PROJECT REFERENCE LIST
1 Whiteman Air Force Base, Missouri Storm Drainage Project
Project # F25606-94-C0020 September 94 - November 95
This project involved the installation of 8500 LF of storm drainage with 103 inlets, grading, seed and sod. The project was performed in the base housing area. ($789,000)
Contract Inspector: Roy Thomas 816-687-6281 2 Whiteman Air Force Base, Missouri Manhole Rehabilitation Project Project # F23606-96-C0013 March 96 - June 97
The contract was for the rehabilitation of 334 manholes, new frame/covers, and the replacement of existing manholes using the Permacast/Permaform process. ($739,000)
Contract Inspector: Roy Faulkner 816-687-6285
3 City of Topeka, Kansas Manhole Rehabilitation Project Project # 29089
April 97 - July 97
This contract was for the rehabilitation of 28 manholes using Permacast Cementitious liner, renewal of 16 manholes using the Permaform process of placing steel forms inside the existing manholes, wrapping the forms with PVC T-Lock lining, and pouring high strength fiber reinforced concrete.
($232,000)
Project Engineer: White, Martin, and Assoc. Robert A. Koopman, P.E. 913-233-8300
4 Jefferson County, Kansas Manhole Rehabilitation Project Lakeshore Estates-Perry Lake, Kansas September 97 - April 98
The rehabilitation of 129 manholes using the Permacast cementitious liner process. ($132,000) Project Engineer BG Consultants Inc.
Mark Bachamp, P.E. 913-537-7448 5 City of San Diego, CA.
Repair Sewer Manholes (So. of PS #1) JOC # 97-00006
October ‘97 to March ‘98
This project was for the renewal of 10 manholes using the Permaform steel forms process and PVC T-Lock lining. Special conditions: This project was conducted in existing manholes over an active Eight foot interceptor line. Safety platforms where placed over the large diameter pipe to allow crews
To work safely inside the manholes. Additional S.C.B.A. and Confined Space training/certification Was required. ($310,000)
Project Engineer: Harry L. Herman Jr., C.E. Public Works Division City of San Diego, CA 619- 654-422
6 City of Hermann, MO. Manhole Rehab # 98-10 September 98 - October 98
Work consisted of the renewal of 26 manholes with Permacast cementitious liner. ($43,000) Public Works Director: Wayne Bruckerhoff
573-486-5400 7 City of Lexington, MO.
Manhole Rehab, Phase 1, Project # 98-PF-19 February 99 to August 99
The rehabilitation of 85 manholes with Permacast cementitious liner, the rehab of 10 manholes that was structurally unsound with Permaform steel forms and PVC liner, epoxy of 7 manholes that had high concentrations of hydrogen sulfide gases. ($238,000)
City Engineer: Kenny Maib, P.E. 1-660-259-4633
Project Engineer: George Butler Associates J. Thad May, P.E. 913-492-0400 8 City of Sioux Falls, SD
Tuthill Lift Station Rehabilitation Project C461232-14 September 99 - October 99
The rebuilding of the effluent rectangular conduit by removal of the old concrete structure and forming and pouring a new concrete conduit with a PVC T-Lock liner to resist against Hydrogen sulfide gases. Special conditions: The project required bypass pumping of seven million gallons of affluent per day for 17 days. ($192,000)
Project Engineer: Larry Fassett P.E. 605-367-7048 9 City of Farmington, MO. October 99 - December 99
Renewal of 53 manholes with Permacast cementitious liner. Grade adjustment of 5 frames & covers. This work was sub contracted through the eastern Missouri licensee. ($45,000.)
Specialty Sewer Services Inc. Norm Sirna
314-731-7784 10 City of St. Louis, MO. January 00-Feburary 00
Renewal of 33 manholes with Permacast cementitious liner. These manholes where rehabilitated as Part of a pipelining project with Insituform Inc. ($39,000)
Specialty Sewer Services Inc.
Norm Sirna
314-731-7784 11 City of Des Moines, IA
April 00-May 00
Rehabilitation of large containment chambers at the main treatment plant with Permacast Cementitious liner, Fortified with Conshield. ($87,000)
Project Engineer: Jeff Hanson P.E. City of Des Moines, IA 515-283-4014
12 City of Saint Louis, MO (MSD) October 00-November 00
Rehab of three concrete shafts over main interceptor line. Maline Drop Shafts where 8x9ft and 54 ft deep. Interior walls had serious deterioration due to heavy concentration of hydrogen sulfide. Rebuilt to original thickness using Permacast Construction Grout and cementitious liner, all fortified with Conshield. ($96,548.)
Project Engineer: Gary Buchanan
Bessell WWTP-Lift Station Division City of Saint Louis, MO
314-436-8773
13 Whiteman Air Force Base, MO. Storm Drainage Project
Project # YWHG 95-2003 December 00-December 01
Work consisted of excavation and installation of 7,150 ft of drainage pipe, 112 drop inlets, 80 under street or driveway bores, and 70,000 yd of grading/seed/sod. ($562,517)
Project Inspector: Gary Hall
660-687-6281 14 Whiteman Air Force Base, MO.
Storm Drainage Project Project #YWHG 94-9103R2 March 01-December 01
Work consisted of excavation and installation of 2,203 ft of storm drainage pipe, 36 drop inlets, 12 under street or driveway bores, and 27,000 yd of grading/seed/sod. ($314,380.)
