2014 MIDAS Technical Seminar
The recent years have seen tremendous advances in High-Rise Building design in India. Structures such as the World One Tower (442m), Oasis Tower (372m) etc., have pushed the envelope like never before. As such, it becomes imperative for practicing engineers to be up to speed with all the latest developments in the field of High-Rise Buildings.
Today even the design codes have become demanding in terms of detailed and precise design. Understanding of behavior of structure and designing for safety brings in more concerns that should be addressed. Additionally, everything needs to be done quickly and efficiently. This creates a need for a powerful tool that addresses all the above issues. midas Gen has the strong ability to help engineers to perform modeling, analysis and design of structures. The software has been successfully applied to numerous projects thereby demonstrating creditability and stability.
This seminar will focus on familiarizing the structural analysis as well as design of buildings. midas Gen models are also compatible with major BIM tools which have gained a lot of importance recently.
About Seminar
MIDAS
TECHNICAL
SEMINAR
Programs
TimeSessions
9:30 - 10:00 Registration 10:00 - 10:30 Opening Remark10:30 - 11:20 Important criteria to be considered for high-rise building design report. Prof. M. A. Chakrabarti, VJTI, (Former Member of High-rise Building Committee)
11:20 - 11:50 Refreshment Break
11:50 - 12:40 Modeling Issues in high-rise buildings Vinayak Naik, Sterling Engineering Consultancy Services
12:40 - 2:00 Lunch break
2:00 - 2:50 Effect of wind loading on tall buildings Prof. Tanuja Bandivadekar, SP College of Engineering
2:50 - 3:40 Foundations for tall buildings Jaydeep Wagh, Geocon International
3:40 - 4:00 Refreshment Break
4:00 - 4:50 Column shortening analysis for high-rise building Ravi Kiran Anne, MIDAS
4:50 - 5:30
Introduction to MIDAS
- Introduction to midas Gen by Shayan Roy, MIDAS - Case studies by Raajesh Ladhad, Structural Concept 5:30 - 5:40 Closing Remark & Lucky Draw
2014 Challenges & Solutions for Tall Building Design
The Institution of Engineers (India, MSC) November 15th, 2014 (Saturday)
2014 Challenges & Solutions for Tall Building Design
Presenters
Speaker’s Profile
Ravi Kiran is high-rise building design and finite element analysis specialist and technical director with 10 years’ experience in high-rise buildings & infrastructure projects.
Erection Engineering of high-rise building
- Column shortening analysis for high-rise building
by Ravi Kiran Anne, MIDAS
Effect of wind loading on tall buildings
by professor Tanuja Bandivadekar, SP College
Foundations for tall buildings
by Jaydeep D. Wagh, Geocon International Modeling Issues in tall buildings
by Vinayak Naik, Sterling Engineering Consultancy Services Pvt. Ltd.
Important criteria to be considered for high-rise building design report.
by Professor M. A. Chakrabarti, VJTI
Former Member of High-rise Building Committee
• Geotechnical consultant for over 10,000 projects across India. • Completed projects in numerous countries of the world, including
USA, Dubai, Nepal, Shri Lanka, and several countries in Africa. • Geotechnical consultant for the tallest buildings in almost all metro cities of India, including Mumbai (6B+130 floors), Delhi (3B+85 floors), Kolkata (65 floors), Bangalore (3B+52 floors)(1997 - Present)
Vinayak Naik has designed number of ROB’s, fly-overs (a notable
example is the Dadar T. T. flyover in Mumbai, Winner of Special Award by Indian Institute of Bridge Engineers for Year 2000), mass housing
projects, tall buildings, Loco car sheds for Railways (Precast / Prestressed), subways (a notable example is CST subway, Mumbai).
Area of Interest
• Vibration control using passive dampers for structures • Vibration control using passive dampers for bridges • Multiple tuned mass dampers
• Mass excited structure, vibration control. • Admixtures for high performance concrete. Area of Interest
• Reliability engineering and system safety • Non-linear dynamic analysis/system • Self Repairable Concrete System
Raajesh Ladhad has designed tall residential buildings, corporate office buildings, commercial buildings, and hospitals. He has personally trained and guided junior and senior engineers to develop structural designs and details in RC and steel structures.
