MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Target Resources Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
1.0 INTRODUCTION
1.1 PURPOSE
The purpose of the Project Quality Plan is to provide the key to the successful outcome
of a project and such is the strategic planning document for the project. It is the
document in which the Project Manager identifies the key challenges and critical
execution issues for the particular project and documents the strategies for ensuring
that these issues get the attention they warrant at crucial times and are managed and
closed out effectively.
This chapter sets out the general structure and approach for the preparation of a Quality
Plan, as the project develops from stage to stage, it does this by:-
Establishing a firm foundation at the outset
Providing ongoing support to good practice throughout the implementation
The PQP:-
Is structured the same for all projects
Provides project specific information within the common structure
Forms a road map through the project
Prompts consideration of the key issues
Is a live document
Is progressively completed
Forms an audit trail
Records changes
1.2 OBJECTIVE OF THE PQP
The objective of the PQP is to ensure that all phase of the project are executed with the
optimum quality of satisfying the client’s requirement.
ACDA site team and consultant project team will be implemented, maintained and
improved through all phase of the project. Implementation of PQP must be fully
supported by all personnel engaged on the project.
1.3 SCOPE
All projects required a PQP. The chapter describes the actions that the Project Manager
must take to initiate and maintain the PQP.
The Project Manager has sole responsibility for the initiation and maintain of the PQP for
the project.
The chapter establishes a clear link between the ISO 9001:2008 requirement and also
with the Client’s requirements.
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Target Resources Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Target Resources Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
2.0
SYSTEM IMPLEMENTATION POLICIES
2.1
Project Quality Statement
i)
ACSB is fully committed to the quality objective of the works for Perumahan
Rakyat Ladang Tanah Merah Project.
ii) The scope of this PQP comprise of collection procedures and instruction in
order to achieve the specified quality as per contract specification and
standards.
iii) All members of ACSB are committed to work as a team to achieve the
objective of our client.
2.2
Quality Policy
i)
To implement the ACSB Quality system employing systematic, planned and
cost effective procedures that determine, assess and achieve quality and
value.
ii) To require the use of appropriate Quality System by our own suppliers and
subcontractors.
iii) To require all staff to perform their duties in compliance with the ACSB
Quality System.
2.3
Quality Objectives
i)
Deliver project within contract time.
ii) Compliance to Client’s requirement.
iii) Minimize defect up to 70%.
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
3.0 PROJECT BRIEF
3.1
GENERAL PROJECT BRIEF
PROJECT:
Merekabentuk, Membina dan Menyiapkan 100 Unit Rumah Teres Satu
Tingkat dan Kerja – kerja Berkaitan Bagi Program Perumahan Rakyat
(PPR) di Ladang Tanah Merah Port Dickson, Negeri Sembilan Untuk
Kementerian Kesejahteraan Bandar, Perumahan dan Kerajaan Tempatan
Contract No.
: KPKT/CPPP/JPN/7/3/2015
Letter of Award
: Ref No.: (2)dlm.KPKT/CPPP/UB/864/2/7-7K
Date of Award
: 11
thFebruary 2015
Contract Period
: 24 Months from the date of site possession
Site Possession
: 16 April 2015
Completion Date
: 15
hApril 2017
Defect Liability Period
: 24 Months
Liquidated & Ascertained
Damages (LAD)
: RM 3,166.00 per calendar day
Contract Sum
: RM 16,842,490.00
Retention Sum
: 10% of Certified Value Up to a maximum of 5% of the
Contract Sum
Client
: KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
Bahagian Pembangunan Dan Pelaksanaan Projek
Cawangan Pelaksanna Dan Penyelenggaran Projek
Aras 5-8, No.51,
Persiaran Perdana, Presint 4,
62100 Putrajaya, Malaysia.
Tel
: 03 - 8891 5000
Fax
: 03 – 8891 3094
Person In-Charge
: 1. Ir. Hj. Mohd Halimi Bin Ismail (KPPK/W3)
: 2. En. Chandiramohan a/l Ranjithan(PP1/W3)
Main Contractor
: ACDA CAPITAL SDN BHD
No.244-24, Jalan Haruan 5/6,
Pusat Komersial Oakland 11,
70200 Seremban,
Negeri Sembilan Darul Khusus
Tel
: 06 – 632 3322
Fax
: 06 – 631 3322
Person In-Charge
: 1. Ir. Haji Nazar bin Ujang
2. En. Kamarul Hisyam Mohd Hashim
Architect
: WAN ARJUNA ARCHITECT (WAA)
