Photovoltaic Power Systems -2
Grid connected PV
Professor Chem Nayar
Curtin University of Technology
Perth , Western Australia
Grid Connect PV Systems
Simplest of systems
No storage
Grid Connect PV Systems
Net Metering – single meter runs in both directions
Can also be with two meters : one to measure energy sold
and the other energy bought
SPECIFICATION (NOMINAL VALUE)
MODEL : PV-MF130EA2
MAXIMUM SYSTEM VOLTAGE
600 V
MAXIMUM POWER (Pmax)
130 W
OPEN CIRCUIT VOLTAGE (Voc)
24.2 V
SHORT CIRCUIT CURRENT (Isc)
7.39 A
MAXIMUM POWER VOLTAGE (Vmp)
19.2 V
MAXIMUM POWER CURRENT (Imp)
6.79 A
Sine wave output Low harmonic distortion (less
than 4%)
Input voltage range 160 – 350 VDC
Output voltage range 187 – 253 VAC
Single phase, can operate in
frequency range 50 Hz +/- 6%
Power factor > 0.98
High efficiency (more than 90%)
Maximum power point tracking
Mains and solar generator are galvanically
isolated
Disconnect from grid line within 1 cycle in
case of abnormal condition
Computer interface for local and remote
monitoring and data retrieval
Connecting Solar Panels
Series connection to increase voltage
Parallel connection for increasing current
Terminology
– Module
– String
– Sub array
– Array
Blocking Diodes to prevent reverse
current flow
Cable Sizing
Size for volt drop
– Maximum of 5% recommended
Size for current rating
– Note that energy can typically feed from both
the array and the power conditioner
– Current rating of the cable is the rating of the
protective device, not the PV output
– Consider cable exposed temperature when
sizing for current rating
Protection Requirements
Module protection – Bypass diodes
String protection
– Blocking diodes
– Fuses
Array protection
– Overcurrent protection
– disconnection
Australian Requirement
Breaker trip current to be between
– 1.25 x Isc
– 2 x Isc
Isc is for the section feeding through the
trip device
Cable is then sized to the breaker
Note some PV manufacturers recommend
maximum fuse ratings for the modules
Components
Over current protection
– Must be DC voltage rated
– DC arcs are hard to extinguish
Disconnection
– Distinguish between isolators for breaking
down the array and load break isolators for
disconnection under load
– Plugs and sockets can’t be separated under
load
Components cont.
Blocking diodes
– Are not considered a fuse
– Cannot be relied upon to block reverse current
– Make sure they meet the voltage rating requirements
of the system
– They can get hot, keep them cool
Australian requirements include breaker the array
into Extra Low Voltage (ELV) sections and being
able to isolate the inverter for removal
Australian considerations
Australian requirements include
– breaking the array into ELV sections for safe
install and maintenance
– being able to isolate the inverter for safe
removal
GRID CONNECTED INVERTER SYSTEM
Converts DC current from solar panels to AC current and feed to the
grid .
The system uses 50 Hz voltage waveform from grid line as a
reference signal and feed current to the grid line. Before connecting,
the inverter will check property of grid line according to following
conditions
:-• Voltage level
• Frequency range
• Phase of signal
If all conditions are within specified range and synchronized with
internal generating frequency, the inverter will be connected to the
grid
In case there is some abnormal condition with the grid, inverter
should disconnect itself for both safety to human life and safety to
the system.