Case Studies using midas Gen
by Raajesh K. Ladhad, Structural Concept Design
The Institution of Engineers (India, MSC) November 15th, 2014 (Saturday)
01
Introduction to MIDAS
Shayan Roy, MIDAS
2014 MIDAS Technical Seminar1 Introduction and Objective
Introduction to midas Gen
MIDAS IT
Welcomes you to its
2014 Technical Seminar
Shayan Roy
MIDAS IT
Introduction to midas Gen
Introduction and Objective
Contents
01
Opening Remarks
02
Introduction to MIDAS
03
Design of High-Rise Building
04
Interaction / Q&A
3 Introduction and Objective
Introduction to midas Gen
3
Objective
01. Introduction to Midas
Introduction and Objective
Introduction to midas Gen
About MIDAS
01. Introduction to Midas
No. 1 Market Share
in Civil Engineering Software Solutions
450 Engineers & Professionals
120
Distribution in over 120 Countries
10,000
Number of Clients
5 Introduction and Objective
Introduction to midas Gen
5
Global Network
01. Introduction to Midas
Introduction and Objective
Export to more than 90 countries worldwide through distributors in 28 countries
Retains the largest CAE market share
Introduction to midas Gen
Business Areas
Bridge & Civil Structures
Building & Plant Structures
Geotechnical Analysis
Mechanical Analysis
Bridge Engineering
Building Engineering
Geotechnical Engineering
Mechanical Engineering
Software
Developments
Engineering
Consultancy
7 Introduction and Objective
Introduction to midas Gen
Business Areas
7 Introdu 7 7 IntroOptimal Solution
for
Practical Engineering
Building Structures
Plant Structures
Civil Structures
CAE Technology & Development
Engineering Consulting Service
P
5[PGTI[
Introduction to midas Gen
Product Line
midas
FX+
midas NFX
Mechanical
Engineering
General Pre & Post Processor for Finite Element Analysis Integrated Design System
for Building and General Structures
midas
Gen
midas DShop
Building & Structural
Engineering
2D / 3D Geotechnical and Tunnel analysis System
midas
GTS
SoilWorks
Geotechnical
& Tunnel
Engineering
midas
Civil
midas
FEA
Bridge & Civil
Engineering
Integrated Solution System for Bridge and Civil Structures
Advanced Nonlinear and Detail Analysis System
Total Solutions for True Analysis-driven Design
Geotechnical Solutions for Practical Design
midas Design+
Structural Component Design & Detailing
Auto-Drafting Module to generate Structural Drawings and Bill of Materials
9 Introduction and Objective
Introduction to midas Gen
Key Clients
International Indian
ACKG HDR Parsons Brinckerhoff AFCONS Arun Gokhale & Associates
AECOM HNTB Ramboll Gruppen CDM Smith DCIPL
ARCADIS Hyder Royal Haskoning CES J+W Consultants
ARUP Hyundai Engineering SMEC EGIS India Milind Kulkarni ATKINS INGEROP SNC-Lavalin International L&T Mahimatura Beca Group Italferr SpA Thornton Tomasetti Louis Berger Group Nagarjuna Constructions
Bechtel Jacobs URS Mott MacDonald Navinnavare
Black & Veatch Korea Power Engineering WSP Group Phiske Consultant Satish Marathe Consultants
CH2M HILL Langan Pragati Consultants Sunil Mutalik
COWI Louis Berger Group S.N.Bhobe & Associates S.W.Mone & Associates
CTI Engineering Michael Baker Corp. STUP Consultants Structus Consultants
Dar Al-Handasah MMM Group Shrikande Consultants Vastec
DHV Group Mott MacDonald Tandon Consultants
GHD Mouchel PWD, Navi Mumbai
Golder Associates MWH Global RDSO
Halcrow Parsons Western Railway
Introduction to midas Gen
Structural Engineering
Burj Khalifa (UAE)
Kingdom Tower (Saudi Arabia)
Beijing Olympic (China)
11 Introduction and Objective
Introduction to midas Gen
Structural Engineering
9 All types of buildings (RC, Steel, Composite)
9 Plant structures, Airport & Hangars
9 Stadiums, arenas & gymnasiums
9 Column shortening prediction and design
9 Post-tension and pre-stressed concrete analysis
9 Nonlinear seismic performance evaluation
9 Structural safety checks through detail analysis
Application Areas
Introduction to midas Gen
Tall Building Projects
Kingdom Tower (Saudi Arabia)
World’s Tallest Building
13 Introduction and Objective
Introduction to midas Gen
Tall Building Projects
g
j
Burj Khalifa (UAE)
The World’s Tallest Building
Introduction to midas Gen
Tall Building Projects
Tall Building Projects
Moscow City Palace Tower (Russia)
15 Introduction and Objective
Introduction to midas Gen
Tall Building Projects
3URMHFW1DPH10)%%QTRQTCVG1HHKEG0CXK/WODCK
'HVLJQHGE\5VTWEVWTCN%QPEGRV0CXK/WODCK
M
HHK
K
D K
Introduction to midas Gen
Tall Building Projects
3URMHFW1DPH-CTPCNC
+P
VGTPCVKQPCN5EJQQN&TQPCIKTK
'HVLJQHGE\5VTWEVWTCN%QPEGRV0CXK/WODCK
17 Introduction and Objective
Introduction to midas Gen
Tall Building Projects
3URMHFW1DPH'NGTTQ(KGUVC5CPRCFC
'HVLJQHGE\5VTWEVWTCN%QPEGRV0CXK/WODCK
Introduction to midas Gen
Tall Building Projects
3URMHFW1DPH/CTKPG#ECFGO[2CPXGN
19 Introduction and Objective
Introduction to midas Gen
Tall Building Projects
3URMHFW1DPH4GNKCDNG6GEJ2CTM0CXK/WODCK
'HVLJQHGE\5VTWEVWTCN%QPEGRV0CXK/WODCK
4GNKCDNG 6GEJ 2CTM 0CXK /WODCK
Introduction to midas Gen
Speciality Projects
peciality Projects
Beijing National Stadium (China)
21 Introduction and Objective
Introduction to midas Gen
Speciality Projects
Temietto di Villa Barbaro (Italy)
Structural Evaluation of Vulnerable Historic
Introduction to midas Gen
23 Introduction and Objective
Introduction to midas Gen
Bridge Engineering
Sutong Cable-stayed Br. (China)
Russky Island Br. (Russia)
Sunda Strait Br. (Indonesia)
Introduction to midas Gen
Bridge Engineering
9
Conventional bridges (skewed slab, frame & culvert)
