PMP Exam Preparation Course Page 1
Project Management Professional
Copyrights
PMP Exam Preparation Course Page 2
This book is produced by Techno Management®, a project management consulting company, registered in Canada. This document may not be reproduced, stored in a retrieval system, or transmitted in whole or in part, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of Techno Management®.
PMBOK and PMP are trademarks registered by the Project Management Institute (PMI) in the United States and other nations.
1- Introduction
PMP Exam Preparation Course Page 3
Table of Contents
1. Introduction ... 5
2. Project Management Framework ... 7
2.1 TERMS AND DEFINITIONS ... 7
2.2 COMPARATIVE OVERVIEW ... 9
2.3 PROJECT CHARACTERISTICS ... 9
2.4 PROJECTS VS.OPERATIONAL WORK: ... 11
2.5 PROJECT CONSTRAINTS ... 11
2.6 ROLE OF A PROJECT MANAGER ... 14
2.7 PROJECT STAKEHOLDERS ... 14
2.8 PROJECT ORGANIZATION STRUCTURE ... 15
2.9 ORGANIZATIONS CHARACTERISTICS ... 18
2.10 LIFE CYCLES AND PROCESS GROUPS ... 19
2.11 PROCESS GROUPS ... 19
2.12 INTERACTION BETWEEN PHASES ... 20
2.13 PMIKNOWLEDGE AREAS ... 21
3. Project Initiation Phase ... 29
3.1 DEVELOP PROJECT CHARTER ... 30
3.2 IDENTIFY STAKEHOLDERS ... 35
4. Project Planning Phase ... 40
4.1 DEVELOP PROJECT MANAGEMENT PLAN ... 41
4.2 COLLECT REQUIREMENTS ... 45
4.3 DEFINE SCOPE ... 51
4.4 CREATE WBS ... 58
4.5 DEFINE ACTIVITIES ... 63
4.6 SEQUENCE ACTIVITIES ... 69
4.7 ESTIMATE ACTIVITY RESOURCES ... 75
4.8 ESTIMATE ACTIVITY DURATIONS ... 80
4.9 DEVELOP SCHEDULE ... 85
4.10 ESTIMATE COSTS ... 94
4.11 DETERMINE BUDGET ... 100
4.12 PLAN QUALITY ... 104
4.13 DEVELOP HUMAN RESOURCE PLAN ... 117
4.14 PLAN COMMUNICATIONS... 123
4.15 PLAN RISK MANAGEMENT ... 129
4.16 IDENTIFY RISKS... 133
4.17 PERFORM QUALITATIVE RISK ANALYSIS ... 139
4.18 PERFORM QUANTITATIVE RISK ANALYSIS ... 144
4.19 PLAN RISK RESPONSES ... 149
4.20 PLAN PROCUREMENTS ... 155
5. Project Execution Phase ... 167
5.1 DIRECT AND MANAGE PROJECT EXECUTION ... 168
5.2 PERFORM QUALITY ASSURANCE ... 172
5.3 ACQUIRE PROJECT TEAM ... 176
5.4 DEVELOP PROJECT TEAM ... 180
5.5 MANAGE PROJECT TEAM ... 187
5.6 DISTRIBUTE INFORMATION ... 191
5.7 MANAGE STAKEHOLDER EXPECTATIONS ... 194
1- Introduction
PMP Exam Preparation Course Page 4
6. Project Monitor and Control Phase ... 203
6.1 MONITOR AND CONTROL PROJECT WORK ... 204
6.2 PERFORM INTEGRATED CHANGE CONTROL ... 207
6.3 VERIFY SCOPE ... 210
6.4 CONTROL SCOPE ... 212
6.5 CONTROL SCHEDULE ... 216
6.6 CONTROL COSTS ... 219
6.7 PERFORM QUALITY CONTROL ... 231
6.8 REPORT PERFORMANCE... 241
6.9 MONITOR AND CONTROL RISKS ... 246
6.10 ADMINISTER PROCUREMENTS ... 250
7. Project Closing Phase ... 254
7.1 CLOSE PROJECT OR PHASE... 255
7.2 CLOSE PROCUREMENT ... 258
8. Appendix-1 Case Study ... 261
9. Appendix-2 Exercise Forms ... 262
9.1 PROJECT CHARTER ... 262
9.2 SCOPE STATEMENT ... 263
9.3 ASSUMPTION LIST ... 264
9.4 WORK BREAKDOWN STRUCTURE ... 265
9.5 ACTIVITY LIST,RESOURCE ASSIGNMENT,DEPENDENCY &TIME ESTIMATE ... 266
9.6 QUALITY MANAGEMENT PLAN ... 267
9.7 RISK ANALYSIS ... 268
9.8 RISK ANALYSIS ... 269
9.9 CHANGE CONTROL... 270
10. Appendix-3 List of Figures ... 271
11. Appendix-4 List of Tables ... 274
12. Appendix-5 List of Exercises ... 275
1- Introduction
PMP Exam Preparation Course Page 5
1. Introduction
This book is directed to the project management professionals who are seeking the Project Management Professional certification. It covers al the material that needed to be covered to help passing the PMP exam and covered in the PMBOK®.
The approach taken here to present the material is different than the one taken in the PMBOK® in that the material goes through the project phase rather than the knowledge areas. This will help presenting the knowledge in a better logical flow that will make it more clear and logical to understand.