PV/Grid Energy System Inverter
Configurations
Large Single Inverter Type (Central
Inverter)
Multiple Small Inverter Type (String
Inverter)
DC Bus (Multi-string Inverter)
“AC” Module
PV/Grid Energy System
Inverter Configurations
Central Inverter Type
Series and Parallel
connection on DC side
All PV panels
connected to single DC
bus
Single Central Inverter
Affected by partial
shading of panels
Only one protection
Kalbarri PV System
in Western Australia (1995)
10kW
10kW
35kVA
(75kVA)
250Vdc
6.6kV
100kVA
415Vac
10kW
10kW
10kW
10kW
35kVA
(75kVA)
250Vdc
35kVA
(75kVA)
250Vdc
6.6kV
100kVA
415Vac
6.6kV
100kVA
415Vac
6.6kV
100kVA
415Vac
String Inverter Type
One inverter per
string
Panels grouped
into smaller
inverter –rated
power of Inverter (
0.7-5kW)
Not so badly
affected by shading
Not badly affected
@ 3.3kW
String Inverter Battery Backup
Controller
Back up Line
AC Grid Line
DC 48 V
AC Line
DC from PV
160 to 240 V
AC Line
DC 48 V
Grid-Connected PV System
with Back up Inverter
Kang Som-Mao, Ratchaburi
PV
CONTROLLER
-BATTERY batteries for S-218C INVERTER APOLLO G –304 And S-218C
DC Linked or Multistring type
Each panel or
group have a
DC-DC step up
converter
High voltage DC
link feeds
transformer-less
converter
DC Linked
#1 String boost HFT L PV C 1 S S3 4 S 2 S 1 D D3 2 D D4 DC C HFT boost L PV C 1 S S3 4 S 2 S 1 D D3 2 D D4 DC C HFT boost L PV C 1 S S3 4 S 2 S 1 D D3 2 D D4 DC C grid i grid L Grid Ground 3 S 4 S 1 S 2 S # 2 String #3 StringAC Modules
One Inverter per
panel
High volume/ low
cost
Inverter characteristics
Efficiency
Response times
Harmonic output
Fault current contribution
Synchronisation
Frequency control
Power factor
Requirement Standard Details
General AS/NZS 3100 Electrical Safety Requirement Compatibility with AS 60038 A.C. Voltage and frequency ratings
electrical installation
Power flow direction N/A Power flow between energy source and grid may be in either direction
Power factor AS 4777.2 Range between 0.8 leading to 0.95 lagging between all outputs from 20% to 100%
of rated volt-amperes Harmonic Currents AS 4777.2
Harmonic current shall not exceed the limits in Table 1. EMC Radio Communications Act Voltage fluctuation AS/NZS
61000.3.3 Rated less that or equal to 16A per a phase and flicker
AS/NZS
61000.3.5 Rated more than 16A per a phase
Impulse protection IEC 60255-5 Withstand a standard lightning impulse of 0.5J, 5kV with 1.2/50 waveform
Transient voltage AS 4777.2 Voltage-duration curve derived from limits measurements taken at a.c. terminal shall
Not exceed the limits listed in Table 2. Direct current N/A Single-phase inverter: the dc output current of the
injection inverter at the a.c. terminals shall not exceed 0.5% of its rated output or 5mA
which ever is greater
Three-phase inverter: the dc output current of the inverter at the a.c. terminals measured between any two phases or between any phase and neutral
shall not exceed 0.5% of its rated output or 5m
which ever is greater Data logging and AS/NZS 60950 Any electronic data logging or communications
communication equipment incorporated in the inverter requires to devices comply with the appropriated requirements
DC-AC ELECTRICAL CONVERSION
EFFICIENCY
Efficiency is the most important parameter for grid-connected PV
generation
Depends on whether galvanic insulation transformer is used
between the AC on the grid side and the DC generated on the PV
side or not.
Transformer can be either 50 Hz LF transformers, or HF
transformers.
The presence or absence of LF or HF transformers in the inverters
influences not only the size, weight, ease of installation and material
costs, but also the earthing and safety measures to be adopted in the
PV system, and the control of DC injection feed into the grid.