9 Curved steel girders, composite, integral bridges
& PC girder bridges
9 Segmental post-tensioning (BCM, ILM, MSS & FSM)
9 Cable stayed bridges & extradosed bridges
9 Suspension bridges (Earth-anchored & Self-anchored)
9 Fatigue check and seismic performance evaluation
9 Wind evaluation (CFD analysis)
9
9
9
i
l b id
( k
k
25 Introduction and Objective
Introduction to midas Gen
Cable Stayed Bridges
able Stayed Bridges
Russky Island Bridge (Russia)
The World’s Longest & Tallest Cable Stayed Bridge
Introduction to midas Gen
Cable Stayed Bridges
Santra Market Bridge, Nagpur
27 Introduction and Objective
Introduction to midas Gen
Cable Stayed Bridges
Tapi Cable Stayed Bridge, Surat
S. N. Bhobhe Consultants, Mumbai
Introduction to midas Gen
Metro Rail
Hyderabad Metro
L&T Rambol, Chennai
Hyderabad Metro
L&T Rambol, Chennai
29 Introduction and Objective
Introduction to midas Gen
Metro Rail
Navi Mumbai Metro
Louis Berger Group, Mumbai
Introduction to midas Gen
Special Structures
Mumbai Monorail Station
31 Introduction and Objective
Introduction to midas Gen
Geotechnical Engineering
Kingdom Tower (Saudi Arabia)
New York Subway (USA)
King’s Cross Station (UK)
Introduction to midas Gen
Geotechnical Engineering
9
Deep foundations & Soil-Structure Interaction
9 Deep excavation and temporary structures
9 Underground structures (subway & disposal facilities)
9 Unconventional tunnel intersections
9 Slope stability and embankments
9 Groundwater Flow and Coupled Analyses
9 Vibration analysis for earthquake & blasting
9
9
9
33 Introduction and Objective
Introduction to midas Gen
Geotechnical Engineering
SoilWorks
Introduction to midas Gen
Tunnel & Underground Structures
Posiva’s ONKALO (Finland)
35 Introduction and Objective
Introduction to midas Gen
Tunnel & Underground Structures
Trans-Hudson Express (U.S.A)
Stability Evaluation for Station Complex
Introduction to midas Gen
Excavations & Foundations
Dubai Tower (Qatar)
37 Introduction and Objective
Introduction to midas Gen
Introduction
Æ Stadiums Æ Power Plants Æ Hangar Æ Airport Æ Transmission Towers Æ Cranes Æ Pressure Vessels Æ Machine Structures Æ Underground Structures …Specialty Structures Applications
Beijing National Stadium Beijing National Aquatic Center Beijing Olympic Basketball Gymnasium
Seoul World Cup Stadium JeonJu World Cup Stadium DeaJeon World Cup Stadium
USA Pavilion China Pavilion German Pavilion
Introduction to midas Gen
Why midas Gen
3UDFWLFDO
(DV\WR8VH
5HOLDEOH
*RRG6XSSRUW
39 Introduction and Objective
Introduction to midas Gen
Reliable
Buildings
Plant Structures
Æ 50 countries, 6500 copies
Æ Partial List of Client
URS Corp. Parsons Brinckerhoff TY LIN Ove Arup Gr. Jacobs Engineering RMJM
Imbsen & Associates Michael Baker Jr.
R.W. Armstrong and Associates Hewson Consulting Engineers
Ltd
Samsung Engg. & Construction POSCO Steel & Construction CALTRANS (California Dept. of
Transportation)
Oregon Dept. of Transportation Pennsylvania Dept. of Transportation US Army …
Various Project
Applications
50 countrrio
rio
pl
pl
Æ Æ 50 couVar
Var
App
App
1
Spatial Structures Specialty StructuresIntroduction to midas Gen
Reliable
Æ MQC System
(midas Quality Control System)
Æ Bug Reporting System
QA & QC System
MQC Sys
A &
Æ MQC S
QA
2
MQC System Bug Reporting SystemVerification
Examples
rif
rif
am
am
Ver
Ver
Exa
Exa
3
Æ More than 100 Verification Examples
41 Introduction and Objective
Introduction to midas Gen
What Gen can Do
Static AnalysisDynamic Analysis
Geometric Nonlinear Analysis
Buckling Analysis
Heat of Hydration Analysis
Construction Stage Analysis
Boundary Change Analysis
Inelastic Time History Analysis
P-Delta Analysis
Material Nonlinear Analysis
Static Seismic Analysis Response Spectrum Analysis
Time History Analysis
Boundary Nonlinear Analysis
Damper, Isolator, Gap, Hook
Settlement Analysis
Large Displacement Analysis
Structural Masonry Analysis
Time Dependent Material Column Shortening Analysis
Pushover Analysis
RC, Steel, SRC, Masonry With and Without Pipe Cooling
Introduction to midas Gen
What Gen can Do
RC Design Steel Design SRC Design
ACI318 AISC-LRFD SSRC79
Eurocode 2, Eurocode 8 AISC-ASD JGJ138
BS8110 AISI-CFSD CECS28
IS:456 & IS:13920 Eurocode 3 AIJ-SRC
CSA-A23.3 BS5950 TWN-SRC
GB50010 IS:800 (1984 & 2007) AIK-SRC
AIJ-WSD CSA-S16-01 KSSC-CFT
TWN-USD GBJ17, GB50017 Footing Design
AIK-USD, WSD AIJ-ASD ACI318
KSCE-USD TWN-ASD, LSD BS8110
KCI-USD AIK-ASD, LSD, CFSD
Slab Design KSCE-ASD
43 Introduction and Objective
Introduction to midas Gen
02
Column shortening analysis
for high rise building using midas Gen
Ravi Kiran Anne, MIDAS
2014 MIDAS Technical Seminarmidas Gen – One Stop Solution for Building and General Structures
Construction Stage Analysis with Special
Emphasis on Column Shortening
midas Gen – One Stop Solution for Building and General Structures
Principal Axis of Building
Why Construction Stage Analysis Column Shortening & Related Issues Effects of Column Shortening Procedure for Accounting Compensation at Site
Lotte World Tower Case Study Q&A
One Stop Solution for Building and General Structures
2014 Technical Seminar Auto Search Principal Axis
Response Spectrum Analysis
- In Irregular Structures, one directional response spectrum results may include a
different
direction’s response.
- When it occurs, the base shear force from the response spectrum analysis is
remarkably smaller than the base shear force calculated from static seismic analysis.
