Best Practices on Construction
Projects
Best Practices on Construction
Projects
Project Management Procedures
Request for Information
Project Management Procedures
Request for Information
January 29, 2008
Presented by the
Claims Avoidance & Resolution Committee
January 29, 2008
Presented by the
PROJECT MANAGEMENT
PROCEDURES
Request for Information
(RFIs)
PROJECT MANAGEMENT
PROCEDURES
Request for Information
(RFIs)
Construction Institute
RFI Best Practices Panel
RFI Best Practices Panel
Claims Avoidance and Resolution Committee
Subcommittee for Project Management Procedures
Stephen A. Hess, PE
Lawrence M. Lenahan, PE
William Scott, PE
RFI Background
RFI Background
RFI is a communication tool to facilitate resolution of
or to clarify design document issues
Typically contractor submits and designer responds
Clarify a legitimate question concerning the design
documents
Keep the project moving forward and build the job
Can lead to Change Orders
Process will vary from project to project
Effectively coordinate and manage RFIs
Assist documenting the history of the project
4
Construction Institute
RFI Background (continued)
RFI Background (continued)
•
Design / Engineering firms becoming more involved with
construction claims (with both Owners and Contractors)
•
Reason - design documents are allegedly:
Faulty
Ambiguous
Inadequate
Incomplete
Conflicting, etc…
•
Claim submitted for acts or omissions of the Design
Professional – based on RFIs
•
Perceived as providing a methodology to document
deficiencies in the contract documents and establish a
basis for additional costs and time
RFI – When Used as Basis for Claims
(Abuses and Pitfalls)
RFI – When Used as Basis for Claims
(Abuses and Pitfalls)
Submitted for a clearly identifiable item that should have been addressed pre-bid
Submitted significant number to establish support for claim
•
“Design was incomplete / faulty – look at the number of RFIs submitted!” Submitted numerous and excessive RFIs (at the same time) and overwhelm the designer or
Designer / Owner hinders the process and does not provide a decision or respond
•
“Delays caused by non-responsive or late replies to RFIs” Insufficient response frustrates the Contractor and does not progress the work
•
“Provide as specified” or “It’s on the drawings” Use RFI to propose alternative construction methods or substitute items (or-equal)
6
Construction Institute
Claims Based on RFIs
Claims Based on RFIs
•
Response to RFI will be the basis for the claim
•
Extreme position that the first RFI indicates incomplete
design
•
Contractor claims for:
Work performed based on response to RFI as a
Change Order
Additional construction costs
Delay damage and off-setting of liquidated damages
•
Owner claims for:
Cost for delayed project completion
Increased interest and expenses
Best Practices
Best Practices
•
Develop an RFI protocol/procedure to address:
The items that will and will not be accepted as an RFI
Information which is on the contract documents will not be
addressed in a response
Define the documentation and supporting data required
Time frame for response
Qualify that the response is not a Change Order
Does not address construction means and methods or site
safety
Will not review requests for substitute items as an RFI
•
Discuss the procedure at pre-construction meeting or include as
part of the bid documents
•
Discuss RFI issues prior to formal submittal
“Confirming RFI” to confirm previous agreement
8
Construction Institute
Best Practices (continued)
Best Practices (continued)
•
Proactively develop RFIs prior to construction or work in
an area
•
Develop an RFI form and require project participants to
use it. Form should require:
Concise statement of the issue (limit to one issue)
Identify the specific plans or specification in question
•
Develop internal procedure for receiving, handling and
responding to RFI in a timely manner
Single source responsibility
Procedure to forward to specialty consultants
Communicate when the RFI will be completed
•
Maintain log and track status (monitored by individual in
company, but not involved with the project)
Best Practices (continued)
Best Practices (continued)
•
Define the response time
Designer will have at least 3 days…
"The Contracting Officer, acting on behalf of the Owner, will be the initial interpreter of the requirements of the Contract
Documents, and in such capacity, will render determinations on the acceptability of the Work. Notices, proposals or other
matters relating to the acceptability of the Work or the
interpretation of the Contract Documents shall be referred to the Contracting Officer in writing, within twenty (20) days after the Program Manager first recognizes the issue, but in no event more than six (6) months after the occurrence
giving rise to the issue, requesting a formal, written
determination, which the Contracting Officer will render on behalf of the Owner within a reasonable time."
