𝑑𝑑 Estimate of mean demand is estimate of demand size times chance

𝐼𝐼𝑃𝑃𝑒𝑒𝑑𝑑 = 1 π‘…π‘…β„Žπ‘…π‘…π‘€π‘€ If there is demand in period t then

𝑒𝑒′

𝑑𝑑 =π‘’π‘’β€²π‘‘π‘‘βˆ’1+𝛽𝛽�1βˆ’ π‘’π‘’β€²π‘‘π‘‘βˆ’1οΏ½ Positively update the chance of demand with smoothing constant Ξ²

𝑧𝑧′

𝑑𝑑 =π‘§π‘§β€²π‘‘π‘‘βˆ’1+𝛼𝛼(π‘§π‘§π‘‘π‘‘βˆ’ π‘§π‘§β€²π‘‘π‘‘βˆ’1) Update estimate of mean demand size with smoothing constant Ξ±

π‘Œπ‘Œβ€²

𝑑𝑑 =𝑒𝑒′𝑑𝑑𝑧𝑧′𝑑𝑑 Estimate of mean demand is estimate of demand size times chance

Related documents