- This causes the scale factor to be very large, also causing an overestimation for the
design.
X
Y
R
xR
YR
xxR
YOne Stop Solution for Building and General Structures
2014 Technical Seminar Auto Search Principal Axis
Response Spectrum Analysis
¾ Principal axis
“ Principal Axes of a building are generally two mutually perpendicular horizontal directions in
a plan of a building along which the geometry of the building is
oriented”
“ Direction in which the seismic load has the largest influence on the structure.”
¾ Ways to Find Principal axis
1. Establishment of the Reaction Direction of the 1st Mode to Principal Axis after Modal Analysis. E.L.Wilson. “Three-Dimensional Static and Dynamic Analysis of Structures”, Computer and Structures, 2002.
2. Finding the Critical Angle Using Modal Analysis Method’s Fundamentals and CQC Theory, Trial and Error Method.
O.A.Lopez and R. Torres. “The Critical Angle of Seismic Incidence and the Maximum Structure Response”, EESD, 1997 3. Trial and Error Method: Practical Approach.
One Stop Solution for Building and General Structures
2014 Technical Seminar Auto Search Principal Axis
Response Spectrum Analysis
¾Auto Search Principal axis
X
Y
midas Gen – One Stop Solution for Building and General Structures
Why Construction Stage Analysis
Column Shortening & Related Issues Effects of Column Shortening Procedure for Accounting Compensation at Site
Lotte World Tower Case Study Q&A
One Stop Solution for Building and General Structures
2014 Technical Seminar
•
In general structures are analyzed assuming that the structure is built and loaded in a moment.
•
Construction of structures is a time taking process and during this period Material Properties,
Loads and Boundaries conditions may change.
Construction Stage Analysis
Why Construction Stage (CS) Analysis
Construction Sequence
Self weight of slab Other Dead Loads (Partions, Finishes)
Completed Structure
Dead Load + Live Load Wind
Earthquake
LL,WL,EQ Acts
One Stop Solution for Building and General Structures
2014 Technical Seminar Construction Stage Analysis
Conventional Analysis Vs. Construction Stage Analysis
Case 1 – ConventionalAnalysis Case 2 – CS Analysis
One Stop Solution for Building and General Structures
2014 Technical Seminar Construction Stage Analysis
Conventional Analysis Vs. Construction Stage Analysis
Case 1 – ConventionalAnalysis Case 2 – CS Analysis
One Stop Solution for Building and General Structures
2014 Technical Seminar Construction Stage Analysis
Conventional Analysis Vs. Construction Stage Analysis
Stage 2
One Stop Solution for Building and General Structures
2014 Technical Seminar Construction Stage Analysis
Conventional Analysis Vs. Construction Stage Analysis
Stage 2
= +
One Stop Solution for Building and General Structures
2014 Technical Seminar Construction Stage Analysis
Where CS Analysis is Required
Long Span Trusses
Long Span Slabs, Beams constructed in multiple stages
Prestressed concrete Structures
CS analysis should be performed for all structures where there is a change in
Support Conditions, Loading and varying material properties (Concrete).
midas Gen – One Stop Solution for Building and General Structures
Construction Stage Analysis
Column Shortening & Related Issues
Effects of Column Shortening Procedure for Accounting Compensation at Site
Lotte World Tower Case Study Q&A
Contents
One Stop Solution for Building and General Structures
2014 Technical Seminar
Column Shortening and Related Issue
σ
When any member is loaded with Axial Load, it undergoes axial deformation
E
= (σ / ε)
ΔL
= (PL/A E)
Why is this
Important
One Stop Solution for Building and General Structures
2014 Technical Seminar
P1,
ΔL1
P2,
ΔL2
The differential shortening happening between the vertical members may cause
additional forces and stress in Beams and Slabs
Column Shortening and Related Issue
Column Shortening
One Stop Solution for Building and General Structures
2014 Technical Seminar
Steel Structures
- Linear elastic Behavior
Stress ∞Strain
Strain is constant for a given Stress during loading & unloading
E = (σ / ε)
ΔL
= (PL/A E)
σ
Column Shortening and Related Issue
One Stop Solution for Building and General Structures
2014 Technical Seminar
Concrete Structures
- Nonlinear Inelastic Behavior
- But in general analysis and design behavior of concrete is treated as Linear Elastic Material
Neither Stress ∞Strain
Nor Strain is constant for a given Stress During loading & unloading
Elastic Strain
+
Inelastic Strain
Column Shortening and Related Issue
Column Shortening
One Stop Solution for Building and General Structures
2014 Technical Seminar
Concrete Structures
Elastic
Shortening
Modulus of Elasticity changes with time.
E
i= (σ / ε)
ΔL
= (PL/A E
i)
Inelastic
Shortening
σ
σ
Creep Shortening. Shrinkage Shortening.Column Shortening and Related Issues
One Stop Solution for Building and General Structures
2014 Technical Seminar
With increased height of structures the effect of column shortening (Elastic & Inelastic)
take on added significance and need special consideration in design and construction.
Elastic Shortening of 80 Storey Steel Structure ~ 180 mm to 255 mm.
Elastic Shortening of 80 Storey Concrete Structure ~ 65 mm.
Total Shortening of 80 Storey Concrete Structure ~ 180 to 230 mm.
Inelastic Shortening ~ 1 to 3 times Elastic shortening.
Column Shortening and Related Issue
Column Shortening
One Stop Solution for Building and General Structures
2014 Technical Seminar
Column Shortening and Related Issue
Two basic prerequisites for accurately and efficiently predicting these effects
are
9
Reliable Data for the creep and shrinkage characteristics of the particular concrete mix
9
Analytical procedures for the inclusion of these time effects in the design of structure.