This book addresses the practical side of the project management by having a case study that will be taken from the very initial project stage to its completion. This will bone through comprehensive group workshops that will facilitate explaining the material in a clear and practical approach.
The book is structured as follow: 1- Project Framework
2- Project Initiation Phase 3- Project Planning Phase 4- Project Executing Phase
5- Project Monitor and Control Phase 6- Appendix-1, Case Study
7- Appendix-2, Exercise Forms 8- Appendix-3, List of Figures 9- Appendix-4, List of Tables 10- Appendix-5, List of Exercises
11- Appendix-6, List of Group Discussions
1- Introduction
PMP Exam Preparation Course Page 6
Group Discussion 1-1-Student’sExpectations
Group Discussion 1.1– Student’s Expectations
Please write down your expectations out of the course. This sheet will be collected, compiled to produce the overall class expectations and will be reviewed by the end of the course.
Your Notes _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________
3- Initiation Phase
PMP Exam Preparation Course Page 7
2. Project Management Framework
This section provides an introduction to the key concepts covered by the PMBOK® Guide. These concepts are valid to manage any project in any size. It will cover the following areas:
1- The purpose of the PMBOK® Guide 2- Project definition
3- Project management definition
4- Relationship among the Project Management, Program management and Portfolio Management
5- Project Management and Operations Management 6- The role of the project manager
7- Project management body of knowledge
2.1 Terms and Definitions
1. Project
A project is a temporary endeavor undertaken to create a unique product or service.
(Source: PMBOK® Guide - Fourth Edition, page 5)
A project is a sequence of unique and connected activities having one goal that must be completed by a specific time, within a budget and according to specification.
2. Program
A program is a group of related projects managed in a coordinated way to obtain benefits not available from managing them individually.
(Source: PMBOK® Guide - Fourth Edition, page 9) 3. Portfolio
A program is a collection of projects or programs and other work that are grouped together to facilitate effective management of that work to meet strategic business objectives.
(Source: PMBOK® Guide - Fourth Edition, page 8) 4. Project management
Project management is the application of knowledge, skills, tools, and techniques to project activities to meet projects requirements.
(Source: PMBOK® Guide – Release 4, page 6) 5. Project Portfolio Management
3- Initiation Phase
PMP Exam Preparation Course Page 8
Project portfolio management refers to the selection and support of projects or program investments, which are guided by the organization's strategic plan and available resources.
6. Standards
It is a document established by consensus and approved by recognized body that provides for common and repeated use rules, guidelines and regulations. They are imposed requirement which specifies product, process or service characteristics.
7. Project Management Office
A project management office (PMO) is an organizational unit to centralize and coordinate the management of projects under its domain.
PMOs can operate on a continuum, from providing project management support functions in the form of training, software, standardized policies, and procedures, to actual direct management and responsibility for achieving the project objectives.
3- Initiation Phase
PMP Exam Preparation Course Page 9
2.2 Comparative Overview
PROJECT
PROGRAMS PORTFOLIOS
Scope Project have defend
objectives, Scope is progressively elaborated throughout the project life cycle
Programs have a larger scope and provide more significant benefits.
Portfolios have a business scope that change with the strategic goals of the organization.
Change Project managers expect
change and implement processes to keep change managed and controlled.
The program manager must expect change from both inside and outside the program and be prepared to manage it.
Portfolio managers continually monitor changes in the broad environment.
Planning Project mangers
progressively elaborate high-level information into
detailed plans throughout the project life cycle.
Program managers develop the overall program plan and create high-level plans to guide detailed planning at the component level.
Portfolio managers create and maintain necessary processes and
communication relative to the aggregate portfolio.
Management Project managers manage
the project team to meet the project objectives
Program managers manage the program staff and the project managers; they provide vision and overall leadership.
Portfolio managers may manage or coordinate portfolio management staff.
Success Success is measured by
product and project quality, timeliness, budget
compliance, and degree of customer satisfaction.
Success is measured by the degree to which the
program satisfies the needs and benefits for which it was undertaken.
Success is measured in terms of aggregate performance of portfolio components.
Monitoring Project managers monitor
and control the work of producing the products, service or results that the project was undertaken to produce.
Program managers monitor the progress of program components to ensure the overall goals, schedules, budget, and benefits of the program will be met.
Portfolio managers monitor aggregate performance and value indicators.
Table 2-1- Comparative Overview
Source: PMBOK® Guide - Fourth Edition, page 9
2.3 Project Characteristics
Projects vary in size and complexity. Regardless the project nature, they all share common characteristics that should be maintained throughout the project life cycle. These characteristics are:
Unique. There is no two identical projects
One time efforts. No second chance.
Defined duration
Defined output
Defined Budget
3- Initiation Phase
PMP Exam Preparation Course Page 10
Group Discussion 2-1- Which one is not a project
Group Discussion 2.1 – Which one is not a project?
Which one of the following list is not a project? I.e. does not match the project definition criteria? Justify your answers:
1. Building a bridge. 2. Painting the house. 3. Learning Tango dance. 4. Having a Family.
5. Implementing National Social Number. 6. Preparing a morning coffee.
Your Notes _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________
3- Initiation Phase
PMP Exam Preparation Course Page 11
2.4 Projects vs. Operational Work:
Projects in nature are one time effort, as opposed to operations, which is a repetitive effort that is systematically repeated on periodical way. Although they are different in their nature, and hence in the way they are managed, yet they share the following characteristics:
Performed by people
Constrained by limited resources
Planned, executed, and controlled. Also, Projects and operations differ in that:
Operations are ongoing and repetitive, while projects are temporary and unique.
