Treasure Valley
Treasure Valley
Electrical Plan
Electrical Plan
Community Advisory
Community Advisory
Committee
Committee
January 25, 2006 January 25, 20062
Agenda
Agenda
10 a.m. Welcome
10:10 a.m. Follow up DSM discussion 10:30 a.m. TVEP – CAC process update 10:40 a.m. Transmission Presentation
Overview & Reliability 11:40 a.m. Lunch
12:10 p.m. Small group discussion –
Transmission in the Treasure Valley
Recap of Previous Meetings
Recap of Previous Meetings
¾August 24 – Toured Facilities
Fossil Gulch Wind Park
Bennett Mountain Power Plant Boise Bench Substation (drive by)
¾September 22 – Toured Facilities
(makeup session)
Bennett Mountain Power Plant Caldwell Substation
4
Recap of Previous Meetings
Recap of Previous Meetings
¾September 28
Overview of Idaho Power System
Discussed base load vs peaking power plants Integrated Resource Plan
Brief discussion of Treasure Valley power
Recap of Previous Meetings
Recap of Previous Meetings
¾October 26
Discussed generation in the Treasure Valley Discussed Treasure Valley distribution
buildout
Breakout discussion about pros and cons of
6
Recap of Previous Meetings
Recap of Previous Meetings
¾November 30
Regional Planning Updates
• Communities in Motion
• Blueprint for Good Growth
Demand Side Management presentation Demand Side Management breakout
sessions
• Barriers to DSM
• What would it take to exceed expected results? • How could Idaho Power encourage community
8
Future Treasure Valley
Future Treasure Valley
Electrical Projections
Electrical Projections
2030 Buildout Population 873,561 2,400,000 Electrical Demand (MW) 2,620 7,200 DSM Potential (20-30% of new load) 230 1600Population & Demand Projections
Population & Demand Projections
¾Buildout population determined using 3
different methods.
The first method was described in October
• Used land based GIS approach based on
availability of land, proximity to transportation etc.
• Assigned 3 density zones
Urban Suburban Rural
10
Population & Demand Projections
Population & Demand Projections
¾The second method used zoning as
determined by using comprehensive
plans of the various cities.
Some cities don’t have comp plans.
• Made assumptions based on nearby cities
For each zone, assigned a loading (kW) per
square mile based on the type of zoning.
Added up load for each zoning type.
For areas outside of city areas of impact,
Population & Demand Projections
Population & Demand Projections
¾ The third method ignored everything other
than residential zoning with the assumption that all residences will be in areas zoned
residential.
Assumed areas will fill in accordance with their
zoning. I.e. R-4 will have 4 residences per acre, etc.
Idaho Power estimates there are about 2.5 people
per customer
Subtracted out land for golf courses, parks, etc.
¾ All three methods result in between 7,000 and
7,200 MW of load.
12
14
Substation Types
Substation Types
¾Source Substation – Act as the receiving
point for energy produced at distant
generation.
Typically 230 kV and higher
Can be co-located with other types of
substations
Send out power at 230 kV to Hub Substations Currently there are 2 Source Substations in
Substation Types
Substation Types
¾Hub Substations – Convert 230 kV
(typically) to 138 kV for transmission to
Distribution Substations.
Each Hub Substation can have 2 or more 138
kV loops fed from them
• 3 to 5 distribution substations per loop
Currently there are 3 Hub Substations in the
16
Substation Types
Substation Types
¾Distribution Substation – Convert the 138
kV transmission from the loops fed by
the Hub Substations to 13.8 or 34.5 kV for
delivery to its end use
Transmission Loop Configuration
Transmission Loop Configuration
¾ Three-Four
230 kV lines into the Hub Substation ¾ Two 138 kV loops (Four Lines) ¾ Three to Five Distribution Stations on a loop 138 kV 230 kV
Treasure Valley 138kV Transmission Layout
Transmission
22
Idaho Power Voltage Levels
Idaho Power Voltage Levels
¾ Extra-high voltage Transmission
230,000; 345,000; 500,000 volts
Used for transmitting electrical energy
over great distance.
Higher voltage lines are more efficient
than lower voltage lines.
• Higher voltage line results in fewer losses
than a lower voltage line.
