• No results found

A project manager has discovered a problem and is trying to determine the cause

In document PMP Questions 300 (Page 23-50)

Theprocess whereby he identifies the variables that have the most influence on the projectby holding all the variables constant and changing one at a time is called:

a. Product correlation b. Design of an experiment c. System integration d. Output processing

100. A control chart is being used to control a manufacturing process. As part of the control asample of five parts is taken from the manufacturing process each hour of operation.Each of the five parts is measured and the dimension is recorded on the work sheet. Thedifference between the highest and lowest measured dimension of the five parts isplotted on the control chart. This is called which of the following values?

a. R b. R bar c. X d. X bar Answers:

81. A

$3122.60

82. A

Is a method of including all of the cost associated with the project over its entire life

83.B 0.777

84. A 1.200

85.D 20,000

86. B 6,500

87. B -2,000

88. C -500

89. C 25,740

90. B

The cost performance index will remain the same for the remaining part of the project

91. B

Budget at completion, earned value, and actual cost 92. C

Reduce EV by $4,000

93. B

Average unit cost decreases as more units are produces

94. C

Implement quality improvements as long as the benefits outweigh the costs

99. B

Design of an experiment

100. A R

101. The totality of characteristics of an entity that bear on its ability to satisfy stated or implied needs is the definition for:

a. Modern quality management b. Quality assurance

c. Quality d. Quality control

102. A large project is being worked on by a large company. The client is interested in knowing how the company will be able to meet the quality needs of the project. In order to satisfy this request of the client the project manager arranges a meeting between the client and the:

a. General manager b. Quality control manager c. Quality assurance manager d. Chief designer

103. One of the fundamental tenets of quality management is that quality:

a. Must exceed customer expectation b. Is planned in and not inspected in c. Will increase cost

d. Costs must all be passed onto the customer

104. A category or rank given to products that have the same functional use but different technical characteristics is called the product’s:

a. Quality

b. Functional characteristics c. Grade

d. Technical characteristics

105. The quality manager of a company wishes to analyze the data that is coming to him in the form of a list of defects that have occurred in the shipping department. The report comes with defects listed chronologically as they occurred, the cost of the repair necessary to correct each defect, the person involved, and a description of the defect.

The manager would like to determine which of the defects should be corrected first according to the frequency of the defect occurring. He should use which of the following quality tools?

a. Cause and effect diagram b. Sampling inspection c. Pareto diagram d. Quality critical path

106. A project manager from the quality control area is trying to categorize the number of mistakes that are made in the area that paints the right front fender of the Mercedes 560 SL.

She list all the possible defects on a sheet of paper and asks the inspector to make a mark each time one of the listed defects is found. This is an example of using which of the following quality tools?

a. Scatter diagram

b. Statistical measurements c. Check sheet

d. Random sampling

107. The project management team should be aware that modern quality management complements modern project management. For example, both disciplines recognize the importance of:

a. Completion in the shortest possible time frame b. Making a maximum profit

c. Having lower cost than competitor d. Customer satisfaction

108. In a manufacturing process that is being controlled by control charts there are variables occurring that will affect the process output. Variations in the process that are considered to be normal process variables are called:

a. Common causes b. Uncommon causes c. Special causes d. Random causes

109. Work results, quality checklists, operational definitions, and the management plan are:

a. Inputs to quality control b. Outputs from quality control c. Inputs to quality assurance d. Outputs from quality assurance

110. A control chart is being used to control a manufacturing process. As part of the control a sample of five years is taken from the manufacturing process each hour of operation. Each of the five parts is measured, and the dimension is recorded on the work sheet. The average of the five parts is plotted on the control chart. This is called which of the following values?

a. X b. X bar

c. Sample average d. Control average

111. A project manager for the quality department is trying to solve a problem with a machine that makes die cast aluminum parts that are used in automobiles. These parts are frequently made with defects. The project manager has decided to hold a meeting to discuss the process of making the parts. He creates a diagram that has branches that

show the possible causes of the problems. Each of the branches breaks the cause down into more and more detail. This diagram is called a:

a. Pareto diagram b. Fishtank diagram c. Cause and effect diagram

d. Scatter diagram

112. As the manager of the production department where electrical circuits are being made you observe the inspection station where the completed printed circuit assemblies are being inspected. In this operation the inspector takes the printed circuit assembly and

puts it into a fixture. The fixture is part of the testing machine that has three digital readouts.