Operational work can be thought of repetitive work that each one is comprised of many related small projects.
2.5 Project Constraints
They are the known factors that limit the project teams’ options. Three main constraints from which, other derivates are produced:
1- Time (Schedule) 2- Budget (Cost)
3- Specifications (Quality)
Project Success Criteria
Projects are said to be successful when the project team manages to complete the project within the agreed upon (contracted) constrains. Generally speaking the project is successful if it is completed:
Within time (schedule)
Within cost (budget)
3- Initiation Phase
PMP Exam Preparation Course Page 12
A project may be sensitive to one of those constraints, but once contract is signed, they are all important and the project manager should adhere to all constraints.
3- Initiation Phase
PMP Exam Preparation Course Page 13
Group Discussion 2-2-Project Constraints
Group Discussion 2.2– Project Constraints
From your perspective, and considering the nature of business of your organization, which of the following constraints is more important?
1. Cost 2. Time 3. Budget Your Notes _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________
3- Initiation Phase
PMP Exam Preparation Course Page 14
2.6 Role of a Project Manager
The project manager is the maestro who orchestrates all the project activities. By doing the analogy with the maestro, the project team will never perform in harmony unless the project manager leads the team and guides each team member to his / her role of the project. The project manager job is a full time job that requires the project manager doing many activities that are not limited to, but include the following:
Acts as the single point of contact on the project.
Planning and organizing the work
Managing the day-to-day activities of a project
Delivering the project deliverables to the client
Identifying potential stakeholders
2.7 Project Stakeholders
Projects are done by people, for people to produce products that will be used by other people. The combined people of these three groups (done by, for, to be used) is called “Stakeholders”. Stakeholders are defined as “any one impacts the project positively or negatively”. The stakeholder list includes, but not limited to:
Project Manager
Customer
Performing organization, owners, government agencies
Project Sponsor
Developing Team
Internal external users
End user
Society, citizens
Others: owners, funders, suppliers
It is the project manager’s responsibility to identify the project stakeholders, as he will need to communicate with them throughout the project life cycle. Missing any stakeholders may lead to miscommunication problems that may jeopardize the project success.
3- Initiation Phase
PMP Exam Preparation Course Page 15
2.8 Project Organization Structure
Organization structure influences the way how projects are managed. The degree of the project management maturity and its project management system also has a high impact on the project success. Organization structure is an organizational environmental factor which affects the resources availability and how they are controlled. It also affects the degree of the authorities of the project manager in the decision making process. Below are the basic organization structures that PMBOK® Guide identifies:
Functional Matrix Weak matrix Balanced matrix Strong matrix Projectized Composite
The PMBOK® Guide is addressing the “Project” organization structure and not the “Company” organization structure. Most companies are based on Functional organization structure, but a project manager in this company can manage a project(s) based on Functional project organization and at the same time other project(s) based on Matrix organization structure.
2.8.1 Functional Project Organization
This is the classical functional organization. In this structure, each employee has one clear superior. Staff members are grouped by specialty area that is called departments or divisions. These areas may be divided further down to a lower level of hierarchy, but they all share the fact that each employee has one clear superior.
Figure 2-1- Functional Origination
Source: PMBOK® Guide - Fourth Edition, page 29 Staff Chief Executive Officer Staff Functional Manager 3 Functional Manager 2 Staff Staff Staff Staff Functional Manager 1 Staff Staff Staff Project Coordination
3- Initiation Phase
PMP Exam Preparation Course Page 16
2.8.2 Matrix Organization
Projects that need to be implemented and managed across divisions need an organizational model that allows communication across divisions. The classical functional organizational will not fit here, as communication between the project manager and the team members should be very fast and does not tolerate the bureaucracy of the functional organization. A new organizational structure is applied here. It is called Matrix, as it works across organization in rows and columns like the mathematical matrix structure. There are three types of matrix organizations:
1. Weak 2. Strong 3. Balanced
1- Weak Matrix Organization
In this organizational structure, many of the functional organization features are maintained. The project manager role is more of a coordinator or expeditor. The project manager can work in this model on part time basis.
Figure 2-2- Weak Matrix Origination
Source: PMBOK® Guide - Fourth Edition, page 29
2- Strong Matrix Organization
This structure requires a full time project manager with considerable authority. Based on the project size, he may be assisted with a full time administrative staff to help in the different project administration functions. This model fits with projects that need high authority project manager. In many cases, the company needs to be structured in a
Staff Chief Executive Officer Staff Functional Manager 3 Functional Manager 2 Staff Staff Staff Staff Functional Manager 1 Staff Staff Staff Project Coordination
3- Initiation Phase
PMP Exam Preparation Course Page 17
certain way to serve this model. A PMO “Project Management Office” is an example of this implementation.
Figure 2-3- Strong Matrix Origination
Source: PMBOK® Guide - Fourth Edition, page 30
3- Balanced Matrix Organization
This model does not provide a full authority to the project manager, yet, it gives him/her enough authority to manage the resources. This model fits with projects that require managing projects across divisions and do not need a high authority project manager.