Inverters with an LF transformer can achieve DC-AC efficiency of
92%,while those with an HF transformer typically achieve a
European Efficiency
Normalized efficiency, ηE, and is
valid for irradiance levels in central
Europe. It is defined as a function of
the efficiency at defined percentage
values for nominal AC power. This is
shown in the following equation:
ηE = 0.03η5% + 0.06η10% +
0.13η20% + 0.1η30% + 0.48η50% +
0.2η100%
94.2 92.6 90.8 92.3 ηE 94.2 92.8 90.0 93.3 100 95.0 93.4 90.9 93.8 50 94.6 93.1 92.5 93.1 30 94.2 92.3 92.0 91.0 20 91.5 88.9 90.4 85.8 10 86.7 85.1 84.8 77.5 5 Transformerless LF (new technology) LF (old technology) HF
Efficiency by inverter type (%) AC power
(% of nominal)
Experimental inverter efficiencies for different string inverters; values used are representative of state-of-the-art technology
MAXIMUM POWER POINT TRACKING EFFICIENCY
The DC power input to an inverter depends on which
point in the current-voltage (I-V) curve of the PV array
it is working at. Ideally, the inverter should operate at
the maximum power point (MPP) of the PV array. The
MPP is variable throughout the day, mainly as a
function of environmental conditions such as
irradiance and temperature, but inverters directly
connected to PV arrays have an MPP tracking
algorithm to maximize energy transfer. The MPP
tracking efficiency, η
MPPT, can be defined as the ratio
of the energy obtained by the inverter from a PV
array, to the energy obtained with ideal MPP tracking
over a defined period of time.
where P
DC
is
the DC input
power to the
inverter and P
M
is the power at
MPP
MAXIMUM POWER POINT
TRACKING EFFICIENCY
Inverters for grid-connected PV
systems must generate energy at a
defined quality
The standards (example:
international Standard IEC
61000-3-2 ) above require a THD of ≤
5% for the harmonic spectra of the
current waveform. nominal.
2 1 1 1 2 1 2 1 100 100 100 %
∑
≠ ⎟⎟⎠ ⎞ ⎜⎜ ⎝ ⎛ = − = = h s sh s s s s dis I I x I I I x I I x THDTotal Harmonic Distortion
Table 1 - Harmonic current limits [2]
Harmonic order number Limit for each individual harmonic based on percentage of fundamental
2-9 4% 10-15 2% 16-21 1.50% 22-33 0.60% Even harmonics 25% of equivalent odd harmonics
Total harmonic distortion (to the 50th harmonic) 5%
Power Factor
Traditionally poor due to
– displacement power factor
– harmonics
Present technology is very good
– Maintain close to unity without great difficulty
– Can regulate power factor or reactive power
for voltage control or power factor correction
applications
Example :Current THD and power
factor vs AC power
DC Injection
Is possible if an output transformer is not
present
Control systems can be added to prevent
excessive injection
Is regulated by standards
Limits of 5 mA (0.025% of the rms output
current for a 5 kW system, based on the IEC
61000-3-2) or 0.5% (UL1741) are being
Synchronisation
Performed automatically
Typically uses zero crossing detection on
the voltage waveform
Can be instantaneous on the next zero
crossing
If phase locked loops are used it could take
Frequency Control
Locked to the grid
May have a bias to drift in the event of grid
failure
Lock range may be limited
– Germany 49.8Hz - 50.2Hz
– Australia 48Hz - 52Hz
Prevention of Islanding
An island occurs when the inverter
continues to supply power to a portion of
the grid that has become isolated from the
rest of the system
The power may be unstable during the
island period
Anti islanding methods
Inverters are required to have measures to
protect against this occurring
– Passive methods
• Under/Over voltage
• Under/Over Frequency
– Active Methods
• Frequency drift
• Impedance measurement
• Power Shifting
Earth Leakage Current
In the US, the National Electrical Code, NEC,
requires all PV installations with system
voltages above 50 V DC to be earthed.
Ground fault protection ('GFP') devices are
used to measure the earth leakage current, in
order to disconnect from the ground (that is,
unearth the installation), in the case of fault.
Stray leakage currents may be an issue in the
sensitivity of this protection.
