Capital Projects Report
February 19, 2019
Capital Plan Progress Highlights
The construction for Sci-High is ahead of schedule with pile driving complete and concrete pile caps and grade beams being placed.
McMain Envelope Repair Phases 1 through 5 have been completed, with the exterior repair and painting proceeding on schedule. The project is scheduled to be complete in the 3 rd quarter of 2019.
Hynes ES Envelope Repair work is scheduled to be complete in February 2019.
Ben Franklin ES Envelope Repair Phase 2 work began on 1/2/19 and is proceeding on schedule
Construction, which is being managed by the RSD, is underway on the
new Karr High School.
DBE Participation
OPSB’s DBE Program finished strong in CY-2018, with respect to capital projects. All General Contractors have displayed strong leadership by strategically partnering with DBE Subcontractors, both Tier 1 and Tier 2.
Since May 2018, Certified State & Local DBE Contractors have ~35%
participation on 9 construction projects at a value of $13,819,844.
Thirty-five (33) DBE Contractors (~73%) are currently participating on 45
individual subcontracting opportunities and are performing 30+ specialized scopes of work.
Sustainability: Eight (8) DBE contractors are participating on multiple projects, which currently entails 40% of all DBE subcontracting
opportunities at OPSB.
DBE Participation (Committed)
Project Contract
Value
Current DBE Participation Value
% of DBE Participation
# DBE Vendors Ben Franklin Elementary School –
Refurbishment: Phase 1 $ 1,980,000 $ 700,000 35% 1
McMain High School – Building Envelope $ 3,542,500 $930,100 26% 4
New Orleans Charter Science and Math High
School – New Construction $ 27,496,000 $9,825,322 36% 20
Douglass Gymnasium - Renovation $ 611,000 $ 167,575 27% 5
Mahalia Jackson Child Center –
Reconfiguration – Phase 1 $ 150,000 $68,400 46% 2
Mahalia Jackson Child Center –
Reconfiguration – Phase 2 $ 113,372 $ 113,372 100% 2
Rosenwald Response Action $1,296,772 $453,430 35% 2
Hynes Elementary Exterior Envelope $ 422,500 $ 165,000 39% 3
Ben Franklin Elementary School –
Refurbishment: Phase 2 $3,960,000 $1,396,645 35% 6
Total $39,572,144 $13,819,844 35% 45
Funding Overview
Eligible/Approved/Reimbursed To Date (thru 8/2018) $ 311,091,446 Eligible Expenditures/Reimbursement Submissions Under
Review $ 6,363,381
Follow-Up on Eligible Executed Work and Execution of Remaining Eligible Work (Includes contents to be
purchased for the new Karr HS and the new New Orleans Charter Science and Math High School)
$ 57,512,215
Total Eligible/Obligated FEMA Dollars (Hurricane Katrina:
DR 1603) $ 374,967,042
Project Summary
Project Current
Budget
Construction Complete Ben Franklin Elementary School – Refurbishment:
Phase 1
$ 7,665,367
December 2018 Ben Franklin Elementary School – Refurbishment:
Phase 2 July 2019
Hynes Elementary School – Envelope Repair $ 423,000 February 2019 Karr High School – New Construction $ 49,549,591 April 2020 McMain High School – Building Envelope $ 5,148,000 August 2019 New Orleans Charter Science and Math High School
– New Construction $ 36,137,138 December 2020
Ben Franklin Elementary School – Refurbishment Phase 1
Project Information
Owner: Orleans Parish School Board
Project Status: Closeout
Funding Source: Bonds
Architect: NY Associates, Inc.
Contractor: Construction Masters, Inc.
Scope of Work
Refurbishment of existing elementary school
Asbestos & lead paint abatement, window refurbishment Brick repair & refurbishment
Interior demolition as needed for structural investigation & inspection Project Status
Abatement complete, window refurbishment 100% complete. Substantial completion was 12/17/2018.
Budget/Cost Information Phases 1 & 2
Current Budget Projected Costs Projected Over/Under
$ 7,665,367 $ 7,665,367 $ 0
Schedule Status
Task Planned Adjusted Actual
Design April 2014 --- May 2017
Procurement March 2015 --- September 2017
DBE Participation (Committed) Contract Value Current DBE
Participation Value
% of DBE Participation
# of DBE Vendors
$ 1,980,000 $ 700,000 35% 1
8
Ben Franklin Elementary School – Refurbishment Phase 2
Project Information
Owner: Orleans Parish School Board
Project Status: Construction
Funding Source: Bonds
Architect: NY Associates, Inc.
Contractor: TBD
Scope of Work
Refurbishment of existing elementary school
Site work, ADA compliance, ceiling replacement, new elevator Floor repairs, update HVAC, sprinkler system & fire alarm
Project Status
Project bid in November 2018. Board approval in 12/2018. Notice to Proceed was provided on 1/2/2019. Interior work is ongoing.
Budget/Cost Information Phases 1 & 2
Current Budget Projected Costs Projected Over/Under
$ 7,665,367 $ 7,665,367 $ 0
Schedule Status
Task Planned Adjusted Actual
Design October 2018 --- October 2018
Procurement November 2018 --- November 2018
Construction Complete
July 2019 --- ---
Move-in August 2019 --- ---
DBE Participation (Committed) Contract Value Current DBE
Participation Value
% of DBE Participation
# of DBE Vendors
$ 3,960,000 $ 1,396,645 35% 6
Hynes Elementary School – Exterior Envelope Repair
Project Information
Owner: Orleans Parish School Board
Project Status: Construction
Funding Source: FEMA/Capital Projects
Architect: SCNZ
Contractor: ---
Scope of Work
Repair of building envelope due to water infiltration Project Status
Notice to Proceed was given 12/20/2018. Brick damaged due to issues with an expansion joint has been replaced. Brick has been removed in areas where water infiltration has been identified and further investigation is underway. Concrete repairs at the perimeter of the building are complete and parking lot repairs are ongoing.