10
Construction Institute
Best Practices (continued)
Best Practices (continued)
•
During construction must reply timely and appropriately
•
Inform the Owner if an RFI results in a design change,
additional costs or delay and document the reason
•
“Dislodge” complex issues from the RFI process
Use subcommittee approach for more complex issues
•
“Dislodge” resolved RFIs from the process
RFI response then moves to Change Order or other
Contractual process
•
Prioritize RFIs
Claim Scenario – Legitimate RFI?
Claim Scenario – Legitimate RFI?
RFI submitted for a clearly identifiable item that
should have been addressed pre-bid or is on
the existing contract documents
•
Are the RFI’s legitimate?•
Check other bidder’s bid documents to demonstrate the contractor missed something that others included•
Should issue be removed from the RFI process and addressed in another forum?12
Construction Institute
Claim Scenario – Design
Incomplete or Faulted
Claim Scenario – Design
Incomplete or Faulted
Submitted significant number to establish support for
a claim that the design was incomplete / faulted
“Look at the number of RFIs we have submitted!”
•
RFI count may or may not indicate an incomplete or late-evolving design•
Significant increase in RFI submissions late in the project often precedes an oncoming design claim•
Are the RFIs valid or should be addressed in another forum?•
Compare RFI with other bidder’s bid documents to demonstrate the contractor missed something that others included•
When were the RFIs submitted relative to work execution? Or relative to the commencement of delaySample RFI Distribution Chart
Sample RFI Distribution Chart
Monthly Detail Drawings Issued to Contractor by Designer
D J F M A M J J A S O N D J F M A M J J A S O N D J F Monthly Detail Drawings Total RFIs
- The designer issued drawings containing new scope and some changed scope through the life of the project
- The RFI's, which were usually sub-contractor items, grew steadilly during the project - the rate actually increased at the end of the prime work period
Claim Scenario – Delayed
Response
Claim Scenario – Delayed
Response
Submitted numerous and excessive RFIs (often at
the same time) to overwhelm the designer and
establish a delay claim caused by late or non-
responsiveness to RFIs
•
Do the RFIs impact critical path activities?•
Were delays cited contemporaneously?•
Is there a review time or process specified in the contract? EJCDC Standard General Conditions of the Construction Contract
AIA General Conditions
Example Claim Presentation of
RFI Response Time
Example Claim Presentation of
RFI Response Time
RFI RESPONSE TIME
0-2 Days 18% 3-7 Days 15% 8-14 Days 7% More than 14 Days 15% No Response 45% 16 Construction Institute
Claim Avoidance - Mitigation
Claim Avoidance - Mitigation
Delays caused by incomplete or faulty design
•
Know the Project schedule
•
Manage the RFI process; do not just accept each as valid
and necessary
RFIs must conform with the intent to clarify contracts
and design documents/specifications.