Some of the popular predictive methods for predicting creep and shrinkage
strains are
9
ACI 209 -92
9
Bazant – Bewaja B3
9
CEB – FIP (1978, 1990)
9
PCA Method (Mark Fintel, S.K.Ghosh & Hal Iyengar)
9
GL 2000 (Gardner and Lockman)
9
Eurocode
One Stop Solution for Building and General Structures
2014 Technical Seminar
Column Shortening and Related Issue
The total strain at any time t may be expressed as the sum of the
instantaneous, creep and shrinkage components:
Where,
ε
e(t) = Instantaneous strain at time t,
ε
c(t) = Creep strain at time t,
ε
sh(t) = Shrinkage strain at time t.
Column ShorteningOne Stop Solution for Building and General Structures
2014 Technical Seminar
Column Shortening and Related Issue
The instantaneous strain in concrete at any time t is expressed by
Where,
σ (t) = stress at time t,
E
c(t) = Elastic modulus of concrete at time t, given by
f
ct= Compressive strength at any time t, given by
α & β are constants depending on Type of Cement & Type of Curing
One Stop Solution for Building and General Structures
2014 Technical Seminar
Column Shortening and Related Issue
Inelastic
Shortening =
Creep
+
Shrinkage
Shrinkage
Creep
Shrinkage is the time-dependant decrease in concrete volume compared with the original placement volume of concrete.
¾Drying Shrinkage is due to moisture loss in concrete.
¾Autogenous Shrinkage is caused by hydration of cement.
¾Carbonation shrinkage results as the various cement hydration products are carbonated in the presence of CO
Creep is time-dependent increment of strain under sustained stress.
¾Basic creep occurs under the condition of no moisture movement to and from the environment.
¾Drying creep is the additional creep caused by drying. Drying creep has its effect only during the initial period of load.
Column Shortening
One Stop Solution for Building and General Structures
2014 Technical Seminar
Column Shortening and Related Issue
Inelastic
Shortening =
Creep
+
Shrinkage
Shrinkage
Creep
As per ACI 209R-92 the creep coefficients are predicted as =
As per the ACI 209R-92, shrinkage can be predicted by
Where,
t = time in days after loading.
vu = Ultimate creep coefficient = 2.35 Jc
Jc = Product of applicable correction factors
After 7 days for moisture cured concrete
After 1-3 days for steam cured concrete
Where,
t = time in days after the end of Initial Curing (Hsh)
u = Ultimate Shrinkage Coefficient = 780 Jsh x 10 -6 m/m
Jsh = Product of applicable correction factors
One Stop Solution for Building and General Structures
2014 Technical Seminar
Column Shortening and Related Issue
Factors affecting the Creep & Shrinkage of Concrete
Concrete (Creep & Shrinkage)
Concrete Composition
Cement Paste Content Water – Cement ratio Mixture Proportions Aggregate Characteristics Degrees of Compaction
Initial Curing
Length of Initial Curing Curing Temperature Curing Humidity
Member Geometry and Environment
(Creep & Shrinkage) Environment
Concrete Temperature Concrete Water Content
Geometry Size and Shape
Loading (Creep Only)
Loading History
Concrete age at load Application During load Period
Duration of unloading Period Number of load Cycles Stress Conditions
Type of Stress and distribution across the Section
Stress/Strength Ratio
Column Shortening
midas Gen – One Stop Solution for Building and General Structures
Construction Stage Analysis
Column Shortening & Related Issues
Effects of Column Shortening
Procedure for Accounting Compensation at Site Live Demonstration
Lotte World Tower Case Study Q&A
One Stop Solution for Building and General Structures
2014 Technical Seminar
Effects of Column Shortening
Absolute shortening is rarely of practical interest.
Differential shortening between adjacent vertical elements is the most important factor for
engineer.
Axial Shortening of vertical elements
will not effect those elements very much,
horizontal elements like beams and slabs
and non structural elements are affected.
Column Shortening
One Stop Solution for Building and General Structures
2014 Technical Seminar
Effects of Column Shortening
¾
Cracks in Partition Walls.
¾
Cracks in Staircases
¾
Deformation of Cladding.
¾
Mechanical Equipment.
¾
Architectural Finishes.
¾
Built in Furnishings.
These non structural elements are not
intended to carry vertical loads and are
therefore not subjected to shortening.
¾
Slabs may not be truly horizontal after some time.
¾
Beams could be subjected to higher bending moments.
¾
Load transfer.
Structural Effects
Non Structural Effects
One Stop Solution for Building and General Structures
2014 Technical Seminar
Effects of Column Shortening
Deformation and breakageofFacades, windows & Parapet walls…
Reverse Inclination of Drainage Piping System
Deformation of Vertical Piping System Deformation and breakage of internalpartitions
Column Shortening
midas Gen – One Stop Solution for Building and General Structures
Construction Stage Analysis
Column Shortening & Related Issues Effects of Column Shortening
Procedure for Accounting
Compensation at Site
Lotte World Tower Case Study Q&A
One Stop Solution for Building and General Structures
2014 Technical Seminar
Procedure for Accounting Column Shortening
Column Shortening
One Stop Solution for Building and General Structures
2014 Technical Seminar
Procedure for Accounting Column Shortening
?
Folpdwlf# Frqglwlrq# Frqglwlrqv# Ordglqj# Frqglwlrq# Frqvwuxfwlrq# Surjuhvv# Rwkhu# Frqglwlrqv# Pre-Analytical Prediction & Continuous Monitoring Experimental Measurements & Construction SurveyPrecise prediction
of shortening
Fruuhfwlr
q#
Column ShorteningOne Stop Solution for Building and General Structures
2014 Technical Seminar
Procedure for Accounting Column Shortening
Analytical MeasurementReflection of physical properties in calculation from material experiment:
Young’s Modulus, Poisson’s Ratio, Mean Compressive strength, Volume to Surface ratio, Shapes, sizes etc.