Figure 2-4- Balanced Matrix Origination
Source: PMBOK® Guide - Fourth Edition, page 30
Staff Staff Staff Staff Staff Staff Project Coordination Project Manager Project Manager Project Manager Staff Chief Executive Officer Staff Functional Manager 3 Functional Manager 2 Staff Functional Manager 1 Manager of Project Managers Staff Chief Executive Officer Staff Functional Manager 3 Functional Manager 2 Staff Project Manager Staff Staff Functional Manager 1 Staff Staff Staff Project Coordination
3- Initiation Phase
PMP Exam Preparation Course Page 18
2.8.3 Projectized Organization
This is the model that the project manager exercises the highest level of authority. Most of the company employees are co-located and involved in the project work.
Figure 2-5- Projectized Origination
Source: PMBOK® Guide - Fourth Edition, page 31
2.9 Organizations Characteristics
Functional Matrix Projectized
Weak Balanced Strong
Project Manager’s Authority
Little or None Limited Low to
Moderate Moderate to High High to Almost Total Resource Availability
Little or None Limited Low to
Moderate Moderate to High High to Almost Total Who controls the Budget? Functional Manager Functional Manager Mixed Project Manager Project Manager Project manager’s role
Part-Time Part-Time Full-Time Full-Time Full-Time
PM admin. Staff Part-Time Part-Time Part-Time Full-Time Full-Time
Table 2-2- Organizational Influence on Projects
Source: PMBOK® Guide - Fourth Edition, page 28 Staff Chief Executive Officer Staff Project Manager 3 Project Manager 2 Staff Staff Project Manager 1 Staff Staff Staff Project Coordination Staff Staff
3- Initiation Phase
PMP Exam Preparation Course Page 19
2.10 Life Cycles and Process Groups
Projects are exactly like people. They grow over time. They are created (incepted), grow (managed) and die (close out). This forms a typical life cycle that projects go through. There two interdependent life cycles:
1- Project Life Cycle
2- Project Management Life Cycle
2.10.1 The Project Life Cycle
This is a product based cycle, through which the product of the project goes through. People involved in this are technical people (accountants, engineers,
programmers, architect, lawyers etc.)
They need to have a strong technical knowledge in their expertise area and they do not need to possess strong project
management knowledge,
although having it is a plus.
Figure 2-6- Project Life Cycle
2.10.2 The Project Management Life Cycle
This is a project based cycle, through which the project goes through. The project manager will manage the project based on this cycle. Each phase will contain many project
management activities. Project managers need to have a strong knowledge in the different project management knowledge areas, and do not need, although will be a plus, to have a strong business knowledge.
Figure 2-7- Management Project Life Cycle
2.11 Process Groups
1- Initiating Process Group. Defines and authorizes the project or a project phase.
3- Initiation Phase
PMP Exam Preparation Course Page 20
2- Planning Process Group. Defines and refines objectives, and plans the course of action required to attain the objectives and scope that the project was undertaken to address.
3- Executing Process Group. Integrates people and other resources to carry out the project management plan for the project
4- Monitoring and Controlling Process Group. Regularly measures and monitors progress to identify variances from the project management plan so that corrective actions can be taken when necessary to meet project objectives.
5- Closing Process Group. Formalizes acceptance of the product, service or result and brings the project or a project phase to an orderly end.
Figure 2-8- Project Process Groups
2.12 Interaction between Phases
The process groups explained above are not to be performed one time only across the project life cycle, but also will be done within each project phase. From the project management perspective, each phase is treated as a complete project that includes all the project management process groups as illustrated in the following figure.
3- Initiation Phase
PMP Exam Preparation Course Page 21
Figure 2-9- Project Process Groups Interaction
Process groups are not discrete. In other words, they should not be done and completed sequentially. There are some overlaps between them as illustrated in the following figure.
Figure 2-10- Process Group Overlapping
2.13 PMI Knowledge Areas
Project Management Institute (PMI) defined the following knowledge areas that are needed to be known by the professional project managers:
1- Project Integration Management 2- Project Scope Management 3- Project Time Management 4- Project Cost Management 5- Project Quality Management
6- Project Human Resources Management 7- Project Communication Management 8- Project Risk Management
3- Initiation Phase
PMP Exam Preparation Course Page 22
On top of the above areas, the “Professional Responsibility” supplement was added. It is not considered as a tenth area, but will be included in the PMP exam preparation test with a relatively low weight.