Fault currents
Battery-less systems can only deliver
what the energy source can deliver
– for PV this can be very little to a maximum
of 1.2 times rated current
– wind is extremely variable
If a battery is present the fault current
contribution is limited by the inverter.
AC Power Output
The losses in a PV system are due to:
– Inverter losses
– Dust/dirt in the modules
– Mismatch in modules
– Differences in ambient conditions from
Standard Test Conditions (STC) – 1000w/m
2,
AM 1.5 and 25
0
C.
1. Select the size of the system to be installed
2. Select main equipment to be installed, calculate
for matching of spec. of
2.1 PV panel
2.2 Grid connected inverter
3. Examine location for PV mounting. There should
be no obstruction of sunlight for whole day or at
least 9.00 a.m. to 4.00 p.m.
4. Consider for tilt angle of panels according to
latitude of that location
5. Select PV mounting structures.
6. Check ampere capacity of each string of inverter, select size
of blocking diode to be 30 % larger than string short circuit
current with diode max voltage more than 2 times of max
system voltage.
8. Select proper wire size so voltage drop for DC side is less
than 3%
8.1 Select wire size between each string to the combiner box
to enable less than 1% voltage drop
8.2 Select wire size between the combiner box to control
box / inverter to enable less than 2% voltage drop
9. Select proper wire size so voltage drop for AC side is less
than 3%
10. Select size of disconnect switch both DC and AC side to
proper rating
1. Select size of system to be around 3 kWp
2. Select main equipments as
2.1 PV panel - Mitsubishi model PV-MF130EA2 - 130 Wp / panel
- 2 strings with 12 panels in each string
- Isc / string = 7.39 amp.
- Total PV power = 130 x 24 = 3,120 Wp - V max = Voc = 24.2 x 12 = 290.4 Vdc
- Oper. volt. at max. power = 19.2 x 12 = 230.4 Vdc - Max DC current = Isc x 2 = 7.39 A x 2 = 14.78 Amp 2.2 Grid connected inverter - Leonics G-303M
- 2.7 kW output
- Max DC voltage = 350 Vdc
- Nominal Operating PV voltage = 230 Vdc
3. Location for PV mounting is on the roof deck with no obstruction of
sunlight for whole day
4. Select hot dip galvanized steel for PV mounting with stainless steel
nuts & bolts
5. Tilt angle of panels is set to 14 deg. facing south as Bangkok locates at
latitude 13.73 deg. North
Case Study : A PV grid connected system in
Bangkok
6. Plan to install control box and inverter in training room , 3 rd floor.
7. Selection of blocking diode
7.1 Min. device rating (I) = Isc x 1.3
= 7.39 x 1.3 = 9.61 A
7.2 Min. device rating (V) = Voc x 2
= 290.4 x 2 = 580.8 V
Then select blocking diode to be 10 ampere 600 V. for each string.
8. Measure cable length of the system
8.1 Cable length between each string to the combiner box = 10 meters
Select wire for each string to be 4 sq.mm. to get voltage drop < 1%
Voltage drop in each string = 11,650 x 10 x 7.39 = 0.86 V
Percentage of volt. Drop = 0.86 / 205 = 0.42 %
8.2 Cable length between combiner box to control box / inverter is 35 m. Select wire size to be 10 sq.mm. to get voltage drop < 2%
Voltage drop = 3,903 x 35 x 7.39 x 2 = 2.02 V
Percentage of volt. Drop = 2.02 / 205 = 0.99 %
9. Cable length between Control Box / Inverter to load panel is 12 meters Select wire size to be 2.5 sq.mm. to get voltage drop < 3%
Voltage drop = 15,695 x 12 x (2,700/238)
= 2.14 V
Percentage of volt. Drop = 2.14 / 238 = 0.90 %
10. Max DC current = 7.39 x 2 = 14.78 A
Max AC current = 2,700 / 232 = 11.64 A
Select both DC and AC breaker to be 20 A
Calculate annual energy output
Use data source and get annual daily average energy
available
Adjust down for losses
– Inverter 7%
– Temperature 15%
– Cable 3%
– Dirt 2%
– Orientation 1%
– Total about 25%-30%
Multiply by the size of the array to get the electrical kWhr
output
– OR
Verify
Does it fit in the area
Does it meet budget
Does it produce required kWhr
Is the CO
2
offset met
Check it works
System Acceptance Test
1. Sum total module ratings at STC (Standard Test Condition) : Watts STC
2. Estimate inverter AC output to be 70% of Watts STC : Watts AC-estimated
3. Measure real AC output and irradiation, then define
Watts AC-corrected = Real AC output / irradiation x 1000
4. Compare that Watts AC-corrected is more than Watts AC-estimated
Result from the installation
Generating power and irradiation is measured on Mar 26, 2004 at 11.25 p.m.
