• No results found

MS Project 2010 Formule

N/A
N/A
Protected

Academic year: 2021

Share "MS Project 2010 Formule"

Copied!
31
0
0

Loading.... (view fulltext now)

Full text

(1)

Building a Project Dashboard with Formulas

in MS Project

Relu Rosenberg

(2)

Introduction

 This presentation will show how to build a Project Dashboard using Excel like formulas and

functions in MS Project

 The study case will walk through the steps for creating a field called “Task Progress” to

calculate the Progress status of a task and use graphical indicators for creating a dashboard

view for active tasks (task level) or project summary view (Summary tasks level)

 Steps

Define the logic

Build the formula

Add graphical indicators for quick identification of tasks status, issues

Build filter based on calculated values to select tasks of interest (focus tasks)

Make customizations available to all your Project plans

Make customizations available to someone else , publish a template plan

 Benefits

Automated calculation and identification of active tasks

(3)

Introduction - 2

 The end result will take you from a project plan with no easy way to identify a status (left) to a

toolbox to produce one click status reports, issues , focus tasks list (right side).

If this interests you, follow the rest of this presentation !

(4)
(5)

Logic #1 – Notes

10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 5

•Logic #1 is very simple to implement as it is based only on

“% Complete” and Start, End dates of the task.

It automates calculation and identification of 8 task status values !

•If %Complete is >0 it will know task work started and it will mark as “In

progress”

•Doesn’t require accurate estimate of %Complete.

•It is suitable for tasks of short duration, w/o interim milestones

•This calculation cannot establish if a task in progress is late or ahead of

the schedule. This is where logic #2 and #3 will help

(6)

Logic #2 – Use task “Status” field

Condition Task Status

Display

Field Value

%Complete = 100 Complete 0

Timephased Cumulative %Complete >0 on midnight of day before On Schedule 1 Timephased Cumulative %Complete =0 on midnight before Late 2

Task Start Date > Today Future Task 3

Go To View->More Views ->”Task Usage”

To add fields

Format -> “Detail Styles” and add “Cumulative Percent Complete” to show pane

To change displayed fields

Format->”Details” and Check/Uncheck fields

(7)

Logic #2 – Notes

10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 7

•Logic #2 leverages the “Status” task field from Microsoft Project. This

will help to determine not just if a task is in Progress but also if it is on

Schedule or Late.

•It is the correct way to calculate because the time phased

“% Complete” accounts for the actual work performed over elapsed

time.

•A resource can have days off , days not worked full time, etc and

comparing ((Date()-*Start+)/*Duration+) with “% Complete” is

misleading.

•Requires more accurate estimate of %Complete of a task

•It’s suitable for tasks of longer duration where %Complete can be

measured

(8)
(9)

Logic 3 - Using EVM SPI

 Resources

 Define all resources

 Assign rates to each resource (Std. Rate, Ovt. Rate)

 Assign resource to each task

 Define Earned Value Calculation options

(Tools ->Options -> Calculation)

 Default task Earned Value method: % Complete

 Edits to total task % complete will be spread to the status date (to see SPI>1)

 Baseline project

 Re-baseline every time you add tasks and resources or change tasks, resources

(10)

Logic 3 – Notes

• Logic #3 is the most sophisticated and accurate. It will allow to

determine if a task in progress is Behind Schedule, On Schedule, Ahead

of Schedule.

• It uses Earned Value Methodology and specifically it uses Schedule

Performance Index.

• For older versions of Microsoft Project which don’t have the SPI

calculated you can add SPI as a customized field, Number , with

following formula:

IIf([BCWS]>0,[BCWP]/[BCWS],0)

Since BCWS is 0 For future tasks in MS Project 2000, the formula checks

and returns SPI=0 to prevent Error due to division by 0.

• It requires accurate measurement of %Complete to provide accurate

indicator of progress status (Ahead, On Schedule, Behind)

(11)

Logic 3 - Task Progress using EVM SPI

(12)

Creating a custom field

 The are several types of fields you can customize, depending on desired data type

 Text, Date , Number are the most used

 Start, Finish, Cost, Duration, Flag are additional types

 Right click on project headings to “Insert Column” , will choose Text type field, Text2 for “Task Progress”

field

(13)

Customize field applet

 Right click on field header and select Customize field

Use Rename to rename the field from Text2 to “Task Progress” for use in formulasCheck the boxes for Formula and Graphical Indicators buttons for customization

(14)

Writing Formulas – simple examples

 We will use these statements and functions

 IIf(expression-to-test, Do-this-if-true,Do-this-if-False)  Date() - returns current system date

 Project fields - designated as [field-name]

 Examples

 Flag all active tasks (Start < Date < Finish)

IIf((Date() > [Start]) And (Date() < [Finish]),"Active Task","")

 Flag all overdue tasks – (Finish < Date) and (%Complete <100)

IIf(([Finish] < Date()) And ([% Complete] < 100),"Overdue","")

 Flag active and overdue tasks – combine the above

IIf((Date()>[Start]) And (Date()<[Finish]), "Active Task",

IIf(([Finish]<Date()) And ([% Complete]<100),"Overdue","") )

(15)