Project Inspector: Gary Hall 660-687-6281 15 City of Kansas City, MO
May 02 - February 03
City Wide Manhole Rehabilitation-Phase 7: Buckeye Creek Project # 757
This contract was for the replacement of 671 frame & covers, 6290 vertical feet of Permacast Cementitious liner (671 manholes), 205 vertical feet of epoxy liner (17 manholes). ($1,017,123.) Project Engineer: Joseph H. Engleman, G.E.
816-513-2207
16 Whiteman Air Force Base, MO. April 02 – November 02
Repair Sewer Laterals for family Housing DO# 7130
Project # 060100
The work consists of excavation, replacement or lining of existing sewer laterals, seed and sod, within the base family housing area. ($292,890)
Base Civil Engineer: Ernie Macios 660-687-6295 17 Whiteman Air Force Base, MO.
March 03 – June 04
Repair Sewer System/Lateral Lines DO # 5001 & 5002
The Work consisted of Excavation & Replacement, CIPP Lining, CCTV Inspection, of Sewer Mains and Laterals in Base Housing. This is a Current IDIQ Project. ($695,000).
Base Civil Engineer: Ernie Macios 660-687-6295 18 Whiteman Air Force Base, MO
February 04 – December, 04 Erosion Control, North Bowl DO # 7274
Work Consists of Excavation and Installation of 1750 lineal feet of Storm Drainage Pipe and concrete Structures along the Airfield Taxi and Runway areas, to include approximately 3.5 Acres of reshaping and Seeding. ($180,000)
Project Manager: Mark Newby
Centennial Contractors Inc
660-563-6307
19 Whiteman Air Force Base, MO July 04 – June 06
DO # 5003, 5004, 5005, 5006, 5007, 5008, 2009 and 5010
These projects where for the Repair and/or Replacement of Sewer Mains and Laterals Base wide. Includes Excavation, Cured-in-Place Pipe (CIPP) Lining, Closed Circuit Televised (CCTV) Inspection, Pipe Cleaning, Pipe and Manhole Installation. ($1,047,053)
Base Civil Engineer: Ernie Macios 660-678-6295 20 City of Osage Beach, MO
Oct 06 - May 07
Project: Tan-tar-a Sewer Rehab Phase 1
This project was for rehabilitation of manholes by Cementitious Lining and Permaform, Relining of the Sewer Mains by Cured-in-Place Pipe (CIPP), and Frame & Cover Replacement. ($103,906)
Project Engineer: Phillip Alton
573-302-2000 ext. 291 21 Burlington Northern Santa Fe Railroad Clovis, N Mexico
Jan 01 – Feb 01
The work consisted of lining new Diesel Refueling structures by Appling Cementitious material and Epoxy Coating. ($78000)
Project Engineer: Kinley Construction
Dennis Hemmingway, P.E. 817-461-2100
22 Whiteman Air Force Base, MO 06 March – 06 Sept
Project: Houx Lake- Erosion Control
This was a combined Erosion Control and Beautification Project in the Houx area Watershed. The work Consisted of Grubbing, Demolition of Sewer, Water, and Electrical Mains and Relocation around the area That was designated for a New Lake. This included the Building of a Concrete Drop Overflow Connected To the Bridge Concrete Conduit under Houx Avenue, an Island with Crossover Walk Bridges, and a Walking Trail. ($374,540)
Base Civil Engineer: Ernie Macios 660-678-6295
23 Whiteman Air Force Base, MO 06 Oct – 07 Sept
Project: Bomb Rack Assembly Building
This consisted of the Excavation, Forming of Foundation Pad and Approaches, Concrete and Reinforcement, Water, Drainage, Grading and Sod. ($121,396)
Base Civil Engineer: Ernie Macios 660-678-6295
24 City of Osage Beach, MO 07 Feb - 07 May
Project: OB06-011
Woodland Shores Sewer Rehab
Project: The work was for the Installation of a new Sewer System in place of the old Septic Units, the installation of a Forced Main Lift Station, and the Reconnection of the Existing Sewer Laterals. ($148,905)
Project Engineer: Phillip Alton
573-302-2000 ext. 291 25 Whiteman Air Force Base, MO
06 March – December 07
Fine Grading in New Housing, Phase 1& 2
Project: This Project was the Backfilling, Tillage, and Grading to Elevation of Topsoil in Preparation of Seeding and Sod to the new Housing Projects. ($343,889)
Mid America Turf: Tim Stroh 660-747-8873 26 Whiteman Air Force Base, MO
06 Nov – December 07 Base Housing Demolition
Project: This work Consisted of Delivery of Backfill Material to 96 Basement Sites, Backfilling, compaction Grading to the proper elevation, and seeding in Preparation of the next Phase of New Housing to be built. ($271,403)
Parsons Evergreene: Carlos Salcedo 660-563-3289
27 Tipton, Missouri 07 Nov – October 08
Project: Clean & Televise (CCTV) Sewer Main Pipeline & Root Control. This included furnishing Videos and Data for Evaluation. ($176,018)
Project Engineer: Allgeier Martin & Associates: Eugene Spears 417-6245703
28 Whiteman Air Force Base, Missouri 07 November – 08 October
BRAC Squadron Building
Project: This work Consisted of Demolition of Base Utilities within the Work Site Area, Clearing and Grubbing, Earthwork, Excavation of the Foundation and Basement Floor, Backfill and Compaction, Installation of to Lift Stations, Sanitary and Storm Sewer installation, and new Parking Area. ($926,000). General Contractor: Mason and Hangar
Richard Cox 913-681-2323