Rehabilitation or Replacement?
That Is The Question
Chris L. Windley PE Greg Anderson, PE
94th Annual Conference
Overview
Project Background
Existing Sewer Condition
Flow Projections and Impact
Replacement/Rehabilitation Alternatives
Evaluation of Rehabilitation Technologies
Project Background
Existing Lower Walnut Creek Interceptor
Approximately 16,000 LF of 48-inch and 54-inch gravity sewer
Reinforced concrete pipe installed around 1975
Located in existing 100’ wide utility easement
Thirty-two (32) manholes – primarily brick construction
Discharges to concrete octagon shaped junction box
Existing Sewer Condition
2012 CCTV and limited manhole inspections indicated
significant corrosion in the majority of the pipe sections.
Existing Sewer Condition
Limited inspections on 4 manholes
Moderate hydrogen sulfide corrosion in the concrete manholes
Existing Sewer Condition
Limited structural analysis for greenway trail construction: Indicated pipe sections could fail under certain loading conditions
The results of this analysis highlighted the need for a rehabilitation technology that provides structural integrity independent of the existing host pipe
Flow Projections and Future Pipe Sizing
2040 planning horizon
Average daily flow of 16.4 mgd
Peak flow of 69.6 mgd
Anticipated single replacement in 66-to 72-inch range.
If rehabilitation was selected, parallel pipe in 54-inch to
Replacement/Rehabilitation Alternatives
CORPUD initiated an evaluation of multiple rehabilitation
technologies and replacement methods for large-diameter gravity sewer.
The evaluation included four alternatives: 1. A single replacement interceptor
2. A single parallel interceptor replacement
3. Rehabilitation of the existing 48-inch and 54-inch interceptor and construction of a parallel interceptor
Rehabilitation Technology Evaluation
Rehabilitation technology for the LWC should provide the
following:
Applicable to the LWC pipe sizes and materials
Corrosion resistance inherent to the rehabilitation technology materials without additives or field-applied coatings or sealants
Stand-alone structural characteristics
Rehabilitation Technology Evaluation
12 technologies reviewed
3 selected for further investigation:
Segmented sliplining
Geopolymer spray-in-place pipe
Cured-in-place pipe (CIPP)
7 criteria to assess the pipe
renewal methods:
Flow capacity and diameter range
Structural integrity
Corrosion resistance
Expected useful life
Construction factors
Social costs
Rehabilitation Technology Evaluation
The Environmental Protection Agency (EPA)
characterizes renewal of gravity sewer mainlines as repair, replacement, or rehabilitation
Repair techniques are generally referred to spot or point
repairs and not applicable to this project
Replacement techniques make no use of the existing
pipe structure and a new stand-alone pipe is provided, such as sliplining
Rehabilitation techniques are defined as those that
utilize the existing pipe structure, such as CIPP or spray-in-place pipe
Replacement - Segmented Sliplining
One of the earliest forms of pipeline rehabilitation
recorded, with installations dating back to the 1940s
The process involves installing a smaller diameter carrier
pipe within the existing host pipe by pushing or pulling the carrier pipe into place and filling the annular space
between the two pipes with grout
The final product provides a new pipe with adequate
structural stability and a projected life expectancy of between 50-100 years
Replacement - Segmented Sliplining
There are many different types of
piping materials that have been successfully used for sliplining applications
The three generally utilized pipe
materials for segmented sliplining are:
Glass-reinforced plastic (GRP)/fiberglass reinforced plastic (FRP)
Polypropylene (PP)
PVC (closed profile)
Will require a reduction in the capacity
Replacement - Segmented Sliplining
Pipe pushing force and push lengths for each type of
sliplining pipe material are project dependent
Grouting is required to seal the annular space between
the new, slipline pipe and host pipe.
A benefit of a segmented installation approach involves
the potential to install the carrier pipe without having to bypass the flow during the sliplining installation
Replacement - Segmented Sliplining
Evaluation Criteria Sliplining - Segmented
Flow Capacity/Diameter Range Reduction of pipe capacity of approximately 20-25% based on LWC slope. Diameter reduction of
approximately 10% depending on pipe material selected.
Structural Integrity Excellent. Structural strength of the slipline pipe is independent of the host pipe.
Corrosion Resistance High
Expected Useful Life 50-100 years
Construction Factors May not require bypass pumping. Requires excavation of installation pits depending on material/length of
push.
Social Costs Residents could be impacted by noise and limited access due to staging of equipment.