•
Track the receipt and return of RFI submittals – take notice
immediately of dramatic increases in RFI count and/or
Claim Avoidance - Mitigation
Claim Avoidance - Mitigation
Delays caused by late or lack of response
•
Establish procedures, including the RFI submission format, within the Contract or prior to construction•
Track receipt and return of all RFIs during the project and act to detect trends•
Know the schedule and prioritize Designer understand the importance of response
Contractor pre-planning work and identify conflicts early
•
Do not “sit” on RFIs - accept and address or reject promptly•
Ensure that RFIs are complete and do not accept RFIs that fail to conform to submission requirements Clarification of Contract or design documents only
18
Construction Institute
Litigation / Legal Considerations
Litigation / Legal Considerations
•
United States v. Spearin, 248 U.S. at 136-37 (1918)
United States Supreme Court: "if the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications." Implied warranty
•
Cumulative effect of changes recognized that inefficiency
claim based on disruptive effect of individual compensable
changes:
Jackson Constr. Co., Inc. v. United States, 62 Fed. CI. 84, 103-04 (2004)
(citing J.A. Jones Constr. Co., ENGBCA Nos. 6348, 6386-6391, 2000-2
B.C.A. (CCH) P31,000, at 153, 107, 2000 WL 1014011 (2000);
McMillin Bros. Constr., Inc., EBCA No. 328-10-84,91-1 BCA P 23,351, at
117,102-05, 1990 WL 140900 (1990), aff'd, 949 F.2d 403 (Fed. Cir. 1991);
Bechtel Nat'l, Inc., NASA BCA No. 1186-7, 90-1 BCA P 22,549, at 113,177-78, 1989 WL 160470 (1989)
Litigation / Legal Considerations
Litigation / Legal Considerations
•
Duty
The government has a duty not to act in a way that will hinder or delay the contractor's performance (“refrain from willfully or
negligently interfering with a contractor's performance.”).
•
Malone v. United States, 849 F.2d 1441, 1445 (Fed. Cir. 1988), modified, 857 F.2d 787 (1988);•
SMS Data Prods. Group, Inc. v. United States, 17 Cl. Ct. 1, 6 (1989). For the government to be found liable for delay a plaintiff must
demonstrate that the government caused the plaintiff a compensable injury. The government, therefore, is not liable for breach of contract, or causes of action that rely upon "severe defects" in contract
drawings, or government hindrance of performance, unless SCBI proves that the alleged defects, changes, or hindrances negatively impacted costs and performance of the contract.
•
Servidone Constr. Corp. v. United States, 931 F.2d 860, 861 (1991);•
Boyajian v. United States, 191 Ct. Cl. 233, 239-47, 423 F.2d 1231, 1235 (1970).20
Construction Institute
Litigation / Legal Considerations
Litigation / Legal Considerations
•
SOUTHERN COMFORT BUILDERS, INC., Plaintiff, v. UNITED STATES, Defendant.No. 00-542C; UNITED STATES COURT OF FEDERAL CLAIMS 67 Fed. Cl. 124; 2005 U.S. Claims LEXIS 225; July 29, 2005
“SCBI alleges that many of the disruptions caused by the government resulted from NASA's failure to respond to plaintiff's RFIs in a timely manner, which addressed interferences or obstructions encountered by SCBI. In the documents provided to the court, SCBI submitted an
RFI log indicating the times within which NASA responded to SCBI's RFIs. Of the RFIs submitted by SCBI, many were answered in about a week's time. Others were responded to more slowly by NASA, including those which resulted in contract change orders.”
Ruled in favor of the Defendant (two contract modifications had to be paid by defendant, all other claims dismissed. Defendant awarded counter claim).
Litigation / Legal Considerations
Litigation / Legal Considerations
•
CADDELL CONSTRUCTION CO., INC., Plaintiff, v. THE UNITED STATES, Defendant.No. 04-461C; UNITED STATES COURT OF FEDERAL CLAIMS; 78 Fed. Cl. 406; 2007 U.S; Claims LEXIS 285; September 7, 2007
Defective design resulted in plaintiff issuing large number of RFIs and government failed to promptly and fully answer and as a result plaintiff missed steel fabrication “window”.
Defendant contended RFI process was obstructed as Defendant held onto RFIs from subcontractors and submitted in large batches and that Plaintiff did not demonstrate delay caused by allegedly slow response
Ruled in favor of the Defendant based on “contractor’s duty to
coordinate” and that the Defendant answered more than one third of the RFIs in less than 30 days and more than 90% in less than 45
days
•
Third party beneficiary status of contractors, Privity, Economic Loss Doctrine, Accepted Work Doctrine22
Construction Institute
Recommended Project Management
Procedure - RFIs
Recommended Project Management
Procedure - RFIs
•
Clearly define and use the RFI process with the designer
to seek clarification or interpretation of conflicts, errors,
discrepancies or ambiguities in the Contract Documents –
limit to clarification only
•
Define and document the response time at the project
(kick-off) pre-construction meeting.
