• No results found

Overview of Baltimore Gas & Electric s Combined Heat & Power (CHP) Program. Bill Wolf Manager I&C Energy Efficiency Programs April 1, 2014

N/A
N/A
Protected

Academic year: 2021

Share "Overview of Baltimore Gas & Electric s Combined Heat & Power (CHP) Program. Bill Wolf Manager I&C Energy Efficiency Programs April 1, 2014"

Copied!
11
0
0

Loading.... (view fulltext now)

Full text

(1)

Overview of Baltimore Gas & Electric’s

Combined Heat & Power (CHP) Program

(2)

2

1.

Energy Solutions for Business

 Incentives up to 50% for retrofit projects or up to 75% of incremental costs for new

equipment

2.

Retrocommissioning (RCx)

 Incentives up to 75% of the cost of the RCx assessment and equipment optimization

3.

Small Business Energy Solutions

 Incentives up to 80% of the total cost of the project

4.

New

Combined Heat & Power (CHP)

 Incentives up to $2 million towards the installation of a CHP unit

Combined Heat & Power is Part of BGE’s Smart Energy

Savers Program® Core Business Programs

These programs support the EmPOWER Maryland Energy Efficiency Act

(3)

3

Background

 In adopting BGE’s 2012-2014 energy efficiency programs, the Commission ordered MD utilities to develop new programs as a way to close the gap in meeting the EmPower Maryland goals

 BGE filed its CHP program in April 2012 and received Commission approval in June 2012 as part of a joint utility filing

 Initial budget of $20 million established amongst BGE ($10.3 million), Pepco and Delmarva Power

 Proposals were solicited through a RFP process performed by each utility in the late summer of 2012 with bids due in December 2012 for BGE and

(4)

4

RFP Results

BGE initially received 16 proposals for a variety of industrial and

commercial (I&C) customers including hospitals, universities,

secondary schools, industrial plants, state facilities and a new casino

Participants included I&C customers, CHP vendors, engineering

consultants, developers and ESCOs

So far, projects with ESCOs seem to be the best coordinated

11 projects initially passed the technical and engineering reviews

with 5 projects failing or being withdrawn by the participant

Gas service upgrades were required on several projects but upgrade

costs to customers have been minimum and have not stopped

(5)

5

Incentive Structure

 Up to $2 million per CHP project

 Design Incentive = $75/kW (paid when initial design and gas costs are complete)

 Construction Incentive = $175/kW (paid when unit is installed and commissioned)

 Production Incentive = $0.07/kWh (paid for 18 months following commissioning)

 Design & Construction Incentive capped at $1 million per project

 Production Incentive capped at $1 million

 Total Incentive design to average approximately $900 / kW

 Incentives designed to cover 25 – 50% of the total cost of installation

(6)

6

Basis for Incentive Levels

Incentive levels and requirements were based on best practices:

 New Jersey’s Office of Clean Energy program provides incentives of $2,000/kW for units under 500kW and $1,000/kW for units between 500kW and 1,000kW.

 Massachusetts provides $750/kW for both small and large CHP systems. The incentive is limited to no more than 50% of installed costs. Resulted in 24 CHP applications projects being approved in the first two years representing 52 MW and 227,000 MWh.

 NYSERDA’s CHP grant program provides incentives that are 30% to 50% of the cost of a CHP project up to $2 million. 18 CHP projects completed representing 21 MW using over $18 million in NYSERDA funding.

 Connecticut’s CHP program provides incentives up to $500/kW. 72 CHP projects have been approved and funded representing 250 MW and $105 million in incentives.