The inspector records the readings on the three digital readouts on his inspection report. This is an example of:

a. Attribute inspection b. Variable inspection c. Sampling inspection d. Process control

113. One of the important advantages of using control charts in managing a production operation is that the control chart tells you when to take corrective action on the process being controlled. Another important result of using control charts is:

a. The control chart identifies the special causes

b. The control chart tells you when you should not take corrective action c. The control chart shows how much the defects are costing

d. The control chart shows who is responsible for the defects

114. According to the ideas behind modern quality management, quality improvements should be made:

a. In large steps through detailed study of problems and then implemented as comprehensive solutions when they are funded

b. In small incremental steps

c. By assignment of permanent quality improvement teams

d. By hiring ISO certification consultants to point out quality deficient areas

115. The Japanese developed a method of modern quality management that relies on continuing small improvements involving everyone from the top management to the lowest level worker in the organization. This is called:

a. Kamban b. Kaizen c. PDCA d. Deming cycle

116. The primary benefits of meeting quality requirements are:

a. Cost and delays are reduced, production improves, cost to customers goes up, and profits go up b. Cost and delays are reduced, production improves, market share increases, and profits go up c. Cost and delays are reduced, capital expenditures go down, market share increases, and profits go up

d. Cost and delays are reduced, production improves, market share increases, and profits are maintained

117. When the quality management discipline is implemented, the benefits to costs ratio should at least be:

a. Unable to be evaluated b. Less than one c. Of little importance d. Greater than one

118. The quality management plan provides input to __________________ and addresses quality control, quality assurance, and quality improvement.

a. The overall project plan b. The WBS

c. The project scope d. External stakeholders

119. Project quality assurance:

a. Includes policing the conformance of the project team to specs

b. Provides the project team and stakeholders with standards, by which the project performance is measured

c. Is a managerial process that defines the organization, design, resources, and objectives of quality management

d. Provide confidence that the project will satisfy relevant quality standards

120. What are the major advantages of the functional type of organization?

a. Single point of contact for the customer b. Stable organizational structure c. Project orientation

d. Multifunctional teams are easy to form

Answers:

101. C Quality

102. C

Quality assurance manager

103. B

Is planned in and not inspected in

104. C Grade

105. C Pareto diagram

106. C Check sheet

107. D

Customer satisfaction

108. A

Common causes

109. A

Inputs to quality control

110. B X bar

111. C

Cause and effect diagram

112. B

Variable inspection

Formatted: Font: (Default) Arial, 10 pt, Font color: Custom Color(RGB(138,140,80)), Border:

: (No border)

113. B

The control chart tells you when you should not take corrective action

114. B

In small incremental steps

115. B Kaizen

116. B

Cost and delays are reduced, production improves, market share increases, and profits go up

117. D

Greater than one

118. A

The overall project plan

119. D

Provide confidence that the project will satisfy relevant quality standards

120. B

Stable organizational structure

121. The project manager’s leadership style should be matched to the corresponding developmental level of the project team and should move through successive steps in the following order:

a. Disciplinary, autocratic, participative b. Projectized, matrix, functional

c. Team building, team development, responsibility assignment d. Directing, coaching, supporting, delegating

122. A company has signed a contract for new work that is different from work that it has done before. The company’s strategic plan calls for much of this kind of work in the future. It is important that it be able to bring the correct shared resources together to work on different parts of the contract. The type of organization that this suggest is a:

a. Functional organization b. Contractor organization c. Matrix organization d. Pure project organization

123. The manager of a large corporation wants to sign a contract to build a nuclear power plant in Botswana several thousand miles away from the home office. The project will take several years to build and test. What type of organization will be best for managing this project?

a. Functional organization b. Contractor organization c. Matrix organization d. Pure project organization