Recommended Project Management
Procedure - RFIs
Recommended Project Management
Procedure - RFIs
•
Define the number of copies required (no oral or incomplete RFIs•
accepted)•
Review and response to RFIs shall not constitute approval, direction, or procedures for means and methods.•
Limit each RFI to a single issue•
Information discernable from the existing documents, or addressing construction means and methods or site safety will not be addressed•
Designer should designate a specific representative to manage the process24
Construction Institute
Recommended Project Management
Procedure - RFIs
Recommended Project Management
Procedure - RFIs
•
RFI Form should include
Chronological number for the RFI (Tracking Mechanism)
Date issued
Name of person and contractor requesting information
Applicable Specification section and page number
Applicable drawing number and title
Clear statement of the request
Remark for any increase in cost or time
•
Designer should review RFI for compliance with protocol
and return any non-complying RFIs
Sample RFI
Form
Sample RFI
Form
26 Construction InstituteSample RFI
Form
(
from Timberline
Software)
Sample RFI
Form
(
from Timberline
Software)
Company Address Company AddressSample RFI
Form
Sample RFI
Form
28 Construction InstituteSample RFI
From ConstructWare Software
Sample RFI
Recommended Project Management
Procedure - RFIs
Recommended Project Management
Procedure - RFIs
•
Upon receipt of RFI, responsible party should
Calculate response due date
Notify Contractor of date received and when
response should be expected
Review for compliance with protocol and
return any non-complying RFIs
Enter RFI into log
30
Construction Institute
Recommended Project Management
Procedure - RFIs
Recommended Project Management
Procedure - RFIs
•
RFI log – manual or electronic, should include:
RFI Number
Name of requester and contractor
Date of receipt
Original response due date
Name of RFI reviewer
Date forwarded for review
Date returned to Contractor
Any extension information (date, etc)
Summary of response
Does response necessitate a change, extra or time
extension
Sample RFI Log
Sample RFI Log
Transit Project
Transit Project
Sample RFI Log
Sample RFI Log
From ConstructWare Software
Sample RFI Log
From ConstructWare Software
34
Construction Institute
Recommended Project Management
Procedure - RFIs
Recommended Project Management
Procedure - RFIs
•
Forward response to Contractor and copy
appropriate parties (Owner, CM, Resident
Engineer)
•
Contractor can disagree with response and
initiate meeting and resolution in another forum
– RFI is closed
Recommended Best Practices
Recommended Best Practices
•
Designer – understand your Contract and the
Contractor’s Contract provisions with the Owner
Use RFIs with owner during design phase
Required response time for RFIs and communicate
expected response time to contractor
Know Contract roles and responsibilities
Understand the Project Schedule
•
Does the Contractor’s schedule need to or include shop
drawing review and other A/E related activities?
•
Monitor and manage RFIs and utilize an RFI log
Be prompt with response and/or document why not
Don’t let paperwork languish!
36
Construction Institute
Additional References
Additional References
•
Defending Claims by Owners & Contractors for
Damages Arising from RFIs and Approved and
Unapproved Change Orders
, Seamen, Drew F.
and Waggoner, Thomas F., at The 40
thAnnual
Meeting of Invited Attorneys, 2002.
•
EJCDC Standard General Conditions
•
AIA A201 General Conditions
•
American Institute of Steel Construction Code of
Standard Practice, Articles 4.4.2 and 4.6
Benefits of Implementing Procedures
Benefits of Implementing Procedures
•
Facilitates communication
•
Streamlines the RFI process
•
Maintains progress on the project
•
Documents project history
•
Helps mitigate and avoids claims
38
Construction Institute