Reflection of effects of Climate on shortening:
AverageTemperature , RH etc.
Construction Sequence:
Stage duration, Additional Steps, Member Age, Load activation age, Boundary activation age etc.
Reflection of the above effects on site master-schedule.
Installation of sensors or gages in members for determining the actual shortening.
Understanding and noting the following:
Curing procedure / Temperature, Actual Shortening,
Change in Ambient Temperature (Important), Actual Humidity,
Deviation from Defined Construction Stages,
Manipulation of factors in analytical Calculation, Re-Analysis…
Experimental Measurement
Using Software or Manually (Manual calculation is almost impossible)
Field Measurements
Method has Limitation
Column Shortening
One Stop Solution for Building and General Structures
2014 Technical Seminar
Procedure for Accounting Column Shortening
͵ΖΥΖΣΞΚΟΒΥΚΠΟ͑ΠΗ͑ͺΟΤΥΒΝΝΒΥΚΠΟ͑ΝΠΔΒΥΚΠΟ͑ ͺΟΤΥΒΝΝΒΥΚΠΟ͑ΠΗ͑ΒΦΘΖ͑ ͲΗΥΖΣ͑ͺΟΤΥΒΝΝΒΥΚΠΟ͑
ͲΗΥΖΣ͑͑ͺΟΤΥΒΝΝΒΥΚΠΟ͑ΠΗ͑ΒΦΘΖ͑ ͲΗΥΖΣ͑ʹΒΤΥΚΟΘ͑ΠΗ͑ʹΠΟΔΣΖΥΖ͑ ͷΚΖΝΕ͑ΕΒΥΒ͑ΔΠΝΝΖΔΥΚΠΟ͑
Field Measurements
One Stop Solution for Building and General Structures
2014 Technical Seminar
Procedure for Accounting Column Shortening
0DQLSXODWLRQRIWKHFRQVWUXFWLRQVWDJHDV SHUVLWHFRQGLWLRQ &RQVWUXFWLRQVWDJHRIHDFKJURXS $FWLYDWLRQRI&RQVWUXFWLRQVWDJHV 3HUIRUP'&6$QDO\VLV
Engineering Re-Analysis
Column ShorteningOne Stop Solution for Building and General Structures
2014 Technical Seminar
Procedure for Accounting Column Shortening
Column Shortening
Preliminary Analysis
Material / Section Properties Applied Load, Schedule
Main analysis
•Updating material properties from experiments
•Construction sequence considering the field condition
1st, 2nd, 3rd Re-Analysis
Suggestion of compensation and details for non-constructed part of structure
Final Report
Shortening, result from test, measurement Review
Material Experiment
•Compressive strength •Modulus of elasticity •Creep & Shrinkage
Measurement
Measurement of strain for Column & Wall
Design with Additional Force Applying Compensation to in-situ structure Pre-Analysis Main Analysis, Construction & Re-Analysi
s
0.0E+00 1.0E-04 2.0E-04 3.0E-04 4.0E-04 0 50100150200250300350 Str ain Day Back Analysis Output (103-1F-01) Strain Gauge Output (103-1F-01)midas Gen – One Stop Solution for Building and General Structures
Construction Stage Analysis
Column Shortening & Related Issues Effects of Column Shortening Procedure for Accounting
Compensation at Site
Lotte World Tower Case Study Q&A
Contents
One Stop Solution for Building and General Structures
2014 Technical Seminar
Compensation at Site
Column Column 1st correction 2nd correction 1st correction Column ShorteningOne Stop Solution for Building and General Structures
2014 Technical Seminar
Movement Related to Construction Sequence
Column Shortening
Depending on the stage of construction:
• Pre-slab installation shortenings
– Shorteningstaking place up to the time of slab installation
• Post-slab installation shortenings
– Shortenings taking place after the time of slab installation
Depending on the construction material:
• Reinforced Concrete Structure
– Pre-slab installation shortenings has no importance – Compensation by leveling the forms
– Post-slab installation shortenings due to subsequent loads and creep/shrinkage
• Steel Structure
– Columns are fabricated to exact length. – Attachments to support the slabs
– Pre-slab installation shortenings need to be known.