23-3, Jalan Wangsa Delima 12,
D`Wangsa, Wangsa Maju,
53300 Kuala Lumpur, Malaysia.
Tel
: 03 – 4143 6616/6617
Fax
: 03 – 4143 6606
Person In-Charge
: 1. Ar. Wan Norarjuna bin Wan Mustafa
2. En. Azam Abd. Halim
Civil & Structure
: RMS & ASSOCIATES CONSULT (RMS)
Engineer
88A, Jalan Badminton 13/29,
Seksyen 13,
40100 Shah Alam, Selangor Darul Ehsan
Tel
: 03 – 5511 7494/7495
Fax
: 03 – 5511 7476
Person In-Charge
: 1. Ir. Hj Zolihan bin Ngadeni
2. Pn. Marlina Azwani Mohd Alias
Mechanical & Electrical
: MECHYLITE CONSULT SDN BHD(MCSB)
Engineer
11A, Jalan Badminton 13/29,
Seksyen 13,
40100 Shah Alam, Selangor Darul Ehsan
Tel
: 03 – 5523 8381
Fax
: 03 – 5523 8382
Quantity Surveyor
: ADAM QS CONSULTANCY SDN BHD (AQSC)
136B,Jalan Burhanuddin Helmi,
Taman Tun Dr. Ismail
60000 Kuala Lumpur
Tel
: 03 – 7727 5503
Fax
: 03 – 5511 3757
Person In-Charge
: 1. Sr. Adam bin Salih
2. En. Mazlan Bin Omar
Landscape Architect
: ZAIMMAR ASSOCIATES(ZA)
B-3-3, Jalan Dataran Sentral 2,
Dataran Sentral, 70200 Seremban
Negeri Sembilan
Tel
: 03 – 6277 5712
Fax
: 03 – 6277 0712
Person In-Charge
: LAr. Marlina Binti Aminudin
Planner
: FOURMATE DESIGN SDN BHD(FDSB)
No. 27-1, Jalan MH-1,
Taman Muzaffar Heights,
Hang Tuah Jaya,
75450 Ayer Keroh
Melaka
Tel
: 03 – 6156 5413/5428
Fax
: 03 – 6156 5436
Person In-Charge
: Ms Joanna
3.2 Summary Scope of Works
AC-DA CAPITAL is comprises generally the supply of all labours, materials, tools,
implement, equipment and everything else necessary for the construction and
completion of MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH
TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN
RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK
KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
Generally the project is divided by sections and the works are executed by nominated
sub-contractors:
Mobilization and demobilization of Main Contractor’ plants, machineries and
manpower to site. Others works includes submission of deliverables to Client and
compliance to rules and regulation of Client and Local Authorities.
Provide all the necessary documents pertaining to CCC to the Superintending
Officer Representative (SOR) before the SOR can issue the Certificate of Practical
Completion (CPC) to the contractor.
b)
Building works consist of:
i)
Work Below Lowest Floor Finish – All structural work/non-structural
work including waterproofing membrane and anti-termite soil treatment.
ii)
Frame – Reinforced concrete.
iii)
Roof – Metal decking and roof clay tile on steel roof trusses; Reinforced
concrete flat roof.
iv)
Wall – Half brickwall and one brickwall complete with stiffeners, single
glazing windows come with aluminums framed.
v)
Door & Windows – Timber doors and PVC doors, casement windows and
louvre windows.
vi)
Wall, Floor Finishes & Ceiling Finishes – All plastering, tiling and flooring,
ceiling boards etc.
vii)
Sanitary Fittings & Accessories – Supply and fix all sanitary fittings and
accessories.
c)
External Works which consist of:
i)
Earthwork
ii)
Surface Water Drainage
iii)
Building Work
iv)
Road and Car park
v)
Sewerage
vi)
Water Reticulation
vii)
Hard & Soft Landscape Works
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
4.0 STATUTORY APPROVAL AND AUTHORITY
4.1
List below is the activities at the ACSB site that needs statutory approval.
Approval shall be obtained from the relevant local or federal statutory bodies.
4.1.1 The project development has to be notified by the client (KPKT) to
the authorities for acknowledgement only.
4.1.2 ACSB is responsible for compliance with all statutory requirements for the
execution of the Work and shall prior to possession of site and
progressively throughout the Contract Period where required, lodge with
the Architect/SO the details of the approvals required and/or which have
been obtained for the contractor to perform the work. There one (1)
authorities requirements and approvals i.e.
a) Majlis Perbandaran Port Dickson (MPPD)
4.1.3 ACSB to obtain Approval for Planning (AP) and other related construction
matters from MPPD and submit/obtain approval and clearance.
4.1.4 The project needs to be registered with Jabatan Keselamatan Dan
Kesihatan Pekerjaan Negeri Sembilan (JKKPNS). The JKKPS registration
number shall be display prominently at the main entrance.
4.1.3
The project also has to be registered with CIDB. The original certification
shall be displayed in the site office. A photocopy of the certificate shall be
kept by the Contract Department.
4.1.4 Storage of new materials such as bagged cement, reinforcement bars and
diesels require a permit from Kementerian Perdagangan Dalam Negeri.
4.1.5 All lifting equipment such as cranes required
Perakuan Kelayakan Mesin
Angkat (
PMA) from the JKKP.
4.2
All the permits and registrations obtained shall be documented and maintained in
the project site office. These documents shall be updated from time to time as
required.
4.3
The Project Manager is responsible to ensure that all requirement
permits/certificates are obtained and updated accordingly.
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
5.0 PROJECT ORGANIZATION, AUTHORITY AND RESPONSIBILITIES
5.1
SITE CONSTRUCTION ORGANIZATION
5.1.1 Executive Management has delegated responsibilities to management level
the project staff with complete authority to take the necessary action to
ensure conformance by all staff member of the Quality System practiced.