• Watts STC = 130 x 24 = 3,120 Wp
• Watts AC-estimated = 3,120 x 0.7 = 2,184 Watts
• Watts AC-corrected = 2,010 / 870 x 1000 = 2,310 Watts
4. Watts AC-corrected (2,310) > Watts AC-estimated (2,184)
Generating Power VS Time for 3.12 kWp
Grid Connected inverter at Leo Electronics Co., Ltd. (Apr 1, 2004)
0
500
1000
1500
2000
2500
7
8
9
10
11
12
13
14
15
16
17
18
Time
Ge
ne
ra
tin
g P
ow
er
Date
Gen. Power
Date
Gen. Power
Date
Gen. Power
1/4/2004
14.30
24/3/2004
13.73
16/3/2004
12.85
31/3/2004
12.79
23/3/2004
12.12
15/3/2004
10.88
30/3/2004
12.13
22/3/2004
10.94
14/3/2004
12.53
29/3/2004
12.33
21/3/2004
8.02
13/3/2004
12.02
28/3/2004
13.49
20/3/2004
7.22
12/3/2004
11.67
27/3/2004
13.51
19/3/2004
8.57
11/3/2004
13.21
26/3/2004
13.14
18/3/2004
11.87
10/3/2004
11.34
25/3/2004
13.01
17/3/2004
14.68
9/3/2004
10.15
Max. Generating Power/day
14.68
kWh/day
Min. Generating Power/day
7.22
kWh/day
Average Generating Power/day
11.94 kWh/day
Tracking Array
The PV array may either be fixed, sun-tracking
with one axis of rotation, or sun-tracking with
two axes of rotation.
Generally fixed arrays are used though
significant increase in energy yield is possible
with single axis tracking with an additional small
gain using duel axis tracking
Trackers
– add cost but offset by PV savings
– require some maintenance
Tracking Relative Energy
Production
0% 20% 40% 60% 80% 100% 120% 140% 160%Albany Geraldton Halls Creek
Fixed north facing at latitude angle NS Axis tracker -horizontal NS Axis tracker -Fixed at latitude angle Dual Axis
34
o57"
28
o48" 18
o14"
Energy from Power of the Sun
0 200 400 600 800 1000 1200 0: 00 2: 00 4: 00 6: 00 8: 00 10: 0 0 12: 0 0 14: 0 0 16: 0 0 18: 0 0 20: 0 0 22: 0 0Time
Power
Energy =Power x Time
Area = 7500W.hr
Peak Sun Hours
0 200 400 600 800 1000 1200 0: 00 2: 00 4: 00 6: 00 8: 00 10: 0 0 12: 0 0 14: 0 0 16: 0 0 18: 0 0 20: 0 0 22: 0 0Equivalent Time at 1 peak sun (1000W/m
2)
7.5 hours
Area = 7500W.hr
0 250 500 750 1000 0:00 6:00 12:00 18:00 0:00 Time Irra dia n ce S (W /sq m ) 18/05/98
A typical sunny day in Perth
0 250 500 750 1000 0:00 6:00 12:00 18:00 0:00 Time Ir ra di an ce S ( W /s qm ) 15/05/98