124. In matrix management organizations, if the organization maintains many of the characteristic of the functional organization and the project managers are considered more like project coordinators or expediters, it is called a:

a. Strong matrix b. Project team c. Weak matrix d. Project office

125. A project manager is selecting team members for her project team. She collects the resumes and past performance reviews for the potential team members and discusses each with their functional manager. Which of the following is not a characteristic that the project manager should use in selecting the team members?

a. Previous experience b. Personal characteristics c. Personal interest d. Salary

126. A project manager is responsible for all that goes on in the project. One of the most important duties that the project manage can perform is the function of:

a. Risk management b. Quality management c. Cost management d. Integration

127. The organization that is a formalized structure directed toward the support of the project community within the organization is called:

a. Matrix organization b. Project office c. Project team

d. Project management office

128. On a project team one of the team members has a problem collecting on a medical insurance claim. The team member comes to the project manager and explains the problem.

The problem is the responsibility of the:

a. Project team b. Project manager c. Executive manager

d. Human resource department

129. The organization that is a formalized structure where the project teams and the project managers reside is called:

a. Matrix organization b. Project office c. Project team

d. Project management office

130. A conflict arises about the method to solve a difficult design problem. The project manager is seeking a method of resolving the conflict. In order to achieve the most long lasting resolution to project conflicts, which of the following approached should be used?

a. Problem solving b. Compromise c. Withdrawal d. Smoothing

131. In a large organization a project expediter is being used to manage a project for an important client. The position of project expediter would be found in what kind of an organization?

a. Strong matrix b. Weak matrix c. Functional d. Projectized

132. The project manager of a project is concerned with managing cost and improving morale and is also concerned about notifying other project managers when individuals from his project team will be available to work on other projects. This is best addressed in the project’s:

a. Communications plan b. Work breakdown structure

c. Staffing plan d. Project schedule

133. The beginning and the end of the project is defined by:

a. The project plan b. The project charter c. The team charter d. The project lifecycle

134. Herzberg divided motivation factors into two classes: satisfiers and dissatisfiers.

Examples of satisfiers are:

a. Vacation time, assignment of a personal staff assistant b. Work satisfaction, fringe benefit

c. Plush office space, performance-based salary raise d. Sense of personal achievement, work satisfaction

135. The skill of listening involves more than just hearing the sounds. One of the characteristics of a good listener is that he or she:

a. Finishes the speaker’s sentences b. Take good notes

c. Repeats some of the things said d. Agrees with the speaker

136. Primary outputs from team development are:

a. Input to performance appraisals b. High project team morale c. Reduced project cost d. Greater customer satisfaction

137. An automotive oil change station was receiving complaints that service took too long. A coffee machine and television were installed in the waiting room and the complaints went down. This is an example of:

a. Smith-Carlisle method b. Creative problem solving c. Analytical problem solving d. Decision analysis

138. A project manager is concerned about team building on her project. One of the mandatory things that she must have in order to have good team building is:

a. Commitment from top level management b. Co-location of team members

c. Establishment of clear negotiated goals d. Open discussion of poor individual performance

139. The project manager of a new project wants to get things started in a positive way with the project team. The project manager wants the team members to get to know one another, to introduce the project team and the project manager to one another, to discuss the objectives and goals of the project, and to identify some of the potential problem areas. This meeting is called a:

a. Project team meeting b. Project kick-off meeting c. Goal setting meeting d. Introduction meeting

140. A project manager is managing a project where there will be a number of persons working together. She wants to enhance the ability of the team to work together and perform as a team.

One of the things that she can do to maximize the ability of the team to do this is:

a. Cohabitation b. Co-location c. Staffing plan

d. Work breakdown structure

Answers:

121. D

Directing, coaching, supporting, delegating

122. C

Matrix organization

123.D

Pure project organization

124.C Weak matrix

125. D Salary

126. D Integration

127. B Project office

128. D

Human resource department

129. D

Project management office

130. A

Problem solving

131. B Weak matrix

132. C Staffing plan

133. D

The project lifecycle

134. D

Sense of personal achievement, work satisfaction 135. C

Repeats some of the things said

136. A

Input to performance appraisals

137. B

Creative problem solving

138. A

Commitment from top level management

139. B

Project kick-off meeting

140. B Co-location

141. A project manager is in need of a solution to a problem. He decides that the best thing will be to arrange a meeting to solve the problem rather than solve the problem himself or by having one of the project team members solve it individually. Generally, this will result in:

a. The group taking more time than one individual b. The solution to the problem being less accurate c. The group taking less time than one individual d. In depends on the specific problem

