• No results found

ITER CRYOGENIC SYSTEM ICEC-2014 LHe PLANTS PARALLEL OPERATION

N/A
N/A
Protected

Academic year: 2021

Share "ITER CRYOGENIC SYSTEM ICEC-2014 LHe PLANTS PARALLEL OPERATION"

Copied!
30
0
0

Loading.... (view fulltext now)

Full text

(1)

LHe PLANTS – PARALLEL OPERATION

ITER Organization

ITER CRYOGENIC SYSTEM ICEC-2014

The views and opinions expressed herein do not necessarily reflect those of the ITER Organization.

(2)

SUMMARY

1. LHe Plants: Schedule

Project Overall Schedule

Project Status

2. LHe Plants: Lay-Out

Cryoplant Building

Main Dimensions

3. LHe Plants: Main Characteristics

Cooling Power

Compressor Stations

Cold Boxes

4. LHe Plants: Process

Control Philosophy

(3)

• Project Overall Schedule

• Project Status

1. LHe PLANTS: SCHEDULE

6 years

ASSEMBLY

PRELIM.

FINAL DESIGN

10 months

12 Months

24 Months

INSTALLATION

15 Months

COMMISSIONING

22 Months

18 Months

PROCUREMENTS

Dec. 2012

Dec. 2018

(4)

• Cryoplant Building

• Main Dimensions

(5)

2. LHe PLANTS: LAY-OUT

CRYOPLANT BUILDING:

120 m x 45 m

Compressor Station:

33 m x 11 m

Oil Removal Skid:

~10 m x ~5 m

Cold Box With Panels:

21 m x 10 m

45 m

(6)

2. LHe PLANTS: LAY-OUT

(7)

COMPRESSOR STATION: 33m x 11m

2. LHe PLANTS: LAY-OUT

L

W

H

BUS

12 m

2.6 m

3.6 m

BLOCK

6 m

3.4 m

3.6 m

(8)

COLD BOXES:

21m x 4.2m – 140 tons

2. LHe PLANTS: LAY-OUT

L

W

H

BUS

12 m

2.6 m

3.6 m

BOX

21 m

4.2 m

4.2 m

(9)

2. LHe PLANTS: LAY-OUT

CRYOPLANT BUILDING:

120 m x 45 m

Compressor Station:

33 m x 11 m

Oil Removal Skid:

~10 m x ~5 m

Cold Box With Panels:

21 m x 10 m

45 m

(10)

3. LHe PLANTS: Characteristics

• LHe Plants

• Compressor Stations

• Cold Boxes

(11)

3. LHe PLANTS: Characteristics

ITER: 25 kW per Plant

CERN: 18kW per Plant

1 LHe Plant:

(12)

3. LHe PLANTS: Characteristics

ITER LHe Plants: ~ 75kW

3 LHe Plants:

Cryogenic Power / Plant: 25 kW

Cryogenic Power / Total:

75 kW

[ 40kW – 110 kW Pulsed]

CERN:

~ 140 kW

(13)

3. LHe PLANTS: Characteristics

3 COMPRESSOR STATIONS:

MYCOM Compressors: x 6 /Plant  x18 Total

Electrical Power:

8 MW /Plant  24 MW Total

1 PLANT

ea.

Type

Power ea.

Flow ea.

Flow Total

LP

X 4

400 L

1 100 kW

400 g/s

1 600 g/s

HP

X 2

400 S

2 500 kW

1 100 g/s

2 200 g/s

(14)

3. LHe PLANTS: Characteristics

3 COMPRESSOR STATIONS:

MYCOM Compressors: x 6 /Plant  x18 Total

Electrical Power:

8 MW /Plant 

24 MW Total

HEAT RECOVERY SYSTEM:

Heating Power:

12 MW

 1 Ton of Oil Equivalent per hour…

Process Heat is used to provide Heating to ITER Buildings.

(15)

3. LHe PLANTS: Characteristics

3 COLD BOXES:

AL Turbines:

x 4 /Plant

LN2 Consumption:

85 000 L/day Total

[ eq. to x 3 Trucks / day]

LN2 Plants on site to cover LHe Plants needs.

1 PLANT

Type

Efficiency

Power ea.

Flow ea.

Temp.

