• No results found

2.4) Long Term Construction Contracts

N/A
N/A
Protected

Academic year: 2021

Share "2.4) Long Term Construction Contracts"

Copied!
7
0
0

Loading.... (view fulltext now)

Full text

(1)

F2-

45

2.4) Long Term Construction Contracts

Percentage of Completion Method

Completed Contract Method

Recognition of Income

Gross Profit recognized in each period of the contract on an accrual basis

Gross Profit recognized only on completion of the contract

Formula Gross Profit recognized in each year =

Cost to date ____ * Expected - Previously Total estimated costs Profit recognized profits

Gross Profit recognized on completion = Contract price - Total costs

Recognition of costs & billings

During the year:

- Both costs & gross profits/losses accumulated in a current asset called CIP (Construction-in-progress)

- Billings accumulated in a current liability called Billings account

At the end of the year:

Billings and CIP are netted on the B/S to report either:

- Current asset (CIP > Billings) - Current liability (CIP < Billings)

Same as % of completion method except that:

- Profits are not included in CIP

- Costs may include a reasonable allocation of G&A expenses for periods prior to completion

Anticipated losses

Anticipated losses are recognized immediately; amount of loss is total estimated loss on the contract plus all profits recognized previously

Anticipated losses are recognized immediately; total estimated loss on the contract is recognized in the current period

Conceptual base &

Advantages

- Based on the matching concept and is more consistent with the revenue recognition principle

- Based on the concept of conservatism - Based on final results rather than estimates

Disadvantages - Dependent on estimates - Violates the matching concept

US GAAP Criteria

Used when:

- Costs to complete and estimates of progress towards completion are reasonably dependable

- Collection is assured

Used when:

- Difficult to estimate costs to complete - Many contracts in progress (such that

approximately an equal number of projects are completed each year) - Duration of projects is small - Collections not assured IFRS If outcomes can be estimated reliably, use

Percentage of completion method;

otherwise, use Cost Recovery method where revenue recognition is limited to costs incurred

Completed contracts method is NOT allowed under IFRS

May use cost recovery method for IFRS

I/S

B/S

CIP = Cost + Profit - Loss (if any)

CIP = Cost - Loss (if any)

Need to estimate y All profits in the year of completion

(2)

F2-

46

Example on Long term construction contracts:

Towers Co. has signed a long term construction contract with one of its clients for total contract price of $300,000.

Below are the estimates made, costs incurred, bills raised and amounts received each year during the contract:

2001 2002 2003 Total

Costs incurred each year . $ 70,000 $110,000 $ 93,000

Estimated costs to complete (at year-end) $200,000 $ 92,000 n/a

Progress billings each year $ 60,000 $115,000 $125,000

Collections on billings each year $ 50,000 $100,000 $150,000

1. Calculate the gross profit recognized during the 3 years of the contract under the Completed contract method and the Percentage of completion method

2. Pass J/E under both the methods

Solution - Part 1 of 2:

Gross Profit Recognized under Completed Contract Method:

2001: nil (as contract was not completed) 2002: nil (as contract was not completed)

2003: Total contract price $300,000

Total costs incurred $273,000 [$70,000 + $110,000 + $93,000]

Gross Profit on construction $ 27,000

Gross Profit Recognized under Percentage-of-Completion Method:

2001 2002 2003

Total Contract price* $300,000 $300,000 $300,000

Less costs:

Actual cost to date (cumulative)* $ 70,000 $180,000 $273,000

Estimated costs to complete $200,000 $ 92,000 n/a Estimated total costs at completion $270,000 $272,000 $273,000*

Estimated total Gross Profit $ 30,000 $ 28,000 $ 27,000*

Apportionment of Gross Profit (based on ratio of costs incurred to-date to estimated total construction costs):

2001: ($70,000/$270,000) x $30,000 $ 7,778

2002: ($180,000/$272,000) x $28,000 $ 18,529

Less: Gross Profit recognized to date $ 7,778

Gross Profit recognized in 2002 $ 10,751

2003: Total Gross Profit to be recognized (actual) $ 27,000

Less: Gross Profit recognized to date ($7,778 + $10,751) $ 18,529

Gross Profit recognized in 2003 $ 8,471

* Actual figures

y x

x+y k

Gross Profit for the year = x x [k – (x+y)] - Previously

x+y recognized gross profit k – (x+y)

