• No results found

D EVELOP S CHEDULE

In document PMP Student Guide (Page 85-94)

4. Project Planning Phase

4.9 D EVELOP S CHEDULE

Figure ‎4-20- 6.5 Develop Schedule Process Source: PMBOK® Guide - Fourth Edition, page 152 1. Activity list

2. Activity attributes 3. Project schedule network diagrams 4. Activity resource

requirements 5. Resource calendars 6. Activity duration

estimates 7. Project scope

statement 2. Critical path

method 3. Critical chain

method 4. Resource

leveling

5. What-if analysis 6. Applying leads

and lags

Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.

Source: PMBOK® Guide – Fourth Edition, page 152

4- Planning Phase

PMP Exam Preparation Course Page 86

Process Interaction

Ø Organizational process assets Ø Enterprise

environmental factors

Ø Project Documents Updates Ø Project schedule

network diagrams Ø Activity list Ø Activity attributes

Involved Documents (IN) ØActivity list

ØActivity attributes ØProject schedule network

diagrams 5.2 Define Scope 9.2 Acquire

Project Team

Ø Project Scope Statement

Ø Project Schedule Ø Activity duration

estimates Ø Activity resource

requirements

Ø Schedule data

Ø Resource Calendars

Ø Schedule baseline

Source: PMBOK® Guide – Fourth Edition Diagram Developed by Techno Management Ø

Figure ‎4-21- Develop Schedule – Process Interaction

Schedule Constraints

Two categories of constraints are directly related to scheduled development:

Imposed Dates, they are:

- Key Events - Major Milestones Example of Constraints:

Constraint Type Description

Start No Later Than The task must start before or on

that date.

Start No Earlier Than The task may not start before this

date.

Finish No Later Than The task must be completed by

that date.

Finish No Earlier Than The task may not be completed

before this date.

4.9.1 Inputs to Develop Schedule 1. Activity list

2. Activity attributes

3. Project schedule network diagrams

4- Planning Phase

PMP Exam Preparation Course Page 87

4. Activity resource requirements 5. Resource calendars

6. Activity duration estimates 7. Project scope statement

8. Enterprise environmental factors 9. Organizational process assets Project Calendars

Project and resource calendars identify when work is allowed. They affect all resources. Resource calendars affect only that resource or group of resources.

4.9.2 Tools and Techniques for Develop Schedule 1. Schedule network analysis

2. Critical path method 3. Critical chain method 4. Resource leveling 5. What-if analysis

6. Applying leads and lags 7. Schedule compression 8. Scheduling tool

1. Schedule network analysis

Schedule network analysis is a technique that generates the project schedule. It employs various analytical techniques, such as:

 Critical path method

 Critical chain method

 What-if analysis

 Resource leveling

2. Critical path method

The critical path method calculates the theoretical early start and finish dates and late start and finish dates without regard for any resource

4- Planning Phase

PMP Exam Preparation Course Page 88

Free Float: is the amount of time that an activity can be delayed without delaying the early start of any immediately following activities.

Calculating Path and Float Forward Pass:

 Early Start (ES) = Total of task durations for all precedent (necessary) tasks

 Early Finish (EF) = ES + Task Duration Backward Pass:

 Late Finish (LF) = Last day of project – Duration of sequential (necessary) tasks to end of project

 Late Start (LS) = LF – Task Duration Float = LF – ES – Task Duration

Task Coding Convention - Early Start = ES - Early Finish = EF - Late Start = LS - Late Finish = LF - Duration = DU Process

a. Construct the Network Diagram b. Apply the Task Duration

c. Calculate the Forward Pass d. Calculate the Backward Pass e. Calculate Floats

a. Construct the Network Diagram

EF

LS LF

ES

DU

4- Planning Phase

PMP Exam Preparation Course Page 89

b. Apply the Task Duration

c. Calculate the Forward Pass

d. Calculate the Backward Pass

58

4- Planning Phase

PMP Exam Preparation Course Page 90

61

C

5

9 10

4

1

B

4

6 9

1

3

A

1

0 1

0

1

F

13

7 13

7

6

E

7

1 7

1

6

D

10

10 13

7

3

G

15

13 15

13

2

4- Planning Phase

PMP Exam Preparation Course Page 91

e. Calculate Floats

3. Critical chain method

The critical path methods calculates the theoretical early start and finish dates, and late start and finish dates without regard for any resource limitations. This is done by performing a forward and backward pass analysis through the schedule network. The resulting early and late start and finish dates are not necessarily the project schedule; rather they indicate the time periods within which the activity could be scheduled.

4. Resource leveling

Resource leveling is necessary when resources are over-allocated such as when the resource is:

- Assigned to two or more activities during the same time period - Shared or critical required resources are only available at certain

times

- Only available in limited quantities.

Resource leveling can often cause the original critical path to change.

It mostly results in extended schedule

Figure ‎4-22- Resource Leveling

63

4- Planning Phase

PMP Exam Preparation Course Page 92

5. What-if analysis

This is based on the calculation of multiple project durations with different sets of activity assumptions. “What-if analysis” using the logic in the network diagram. A well known technique of “What if analysis” is called Monte Carlo Analysis, it is:

- The most common technique.

- Distribution of probable results is defined for each activity, and then used to determine the distribution of probable results for the total project.

- Also used in Project Risk Management

6. Applying leads and lags

A lead allows an acceleration of the successor activity, while a lag directs a delay in the successor activity

7. Schedule compression

The two main techniques that are used to compress schedules are:

a- Fast tracking: A schedule compression technique in which phases or activities normally performed in sequence are performed in parallel.

b- Crashing: It is a schedule compression technique in which cost and schedule tradeoffs are analyzed to determine how to obtain the greatest amount of compression for the least incremental cost.

8. Scheduling tool

 MS Project

 Primavera

4.9.3 Outputs of Develop Schedule 1. Project schedule:

- Milestones charts - Bar charts

- Project schedule network diagrams 2. Schedule baseline

3. Schedule data

4. Project document updates:

- Activity resource requirements - Activity attributes

- Calendar - Risk register

4- Planning Phase

PMP Exam Preparation Course Page 93

Exercise ‎4-9- Develop Schedule

Exercise 4.9 – Develop Schedule

The following information and questions 1 through 9 refer to below network diagram

Assume that the work is on a single shift basis and will seven days per week until the job is done. The project is to begin on May 1.

B

H E

C A

F D

G

3

FS-2

1

3 4

5 4

2

7

1. What day in May will activity D have for its early finish date?

2. What is the free float for activity F?

3. What is the free float for activity D?

4. What is the critical path of the project?

5. What is the late start for activity F?

6. How long is the project in days?

7. What is the early start for activity F?

8. If there is a delay in activity F of six days, what is the effect on the project completion date?

9. What is the early finish date of activity A?

4- Planning Phase

PMP Exam Preparation Course Page 94

In document PMP Student Guide (Page 85-94)