5.1.2 Site Construction Organization team will be made up at Project Manager,
Project Engineer, Site Safety Supervisor, Civil/Site/M & E Supervisors as
well as other direction, supervision and co-ordination to carry out the
construction programmed in accordance with contract requirement. (Refer
Appendix 1: ACSB/PPR LTM/PQP/OC).
5.1.3 The Site Management will direct and co-ordinate the appointed
sub-contractors and the operation of machineries at site to achieve an efficient
rate of progress. They will ensure the necessary degree of control is
exercised to meet the various safety, security and environmental
regulations requirement. They will lease with all relevant parties and
developments to promote effective co-ordination of information and
activities.
5.1.4 Site Construction Organization will be responsible for enforcing policies
that assure ACSB meets and maintains the stated objectives of safety,
security, logistic, Quality Assurance and Environmental requirements.
5.2
QUALITY ASSURANCE COMMITTEE
The member of the QA Committee shall comprise of the Project Manager, Project
Engineer and All Nominated Sub-Contractor. The QA Committee shall meet at least
once in 6 month to discuss and highlight problems encountered in the
implementation and operation at the QA System.
5.3
RESPONSIBILITIES OF KEY PERSONNEL
The Responsibilities of Key Personnel are as per the following:
5.3.1 PROJECT MANAGER
The Project Manager shall be report to the ACSB Project Director and shall fully
responsible to oversee the management.
Overall planning, coordinating site activities, site management and budgeting.
Lead a team of Engineers and Site Management Team.
Liaises with the employer representatives, consultant, subcontractors, suppliers and
local authorities.
5.3.2 SITE ENGINEER
The Engineer report to the Project Manager. He may be reported to Project
Director if requested.
Assisting Project Manager in planning and monitoring, preparing monthly, weekly
and daily work programs, checking, resolving, clarifying inconsistencies in drawing
well before work is carried out.
Attending Technical, ‘contractors’ meeting and communicating correct &
tip-to-date construction information between all parties.
Relating all instruction from Project Manager to sub-contractors.
Preparing or compiling from technical information (shop drawing, temporary
work design, bar bending schedules) to facilities works at site.
Supervising and coordinating works amongst subcontractors, checking
sub-contractor’s work to eliminate mistakes abortive works.
Liaising with consultant’s representative at site and assisting sub-contractors to
solve problems.
Advising sub-contractors on technical matters and ensuring sub-contractors
compliance to specification.
Verifying work done by sub-contractors.
5.3.3 SITE SUPERVISOR
The Site Supervisor reports to the Site Engineer or Senior Site Supervisor. They
may be reporting to the Senior Site Engineer or Project Manager if assign.
Supervising and coordinating works amongst contractors, checking
sub-contractor’s works to eliminate mistake and abortive works.
Liaising with consultant’s representative at site, coordinating inspection amongst
sub-contractors, consultant and QA/QC team.
Assisting sub-contractors to solve site problems and advising sub-contractors on
technical matters.
Ensuring sub-contractor’s on technical matters, communicating correct and
up-to-date construction information between all parties
Keep daily progress records and attending Monthly, Weekly and Daily contractors’
Meetings.
Measuring works done by sub-contractors and witnessing performance of test.
5.3.4 QUANTITY SURVEYOR (QS)
The Quantity Surveyor reports to and assists the Project Manager, taking-off quantities.
Assisting in preparation and submission of tenders, assisting the Project Manager in
preparing the Project budget and preparation material schedules.
Sourcing, calling evaluating quotations and tenders for supply of materials and
services.
Preparing cost estimates, quotations and tenders for new work items, measuring
work done at site and preparing interim claims and evaluating sub-contractors’
work done and prepare claim certificates.
Assisting the set-up of Management Information System and assisting the Planning
Sub-Department to prepare reports for various projects.
Preparation and submission of contractual claims, variation etc.
Assisting the preparation of the project final accounts.
5.3.5 PLANNING
Will plan and schedule engineering, procurement and construction details through
interaction with engineering, procurement and construction personnel to include
creation of activities, logic, durations, coding, resource assignments and calendar
assignments.
Will sequence major work priorities into a logical schedule and manpower load
schedule based on estimated direct hours and calculate percent complete from
schedule.
Work with functional management to resolve scheduling issues of risk.
Oversee or conduct training programs for planning and scheduling, providing
technical assistance to various departments.
Communicate scheduling problems in high-risk project to functional and power
division management.
Review project contracts, documents and drawings to determine project scope and
schedule development and to ensure Project PPR LTM complies with functional
requirements.
Oversee the verification of accuracy of critical paths across projects and review and
validation of overall project duration on multiple projects.
Will produce ad hoc reports upon request and monitor schedule for changes in float,
correct logistic, potential problems,
Communicate any schedule problem areas to project team and provide
solutions/options for resolution and monitor upstream activities that feed
engineering, procurement and construction activities for any potential impacts and
report these items to site management.
Will reflect schedule change orders in the project schedule and provide Schedule
“what-if” scenarios when requested.
Review and validated schedule progress via physical work product inspection and
maintain through knowledge of total project progress via visual inspection.
Travel to multiple project areas and/or project sites to support project needs.