(7)

7

Minimum Qualification Requirements

 No net metering or exporting of electricity

 Equipment can be natural gas or bio-gas turbine, micro turbine or reciprocating

engine (Fuel cells are also considered)

 No project size limit but must maintain a system efficiency of 65%

 Must pass BGE’s Total Resource Cost Test (> 1.0)

 Subject to BGE’s Schedule S Standby Tariff

 Must meet BGE’s Interconnections requirement

 Must obtain proper MD Department of Environment permits

 Customer responsible for all natural gas service upgrades

(8)

8

Approved Project Characteristics

Project sizes ranged from two projects at 75 kW up to three projects

at 2,000 kW with the rest somewhere in between

Fuel sources were all natural gas and one bio-gas

All CHP systems were reciprocating engines with no turbines (only

fuel cell proposal was withdrawn by customer)

25% of the projects included absorbers for chilled water

Efficiency levels ranged from 68% to 82%

BGE incentives typically covered 20% to 45% of the development cost

Development cost ranged from $1,900/kW to $4,200/kW depending

on the size of the unit (smaller units had higher $/kW)

Payback periods ranged from 2.2 years to 11.6 years with incentives

and 4.1 years to 14.5 years without incentives

(9)

9

Barriers and Lessons Learned

CHP project timelines are much longer than anticipated due to

customer decision making process and engineering interaction

Incentives do drive participation and project size (No CHP projects

were received before program began and no projects have been

larger than 2 MW (which is about where you reach the $2 million cap)

Don’t underestimate complexity of the internal customer approval

process – need top management’s full support to move forward

CHP is a complex/complicated process for customers. Need to engage

with them on an intimate 1 to 1 basis to promote the technology and

assist them throughout the entire implementation process

Facility engineers can be road blocks since they are responsible for

the additional operation and maintenance duties

(10)

10

Current Status

 In August 2013, BGE received Commission approval to increase its CHP budget by $10.7 million and provide incentives for projects approved by BGE by 2014 and completed by 2016

 Twelve (of 18) CHP proposals making progress towards implementation

 Nine projects pre-approved - 8.6 MW, 67,000 MWh

 Design incentives paid on five projects -$201,000

 Four projects have equipment on site, are testing their installations, and expect production to begin by the second quarter 2014

 Several small, 75kW units at two Baltimore County schools and Johns Hopkins University and one large, 2 MW unit at a local hospital

 Two additional mid-size projects to be completed in 2014

 Remaining projects to be completed in 2015 along with discussions with five large customers for 2015 and beyond

(11)

11

Next Steps

BGE is now accepting additional applications on a first come basis

with no RFP process (recently received an application for a large

waste treatment facility potentially using bio-gas)

Marketing is focused on direct, one-on-one communication with

customers and trade allies by hosting small-group seminars discussing

the technology

Account Managers are targeting market segments where CHP is a

good solution

BGE is attempting a broader strategic outreach to ESCOs, professional

trade associations as well as customer associations

Other outreach and marketing tactics include newspaper editorials,

magazines that feature CHP, digital marketing, direct mailings and

email blasts

References

Related documents

The proposed design guide includes an overall fire safety strategy for post-tensioned timber buildings and a simplified calculation method for the fire resistance

Did the facility develop a plan of care with measurable goals and interventions to address the care and treatment related to the resident's indwelling catheter, services to restore

Helping students develop healthcare delivery skills is a process of introducing and demonstrating skills, providing opportunities for practice and feedback in simulated

In the present study we use the same IV approach to model the causal impact of Vietnam- era military service on four novel outcomes: residential stability, marital stability,

This collection contains correspondences, biographical materials, clippings, materials from organizations, academic materials, research materials, publications by and not by Sperry

3, 34, 35 More specifically, the presence of pain was investigated in one cohort of more than 3,000 moderate to severely injured patients, 36 where approximately two-thirds

Visualization of molecular distribution of m/z values that were expressed to higher levels in cancer tissue from all cases1. The ROI of each case is defined by a dashed line

Binnen het conceptuele onderzoek dat deze thesis beslaat wordt op zoek gegaan naar een antwoord op de vraag: “Op welke manier kan Wittgensteins opvatting van relationaliteit en