– Compensation for the summation of Pre-installation and Post-installation shortenings
One Stop Solution for Building and General Structures
2014 Technical Seminar Column Shortening
Compensation at Site
zshiG{orUG iGOdGoGG G ہۄۇۇۀۍGoGGG
GG jGyGjvuNjGjG
G
ࣜThe order of construction#
installation of column forms
insertion of FILLER
insertion of correcting FILLER
Installation of SLAB forms
midas Gen – One Stop Solution for Building and General Structures
Construction Stage Analysis
Column Shortening & Related Issues Effects of Column Shortening Procedure for Accounting Compensation at Site
Lotte World Tower Case Study
Q&A
Contents
L
Lotte World TowerOverview
.QECVKQP -DPVLO6HRXO6RXWK.RUHD *GKIJV 4QQHėP#PVGPPC5RKTGėP 0QQH(NQQTU (NQQT#TGC P )XQFWLRQ8VDJH 2IILFH5HVLGHQWLDO+RWHO2EVHUYDWLRQ'HFNP 6WUXFWXUH7\SH 5HLQIRUFHG&RQFUHWH6WHHO /DWHUDOORDG UHVLVWLQJV\VWHP &RUH:DOO2XWULJJHU7UXVV%HOW7UXVV )RXQGDWLRQ7\SH 0DW)RXQGDWLRQ %QPUVTWEVKQP2GTKQF 0DUFKa.QVVG9QTNF6QYGT
43
L
Lotte World Tower
Construction Site Structural Schematic
L
Lotte World TowerOverview
ݡɻ ʾ˒ Initial Curing <Elastic> <Inelastic>
Con’c Vertical Member
Pre-slabInstallationshortening
Core wall Column
Core Shortening Column Shortening < Deferential Deformation > Deferential Shortening (FOFSBM ↟)FJHIUNGMPPST Tower Deformation ↟%FGPSNBUJPOPGUIFUPXFSJTBOBUVSBMMZPDDVSSJOHEFQFOEJOHPONBUFSJBM DPOTUSVDUJPONFUIPE ↟7FSUJDBM%FGPSNBUJPO 7FSUJDBM4IPSUFOJOH4FUUMFNFOU$POTUSVDUJPO&SSPST ↟)PSJ[POUBM%FGPSNBUJPO %JGGFSFOUJBM4IPSUFOJOH4FUUMFNFOU 6OFWFOMPBEEVFUPDPOTUSVDUJPONFUIPE "TZNNFUSJDGMPPSQMBO$POTUSVDUJPOFSSPST Horizontal Deformation Vertical Deformation With Time
45
L
Lotte World TowerPre-Analysis - Deformations
Vertical deformation Differential Shortening Horizontal deformation Differential settlement• Deferential shortening btw Core & Column ֜ Steel column: Max 55mm
֜ Mega column: Max 65mm
• Top of tower
֜ Steel Frame: 368.7 mm ֜ Core wall: 314.0 mm
• Top of mega column
֜ Mega Col: 297.8 mm ֜ Core wall: 232.8 mm
A BOVE F IRE SHUTTERA BOVE A BOVE F IRE SHUTTERA BOVE
:&KT ;&KT 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 • Prediction X dir: 27.2mm Y dir: 115.5mm Safety check Æ Elevator’s rails Æ Vertical Pipes X Y .&(" $0- $03&8"--'06/%"5*0/ .&(" $0- .&(" $0- $03&8"--'06/%"5*0/ .&(" $0- <initial> <Complete>
֜ Core wall settlement: 35mm ֜ Column settlement: 16mm
Core wall Column
Core
Shortening Column Shortening
Deferential Shortening
Lantern & Core
L
Lotte World Tower
Pre-Analysis - Deformations
Outrigger’s additional stress Slab’s additional stress
Podium’s additional stress
Differential Deformation btw Slab-Column Æ Slab has additional stress
• Additional stress btw tower & podium
Æ Max 100 ton.m
Æ Require Settlement
Joint & Safety check
• Additional Stress without Delay Joint
֜ 1st outrigger (L39~L43): 3,600 tons
֜ 2nd outrigger (L72~L75): 4,700 tons
֜ required a delay joint installation
• Additional Stress with Delay Joint
֜ 1st outrigger (L39~L43): 1,700 tons ֜ 2nd outrigger (L72~L75): 2,000 tons Podium
Towe
r
connection L87~L103 L72~L75 L39~L43 B06~B0147
L
Lotte World Tower
Pre-Analysis – Compensation
- Core Wall: Absolute correction for securing design level
- Column: Relative correction for deferential shortening
Ⴃ Relative correction between core and column
Ⴃ correction due to measurement
pre-Analysis Analysis Re-analysis 1~6 times Material Test Measurement 1st correction 2nd correction Additional correction for unconstructed B06 L01 L40 L20 L10 L30 L50 L60 L70 L80 L90 L100 L110 L120 TOP 2nd O/R 1st O/R Lantern 1st B/T 2nd B/T
)ORRU &RUH &ROXPQ
// 'HVLJQOHYHOPP 6WHHOFROXPQV // 'HVLJQOHYHOPP 6WHHOFROXPQV // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP // 'HVLJQOHYHOPP &RUHOHYHOPP %/ 'HVLJQOHYHOPP &RUHOHYHOPP
L
Lotte World Tower "OBMZTJT$POEJUJPOBOE"TTVNQUJPO "Analysis Tool: midas/GEN
Outrigger Installation Condition: After completion of frame construction, 1st & 2nd outrigger installation
Environment: Average relative humidity 61.4%
- 3D Structural Analysis with changes of material properties Material properties
- Regression analysis results from the material test data (6 month )
- Comparing to pre-analysis results, 32~33% in creep deformation, 39~42% in shrinkage deformation
- Relative humidity of average 5 years Target period of shortening
- Safety verification: 100years after (ؒultimate shortening) - Service verification: 3years after (95% of ultimate shortening) Loading Condition
- Dead Load & 2nd Dead Load: 100%, Live Load: 50% foundation/ground analysis results Apply soil stiffness from
49
L
Lotte World Tower
Material Test Results
Material test results for re-analysis
<Comparison Graph of Shrinkage>
Pre-analysis Re-analysis Design Strength Ultima te S hrink a g e S tra in (με )
<Comparison Graph of Specific Creep>
Pre-analysis Re-analysis Design Strength Sp ecif ic C reep
<Comparison Graph of Elastic Modulus>
Re-analysis (Material Test) Pre-analysis (Theoretical Eq.)
Concrete Age (Day)
Elastic M odulus 28 days
L
Lotte World Tower /% . 29 . /% . /% . /% . /% . /% . /% . /% . 29 . 29 . 29 . 29 . 29 . 29 . 29 . 2 9 . 2 9 . 29 . +9 . +9 . +9 . +9 . %QN/+0 9CNN/+0 %QN/#: 9CNN/#: 29 . 29 . 2 9 . 2 9 . 4IPSUFOJOH3FTVMUTm.FHB$PMVNO4IPSUFOJOH #_- 4I Target Period: 3years
- 3 years was determined as the optimal time of target serviceability application.