Budget/Cost Information Phases 1 & 2
Current Budget Projected Costs Projected Over/Under
$ 422,500 $ 422,500 $0
Schedule Status
Task Planned Adjusted Actual
Design February 2018 August 2018 August 2018
Procurement October 2018 --- October 2018
DBE Participation (Committed) Contract Value Current DBE
Participation Value
% of DBE Participation
# of DBE Vendors
$422,500 $165,000 39% 3
McMain High School – Building Envelope
Project Information
Owner: Orleans Parish School Board
Project Status: Construction
Funding Source: FEMA
Architect: Concordia, LLC
Contractor: Tuna Construction
Scope of Work
Refurbishment of building envelope (excluding roof)
Including but not limited to windows, doors, stucco, and painting Project Status
Phases 1 – 5 are complete. Exterior repair and painting are ongoing.
Budget/Cost Information Phases 1 & 2
Current Budget Projected Costs Projected Over/Under
$ 5,148,000 $ 4,635,866 ($ 512,134)
Schedule Status
Task Planned Adjusted Actual
Design March 2018 --- March 2018
Procurement May 2018 June 2018 June 2018
Construction August 2019 --- ---
DBE Participation (Committed) Contract Value Current DBE
Participation Value
% of DBE Participation
# of DBE Vendors
$3,542,500 $930,100 26% 4
New Orleans Charter Science & Mathematics High School – New Construction
Project Information
Owner: Orleans Parish School Board
Project Status: Construction
Funding Source: FEMA/Bonds/Capital Projects
Architect: Verges Rome
Contractor: McDonnel Group
Scope of Work
Demolition of Wicker Elementary School Construction of a new high school
Project Status
Pile cap and grade beam placement is ongoing. Sub-surface drainage and utility construction are underway.
Budget/Cost Information Phases 1 & 2
Current Budget Projected Costs Projected Over/Under
$ 36,137,138 $ 33,884,511 ($ 2,252,627)
Schedule Status
Task Planned Adjusted Actual
Design April 2018 --- April 2018
Procurement May 2018 August 2018 August 2018
Construction December 2020 --- ---
Move-In April 2021 --- ---
DBE Participation (Committed) Contract Value Current DBE
Participation Value
% of DBE Participation
# of DBE Vendors
$ 27,496,000 $ 9,825,322 36% 20
RSD Capital Project Summary – Phase II
RSD: DBE Participation (Committed)
Project Contract Value Current DBE
Participation Value
% of DBE Participation
# DBE Vendors
Karr H.S. (CMAR) $ 46,938,195 $ 14,563,362 31.03% 16
Booker T Washington (CMAR) $ 55,164,066 $ 19,038,139 34.51% 34
John McDonogh (CMAR) $ 32,143,589 $ 11,400,172 35.47% 29
Harriet Tubman Renovation $ 13,947,000 $ ,048,926 29.03% 16
Thurgood Marshall Refurbishment $ 4,867,000 $ 1,249,326 25.67% 12 Fisk Howard Exterior Envelope Repairs $ 180,165 $ - 0.00% 0 McDonogh #28 Flooring (Phase II) $ 397,000 $ 150,360 37.87% 3
Harriet Tubman Cottage $ 552,000 $ 118,329 21.44% 6
Schaumburg Roof Repairs $ 2,031,362 $ 261,668 12.88% 6
Village de l'Est & Sarah T. Reed HVAC & Fencing $ 1,474,000 $ 342,326 23.22% 4 Sophie B. Wright Interior Painting and Wood
$ 167,122 $ 111,357 66.63% 1
RSD: Karr High School – New Construction
Project Information
Owner: Orleans Parish School Board
Project Status: Construction
Funding Source: FEMA
Architect: Trapolin Peer Architects, APC
Contractor: Core Construction Services, LLC - CMAR
Scope of Work
Construction of new high school – Construction Manager at Risk Project Status
Structural steel and decking are being set. Framing contractor has mobilized.
Budget/Cost Information Phases 1 & 2
Transferred Projected Costs Projected Over/Under
$ 49,782,165 $ 48,773,696 ($1,008,469)
Schedule Status
Task Planned Adjusted Actual
Design November 2017 March 2018 March 2018
Procurement January 2018 March 2018 March 2018
Construction July 2020 --- ---
Move-In --- --- ---
DBE Participation (Committed) Contract Value Current DBE
Participation Value
% of DBE Participation
# of DBE Vendors
$ 46,938,195 $ 14,563,362 31.03% 16
RSD: Booker T. Washington - New
Project Information
Project Control: Recovery School District Project Status: Construction
Funding Source: FEMA
Architect: Hewitt Washington & Associates
Contractor: Core Construction Services, LLC - CMAR
Scope of Work
Construction of a New High School Restoration of existing Auditorium
Project Status
Installation of interior finishes is underway. Casework is being installed.
Installation of storm-water retention structure is in progress. Installation of brick on facades of the Auditorium building is beginning.
Budget/Cost Information Phases 1 & 2
Current Budget Projected Costs Projected Over/Under
$70,329,905 $67,380,498 ($2,949,407)
Schedule Status
Task Planned Adjusted Actual
Design --- --- December 2017
Procurement --- --- ---
Construction January 2019 May 2019 ---
DBE Participation (Committed) Contract Value Current DBE
Participation Value
% of DBE Participation
# of DBE Vendors
$ 55,164,066 $ 19,038,139 34.51% 34