5.3.6 LICENSED SURVEYOR
Licensed Surveyor will be assigned by the Project Manager specific Construction
Team as and when necessary. When looking for a particular project, they shall be
taking instruction form the respective Senior Project Manager whilst still liaising
closely with the Planning Department for technical assistance.
Counter-checking the accuracy of Monuments and Benchmark provided by other
parties.
Checking, confirming the correctness and resolving any dimensional discrepancies
in drawings.
Liaising and resolving setting out discrepancies with relevant parties.
Surveying details for planning, design and construction purposes and to check
Existing Ground Levels.
Setting out of control point, benchmarks, slope stakes, references lines, boundaries,
alignment, levels at site for various works.
Measuring completed works and preparing Site Measurement Records for payment
purpose.
Surveying for as-built drawing preparation
5.3.7 SITE SAFETY SUPERVISOR
The Site Safety Supervisor reports to the Project Manager on all matters pertaining
to workmen’s health, safety and security.
Advising the Project Manager on issues related to health, safety and security at work
sites, including Statutory Requirement and Good Practices.
Ensuring the health and safety procedures are followed and all statutory
requirements are fulfilled.
Implementing Health and Safety Programmed at project sites.
Enforcing the use of personal protection equipment, improves existing method of
workmen.
Determining the cause of accident and recommending means of prevention,
Identifying and rectifying any unusual measure taken at work site.
Setting up and operating a security system which monitors the movement of
workers, materials, goods, plants and machinery into and out of the project site.
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
6.0 QUALITY MANAGEMENT SYSTEM
6.1 MAIN CONTRACT PARTIES
The Quality System personnel are responsible for the successful implementation and
operation of this PQP.
To achieve quality, everyone is required to:
i)
Follow set procedures
ii) Inspect their own work as to its quality
iii) Identify all occurrence of problems
iv) To report to Project Manager any discrepancies between the documented
Quality System and actual working practices.
v)
Continually search for better ways of doing things.
vi) Have pride in the result of their work.
6.2
STRUCTURE
Our project Quality Management System consists of the following documents:
6.2.1 Project Quality Plan
This document defines the composition of the Quality Management System
for the project to satisfy each element of ISO 9001:2008.
It encompasses the Project Quality Objectives, the project organization, the
activities to be performed, the progress monitoring mechanism, the interface
with other parties and other project specific information. It defines
operational controls needed at each stage of the product delivery cycle.
6.2.2
Quality Procedures
This document establishes the producers of what is to be done to satisfy each
element of the Project Quality Plan.
The following List of Procedures with a tick (√) is applicable to this project. The project
team shall refer the Procedures Manual to implement these procedures.
NO. PROCEDURE DOC.REF APPLICABLE
1.0 MAGEMENT SYSTEM
- Guideline For Procedure Preparation ACSB/MS-01
2.0 QUALITY MANUAL
- Quality Manual Procedure ACSB/QM-01
√
3.0 DOCUMENT PROCEDURE
- Control of Document Procedure ACSB/DP-01
√
- Control of Record Procedure ACSB/DP-02√
- Control of Non-Conforming Procedure ACSB/DP-03√
- Internal Audit Procedure ACSB/DP-04√
- Corrective Action Procedure ACSB/DP-05√
4.0 PROJECT IMPLEMENTATION PROCEDURE
- Tendering Procedure ACSB/PIP-01 - Detailing Work Schedule Procedure ACSB/PIP-02 - Project Insurance, Performance &
advance Bond Procedure
ACSB/PIP-03
- Project Procurement Procedure ACSB/PIP-04
√
- Claims Procedure ACSB/PIP-05
√
- Monitoring of Project Progress Procedure ACSB/PIP-06
√
- Maintenance of Plant, Equipment & ToolsProcedure
ACSB/PIP-07
√
NO. PROCEDURE DOC.REF APPLICABLE
5.0 SITEPROCEDURE
- Mobilization & Demobilization ACSB/SP-01
√
- Control of Contract Drawings Procedure ACSB/SP-02√
- Main Contract Administration Procedure ACSB/SP-03√
- Site Security Procedure ACSB/SP-04√
- Occupational Health & Safety Procedure ACSB/SP-05√
- Calibration & Maintenance of MeasuringInstruments & Test Equipments Procedure
ACSB/SP-06
√
- Purchase/Hire of Plant & Equipment Procedure
ACSB/SP-07
√
- Purchase of Construction Materials Procedure
ACSB/SP-08
√
- Employment of Sundry Workers Procedure ACSB/SP-09
√
- Site Office Administration Procedure ACSB/SP-10√
- Quality Records Procedure ACSB/SP-11√
- Site Instructions Procedure ACSB/SP-12√
- Monitoring of Project Progress Procedure ACSB/SP-13√
- Material Handling & Control Procedure ACSB/SP-14√
- Identification & Traceability of WorksProcedure
ACSB/SP-15
√
- Inspection & Testing of Works Procedure ACSB/SP-16
√
- As-Built Drawing Procedure ACSB/SP-17√
6.2.3 Method Statement Manual
The procedure in this manual technically outlined the method to be adopted to
execute the construction processes. Each method statement describes the method of
handling, construction, testing or use of equipment for the particular activity.
The following Method Statements List with a tick (√) is applicable to this project.