3- Initiation Phase
PMP Exam Preparation Course Page 23
Project Management Process Groups and Knowledge Area Mapping Note: Numbering starts form 4, to match the numbering of the PMBOK® Guide
Knowledge Areas
Project Management Process Groups Initiating Process Group Planning Process Group Executing Process Group Monitoring & Controlling Process Group Closing Process Group 4. Project Integration Management 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Execution 4.4 Monitor and Control Project Work 4.5 Perform Integrated Change Control 4.6 Close Project or Phase 5. Project Scope Management 5.1 Collect Requirements 5.2 Define Scope 5.3 Create WBS 5.4 Verify Scope 5.5 Control Scope 6. Project Time Management 6.1 Define Activities 6.2 Sequence Activities 6.3 Estimate Activity Resources 6.4 Estimate Activity Durations 6.5 Develop Schedule 6.6 Control Schedule 7. Project Cost Management 7.1 Estimate Costs 7.2 Determine Budget 7.3 Control Costs 8. Project Quality Management
8.1 Plan Quality 8.2 Perform Quality Assurance 8.3 Perform Quality Control 9. Project Human Resource Management 9.1 Develop Human Resource Plan 9.2 Acquire Project Team 9.3 Develop Project Team 9.4 Manage Project Team 10. Project Communications Management 10.1 Identify Stakeholders 10.2 Plan Communications 10.3 Distribute Information 10.4 Manage Stakeholder Expectations 10.5 Report Performance 11. Project Risk Management 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Monitor and Control Risks 12. Project Procurement Management
12.1 Plan Procurements 12.2 Conduct Procurements
12.3 Administer Procurements
12.4 Close Procurements
Table 2-3- Project Management Process Groups and Knowledge Area Mapping
3- Initiation Phase
PMP Exam Preparation Course Page 24
Initiating Process Group
4.1 Develop Project Charter 10.1 Identify Stakeholders
3- Initiation Phase
PMP Exam Preparation Course Page 25
Planning Process Group
4.2 Develop Project Management Plan 5.1 Collect Requirements
5.2 Define Scope 5.3 Create WBS 6.1 Define Activities 6.2 Sequence Activities
6.3 Estimate Activity Resources 6.4 Estimate Activity Durations 6.5 Develop Schedule
7.1 Estimate Costs 7.2 Determine Budget 8.1 Plan Quality
9.1 Develop Human Resource Plan 10.2 Plan Communications
11.1 Plan Risk Management 11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses
12.1 Plan Procurements
3- Initiation Phase
PMP Exam Preparation Course Page 26
Executing Process Group
4.3 Direct and Manage Project Execution 8.2 Perform Quality Assurance
9.2 Acquire Project Team 9.3 Develop Project Team 9.4 Manage Project Team 10.3 Distribute Information
10.4 Manage Stakeholder Expectations 12.2 Conduct Procurements
3- Initiation Phase
PMP Exam Preparation Course Page 27
Monitoring & Controlling Process Group 4.4 Monitor and Control Project Work 4.5 Perform Integrated Change Control 5.4 Verify Scope
5.5 Control Scope 6.6 Control Schedule 7.3 Control Costs
8.3 Perform Quality Control 10.5 Report Performance 11.6 Monitor and Control Risks 12.3 Administer Procurements
3- Initiation Phase
PMP Exam Preparation Course Page 28
Closing Process Group
4.6 Close Project or Phase 12.4 Close Procurements
Figure 2-15- Closing Process Group
Project Management Process Interaction
3- Initiation Phase
PMP Exam Preparation Course Page 29
3. Project Initiation Phase
Project initiation phase is the phase in which the project idea is incepted and a decision is made whether the project will be selected by the organization for implementation or will be postponed for a later date or will be rejected. This phase combines the following two processes, within the initiation process group:
4.1 Develop Project Charter 10.1 Identify Stakeholders
3- Initiation Phase
PMP Exam Preparation Course Page 30
3.1 Develop Project Charter
Figure 3-1- Develop Project Charter Process
Source: PMBOK® Guide – Fourth Edition, page 73 Definition
Develop Project Charter is the process of developing a document that formally authorizes a project or a phase and documenting initial requirements that satisfy the stakeholders' needs and expectations.
3- Initiation Phase
PMP Exam Preparation Course Page 31
Process Interaction
Figure 3-2 - Develop Project Charter – Process Interaction
3.1.1 Inputs to Develop Project Charter 1. Project statement of work
2. Business case 3. Contract (if available)
4. Enterprise environmental factors 5. Organizational process assets 1. Project statement of work
Statement of work is the document that describes the project work. It contains the following:
Business needs
Product scope description
Strategic plan 2. Business case
It is the document that includes the necessary information from the business perspective. It contains:
Market demand
3- Initiation Phase
PMP Exam Preparation Course Page 32
Customer request
Technologies advance
Legal requirement
Ecological impacts
Social need 3. Contract (if available)
A contract from the customer’s acquiring organization is an input if the project is being done for an external customer.
4. Enterprise environmental factors
Governmental or industry standards
Organization infrastructure
Marketplace conditions 5. Organizational process assets
Organizational standard processes, policies, and standardized process definitions for use in the organization
Templates (e.g. project charter template)
Historical information and lessons learned knowledge base
3.1.2 Tools and Techniques for Develop Project Charter 1. Expert judgment
1. Expert judgment
Expert judgment is used to assess the input used to develop the charter. The expertise is obtained from:
Other units from the organization
Consultants
Stakeholders, including customers or sponsors
Professional and technical associations
Industry groups
Subject matter experts
Project management office (PMO)
3.1.3 Outputs of Develop Project Charter 1. Project charter
1. Project charter
The project charter documents the business needs and the current customer requirements by addressing:
3- Initiation Phase
PMP Exam Preparation Course Page 33
Project purpose or justification
Measurable project objectives and related success criteria
High-level requirements
High-level project description
High-level risks
Summary milestone schedule
Summary budget
Project approval requirements (what constitutes project success, who decides the project is successful and who signs off on the project)
Assigned project manager, responsibility and authority level
Name and authority of the sponsor or other person (s) authorizing the project charter.
3- Initiation Phase
PMP Exam Preparation Course Page 34
Exercise 3-1 - Develop Project Charter
Exercise 3.1 – Develop Project Charter
In the provided case study in Appendix 1, develop the project charter.
Note: use the following form. Your Notes _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________
3- Initiation Phase
PMP Exam Preparation Course Page 35
3.2 Identify Stakeholders
Figure 3-3- Identify Stakeholders Process
Source: PMBOK® Guide – Fourth Edition, page 246 1.Project charter 2.Procurement documents 3.Enterprise environmental factors 4.Organizational process assets
Inputs
1. Stakeholder analysis 2. Expert judgment Tools & Techniques 1.Stakeholder register 2.Stakeholder management strategyOutputs
DefinitionIdentify Stakeholders is the process of identifying all people or organizations impacted by the project, and documenting relevant information regarding their interests, involvement, and impact on project success.