LN2

-

-

110 kW

LN2 250 g/s

80 K

Turbine 1

TC-4

77 %

15 kW

115 g/s

50 K

Turbine 2

TC-4

77 %

13 kW

170 g/s

30 K

Turbine 3

TC-4

77 %

11 kW

230 g/s

20 K

Turbine 4

TC-5

74 %

11 kW

1300 g/s

5 K

1 COLD BOX:

(16)

• Main Challenges

• Control Philosophy

• Three Plants in Parallel

4. LHe PLANTS: Process

(17)

4. LHe PLANTS: PROCESS

• Main challenges:

 Multiple Users

 Pulsed Loads

 3 LHe Plants in Parallel

110 kW eq. @ 4.5K

40 kW eq. @ 4.5K

75 %

25 %

65 % Variations

over 30 minutes

(18)

1 LHe PLANT:

4. LHe PLANTS: PROCESS

LHe Tank

LN2 Pre-Cooling

Turbo-Expanders

[x3]

Turbo-Expander

LHe Sub-Cooler

2 Stage Compressor Station

(19)

3 LHe PLANTS:

4. LHe PLANTS: PROCESS

P

L

40 kW

110 kW

0 kW

MIN

MAX

MIN

• MIN Load: 1 200L LHe accumulated

• MAX Load:

1 200L LHe consumed

- 210 g/s

+ 210 g/s

0 g/s

1 200L

1 200L

30 min

(20)

3 LHe PLANTS:

4. LHe PLANTS: PROCESS

P

L

1 200 L of VARIATION

175 000 L

~1 % of TOTAL VOLUME

15 000 L

For 3 Plants: 1 200L Level Variation ~1%

LHe Tank designed to store the entire ITER LHe Inventory

(21)

3 LHe PLANTS:

(22)

4. LHe PLANTS: PROCESS

P

(23)

4. LHe PLANTS: PROCESS

P

3 LHe PLANTS:

EXCESS CAPACITY SHARING: Take what you need!

L

L

L

(24)

4. LHe PLANTS: PROCESS

P

3 LHe PLANTS:

FLOW RETURN FROM USER !

L

L

L

(25)

4. LHe PLANTS: PROCESS

P

3 LHe PLANTS:

FLOW RETURN FROM USER ! MAIN CHALLENGE !

L

L

(26)

4. LHe PLANTS: PROCESS

P

3 LHe PLANTS:

FLOW RETURN FROM USER ! MAIN CHALLENGE !

L

L

L

T

T

T

(27)

4. LHe PLANTS: PROCESS

P

3 LHe PLANTS:

FLOW RETURN FROM USER ! MAIN CHALLENGE !

L

L

L

T

T

T

CONTROLLER

Up to 4 000 g/s

(28)

3 LHe PLANTS:

COMPRESSOR STATION SHARING

4. LHe PLANTS: PROCESS

COMPRESSOR STATION INTERCONNECTED:

Same LP Pressure:

Better GHe Flow sharing.

Efficient Mass Balance:

(29)

MAIN CONCLUSIONS:

SHe Production:

Users are served in priority.

Excess flow sent to the LHe Tank.

LHe from LHe Tank used for Sub-Cooler.

Users Return GHe Repartition:

Based on Temperature Monitoring.

Compressor Station:

Interconnected

More Robust

Better Mass and Flow Balance

(30)

THANK-YOU FOR YOUR ATTENTION

LHe PLANTS – PARALLEL OPERATION

ITER Organization

The views and opinions expressed herein do not necessarily reflect those of the ITER Organization.

References

Related documents

States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government

IN CLASS ASSIGNMENT: Make 2 contact sheets and 1 print Due: 2 rolls of 120 film developed/ bring in

The action taken to initiate library involvement in data management activities was to host a half-day data management symposium, with the target audience being researchers –

features, in terms of orbital velocities, radar cross section modulations, and Tsunami wave height, in order to validate new concepts for Tsunami early warning (providing

- If employer provides insurance, employee cannot receive subsidies to buy insurance on the exchanges, including for family coverage.. - Families with income < $24K will get

Cleveland Clinic first focused on increasing awareness of hypertension among all of the team members involved in patient care: clerical support staff, clinical support

The views and opinions expressed in this presentation are those of the author alone and do not necessarily reflect the views or policies of any other individual, institution

Therefore, we can estimate the mass flux of COM and soil particles and evaluate the effect of wind erosion on soil fertility using the AMS with the BSNE