The project team shall refer to the Method Statements Manual to implement these
documents.
NO. PROCEDURE DOC.REF APPLICABLE
1.0 STRUCTURALWORKS
- Structural Reinforced Concrete Work & Formwork for Building RC Retaining Wall
ACSB/CNS/MS/
√
2.0 CIVIL WORKS
- Drainage Work ACSB/CNS/MS/
√
- Sewerage Work ACSB/CNS/MS/
√
- Water Reticulation Work ACSB/CNS/MS/
√
- Retaining Wall ACSB/CNS/MS/
√
- Road Work ACSB/CNS/MS/
√
- Turfing Work ACSB/CNS/MS/
√
NO. PROCEDURE DOC.REF APPLICABLE
3.0 ARCHITECTURAL WORKS
- Anti-Termite Work ACSB/ARCH/MS/
√
- Brick Work ACSB/ARCH/MS/
√
- Door & Window Frame ACSB/ARCH/MS/
√
- Roof Trusses and Covering ACSB/ARCH/MS/√
- Plastering Work ACSB/ARCH/MS/√
- Ceiling Work ACSB/ARCH/MS/
√
- Screeding Work ACSB/ARCH/MS/
√
- Tiling Work ACSB/ARCH/MS/
√
- Glazing Work ACSB/ARCH/MS/
√
- Painting Work ACSB/ARCH/MS/
√
- Door & Window Casement ACSB/ARCH/MS/
√
- Furniture ACSB/ARCH/MS/
√
4.0 MECHANICAL WORKS
- Underground Pipe for Cold Water Plumbing
ACSB/MECH/MS/
√
- Underground Sanitary Pipe Installation
ACSB/MECH/MS/
√
- Sanitary Pipes Concealed in Walls Installation
ACSB/MECH/MS/
√
- Domestic Water Pump Installation ACSB/MECH/MS/
√
- Water Storage Tank Installation ACSB/MECH/MS/√
- Poly Steel Pipe for Cold WaterPlumbing Installation
NO. PROCEDURE DOC.REF APPLICABLE
4.0 MECHANICAL WORKS (CONT’D)
- Installation of gate Valve & Stop Valve
ACSB/MECH/MS/
√
- Air Conditioning Refrigeration Pipe Installation
ACSB/MECH/MS/
√
- Air Conditioning Pipe Insulation ACSB/MECH/MS/
√
NO. PROCEDURE DOC.REF APPLICABLE
5.0 ELECTRICAL WORKS
- Underground Pipe for
Electrical/Telephone ACSB/ELEC/MS/
√
- Concealed Conduit in Floor Slab ACSB/ELEC/MS/√
- Concealed Conduit inside Brickwall ACSB/ELEC/MS/√
- Cable Installation & Termination ACSB/ELEC/MS/√
- Conduit (Exposed) Installation ACSB/ELEC/MS/√
- Conduit Junction Box Installation ACSB/ELEC/MS/√
- Lightning Protection System ACSB/ELEC/MS/√
- Earthing Installation for DB & DP ACSB/ELEC/MS/√
- Electrical Distribution SystemIncluding Feeder Pillar Switch Board and Distribution Box.
ACSB/ELEC/MS/
√
- Installation of Trunking ACSB/ELEC/MS/
√
- Installation of Fan Hook ACSB/ELEC/MS/√
- Electrical, Telephone and TV Wiring ACSB/ELEC/MS/√
- TNB Metering Panel ACSB/ELEC/MS/√
6.2.4 Inspection and Test Plan
It describes all the approval, inspection and testing requirement relevant to a
particular operation or element of work of the project, in the sequences that are
carried out.
Refer to Inspection and Test Plan Manual. (ACSB/PPR LTM/PQP/ITP)
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
7.0 DOCUMENT AND DATA CONTROL
The Project Manager and his Site Supervision are responsible for ensuring that all critical stages of the construction process are adequately supervised, and the quality of works meet the standards and requirements spelt out in the contract document and specifications.
Method of construction proposed by us, especially for special construction process, shall be review/approved by the Project Manager, Consultant/Client to ensure that adequate quality control measures have been specified.
Where equipment, such measuring instruments, is being used during the process such equipment shall be suitably serviced and maintained to ensure continuing process capability.
The procedure ensures that incoming documents and data where appropriate are suitably reviewed before distribution, out-going documents are suitably reviewed and approved by authorized personnel before issue, that up-to-date are available to all who need them and that obsolete are removed or otherwise assured against use.
7.1 DOCUMENT AND DATA APPROVAL ISSUE
The following categories of documents have an impact on the quality of the Project and are therefore controlled through a process of review, approval and documentation as described in the Quality Procedures.
7.1.1 Project Quality Plan
This document is maintained and controlled by QA Manager who responsible for reviewing, updating and distributing it.
This document including all amendments and revisions shall be approved by the Project Manager.
7.1.2 Project Related Document and Data
The above category includes the following: i) Project Contract Documents ii) Project Drawing
iii) Project Files iv) Site Records
Procedures controlling the preparation, review and approval of these documents and data, where applicable, are spelt out in the Quality Procedures.
7.1.3 Other Quality Records
Other quality document, such as quality training records, internal quality auditing records, management review records, quality system files etc should be properly kept, filed and maintained by the QA Manager.