3- Initiation Phase
PMP Exam Preparation Course Page 36
Process Interaction
Figure 3-4Identify Stakeholders – Process Interaction
Dimensions of Communication Activities
The project manager is the center of the communication hub within the
project. He communicates will all project stakeholders in many different levels, as follows:
Internal and External
Formal and Informal
Vertical and Horizontal
Official and unofficial
Written and Oral
Verbal and Non-Verbal
3.2.1 Inputs to Identify Stakeholders 1. Project charter
2. Procurement documents
3. Enterprise environmental factors 4. Organizational process assets
3- Initiation Phase
PMP Exam Preparation Course Page 37
3.2.2 Tools and Techniques for Identify Stakeholders 1. Stakeholder analysis
2. Expert judgment 1. Stakeholder analysis
It is the technique of systematically gathering and analyzing qualitative and quantitative information to determine whose interest should be taken into account. It defines the interest, expectations and influence of stakeholders and relate them to the purpose of the project.
Steps of Stakeholders Analysis
Step 1: Identify all potential project stakeholders and relevant information.
Step 2: Identify the potential impact or support each stakeholder could generate:
Power/interest grid
Power/influence grid
Influence/impact grid
Salience model
Step 3: Assess how key stakeholders are likely to react or respond in various situations.
Power / Interest Grid
Power interest grid is the method of grouping the stakeholders based on their level of authority (power) and their level of concern (interest) regarding the project outcome.
Figure 3-5 Power / Interest Grid
2. Expert judgment Keep Satisfied Monitor Keep Informed Manage Closely
Interest
Power
Low High High G F A D H B E C3- Initiation Phase
PMP Exam Preparation Course Page 38
Identifying the project stakeholders requires high level of knowledge and expertise in order not to miss any one who could be with an important role in the project and missing him/her may damage the project outcome. Experts include, but not limited to the following:
Senior management
Other units within the organization
Identified key stakeholders
Project managers who have worked on projects in the same area
Subject matter experts (SMEs) in business or project area
Industry groups and consultants, and
Professional and technical associations 3.2.3 Outputs of Identify Stakeholders 1. Stakeholder register
2. Stakeholder management strategy 1. Stakeholder register
Stakeholder register is the repository that contains all the details about each stakeholder, including the following:
Identification information
Assessment information
Stakeholder classification 2. Stakeholder management strategy
Based in the identified stakeholders, included in eth stakeholders’ register, a strategy will be assigned to each key stakeholder. The strategy will include elements such as:
Key stakeholders who can significantly impact the project
Level of participation in the project desired for each identified stakeholder, and
3- Initiation Phase
PMP Exam Preparation Course Page 39
Exercise 3-2 - Stakeholder Analysis
Your Notes _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________
Exercise 3.2 – Stakeholder Analysis
In the provided case study, analyze the stakeholder and communication needs by providing the following information:
1. Stakeholder 2. Organization 3. Position
4. Communication Needs
4- Planning Phase
PMP Exam Preparation Course Page 40
4. Project Planning Phase
Project planning phase is the phase where all the project plans are created. It is the time where all project activities are identified, assigned and scheduled. During the phase, the following twenty planning processes are executed:
4.2 Develop Project Management Plan 5.1 Collect Requirements
5.2 Define Scope 5.3 Create WBS 6.1 Define Activities 6.2 Sequence Activities
6.3 Estimate Activity Resources 6.4 Estimate Activity Durations 6.5 Develop Schedule
7.1 Estimate Costs 7.2 Determine Budget 8.1 Plan Quality
9.1 Develop Human Resource Plan 10.2 Plan Communications
11.1 Plan Risk Management 11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses
4- Planning Phase
PMP Exam Preparation Course Page 41
4.1 Develop Project Management plan
Figure 4-1 - Develop Project Management plan Process
Source: PMBOK® Guide – Fourth Edition, page 78 1.Project charter 2.Outputs from planning processes 3.Enterprise environmental factors 4.Organizational process assets
Inputs
1. Expert judgment Tools & Techniques 1.Project management planOutputs
DefinitionDevelop Project Management Plan is the process of documenting the actions necessary to define, prepare, integrate and coordinate all subsidiary plans.
4- Planning Phase
PMP Exam Preparation Course Page 42
Process Interaction
Figure 4-2Develop Project Management plan – Process Interaction
4.1.1 Inputs to Develop Project Management plan 1- Project charter
2- Outputs from all planning processes 3- Enterprise environmental factors 4- Organizational process assets
4.1.2 Tools and Techniques for Develop Project Management plan
1- Expert judgment 1. Expert judgment
In this process, expert judgment is utilized to:
Tailor the process to meet the project needs
Develop technical and management details
Determine the requires resources and skill levels
4- Planning Phase
PMP Exam Preparation Course Page 43
4.1.3 Outputs of Develop Project Management plan 1- Project management plan
1. Project management plan
The project management plan integrates and consolidates all of the subsidiary management plans and baselines from the planning processes and includes the project baseline and subsidiary plans Project Baseline
Project baselines include, but are not limited to:
Schedule baseline
Cost performance baseline, and
Scope baseline Subsidiary Plans
Subsidiary plans include, but are not limited
Scope management plan
Requirements management plan
Schedule management plan
Cost management plan
Quality management plan
Process improvement plan
Human resource plan
Communications management plan
Risk management plan
4- Planning Phase
PMP Exam Preparation Course Page 44
Exercise 4-1 - Change Management Process
Exercise 4.1 – Change Management Process
Change management plan is part of the overall project plan, discuss the below change management process and reflect it to your environment.