• Idaho Power loses between 2 and 3 percent
of its energy due to line losses on the extra-high voltage transmission system.
¾230 kV corner
structure.
Similar in diameter
24
¾230 kV
transmission on
Eagle Road
Note the transmission line is in road right-of-way.138 kV and 230 kV lines running down
26
Idaho Power Voltage Levels
Idaho Power Voltage Levels
¾ Sub-transmission lines
69,000; 138,000; 161,000 volts Used for transmitting energy
between substations that are close to one another
• Up to ~ 100 miles
Will typically not carry as
much energy as extra-high voltage lines.
138 kV
13.8 kV Underbuild
Idaho Power Voltage Levels
Idaho Power Voltage Levels
¾Distribution Lines
13,800; 34,500 volts Used for transmitting
energy to its end use.
• Commercial facilities • Small factories
• Small transformer
outside a group of houses.
28
Transmission Line Capacity
Transmission Line Capacity
¾ There are many factors that go into
determining how much power a given
transmission line can carry. For general purposes, we can say:
500 kV line can carry ~ 1,000 to 1,500 MW 345 kV line can carry ~ 700 to 1,000 MW 230 kV line can carry ~ 300 to 500 MW
¾ All the above lines will normally be operated in
parallel (electrically alongside) with another line of equal size or a set of lower voltage lines.
Transmission Reliability
Transmission Reliability
¾Idaho Power must be able to reliably
serve its customers under all normal
operating conditions and under expected
abnormal operating conditions (events
that are statistically likely to occur fairly
often)
30
Transmission Reliability
Transmission Reliability
¾ Idaho Power voluntarily complies with WECC
reliability standards.
By agreement, WECC can impose financial
penalties on Idaho Power for reliability violations
¾ Idaho Power must periodically submit reports
to the WECC on varying reliability topics.
¾ IPUC has some oversight authority
Can force Idaho Power to improve its system if
Transmission Reliability
Transmission Reliability
¾ Transmission system must be able to survive
the single worst contingency (abnormal condition) on the system.
No one event on a major transmission line can
disrupt the system, making it unable to supply all the end users.
Certain transmission lines are not loaded to their
full capacity – they hold some in reserve.
Additional capacity is held in reserve so that energy
can be imported from surrounding utilities should Idaho Power lose generation.
32
Transmission Reliability
Transmission Reliability
¾Idaho Power must also adhere to what’s
known as an “n-1” criterion.
For multiple transmission lines delivering
power to the same point, if one of the lines goes out of service, the remaining lines must be able to carry both the load they were
carrying before the event, plus the load carried by the line that is out of service.
• This is true even if the line with the highest
capacity is the one that goes out of service.
N
34
Transmission Reliability
Transmission Reliability
¾Not all transmission has backup
Many times, a single lower voltage line will
be the only transmission serving an area so that if the line goes out of service, the
customers being served by that line lose power.
• Typical of smaller demand areas such as in
Transmission Reliability
Transmission Reliability
¾Not everyone sees the same level of
reliability.
It would be prohibitively expensive to ensure
all customers had the same reliability.
Customers located in urban areas generally
have the ability to receive power from more than one feeder.
More remote customers have only one feeder
serving their area.
In mountainous areas, snow and wind will
36
Transmission Right of Way
Transmission Right of Way
¾ The width of right-of-way corridor required
for a transmission line is set by the National Electrical Safety Code.
Takes into account blowout
• How far the wire can be expected to swing during a high
wind on a hot day.
• Can’t come close to structures or trees because of wind.
¾ If a tower is made taller, sometimes it will
require less ROW width.
¾ Single pole structures also require less ROW
width than do lattice structures.