7.2 DOCUMENT AND DATA CHANGES/AMENDMENTS
The Quality Procedures also spell out the detailed procedures on how changes are to be made to the Quality System document and data of construction drawings.
7.3 DOCUMENTATION CONTROL
A) INCOMING/OUTGOING CORRESPONDENCE FILE CODE
FILE CODE TYPE OF FILE
WAA Incoming and Outgoing Correspondence from Architect Consultant
RMS Incoming and Outgoing Correspondence from C & S Consultant
MCSB Incoming and Outgoing Correspondence from M & E Consultant
AQSC Incoming and Outgoing Correspondence from QS Consultant
ZA
Incoming and Outgoing Correspondence from Landscape ConsultantSC
Incoming and Outgoing Correspondence from SubcontractorAUT
Incoming and Outgoing Correspondence from AuthoritiesKPKT
Incoming and Outgoing Correspondence from ClientB)
CONTRACT FILE CODE
FILE CODE
TYPE OF FILE
LA LA, CPC, CF (Client and Sub-Contractor)
IB Insurance and Bonds
CD Contract Documents
B)
CONTRACT FILE CODE (CONT’D)
FILE CODE TYPE OF FILE
BQ Bill of Quantities (BQ)
TA Tenancy Agreement
SCG Sub-Contractors Guarantees and Warrantees
MAL Material Approval List and Certificates
EOT Extension of Time
CIDB CIDB (Expand as required)
C) PAYMENT FILE CODE
FILE CODE TYPE OF FILE
FA Final Account
CLAIM Claim to Client
PAYMENT Payment to Sub-Contractor
VO Variation Order Claims
PO Purchase Order and Delivery Order (Expand as required)
D) TENDER FILE CODE
FILE CODE TYPE OF FILE
QUOT Suppliers Quotation
E) MINUTE OF MEETING FILE CODE
FILE CODE TYPE OF FILE
SM Minutes of Site Meeting
TM Minutes of Technical Meeting
SCM Minutes of Sub-Contractors Meeting
F) PROJECT FILE CODE
FILE CODE TYPE OF FILE
SOI Superintending Officer Instruction
SD Site Directive
RFI Request for Information
IR Inspection Request
TR Testing Report
PR Project Progress Report
NCR Non-Conformance Report
SF Submittal Form
G) ADMINISTRATION FILE CODE
FILE CODE TYPE OF FILE
LEAVE Staff Leave Record
PETTY CASH Petty Cash
ASSET Office Equipment Record
STAFF Staff Report
BILL Site Office Bill
SITE DOCUMENT CONTROL FLOW CHART
Process Incoming Correspondence Responsibilities
START RECEIVE CORRESPONDENCE PROJECT MATTERS DATE STAMP, REGISTER REFERENCE DUPLICATION OF DOCUMENT/CORRESPONDENCE DEFINE DISTRIBUTION CIRCULATION TO RESPECTIVE SECTION MANAGER DEFINE ACTIONEE DISTRIBUTION ACTIONEE SUBJECT FILE END ADDRES S ORIGINAL CORRESPONDENCE TO MASTER FILE END Document Control/Clerk Document Control/Clerk Document Control/Clerk -Do- Clerk Project Manager Project Manager Project Manager Department Clerk Department Clerk
SITE DOCUMENT CONTROL FLOW CHART
Process Outgoing Correspondence Responsibilities
START
DRAFT CORRESPONDENCE FOR APPROVED
ASSIGNED & REGISTER REFERENCE NUMBER TYPING CHECK ACCEPTABLE INITIAL SIGNATURE REGISTER SUBJECT FILE END Staff Document Control/Clerk Clerk Author Author Author Project Manager Document Control/Clerk Document Clerk MASTER FILE Document Control/Clerk
INCOMING DRAWINGS WORK FLOW CHART
START
Received drawings from sender and check Drawings Transmittal against drawings
Stamp “Date Received” on the Drawing Transmittal and return copy to sender. Stamp “Data Received” on
every drawing received
Record drawings received on the Drawing Register. Distribute drawings to relevant personnel for action
Replace old drawings with current revision. Stamp “Superseded” on old drawings and keep them
separately
Record and keep superseded drawings in the RECALL BOX
Maintain drawings as per Drawing Register
Are drawings receive complete/correct END Requested incomplete Drawings from sender/Inform incorrect drawings
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
8.0 MAINTENANCE OF INSPECTION, MEASURING AND TEST EQUIPMENT
8.1 In order to ensure that all equipment/instrument are in good condition to meet its accuracy, that equipment/instrument required calibration shall be done on regular basis or depending on their specified frequency.
8.2 The calibration exercise shall be performed by a organized independent body. The calibration reports shall be submitted to consultant for review. The attached flow chart showing how the calibration being handled.
8.3 The equipment/instrument should have valid calibration report prior to its usage. 8.4 Consultant shall verify on site that the calibrated equipment/instruments are being used.
8.5 The calibration certificate must be readily available at site and must indicate the following items:
i) Date of the calibration done ii) Date of the calibration required iii) Validity period
iv) Serial no.
