• No results found

GRID CONNECTION OF POWER GENERATING FACILITIES. FEBEG POSITION Elia WG Belgian Grid ( )

N/A
N/A
Protected

Academic year: 2021

Share "GRID CONNECTION OF POWER GENERATING FACILITIES. FEBEG POSITION Elia WG Belgian Grid ( )"

Copied!
15
0
0

Loading.... (view fulltext now)

Full text

(1)

GRID CONNECTION OF POWER

GENERATING FACILITIES

FEBEG POSITION

Elia WG ‘Belgian Grid’

(2)
(3)

CONTENT

• Current developments

• General principles

• Integrating new power plants in the grid

• Grid connection procedure

• Firm capacity for injection

• Congestion management

• Derogations

(4)

CURRENT DEVELOPMENTS

• Proposals Elia (WG Belgian Grid) for new capacity

reservation procedure

• Proposals Elia (WG Belgian Grid) for new connection

procedure

• Proposals in Policy Platforms VREG and CWaPE (REDI)

regarding flexible access (= conditional connection)

(5)

GENERAL PRINCIPLES (1)

• Need for transparent and efficient procedures for

non-discriminatory connection of new power plants to the grid

(art. 23,1 of EU Electricity market directive)

• All new generation capacity should be timely connected to

the grid (art. 23,2):

– connection cannot be refused on the grounds of possible future limitations to available network capacities current situation in BE is not compliant

– connection cannot be refused on the ground that it will lead to additional costs linked with necessary capacity increase of system elements

• Power generators need firm commitment and predictable

conditions at the moment of their investment decision

(6)

GENERAL PRINCIPLES (2)

• Grid operators should employ all reasonable means to

timely connect all new generation capacity:

– at a reasonable cost

– at the most appropriate connection point (location, voltage, …) – without imposing disproportionate or discriminatory technical or

operational constraints to power generators

• Grid operators should proactively invest with a long term

vision in order to reach this objective

1

– ensure the long-term ability of the system to meet demands for transmission of electricity in a secure, reliable and efficient way

– contribute to security of supply through adequate transmission capacity and system reliability

• Solidarity and coordination between TSO and DSOs

regarding grid investments and choice of most appropriate

connection point for power plants

(7)

INTEGRATING NEW POWER PLANTS IN THE GRID

Power generation development

Connection Procedure Grid development Strategy Project planning TYND Development Phase

Orienting study Detailed study Engineering Realization Connection Specs, Licensing,

RFI, RFP, …

Engineering

Build First Firing

Investment planning … Engineering Permitting Grid reinforcements Investment decision Connection Agreement

Firm grid capacity available

Consultation

Request Request Commitment

for firm capacity

(Congestion Management)

Grid reinforcements

(8)

CONNECTION PROCURE

Capacity reservation

• TSO should treat all applications for grid connection on a

transparent and non-discriminatory manner

• At the moment of its investment decision (financial closing)

the applicant needs firm commitment that grid capacity will

be firmly available at the commissioning date

• Objective is to avoid grid capacity hoarding for non realistic

projects and reduce interdependencies and administrative

overhead for Elia and applicant:

– frequent in between checks based on permitting status or confirmations of requests should be avoided

(9)

CONNECTION PROCEDURE

Principles

• Connection procedure should be transparent and efficient

and based on non-discriminatory criteria:

– objective criteria to assess request for connection – informative orienting study

– formal request for detailed study (leading to connection options, including conditions, timing and costs)

– formal & mutual acceptance of one option – signing of the connection agreement

– start realization according to planning and payment scheme

• Signing of the connection agreement:

– firmly allocates the capacity to the applicant

– fixes all terms and conditions between applicant and grid operator, including arrangements if grid operator is unable to timely realize grid

connection (reinforcement) or if power plant project is delayed or definitely stopped

(10)

CONNECTION PROCEDURE

Agreement

General

terms and conditions

Specific

terms and conditions

In case of

withdrawal connection request In case of timely

realization of connection

In case of untimely realization of connection

In case of untimely

realization grid reinforcements

… Possible compensation depending on phase of realization Payment Compensation Congestion management …

(11)

FIRM CAPACITY FOR INJECTION

• Flexible connection is unacceptable

– lack of incentives for grid investments

– discourages investments in generation capacity – discriminatory competition distortion

– additional uncertainty and missed revenues for power generator

• NMA1: ‘flexible connections are discriminatory because they

make a distinction between existing and new connections’

• If grid infrastructure is not sufficient to guarantee firm

connection capacity: market based congestion management

as temporary solution pending urgent grid investments

(12)

CONGESTION MANAGEMENT (1)

• Objective criteria to measure/predict actual/future congestion

proactive investment program

• Structural congestion is unacceptable

• Occasional congestion:

– should also be prevented by timely investments

– market based congestion management can offer temporary solution

• Market based congestion management system with fair

compensation ensures:

– grid operators can assess whether they compensate grid users to ramp up/down or invest in grid reinforcements

– a correct price which reflects scarcity or oversupply of flexibility

– a fair compensation incentivizes market operators to invest in flexible generation capacity or flexible demand

(13)

CONGESTION MANAGEMENT (2)

• System redispatch with up- and downward regulation can

be implemented according to the Dutch Model:

– clear identification of congested zones on TSO and DSO grid – voluntary and, if necessary, mandatory bidding

– applicable on all grid users (both generators and end users), including already connected parties no discrimination

– biddings for different categories of units to prioritize renewables and cogeneration

– fair and market based compensation

(14)

DEROGATIONS

• Derogations of these principles should be avoided:

– except for system security reasons

– existing derogations such as mutually agreed upon grid access

constraints for specific connections during a limited number of hours for the maintenance of grid components, should not be considered as a precedent

(15)

CONCLUSIONS

• Grid operators should employ all necessary means to

timely connect all new generation capacity

• Complexity and uncertainty in the connection procedure

and agreement should be reduced

• Grid capacity for injection needs to be firm

• Structural congestion must be avoided by timely

investments

• Occasional congestion should also be prevented by grid

reinforcements or managed with a market based

References

Related documents

In this context this article identifies the international standing of the South African universities in the various scientific disciplines, compares them with their standing over

Quality teaching is focused on student achievement (including social outcomes) and facilitates high standards of student outcomes for heterogeneous groups of students.

The survey shows that some countries have been much better than others in establishing systems that combine high-quality initial education with opportunities and incentives for the

Travel Time (days) from release in Wells Reservoir to detection at WEJ by fish fork-length (mm) for all sub-yearling Chinook (N=32) detected at WEJ in 2017-2018. * Detections

Dahua 4-button 2MP IP Villa Outdoor Station, Viewing Wide Angle 140 degree, ICR Night vision and Voice indication, Mifare Card Reader, Built-in Speaker, Group Call, Video and

Do not move the casualty or administer treatment unless trained Action 5edical Incident Action Supv have mobile  phone  Notify  Notify Steven -uddell

For intermediate forecast hori- zons, especially following spending and transfer shocks, the truncated present-value of surpluses can be grossly out of line with the value of

Errors are displayed after adding, removing, and then adding dialog through the Configuration Tools icon... If your site uses this platform combination, you should not upgrade to