Do not affect

G.P. calculations

(3)

F2-

47

Solution - Part 2 of 2: Percentage of

completion method

Completed contract method

2001:

1. Costs of construction:

Construction in progress A/P or Cash

2. Progress billings:

Accounts receivable Progress billings 3. Collections on billings:

Cash

Accounts receivable 4. Recognition of Gross Profit:

Construction in progress Gross Profit on construction

70,000

70,000

60,000

60,000

50,000

50,000

7,778

7,778

70,000

70,000

60,000

60,000

50,000

50,000

(no profit recognized until completion) 2002:

1. Costs of construction:

Construction in progress A/P or Cash

2. Progress billings:

Accounts receivable Progress billings 3. Collections on billings:

Cash

Accounts receivable 4. Recognition of Gross Profit:

Construction in progress Gross Profit on construction

110,000

110,000

115,000

115,000

100,000

100,000

10,751

10,751

110,000

110,000

115,000

115,000

100,000

100,000

(no profit recognized until completion) 2003:

1. Costs of construction:

Construction in progress A/P or Cash

2. Progress billings (final):

Accounts receivable Progress billings

3. Collections on billings (in full):

Cash

Accounts receivable 4. Recognition of Gross Profit &

closing accumulated account balances:

Construction in progress Gross Profit on construction

Progress billings

Construction in progress

93,000

93,000

125,000

125,000

150,000

150,000

8,471

8,471

300,000

300,000

93,000

93,000

125,000

125,000

150,000

150,000

27,000

27,000

300,000

300,000

Construct

Bill

Receive Cash Gross Profit

B/S

B/S

B/S I/S

B/S

B/S Do not affect

G.P. calculations

(4)

F2-

48

Example of Loss in Long term construction contracts:

Walls Co. has signed a long term construction contract with one of its clients for total contract price of $300,000.

Below are the estimates made, costs incurred, bills raised and amounts received each year during the contract:

2001 2002 2003

Total

Costs incurred each year . $ 70,000 $150,000 $ 93,000

Estimated costs to complete (at year-end) $200,000 $ 92,000 n/a

Progress billings each year $ 60,000 $115,000 $125,000

Collections on billings each year $ 50,000 $100,000 $150,000

Calculate the income (or loss) recognized during the 3 years of the contract by the Completed contract method and the Percentage of completion methods

Solution:

Gross Profit or Loss Recognized under Completed Contract Method:

2001: nil (as contract was not completed)

2002: Total contract price $300,000

Actual costs incurred - $220,000

Estimated costs to be incurred - $ 92,000 Estimated loss to be recognized immediately $ - $ 12,000

2003: Total contract price $300,000

Total costs incurred - $313,000

Total loss on construction $ 13,000

Less: Loss recognized in 2002 - $ 12,000

Loss recognized in 2003 - $ 1,000

Gross Profit or Loss Recognized under Percentage-of-Completion Method:

2001 2002 2003

Total Contract price* $300,000 $300,000 $300,000

Less costs:

Actual cost to date (cumulative)* $ 70,000 $220,000 $313,000

Estimated costs to complete $200,000 $ 92,000 n/a Estimated total costs at completion $270,000 $312,000 $313,000*

Estimated Gross Profit $ 30,000 - $12,000 - $13,000*

Apportionment of Gross Profit or Loss:

2001: ($70,000/$270,000) x $30,000 $ 7,778

2002: Estimated loss (loss not apportioned) - $12,000

Profit recognized to date - $ 7,778

Loss recognized in 2002 (entire loss recognized) - $19,778

2003: Total loss to be recognized (actual) - $13,000

Loss recognized to date ($19,778 - $7,778) $12,000

Loss recognized in 2003 - $ 1,000

* Actual figures

(70 + 150)

Loss – Recognize 100%

immediately even under Completed Contract method

J/E for in case of loss:

Loss X CIP X

Loss – Recognize 100%, not % of completion Need to

Reverse

(5)

F2-

49

➢ Recap of Revenue Recognition Step 5 - An entity should recognize revenue when (or as) it satisfies a performance obligation by transferring a promised good/service to a customer. For each

performance obligation, determine if it is satisfied “over time” (typically, promises to transfer services); else, consider satisfied at a “point in time” (typically, promises to transfer goods)

• Satisfied “over time”

✓ If one of the following criteria is met:

 Customer simultaneously receives and consumes the benefits provided by the entity’s performance as the entity performs

 Entity’s performance creates or enhances an asset (e.g., work in process) that the customer controls as the asset is created or enhanced

 Entity’s performance does not create an asset with an alternative use to the entity, and the entity has an enforceable right to payment for performance completed to date

✓ For each performance obligation satisfied “over time”, an entity shall recognize revenue

“over time” by consistently applying a method of measuring the progress toward complete satisfaction of that performance obligation. Appropriate methods include:

 Output methods - Recognize revenue on the basis of value of the goods/services transferred-to-date to the customer relative to the remaining goods or services promised under the contract

 Input methods - Recognize revenue on the basis of the entity’s efforts/inputs (e.g., resources consumed, labor hours expended, costs incurred, time elapsed, machine hours used) relative to the total expected inputs to satisfy the performance obligation

Percentage of Completion Method = Recognize Revenue “over time”

Pat Co. is constructing a building on a land parcel owned by its client Rover Co. Pat recognizes revenue

“over time” using the Percentage of Completion Method as:

▪ Pat has a right to payment at various stages

▪ Rover has legal title of the asset

▪ Rover has physical possession of the asset

▪ Rover has ongoing use and benefits of the asset Pat can use either of the below methods:

▪ Output method - Recognize revenue on the basis of direct measurement of the value to the customer of goods or services transferred to date. Under the output method, progress is measured by the result of the work performed, such as appraisal of the completed portion or milestones reached

▪ Input method - Recognize revenue on the basis of contractor’s “inputs” to the satisfaction of the performance obligation [refer earlier examples on Percentage of Completion method]

- However, note that costs incurred related to rework or wasted materials would be excluded from input measurement, as these costs do not represent the transfer of goods or services to the customer

- In addition, the cost of uninstalled materials do not represent contractor’s progress towards fulfilling its performance obligations and should, therefore, not be included in the measurement of progress towards completion calculation. While uninstalled materials are excluded from the measurement of progress, the contractor is permitted to recognize revenue equal to the cost of the uninstalled materials (excluding gross profit) under the new revenue recognition standards

Criteria generally met since customer

holds legal title. Also, ongoing use &

benefit of the asset with

customer

Percentage of Completion method

(6)

F2-

50

• If not satisfied “over time”, considered satisfied at a “point in time”

✓ To determine the “point in time” at which to recognize revenue, need to consider indicators of the transfer of control, which include the following:

 Entity has a present right to payment for the asset

 Customer has legal title to the asset

 Entity has transferred physical possession of the asset

 Customer has the significant risks and rewards of ownership of the asset

 Customer has accepted the asset

Completed Contracts Method = Recognize Revenue at a “point in time”

Cathy Co. is developing a property on a land parcel it owns, and has contracted to sell the same to Range Co. once the development is complete. Cathy has physical possession, legal title, and use and benefit of the property until project completion and handover to Range. Therefore, during the construction progress, Range does not gain anything from the work done. As per the contract, even though Range pays Cathy periodically for progress completed, there is no transfer of control yet. So Cathy uses the completed contract method and recognizes revenue on project completion and handover to Range.

method

(7)

F2-

51 (This page is left blank for any reference notes on

Long Term Construction Contracts)

References

Related documents

K Summary of Each Time-and-Materials and / Labor Hour Contracts Information, Including Labor Categories, Labor Rates, Hours, and Amounts; Direct Materials; Other Direct Costs;

Protect us, Lord, as we stay awake; watch over us as we sleep, that awake, we may keep watch with Christ, and asleep, rest in his peace.

 Come, let us sing to the Lord, and shout with joy to the Rock who saves us.. The Lord is God, the mighty God, the great king over all

Explosives shall notify or pending receipt of restricted stock as determined by a state must honor an initial child support money to a grand

O DEvi KamalA, You are the beloved of Vishnu, Devi of prosperity and beauty and adored by the three worlds. As you are a constant with Vishnu, please be constant with me. Whoever

He has come to the help of his servant Israel ✶ for he has remembered his promise of mercy, the promise he made to our fathers, ✶. to Abraham and his children

When Moses had read all the commandments of the law to the people, he took the blood of goats and calves, together with water and crimson wool and hyssop, and sprinkled the book

May the Lord bless you, and peace will be yours all the days of your life..