8.6 The list of the new equipment/instrument to be utilized on site shall be submitted to consultant from time to time together with the calibration reports.
CONTROL OF INSPECTION, MEASURING AND TEST EQUIPMENT ACSB Equipment/Instrument Calibrate Recognized independent Body conduct Calibration Report
ACSB submit calibration Report to consultant for
review
Consultant to review and verify
ACSB use the equipment/instrument on site Consultant to witness
when required
If expired recalibrate Equipment/Instrument Not usable
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
9.0 INSPECTION AND TEST PLAN
The Inspection and Test Plan or usually known as Inspection Request (IR) on the site will be prepared on trade of work basis.
For list of ITP, please refer to the Section 16.0 in this PQP.
9.1 RECEIVING INSPECTION AND TESTING
All our design calculations (from sub-contractors) shall be checked by the consultants for completeness to ensure that all requirements and standard specified have been complied with.
Whenever material samples and shop drawings are received, they shall checked or tested and accepted by the S.O/C.O.W before being used on site to ensure that all requirements and standards are complied with.
Items such as steel bars and structural timber product must be accompanied by the relevant Mill Certificate and SIRIM Certificate respectively.
9.2 IN PROGRESS AND FINAL INSPECTION, TESTING AND TEST RECORDS
Prior to and during the construction process, the Project/Site Engineer and Site Supervisors are responsible for checking and inspecting all critical stages of the construction work to ensure all requirements are met.
Shall notify the S.O/C.O.W at least 24hrs in advance prior to any inspection being carried out.
Subsequently, the relevant work should also be inspected by the consultant’s representative for approval. All approvals and comments should be documented. Any comments that need to be action shall be carried out and also documented.
The project engineer shall review all testing result or reports and the site supervisor shall keep the test records of every stage of the construction processes.
MATERIALS APPROVAL FLOW CHART
Supplier, Manufacturer test Report/Mill Certs
during delivery ACSB/ Consultant joint inspection for selected Reject Return OK
Sub-contractor submit list of supplier/manufacturer
with catalogue and samples
Client/TRSB/ Consultant
review
Factory visit when required
Material approved for construction used
Separate or in Dumping Site
Reject Return OK
Sub-contractor submit list of supplier/manufacturer
with catalogue and samples
Client/ACSB/ Consultant
review
Factory visit when required
EARTHWORK QA/QC FLOW CHART
Description
Action person
5) Testing
(Compaction Test)
5) Field density test (sand replacement method)-compaction test SC RMS 4) To check invert level (1L), Temp, Earth drain, Silt trap, Temp Culvert
ACSB RMS SC
4) Earthwork
3) Site Clearing 3) Boundary Identified ACSB SC RMS
1) Survey Accept 1) Accept/contest SC
2) Resurvey spot check
2) All relevant parties to spot check
ACSB RMS SC
No
6) As-Built surveyor 6) As built by license survey
CONCRETE WORKS QA/QC FLOW CHART
Description
3) Review concrete material according to specificationAction
TRSB yes return yes5) Concrete finish & Cube test – post concrete checklist
RMS ACSB
Casted Concrete Issued NCR
RMS ACSB
4) Check concrete quality e.g slump test, structure ready for concreting – pre pour concrete checklist Concrete Placing No (Reject) yes Concrete Materials No (Reject) 1) Check equipment calibrate
report & all relevant report
RMS ACSB
Design Mix Trial Mix
RMS ACSB
Supplier (Batching Plant)
2) Design mix review and carry out cube test
yes No 3) Review concrete material according to specification RMS ACSB yes yes
Acceptance Refer NCR flow chart 6) End
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
10.0 PROCEDURES/METHOD OF STATEMENT REFERENCES
The Method of Statement for this project is handled as follows:
Preparation - Sub-Contractors, Supplier and Site Engineer Checking - Project Manager
Approval - Consultant/Client
For the latest list of Method Statement and Manuals, please refer to the Section 6.0 (6.2.3) this PQP and Work Method Statement (ACSB/PPR LTM/PQP/MS).
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
11.0 HANDLING OF FEEDBACK, NON-CONFORMANCE, CORRECTIVE AND PREVENTIVE ACTION
11.1 OBJECTIVE
To ensure that all feedback or complaints received from clients and staffs, all non-conformances detected during the various process, must be identified. Corrective and preventive proposed action shall be implemented in order to improve the quality system and to prevent recurrence of non-conformance.
11.2 SCOPE
This procedure shall apply to all process in the project.
11.3 RESPONSIBILITIES
All staffs are encouraged to provide feedback on the QA System. The Project Manager has overall responsibility for ensuring that all designed personnel are notified of non-conformance product situation and deal expeditiously with client’s complaint and ensure effectiveness of corrective action.
11.4 PROCEDURE
11.4.1 ACSB Project Management and consultants are encouraged to rise up non-conformance report (NCR) whenever notices/detected any non-non-conformance product or material in the project.
11.4.2 Copy of NCR will be forwarded to relevant contractors and the sub-contractor should propose corrective action in order to solve and prevent the same defect recurrent.
11.4.3 All Corrective Action Request (CAR) submitted by sub-contractors will be reviewed and evaluated by ACSB Project Management and relevant consultant.