38
Transmission Right of Way
Transmission Right of Way
¾500 kV
Single circuit – 150 feet
Two circuits in same ROW – 300 feet
• Separate pole lines
Single circuit along road ROW – 70 feet
• If the road ROW has landscaping and burming,
this can decrease the need for additional
transmission ROW since the transmission can overhang
Transmission Right of Way
Transmission Right of Way
¾345 kV
Single circuit – 130 feet
Two circuits in same ROW – 300 feet Single circuit along road ROW – 60 ft
• If the road ROW has landscaping and burming,
this can decrease the need for additional
transmission ROW since the transmission can overhang
40
Transmission Right of Way
Transmission Right of Way
¾230 kV
Double circuit (same tower) – 80 feet
• Normally we will run double circuits for 230 kV
Double circuit along road Row – 40 feet
• If the road ROW has landscaping and berming,
this can decrease the need for additional
transmission ROW since the transmission can overhang
¾230 kV
transmission on
Eagle Road
Note the transmission line is in road right-of-way.42
Increasing Capacity of Existing
Increasing Capacity of Existing
Lines
Lines
¾ The capacity of existing transmission lines can
sometimes be increased
Increase wire size
• If structurally able
Increase voltage
• If electrical clearances are great enough • If ROW is available
¾ If the line was already serving an end-load, that
load still must be served
Small Group Discussion
Small Group Discussion
¾What are important issues to consider
when locating transmission lines in the
Treasure Valley? (What are the “most”
important?)
¾Where would you like to see transmission
lines enter the Treasure Valley?
¾Explore the possible corridors that
transmission lines could use to cross the
Treasure Valley
A Buildout Scenario
Midpoint GEN Existing Existing 2004 2004 Mt. Home Brownlee Ontario Boise Bench Caldwell Locust
46 Midpoint GEN Nampa 230 Nampa 230 Mt. Home Ontario Boise Bench Caldwell Nampa Brownlee
Midpoint GEN Happy Happy Valley 230 Valley 230 Mt. Home Ontario Boise Bench Caldwell Nampa Brownlee Happy Valley
48 Midpoint GEN Middleton Middleton Mt. Home Ontario Boise Bench Caldwell Middleton Nampa Brownlee
Midpoint GEN Pearl to Pearl to Middleton Middleton Mt. Home Ontario Boise Bench Caldwell Middleton Pearl Switching Station Brownlee
50 Midpoint GEN Pearl to Pearl to Locust Locust Mt. Home Ontario Boise Bench Caldwell Pearl Locust Brownlee
Midpoint GEN Pearl to Pearl to Happy Happy Valley Valley Mt. Home Ontario Boise Bench Caldwell Happy Valley Pearl Brownlee
52 Midpoint GEN Mora 230 Mora 230 Mt. Home Ontario Boise Bench Caldwell Mora Brownlee
Midpoint GEN MORA to MORA to Mt Home Mt Home Mt. Home Ontario Boise Bench Caldwell Mora Brownlee
54 Midpoint GEN MORA to MORA to Cloverdale Cloverdale Sub Sub Mt. Home Ontario Boise Bench Caldwell GEN Mora Cloverdale Brownlee
Midpoint GEN Cloverdale Cloverdale Tap Tap Mt. Home Ontario Boise Bench Caldwell GEN Cloverdale Mora Brownlee
56 Midpoint GEN Dry Creek Dry Creek Mt. Home Ontario Boise Bench Caldwell GEN Dry Creek Brownlee
Midpoint GEN Nampa to Nampa to Cloverdale Cloverdale Mt. Home Ontario Boise Bench Caldwell GEN Cloverdale Nampa Brownlee
58 Midpoint GEN Midpoint to Midpoint to Southwest Southwest Treasure Valley Treasure Valley Mt. Home Ontario Boise Bench Caldwell GEN Midpoint Brownlee Southwest TV PacifiCorp
Midpoint GEN Southwest Southwest Treasure Valley to Treasure Valley to Western Canyon Western Canyon County County Mt. Home Ontario Boise Bench Caldwell GEN Midpoint Brownlee Southwest TV PacifiCorp
60 Midpoint GEN Southwest Southwest Treasure Valley to Treasure Valley to Northwest Northwest Mt. Home Ontario Boise Bench Caldwell GEN Midpoint Northwest Brownlee Southwest TV PacifiCorp
Midpoint
GEN
Convert
Convert Bowmont Bowmont Sub to 230 Sub to 230 Mt. Home Ontario Boise Bench Caldwell GEN Midpoint Northwest Brownlee Southwest TV PacifiCorp
62 Midpoint GEN Treasure Valley Treasure Valley Build
Build--OutOut
Mt. Home Ontario Boise Bench Caldwell GEN Midpoint Southwest TV PacifiCorp Northwest Brownlee