Initial assessment, appoint assessor Analysis, evaluation, assess Impact Complete chg. req. Impact Study Agree Make changes File Change Request Initial review &
discussion Discuss/ negotiate with Tech.Lead Call Change Mgnt. Meeting Agree Stop Raise Change Request Form START Tech. Lead Assessor Assessor Review assessment Tech. Lead Yes No Impact Dev. Team Stop Initiator Yes No No Yes Change has an Impact
Amend Agreements Update Proj. Plan
Re-baseline Will it affect Cost or timescales No Change Reqest Endorsement by Steering Committee Yes
4- Planning Phase
PMP Exam Preparation Course Page 45
4.2 Collect Requirements
Figure 4-3- Collect Requirements Process
Source: PMBOK® Guide - Fourth Edition, page 105 4.2.1 Inputs to Collect Requirements
1- Project Charter 2- Stakeholder Register
1- Project Charter: is used to provide the high-level project requirements that can be developed.
2- Stakeholder Register: is used to identify stakeholders that can provide information on detailed project and product requirements. 4.2.2 Tools and Techniques for Collect Requirements
1- Interviews 2- Focus Groups 1.Project charter 2.Stakeholder register
Inputs
1. Interviews 2. Focus groups 3. Facilitated workshops 4. Group creativity techniques 5. Group decision making techniques 6. Questionnaires and surveys 7. Observations 8. Prototypes Tools & Techniques 1.Requirements documentation 2. Requirements management plan 3.Requirements traceability matrixOutputs
DefinitionCollect requirements is the process of defining and documenting stakeholders’ needs to meet the project objectives.
4- Planning Phase
PMP Exam Preparation Course Page 46
3- Facilitated Workshops 4- Group Creativity Techniques
1. Interviews
They are formal or informal approach to discover information from stakeholders by talking to them directly. It is typically performed by asking prepared and spontaneous questions and recording the responses. Interviews are often conducted “one-on-one”, but may involve multiple interviewers and/or multiple interviewees. Interviewing experienced project participants, stakeholders and subject matter experts can aid in identifying and defining the features and functions of the desired project deliverables.
2. Focus Groups
Bring together pre-qualified stakeholders and subject matter experts to learn about their expectations about a proposed product. A trained moderator guides the group through an interactive discussion, designed to be more conversational than a one-on-one interview. 3. Facilitated Workshops
Requirements workshops are focused sessions that bring key cross-functional stakeholders together to define product requirements. Workshops are considered as primary techniques for quickly defining cross-functional requirements and reconciling stakeholder differences. These differences can be discovered and resolved more quickly than in individual interviews
4. Group Creativity Techniques
Brainstorming
Nominal group technique
Delphi Technique
Idea/mind mapping
Affinity diagram
4.2.3 Outputs of Collect Requirements 1- Requirements documentation
2- Requirements management plan 3- Requirements traceability matrix
1. Requirements documentation
Requirements Documentation describes how individual requirements meet the business need of the project. Requirements may start out at a
4- Planning Phase
PMP Exam Preparation Course Page 47
high level and become progressively more detailed as more information is known. Before being baselined, requirements must be unambiguous, traceable, complete, consistent, and acceptable to key stakeholders.
Requirements Documentation Components
There is no standard template to produce the requirements document. But below are its general components:
Business need or opportunity to be seized.
Business and project objectives for traceability
Functional requirements, describing business process, information and interaction with the product as appropriate which can be documented textually in a requirements list
Non-functional requirements such as level of service, performance, safety,
security, compliance, supportability, retention etc.
Quality requirements
Acceptance criteria.
Business rules stating the guiding principles of the organization
Impacts to other organizational areas
Impacts to other entities inside or outside
Support and training requirements
Requirements assumptions and constraints
2. Requirements management plan
It documents how requirements will be analyzed, documented and managed throughout the project. It contains the following components:
How requirements activities will be planned, tracked and reported.
Configuration management activities such as how changes to the product, service or result requirements will be initiated, how impacts will be analyzed
Requirements prioritization process
Product metrics that will be used and the rationale for using them
Traceability structure that is which requirements attributes will be captured on the traceability matrix and to which other project documentation requirements will be traced.