142. A project manager will manage a large complicated project that is located in a remote part of Africa. The project will last for five years and will have the product of producing a nuclear reactor that will generate 900 megawatts of power at start-up. The best kind of organization for managing this project is:

a. Strong matrix management b. Weak matrix management c. Projectized organization d. Functional organization

143. Project human resources management is divided into which of the following?

a. Organization planning, staff acquisition, and team development b. Leadership, team building, and negotiation

c. Recruitment, labor relations, and personnel administration d. Team building, communication, and labor relations

144. A project manager wants to do as much as she can to help in developing her project team. A key barrier to project team development is which of the following?

a. Strong matrix management structure

b. Major problems that delay the project completion date or budget targets c. Team members who are accountable to both functional and project managers d. Formal training plans that cannot be implemented

145. Which of the following media can a communicator use to present information?

a. Visual

b. Audio and visual c. Tactile

d. Visual, audio, and tactile

146. The three principal interests in maintaining good document control are:

a. Timely communication, collection of performance appraisal data, and assuring proper disposal of sensitive documents

b. Timely communication, maintain proper approvals, and communication cost control

c. Effective communication, ability to reconstruct why decisions were made, and historical value d. Security, change management, and procedural documentation

147. A project manager wants to handle communications well in his project. In order to do this he has chosen to write a communication plan. Of the items listed below, which one is not part of the communication plan?

a. Collection and filling structure b. Distribution plan

c. Method for accessing information d. Project organization structure

148. Which of the following are filters that the receiver uses to filter messages?

a. Language and knowledge b. Distance

c. Culture and distance

d. Language, distance, culture, and knowledge

149. A project manager has many different ways of communicating. Which of the following is a good communication tools for the project manager to use?

a. Sending a videotape of the project progress to the client b. Inputting a task into the project manager’s personal computer c. Writing notes on a handheld computer

d. Putting the project budget into a spreadsheet

150. The use of brainstorming as a communication technique encourages which of the following?

a. Team building and convergent thinking b. Divergent thinking

c. Analytical results

d. Use of the scientific method

151. Which of the following techniques allows for the participants to be anonymous?

a. Brainstorming b. Nominal group c. Delphi technique d. Crawford slip

152. Which of the following is not a standard type of communication?

a. Written b. Verbal c. Nonverbal d. Clairvoyant

153. During a project meeting a disagreement between two members of the project team began. The disagreement was over a technical detail of the project. The project manager was in attendance in the meeting. It is important that the conflicting opinion of the two team members be resolved as quickly as possible. It is even more important that the difference of opinion be resolve correctly. What should the project manager do?

a. The project manager should make the decision right away to save time and not let the two disagreeing parties stay in disagreement very long

b. End the meeting and give everyone a few days to cool off

c. Assign someone to find out more factual information about the problem

d. The project manager should suggest a compromise between the two disagreeing team members

154. In the communication model, communications between the sender and the receiver often are affected by communications barriers. These include all of the following except:

a. Cultural differences b. Differences in motivation c. Educational differences

d. Lack of a communications device

155. A project manager has one member of the project team working on a critical problem. The person working on the problem verbally communicates to the manager that this correction to the problem will probably cost $1,000. Which form of communication should the project manager use to respond to the team member?

a. Written b. Oral c. Form letter d. Formal

156. Who is responsible for communications for the project team?

a. The human resources representative

b. The representative from the management information systems department c. The project manager

d. The communications department

157. Statements such as “It’s never been done before: or “It will cost a fortune” are examples of:

158. The project manager has a very complex communication to prepare for the program manager. In order to ensure that the communication will be understood as completely as

158. The project manager has a very complex communication to prepare for the program manager. In order to ensure that the communication will be understood as completely as

In document PMP Questions 300 (Page 23-50)

Related documents