Writing the Formulas for “Task Progress” logic

 Below formulas implement the logic diagrams (decision trees) depicted in slides

 It is recommended to check each decision path in the formula using the Logic diagram

 Easiest way to test the values is by adjusting the % Complete

10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 15

Logic 1 - % Complete and Start/Finish Dates

IIf(*% Complete+=100,"Complete",IIf(*Estimated+=Yes,"TBD",IIf(Date()>*Finish+,”Not Finished", IIf(Date()>*Start+,IIf(*% Complete+=0,“Not Started",IIf((*Finish+-Date())<7,"Ending Next", "In progress")),IIf([Start]-Date()<7,"Starting Next","Future")))))

Logic 2 - % Complete, Task Status and Start/Finish Dates

IIf([% Complete]=100,"Complete",IIf([Estimated]=Yes,"TBD",IIf(Date()>[Finish],"Not

Finished",IIf(Date()>[Start],IIf([% Complete]=0,"Not Started",IIf(([Finish]-Date())<7,"Ending Next",IIf([Status]=1,"On Schedule","Late"))),IIf([Start]-Date()<7,"Starting Next","Future")))))

Logic 3 - Use SPI and Start/Finish Dates

IIf([% Complete]=100,"Complete",IIf([Estimated]=Yes,"TBD",IIf(Date()>[Finish],"Not

Finished",IIf(Date()>[Start],IIf([% Complete]=0,"Not Started",IIf(([Finish]-Date())<7,"Ending Next",IIf([SPI]<1,"Late",IIf([SPI]>1,"Ahead","On Schedule")))),IIf([Start]-Date()<7,"Starting Next","Future")))))

(16)

Formula written in structured format

IIf([ % Complete]=100, “Complete" IIf([Estimated]=Yes, "TBD", IIf(Date()>[Finish], "Not Finished", IIf(Date()>[Start], IIf([%Complete]=0, "Not Started", IIf(([Finish]-Date())<7, "Ending Next", IIf([Status]=1, “On Schedule”, “Late” ) ) ), IIf([Start]-Date()<7, "Starting Next", "Future Task"

(17)

Using Formula Applet

 Press Formula button to open the applet

 Use Field button to inserts field names in formula and Function button to select functions

 To learn more about functions search for “Project functions” in Help

(18)

Add Graphical Indicators

 Check Graphical Indicators … Radio button to enable

 Press Graphical Indicator… Button to define the values

 Select “Nonsummary rows” to display indicator for tasks only

(19)

Set Calculations Mode

 Confirm/Set Calculations mode to Automatic

 Tools->Options->Calculation Tab

Check/Set Calculation Mode: Automatic

(20)

Project Plan without Graphical Indicators

(21)

Project Plan with Calculated Status & Graphical Indicators

(22)

Project Plan with Graphical Indicators – 2

(23)

Project tasks review using filters

10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 23

 Select tasks of interest

 In progress, Ending Next, Starting Next

 Select issues

 Not started, Late, Not Finished, TBD (Dates not Confirmed)

 Create Filter

 Got to Project->Filtered For->More Filters  Select New

 Check radio button for Task filter  In New Filter Applet

o Define the Name

o Check Show In Menu to see it in Filters list o Define the rules for tasks selection

(24)
(25)

Project tasks review – Filter: Focus tasks (less clutter)

10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 25

(26)

Project tasks review – Filter: Issues

(27)

Project Dashboard – phase level report for management

10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 27

(28)

Project Dashboard – Phase & Major Activities review

(29)

Share customizations

10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 29

 Make customizations available to all your projects

 Any MS Project object customized in a project plan will be saved within the project file only.

 In order to make these objects available to the other projects they need to be saved in the global template.  Identify all customizations

o Tools->Organizer and go through each tab (object category).

o Left side “Global.MPT” represents global objects, right side shows the objects exiting only in the specific project file.

(30)

Share customizations - 2

 Share customizations with others

 Create a blank project files

 Copy all customizations from Global to the Project file

o Tools->Organizer and go through each tab (object category).

o Left side “Global.MPT” represents global objects, right side shows the objects exiting only in the specific project file.

(31)

Questions ?

Email: [email protected]

References

Related documents

Decrease in the adult-to-adult social transmission rate, and a decrease in the child- to-child and adult-to-child social transmission rates, and an increase in the overweight and

Each hour of SPPS uses P200 of programming budget and P500 of storage budget, while each hour of STAA uses P800 of programming budget and P1,000 of storage budget.. What

We identify three findings about the impact of a global uncertainty shock: (i) emerging market countries suffer a median fall in investment approximately three times as large as

Projections of changes in the onset and cessation of wet seasons across Africa under future climate change, produced using CMIP5 models, show the onset and cessation of the

NICE guidelines need to include guidance on post-abortion contraceptive services. The range of contraceptive services should be tailored to the needs of the local population.

Further, the empirical results here support Gorton’s findings that note prices were lower when banks suspended specie payments and that discounts were not closely related to the

Source: “WORKING WELL: A Global Survey of Health Promotion, Workplace Wellness and Productivity Strategies” Buck Consultants, July 2014.. Top reasons outcomes are not measured 14%

LA Mart offers marketing opportunities during Markets for on-site advertising, so you get the most out of Market. Contact Rhea Harding for more information about on-site