The Delphi Technique
It is an anonymous way to reach a consensus of experts on a subject. It involves the following:
Questionnaire to solicit
ideas from the experts
Responses are
submitted anonymously, compiled, and then circulated to the experts for review
4- Planning Phase
PMP Exam Preparation Course Page 48
3. Requirements traceability matrix
It is a table that links requirements to their original business objective. This process includes:
Requirements to business needs, opportunities, goals, and objectives
Requirements to project objectives
Requirements to project scope/WBS deliverables
Requirements to product design
Requirements to product development
Requirements to test strategy and test scenarios, and
4- Planning Phase
PMP Exam Preparation Course Page 49
Group Discussion 4-1-Requirements Gathering Challenges
Group Discussion 4.1 – Requirements Gathering Challenges
Highlight the most problematic areas in the process of gathering requirements in your organization. Use the following as guidelines:
1. Lacking time to complete the requirement gathering process 2. Customers may not know what they really want
3. Too many changes
Your Notes _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________
4- Planning Phase
PMP Exam Preparation Course Page 50
Exercise 4-2-Create Project Charter
Exercise 4.2 – Create Project Charter
Based on the supplied case study, create the Project Charter that will provide a high authority for the project manager. Consider specifying the following:
1. Customer 2. Project Name 3. Project Description
4. Project Manager: Name and Authority Level 5. Business Needs
6. Issued By Manager
Note: Use form 9.1 in Appendix 2
Your Notes _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________
4- Planning Phase
PMP Exam Preparation Course Page 51
4.3 Define Scope
Figure 4-4- Define Scope Process
Source: PMBOK® Guide - Fourth Edition, page 112 1.Project charter 2.Requirements documentation 3.Organizational process assets
Inputs
1. Expert judgment 2. Product analysis 3. Alternatives identification 4. Facilitated workshops Tools & Techniques 1.Project scope statement 2.Project document updatesOutputs
DefinitionDefine Scope is the process of developing a detailed description of the project and product.
4- Planning Phase
PMP Exam Preparation Course Page 52
Group Discussion 4-2- Scope Creep Indicators
Group Discussion 4.2– Scope Creep Indicators
From your perspective, what do you think of the following three statements?
1. Exceeding Customer Expectations 2. Delivering State of the art products
3. Providing low cost items, that may not cost anything free of charge
Your Notes
1. Exceeding Customer Expectations
_________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________
2. Delivering State if the art products
_________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________
3. Providing low cost items, that may not cost anything free of charge _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________
4- Planning Phase
PMP Exam Preparation Course Page 53
4.3.1 Inputs of Define Scope 1- Project charter
2- Requirements documentation 3- Organizational process assets:
4- Policies, procedures, and templates for a project scope statements 5- Project files from previous projects, and
6- Lessons learned from previous phases or project
4.3.2 Tools and Techniques for Define Scope 1- Expert judgment
2- Product analysis
3- Alternatives identification 4- Facilitated workshops
1. Expert judgment
This is the tools of getting the opinion of experts who have had previous experience in similar projects. Experts can be obtained from the following categories:
Other units within the organization
Consultants
Stakeholders including customers or sponsors
Professional and technical associations
Industry groups and
Subject matter experts 2. Product analysis
Each application area has one or more generally accepted methods for translating high-level product descriptions into tangible deliverables. Product analysis includes techniques such as:
Product breakdown Systems analysis Requirements analysis System engineering Value engineering Value analysis. 3. Alternatives identification
Identifying alternatives is a technique used to generate different approaches to execute and perform the work of the project. A variety of general management techniques can be used such as brainstorming, lateral thinking, pair wise comparisons, etc.
4- Planning Phase
PMP Exam Preparation Course Page 54
4.3.3 Outputs of Define Scope 1- Project scope statement 2- Project document updates
1. Project scope statement
This document describes, in detail, the projects deliverables and the work required to create those deliverables.
It also provides a common understanding of the project scope among project stakeholders. The Project Scope Statement may contain explicit scope exclusions that can assist in managing stakeholder expectations. Below are some of the benefits of the project scope statement:
Help the project team to perform more detailed planning
Guides the project team’s work during execution
Provides the baseline for evaluating whether requests for changes or
additional work are contained within or outside the project’s boundaries
Scope Statement Content
As the details are not always ready from day one of the project, so this document may be compiled progressively over a period of time. The contents of this document include, but not limited to the following:
Product scope description
Product acceptance criteria
Project deliverables
Work breakdown structure
Project exclusions Project constraints Project assumptions Project boundaries Project resources Project milestones Project stakeholders Project Risks Identifying Constraints
Examples of constraints that may be faced during a project:
Budget
Schedule
People
Facilities and Equipment
Constraints:
Are known factors, which limit the project team’s options.
Assumptions:
Are factors that, for planning purposes, are considered to be true, real, or certain. They need to be validated during the course of project planning
4- Planning Phase
PMP Exam Preparation Course Page 55
Fault tolerant objectives
Portability requirements
The real world Identifying Assumptions
Assumptions are identified and documented during the planning process as they affect all aspects of planning. They need to be verified to ensure that they are true. In case if it is proven to be false, then re-planning is needed. They always carry a certain degree of risk
Unquantifiable Expectations
Some expectations “requirements” may be difficult to quantify, they need to be quantified as much as possible, and otherwise they become a risk item of unclear requirements. Examples of these are:
Customer satisfaction
Company Image
Community Perception 2. Project Document Updates
As mentioned earlier, the project management team does not always have answers to all planning questions. Facts come up during different times during the project life cycle. This entails changing the project related documents as and when new facts come up. Changes also come due handling authorized change requests. Examples of the documents that will be changed in this process are:
Stakeholder register
Requirements documentation
4- Planning Phase
PMP Exam Preparation Course Page 56
Exercise 4-3-Create Scope Statement
Exercise 4.3 – Create Scope Statement
Based on the supplied case study, create the Project Scope Statement that will highlight the minimum project information. Consider this as the business case used in your organization. Include the following information:
1. Project Name 2. Project Manager
3. Business Needs (project justification) 4. Summary of Product Description 5. Deliverables
6. Objectives (cost, schedule, quality measures, other) 7. Project Constraints
8. Project Risks (high level) Note: Use form 9.2 in Appendix 2
Your Notes _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________