Rehabilitation - Geopolymer Centrifugally
Sprayed-In-Place Pipe
The most utilized material for rehabilitating large-diameter
concrete pipes and concrete structures is a Portland cement-based cementitious mortar
Recent advancements in the development of
geopolymer-based materials with anti-microbial systems now provide a renewal system applicable for large-diameter piping systems and structures that are subjected to corrosive
Rehabilitation - Geopolymer Centrifugally
Sprayed-In-Place Pipe
Evaluation of the geopolymer technology indicated that,
to accurately identify the associated cost for completing rehabilitation of the 48-inch and 54-inch gravity sewers, several key items would need to be evaluated, including:
Bypassing of wastewater flows if necessary, based on the size of the parallel line
Equipment setup for centrifugal casting
Rehabilitation - Geopolymer Centrifugally
Sprayed-In-Place Pipe
Evaluation Criteria Geopolymer Coating
Flow Capacity/Diameter Range Negligible. Geopolymer application will only be ½-inch thicker than original deteriorated thickness of concrete pipe
Structural Integrity Excellent
Corrosion Resistance High, but limited age on existing applications in sanitary sewer
Expected Useful Life 50-100 years
Construction Factors May require bypass pumping of a minimum of two sections of interceptor at a time if parallel line is not available to convey flow. Receiving surface must be cleaned and all loose material removed
Social Costs Does not require excavation pits on both sides. Residents could be impacted by noise and limited access due to staging of equipment.
Rehabilitation - Cured-In-Place Pipe (CIPP)
CIPP was the initial product utilized for rehabilitating
deteriorating utility piping, with the first known installation dating back to 1971.
It is estimated that approximately 40,000 miles of CIPP
liners have been installed worldwide to date.
Basic CIPP concept involves resin impregnation of a felt/
fiberglass tube by use of a pinch roller type assembly, with needle felt tubing being saturated at a controlled volume per length of proposed installation.
Following resin impregnation, the tubing is inserted within
a host pipe using water or air pressure and cured by the introduction of heat, UV light or ambient temperature
Rehabilitation - Cured-In-Place Pipe (CIPP)
Currently there are many variations in method of
installation, tube construction, resin systems and curing methods.
Structural enhancements in CIPP lining are more related
to resin and tube material changes than installation and cure methods. Improvements/changes in installation
method generally dictate the cure method and are generally driven by a cost saving advantage.
Rehabilitation - Cured-In-Place Pipe (CIPP)
Evaluation Criteria Cured-In-Place Pipe
Flow Capacity/Diameter Range Negligible. CIPP liner will generally replace original deteriorated thickness of concrete pipe and flow characteristics of the pipe will be enhanced with reduced roughness and elimination of joints Structural Integrity Excellent
Corrosion Resistance High
Expected Useful Life 50-100 years
Construction Factors Required onsite resin impregnation will significantly affect the cost of installation. May require bypass pumping if parallel line is not available to convey flow. Social Costs Does not require excavation pits, however due to the
size of the CIPP liner tops of manholes will need to be removed.
Discussion
The analysis revealed that each of the three types of
products/installation processes evaluated could be successfully employed on the LWC project.
All of the products provide corrosion resistance
When evaluating the soft costs associated with each
option, the commonality that exists is the need for accessing the piping to install any of the products.
Sliplining approach requires the most excavation
Both the geopolymer and CIPP liner installation
Discussion
The geopolymer and CIPP liner approaches offer the
best solution from a hydraulic standpoint
Geopolymer products have limited long-term data
available on corrosion resistance in sanitary sewer environments
The City has limited experience with geopolymer
products and there are limited applications of the relatively new product in North Carolina.
Conclusions
Based on presentation of the results and discussions with
CORPUD, the client selected CIPP and segmental sliplining with fiber reinforced plastic/glass reinforced plastic (FRP/GRP) pipe to be further evaluated for applicability and cost in this particular situation
Conclusions
Alternative Description Opinion of Probable Construction
Cost 1 A single, replacement interceptor located in the same
alignment as the existing interceptor and sized to carry the
entire future flow. $29,704,000
2 A single, parallel interceptor replacement sized to carry the entire future flow and abandonment of the existing 48-‐‑inch and
54-‐‑inch interceptor. $27,053,000
3 Rehabilitation of the existing 48-‐‑inch and 54-‐‑inch interceptor and construction of a parallel interceptor sized to carry the remainder of the future flow.
~$31,000,000 to $33,000,000 depending on rehabilitation
method
4 A combination of Alternative 2 (single, larger parallel
interceptor) and Alternative 3 (rehabilitation/smaller parallel interceptor) to address areas with potential constructability issues.
~$28,250,000 to $28,550,000 depending on rehabilitation
Conclusions
Alternative 2— a single parallel interceptor replacement
sized to carry the entire future flow and abandonment of the existing 48-inch and 54-inch interceptor—offers the most viable and economical solution for the CORPUD.
the parallel line sizes required for rehabilitation of the existing interceptors were only one to two typical pipe diameters smaller than the single replacement line
the capital and social cost incurred to install the parallel lines in addition to rehabbing the existing lines outweighed the cost of a single replacement line.
The Lower Walnut Creek Interceptor replacement is
Contact Information: Chris Windley, PE 919-233-8091 [email protected] Greg Anderson, PE 757-965-2848 [email protected]