11.4.4 Sub-contractor must include all corrective action requests together with Method Statement and material brochure if necessary.
11.4.5 When a corrective action request is agreed or approved. ACSB Project Management and consultant shall monitor and ensure that relevant CAR is done within the stated time stated. If CAR is not given within the time stated, Project Management shall extend the letter with a copy of NCR to the Director(s) of the relevant company.
11.4.6 ACSB Project Management and consultants shall inspect to verify that the CAR’s are completed and satisfactory signed by relevant parties hence closing the NCR. 11.4.7 All closed NCR must compile and accessible for every staff.
FLOW CHART FOR THE CONTROL OF NON-COMPLIANCE REPORT
Non Conformance Activity/Product Notice/Detect
NCR Issue to Sub-contractor
Corrective Action Request (CAR) to be submitted within
Agreed time frame
Review and evaluate Corrective Action Request
(CAR)
Proceed with Corrective Action
Inspect Corrective Action
Project Eng. Manager and Consultant approved and
closure of NCR
NCR is closed and filed ACSB Project Management
Consultant
Sub-contractor
ACSB Project Management Consultant
ACSB Project Management Consultant
ACSB Project Management Consultant Sub-contractor Returns to sub-contractor re do redial works Yes Yes Yes Yes Yes No No
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
12.0 MAJOR PLANT AND MACHINERY SCHEDULE
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
13.0 MEETING AND ATTENDANCE
The meeting for this project shall be check as follows:
NO
MEETING
FREQUENCY
1)
Client
Every Month
2)
Sub-con Coordination Meeting
Weekly
3)
Safety and Health Committee Meeting
Every Month
4)
Technical Meeting
Every Month
5)
Staff Meeting
Every Month
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
14.0 LIST OF QUALITY RECORDS
The List of Quality Records is as follows:
NO QUALITY RECORDS MAINTAINED AT SITE BY RETENTION PERIOD REMARKS
1) All Correspondences PM 7 Years
2) Project Quality Plan PM 7 Years
3) Inspection and Test Data QA/QC 7 Years
4) Calibration Data QA/QC 7 Years
5) Specification QA/QC 7 Years
6) As Built and Structural Drawings QA/QC 7 Years
7) NCR Report QA/QC 7 Years
8) Internal Quality Audit QA/QC 7 Years
9) Site Meeting Minutes PM 7 Years
10) Request for Inspection QA/QC 7 Years 11) All Checklist for Inspection QA/QC 7 Years
12) Post Concreting QA/QC 7 Years
13) Other files PM 7 Years
* Upon completion of the project, all Quality shall be sent for storage by the Human Resources Department to an appointed third party store.
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
15.0 FORMS AND CHECKLIST
15.1 FORMS (CLIENT/CONSULTANT)
NO. DESCRIPTION DOCUMENT REFERENCE
1. Architect’s Instruction/ Superintending Officer Instruction KPKT/PPRLTM/PQP/F01 2. Architect’s Instruction/ Superintending Officer Recommendation KPKT/PPRLTM/PQP/F02 3. Drawing/Information Transmittal Form KPKT/PPRLTM/PQP/F03
4. Site Directive KPKT/PPRLTM /PQP/F04
5. Request For Information KPKT/PPRLTM /PQP/F05
6. Non Conforming Report KPKT/PPRLTM /PQP/F06
7. Inspection Request KPKT/PPRLTM /PQP/F07
8. Notification of Potential Change KPKT/PPRLTM /PQP/F08
9. Submittal Form KPKT/PPRLTM /PQP/F09
10. Sample Identification Tag KPKT/PPRLTM /PQP/F10
11. Shop Drawing Register KPKT/PPRLTM /PQP/F11
12. Meeting Attendance KPKT/PPRLTM /PQP/F12
15.2 FORMS (ACSB)
NO. DESCRIPTION DOCUMENT REFERENCE
1. Request For Inspection ACSB/PPRLTM /PQP/F01 2. Request For Information ACSB/PPRLTM /PQP/F02
15.3 CHECKLIST’S LIST (ACSB)
NO. TYPE OF WORKS APPLICABLE
1.00 Architect Checklist 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08
- Anti-Termite Works Inspection - Brickworks Inspection
- Aluminium and Glazing Works - Ceiling Works
- Cement Screeding Works - Door and Window Works - Floor Tiling Inspection - Panting Works √ √ √ √ √ √ √ √
2.00 Civil And Structure Checklist
2.01 2.02 2.03 2.04 2.05 2.06 - Excavation Works
- Installation Of Reinforced Earth Wall - Rebar Testing Before Fabrication
- Cast In-Situ RC (Pre-Concreting) Inspection - Cast In-Situ RC (Post-Concreting) Inspection - Concreting Works Inspection
√ √ √ √ √ √ 3.00 M&E Checklist 3.01 - AC Pipework inspection √
3.02 - Cold Water Plumbing Inspection √ 3.03 - Conduit, Trunking and Cable Tray Inspection √ 3.04 - Hot Water Plumbing Inspection √ 3.05
3.06
- Lightning and Small Power Inspection - Sanitary Plumbing Inspection
√ √
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR,
PERUMAHAN DAN KERAJAAN TEMPATAN
NOTE :
The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.