Maximum shortening of mega column
- SubTo: 131.4~137.2mm (L65, L69)
(80~83% of pre-analysis)
Shortening of core walls
- SubTo: 74.1~85.9mm (L71)
(77~78% of pre-analysis)
Differential shortening between column-core
- 53.1~60.9mm (L65)
Settlement Shortening
- Mega column: 21.2~25.5mm (B6) - Core wall: 23.6~29.1mm (B6)
51
L
Lotte World Tower 4IPSUFOJOH3FTVMUTm4UFFM$PMVNO4IPSUFOJOH -_- 4I Target Period: 3years
- 3 years was determined as the optimal time of target serviceability application.
Maximum shortening of steel
column
- SubTo: 110.4~136.9mm (L76)
(80% of pre-analysis)
- Total: 260.7~286.1mm (L76)
(80% of pre-analysis) Shortening of core walls
- SubTo: 67.8~81.0mm (L76)
(65~70% of pre-analysis)
- Total: 162.9~213.6mm (L76)
(67~70% of pre-analysis)
Differential shortening between
Column-core - 40.1~44.5mm (L76) 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . 5% . %QN/+0 9CNN/+0 %QN/#: 9CNN/#: 29 . 29 . 29 . 29 . 29 . 29 . 29 . 29 . 2 9 . 2 9 . 29 . +9 . +9 . +9 . +9 . 29 . 29 . 2 9 . 2 9 .
Re-analysis Results
L
Lotte World TowerVertical Shortening Measurement
B06 L01 L38 L18 L10 L28 L50 L60 L70 L76 L90 B03 Foundation settlement 400 gauges (30~60 per floor)
A BOVE F IRE SHUTTERA BOVE A BOVE F IRE SHUTTERA BOVE
: Mega Column : External Core : Internal Core
Ⴃ Gauges Location in Plan
Ⴃ Gauges Location of settlement
: Load cell : Level surveying : Strain Gauge : B006~L070 A˅ A-A˅ যஏ ৻Ҙஏ : B006~L050 A
53
L
Lotte World Tower
Compensation due to core and column differential shortening C
)ORRU &RUH &ROXPQ
// 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP ಹ ಹ ಹ / 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP / 'HVLJQOHYHOPP 'HVLJQOHYHOPP /%
Re-analysis Results
L
Lotte World Towerz Additional stress due to differential shortening
between core & column
z Provide outrigger delay joint
Steel Outrigger Delay Joint ཱ Steel Outrigger Adjustment Joint
(Securing safety under construction)
Outrigger Structural Safety issues and alternatives proposed
Effect & Safety Measure
Ⴃ 2nd Outrigger (L72~L75)
55
L
Lotte World Tower
Midas Gen – One Stop Solution for Building and General Structures
Construction Stage Analysis
Column Shortening & Related Issues Effects of Column Shortening Procedure for Accounting Compensation at Site
Lotte World Tower Case Study Some Useful Features in the software Q&A
Contents
One Stop Solution for Building and General Structures
2014 Technical Seminar
Material Stiffness Changes for Cracked Sections
Useful Features in midas Gen
Specific stiffness of specific member types may be reduced such as the case where the flexural stiffness of lintel beams and walls may require reduction to reflect cracked sections of concrete.
Section stiffness scale factors can be included in boundary groups for construction stage analysis. The scale factors are also applied to composite sections for construction stages.
One Stop Solution for Building and General Structures
2014 Technical Seminar
Spring Supports for Soil Interaction
Useful Features in midas Gen
Point Spring Support (Linear, Comp.-only, Tens.-only, and Multi-linear type)
Surface Spring Support (Nodal Spring, and Distributed Spring)
Springs can be activated / deactivated during construction stage analysis.
[Nonlinear point spring support]
[Nodal Spring and Distributed Spring] [Surface Spring Support]
[Pile Spring Support]
One Stop Solution for Building and General Structures
2014 Technical Seminar
Detailed Design Reports
midas Gen – One Stop Solution for Building and General Structures
2014 MIDAS Technical Seminar
Challenges & Solution for Tall Building Design
03
Project Applications
using midas Gen
Structural Concept Designs Pvt., Ltd.
Project Applications using midas Gen
- Challenges & Solutions of Tall Building Design -
Raajesh K. Ladhad
Structural Concept Designs Pvt., Ltd.
- Project Applications using midas Gen-
2014 Challenges & Solutions of Tall Building Design
Elerro Fiesta, Sanpada, 2012
- Project Applications using midas Gen-
2014 Challenges & Solutions of Tall Building Design
Marine Academy, Panvel, 2010
- Project Applications using midas Gen-
2014 Challenges & Solutions of Tall Building Design
Pot 5, Sector 11, Ghansoli
- Project Applications using midas Gen-
2014 Challenges & Solutions of Tall Building Design
Bhagwati Tower, Ghansoli
G+40, Shear Wall System,
- Project Applications using midas Gen-
2014 Challenges & Solutions of Tall Building Design
- Project Applications using midas Gen-
2014 Challenges & Solutions of Tall Building Design
Kesar group Matunga,
G+20, Shear Wall and partial Braced
- Project Applications using midas Gen-
2014 Challenges & Solutions of Tall Building Design
Dimension Paradise Group, Kharghar
G+20, Shear Wall and partial Braced
g
g
- Project Applications using midas Gen-
2014 Challenges & Solutions of Tall Building Design
Sai World City, Kharghar
G+45, Shear Wall
- Project Applications using midas Gen-
2014 Challenges & Solutions of Tall Building Design
Plot No. 22, Sector 4, Sanpada
G+16, Shear Wall
ada
ada
- Project Applications using midas Gen-
2014 Challenges & Solutions of Tall Building Design
K12 Taloja, Y column
- Project Applications using midas Gen-
2014 Challenges & Solutions of Tall Building Design